CN220598703U - Fast-assembling ground beam column structure - Google Patents

Fast-assembling ground beam column structure Download PDF

Info

Publication number
CN220598703U
CN220598703U CN202322122591.7U CN202322122591U CN220598703U CN 220598703 U CN220598703 U CN 220598703U CN 202322122591 U CN202322122591 U CN 202322122591U CN 220598703 U CN220598703 U CN 220598703U
Authority
CN
China
Prior art keywords
ring
ground beam
cage
concrete
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322122591.7U
Other languages
Chinese (zh)
Inventor
王铁成
王依兒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202322122591.7U priority Critical patent/CN220598703U/en
Application granted granted Critical
Publication of CN220598703U publication Critical patent/CN220598703U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a fast-assembled ground beam column structure which sequentially comprises a concrete cushion layer, a concrete bearing platform, a brick foundation and a ground beam from bottom to top, wherein the ground beam comprises a ground beam reinforcement cage and a ground beam concrete layer, a columnar ring vertical reinforcement cage is fixed on the concrete cushion layer, penetrates through the concrete bearing platform and the brick foundation, penetrates through the ground beam reinforcement cage, is fixed with the ground beam reinforcement cage, and extends upwards to the upper part of a bottom beam. The improved scheme of the utility model effectively solves the problems of low connection strength of the bottom beam and the structural column and low construction efficiency in the existing building construction, thereby improving the performance, safety and maintainability of the whole building structure.

Description

Fast-assembling ground beam column structure
Technical Field
The utility model belongs to the technical field of connection of building structural columns and bottom beams, and particularly relates to a fast-assembled ground beam column structure.
Background
In the building construction process, the connection relation between the bottom beam and the structural column refers to a physical connection mode between a ground beam (also called a bottom beam, a bottom plate beam and a bottom beam) and a stand column (also called a structural column and a post), so that the stability, the safety and the bearing capacity of a building structure are ensured. This connection plays a key role in the overall structure of the building, since the connection of the bottom beams to the structural columns is responsible for transferring the upper load to the foundation, ensuring that the building can stably bear external loads.
Common connection relations between the bottom beams and the structural columns include the following: rigid connection: in rigid connection, the bottom beams and the structural columns are directly connected together by welding, bolting or other similar means to form a rigid whole. The connecting mode can effectively transfer load and provide a stable structure; semi-rigid connection: the semi-rigid connection is interposed between the rigid connection and the flexible connection. In this case, the bottom beam and the structural column may be connected by bolts, pins, or the like, but the connection is not as strict as that of a rigid connection. This may allow some minor deformation, but still maintain a high stability; and (3) flexible connection: the flexible connection allows for some relative displacement between the sill and the structural columns, typically by an elastic material, rubber pad, or the like. The connection mode can absorb part of energy under the conditions of earthquake and the like, so that the risk of structural damage is reduced; prestress connection: the prestress connection fixes the bottom beam and the structural column by applying prestress force, so that the stability and the bearing capacity of the connection are improved; and (3) foundation reinforcement connection: in some buildings, the connection of the bottom beams to the structural columns may need to be combined with a foundation stabilization system to ensure the stability and safety of the connection.
The connection between the bottom beam and the structural column in the existing building construction process has the following problems and disadvantages: the connection design is unreasonable: the low connection strength may be caused by unreasonable connection design, and a more effective connection mode is needed to ensure the stability and safety of the structure; lack of pre-fixation measures: the lack of pre-fixing measures at the bottom of the structural column may be a result of insufficient planning and preparation at the early stage of construction, taking into account the need to ensure the stability of the structural column prior to construction; the righting design is insufficient: additional righting means may not only add to the construction complexity, but may be inefficient, requiring more reliable righting systems to be designed to maintain the verticality of the structural column; safety and reliability are not sufficient: the low strength of the connection and the unstable structure column directly affect the safety and reliability of the overall structure, which may cause problems in long-term use.
Because the connection problem between the bottom beam and the structural column in the existing building construction relates to challenges in connection strength, structural column stability, safety, construction efficiency and the like, a bottom beam column connection structure form which can meet the stability and bearing performance of the structural column and has quick assembly performance is needed.
Disclosure of Invention
Aiming at the problems of low strength and low construction efficiency of the existing beam-column connection structure, the utility model provides a fast-assembled ground beam-column structure.
The utility model solves the technical problems as follows: adopt a fast-assembling ground beam column structure, from bottom to top includes concrete cushion, concrete cushion cap, brick basis and earth beam in proper order, and wherein the earth beam includes earth beam steel reinforcement cage and earth beam concrete layer, is fixed with the columnar ring at concrete cushion and erects the muscle cage, and this ring erects the muscle cage and runs through behind concrete cushion cap and brick basis, runs through again in earth beam steel reinforcement cage, and is together fixed with earth beam steel reinforcement cage to upwards extend to on the floorpan.
Preferably, a locating plate is fixed on the upper side of the ground beam reinforcement cage, a through hole is formed in the middle of the locating plate, and the ring vertical reinforcement cage passes through the through hole.
Preferably, the ring vertical rib cage comprises a plurality of vertical ribs and a plurality of layers of ring ribs, and each ring rib is respectively sleeved and fixed on the outer sides of the plurality of vertical ribs.
Preferably, a ground steel plate is fixed at the bottom of the ring vertical rib cage frame, and the ground steel plate is fixed with the concrete cushion.
Preferably, a layer of foundation reinforcement mesh is laid between the concrete cushion and the concrete bearing platform.
Preferably, the lowermost ring vertical rib cage is based, and each ring vertical rib cage is further connected in an upward extending manner through a connecting or sleeving manner.
The utility model has the beneficial effects that: the improved scheme effectively solves the problems of low connection strength between the bottom beam and the structural column and low construction efficiency in the existing building construction through the innovative structural design, thereby improving the performance, safety and maintainability of the whole building structure.
Connection strength promotes: through the design of introducing ring vertical bar cage and lower margin steel sheet, joint strength obtains showing and promotes. The welding and fixing modes can enable the connection between the structural columns and the bottom beams to be firmer, so that the stability and the bearing capacity of the whole structure are improved.
The construction efficiency is improved: the prefabricated ring vertical rib cage frame and the foundation steel plate are adopted, so that the welding and assembling work on site is reduced, the construction process is simplified, the construction period is shortened, and the labor cost is reduced.
Structural stability is enhanced: the vertical fixation of the structural column is realized at the initial stage of construction, the rooting effect is similar to that of the structural column, the root stability of the structural column is improved, and the structural column is favorable for resisting external load, earthquake and other forces.
Safety improvement: the improvement of the connection strength and the enhancement of the structural stability can obviously improve the overall safety of the building. The risks of structural instability and connection breakage are reduced, and the occurrence probability of accidents is reduced.
The construction difficulty is reduced: the prefabricated components and designs are used, so that on-site processing and adjustment are reduced, the technical difficulty in the construction process is reduced, and the possible construction problems are reduced.
Drawings
FIG. 1 is an external schematic view of a ground beam column structure;
FIG. 2 is a schematic view of the internal structure of the ground beam column structure of FIG. 1;
FIG. 3 is a schematic view of the external appearance of the ring rib cage;
fig. 4 is a schematic view of the structure of the steel plate at the bottom of the ring rib cage.
Reference numerals in the drawings: a concrete cushion layer 1; a concrete bearing platform 2; a brick base 3; a ground beam reinforcement cage 4; a ring rib cage 5; a ground foot steel plate 6; a steel plate fixing hole 7; a positioning plate 8; a ground beam concrete layer 9; a base reinforcing mesh 10; a welding point 11; vertical ribs 51; the annular rib 52.
Description of the embodiments
The utility model will be further described with reference to the drawings and examples.
Example 1: the utility model provides a fast-assembling ground beam column structure, carries out the institutional advancement to the low and problem of efficiency of construction low of beam column connection structure intensity in the present to current building construction process, and this scheme includes from bottom to top in proper order including concrete cushion 1, concrete cap 2, brick basis 3 and floor beam, wherein, the floor beam includes floor beam reinforcement cage 4 and floor beam concrete layer 9.
Specifically, as shown in fig. 1 and 2, a ring vertical bar cage 5 is fixed to the concrete cushion 1, and as shown in fig. 3, the ring vertical bar cage 5 includes a plurality of vertical bars 51 and a plurality of layers of ring bars 52, and each ring bar 52 is respectively sleeved and fixed to the outer sides of the plurality of vertical bars 51. As shown in fig. 4, a foundation steel plate 6 is fixed at the bottom of the ring vertical bar cage 5 and is fixed with the concrete cushion 1, specifically, the vertical bars of the ring vertical bar cage 5 (structural column) are welded with the column foot plate, and a welding point 11 is arranged between the bottom of each vertical bar and the foundation steel plate 6.
The ring vertical bar cage frame 5 penetrates through the concrete bearing platform 2 and the brick foundation 3, penetrates through the ground beam reinforcement cage 4 and is fixed with the ground beam reinforcement cage 4. Specifically, be fixed with locating plate 8 in the roof beam steel reinforcement cage 4 upside, locating plate 8 middle part is provided with the through-hole, and the ring erects muscle cage 5 and passes through this through-hole.
Fig. 4 shows that the steel plate fixing hole 7 is formed in the center of the foundation steel plate 6, the embedded part is arranged on the concrete cushion 1, the steel plate fixing hole 7 is sleeved on the outer side of the embedded part, or the expansion wires are driven into the concrete cushion 1 through the steel plate fixing hole 7, so that the foundation steel plate 6 and the concrete cushion 1 are firmly fixed together, and the annular vertical rib cage 5 and the concrete cushion 1 are vertically fixed together. Fig. 4 shows a finished steel toe plate secured to the mat layer with 14 x 150 nails in accordance with the structural coordinates.
Fig. 2 shows that a layer of foundation reinforcement mesh 10 can also be laid between the concrete cushion 1 and the concrete cap 2.
Based on the structure, the ring vertical rib cage frame 5 and the concrete cushion layer 1 can be ensured to be in a vertical fixing state at the initial stage of construction, so that the structural column has rooting effect, and the strength of the root of the structural column is improved. And then the concrete bearing platform 2 is formed by pouring on the foundation, so that the annular vertical rib cage 5 is positioned on the inner side of the concrete bearing platform 2. And continuously paving a brick foundation 3 on the basis of the concrete bearing platform 2 to determine the height of the bottom beam. The upper side of the brick foundation 3 is paved with a template and a ground beam reinforcement cage 4, and the ring vertical reinforcement cage 5 at the lowest section penetrates through the ground beam reinforcement cage 4 and is fixed through a locating plate. The locating plate can be welded on the upper side of the ground beam reinforcement cage 4, or the locating plate is provided with an assembly hole which is connected on the upper side of the ground beam reinforcement cage 4 through binding or bolts, and the upper section of the vertical reinforcement cage 5 is stable by using the locating plate to keep the ring. Thereby, the bottom and upper part of the ring vertical bar cage 5 are fixed to form a firm structural column shape. Based on the lowest section ring vertical rib cage 5, each section ring vertical rib cage 5 is further connected in an upward extending mode through connection or sleeving.
The implementation process of the scheme comprises the following steps:
1. preparation: detailed planning and design is first required before starting the construction. This includes determining the location, height and number of structural columns, and formulating construction sequences and steps.
2. And (3) construction of a concrete cushion layer: when the construction is started, the concrete cushion 1 is first constructed. At the fixed position of the concrete cushion 1, a ring vertical bar cage 5 is installed. The ring vertical bar cage 5 comprises a plurality of vertical bars 51 and a plurality of layers of ring bars 52, the bottoms of the ring vertical bars are welded with the foundation steel plates 6, and the ring vertical bars are fixed with the vertical bars through welding points 11.
3. And (3) construction of a concrete bearing platform: the ring vertical rib cage 5 penetrates through the concrete bearing platform 2 and is fixed in the concrete bearing platform. This allows the structural column to have a vertical fixation at the beginning of construction, similar to the "rooting" effect, thus enhancing the root strength of the structural column.
4. Paving a brick foundation: and continuously paving a brick foundation 3 on the concrete bearing platform 2 to determine the height of the bottom girder.
5. And (3) construction of the ground beam: above the brick foundation 3, a formwork and a girder steel reinforcement cage 4 are installed. The upper side of the ground beam reinforcement cage 4 is provided with a locating plate 8 which passes through from the central through hole, so that the ring vertical reinforcement cage 5 is fixed on the ground beam through the locating plate.
6. Pouring a ground beam concrete layer: and pouring concrete on the ground beam reinforcement cage 4 to form a ground beam concrete layer 9, and fixing the ring vertical reinforcement cage 5 and the ground beam together.
7. Connection of ring vertical rib cage: starting from the ring vertical rib cage 5 at the lowest section, each section of ring vertical rib cage 5 is connected in a section-by-section upward extending mode, and the stability of the whole structure is ensured through a connecting or sleeving mode.
8. Final adjustment and fixing: once all the ring vertical bar cages 5 are connected and fixed on the ground beam, final adjustment and inspection is performed, ensuring the perpendicularity and stability of the structural columns, including erecting the templates for the structural columns and pouring concrete to form the columns.
The advantage of this improvement scheme lies in through using innovative designs such as ring erects muscle cage, has solved the problem that current beam column connection structure intensity is low and the efficiency of construction is low. By achieving vertical fixation of the structural columns at an early stage, this solution is expected to improve the stability and load-bearing capacity of the overall structure, while also reducing the time and labor costs required for construction.
The above detailed description of the present utility model is merely illustrative or explanatory of the principles of the utility model and is not necessarily intended to limit the utility model. Accordingly, any modification, equivalent replacement, improvement, etc. made without departing from the spirit and scope of the present utility model should be included in the scope of the present utility model.

Claims (6)

1. The utility model provides a fast-assembling ground beam column structure, from bottom to top includes concrete cushion (1), concrete cushion cap (2), brick basis (3) and earth beam in proper order, and wherein the earth beam includes earth beam steel reinforcement cage (4) and earth beam concrete layer (9), its characterized in that, is fixed with columnar ring at concrete cushion (1) and erects muscle cage (5), and this ring erects muscle cage (5) run through behind concrete cushion cap (2) and brick basis (3) again, runs through in earth beam steel reinforcement cage (4), and is in the same place with earth beam steel reinforcement cage (4) are fixed to upwards extend to on the floorpan.
2. The quick-assembly ground beam column structure according to claim 1, wherein a positioning plate (8) is fixed on the upper side of the ground beam reinforcement cage (4), a through hole is formed in the middle of the positioning plate (8), and the ring vertical reinforcement cage (5) passes through the through hole.
3. The quick-assembly ground beam column structure according to claim 1, wherein the ring vertical rib cage (5) comprises a plurality of vertical ribs (51) and a plurality of layers of ring ribs (52), and each ring rib (52) is respectively sleeved and fixed on the outer sides of the plurality of vertical ribs (51).
4. The quick-assembly ground beam column structure according to claim 1, characterized in that a ground steel plate (6) is fixed at the bottom of the ring vertical rib cage (5), and the ground steel plate (6) and the concrete cushion (1) are fixed together.
5. The fast-assembled ground beam column structure according to claim 1, characterized in that a layer of foundation reinforcement mesh (10) is also laid between the concrete cushion (1) and the concrete cap (2).
6. The quick-assembly ground beam column structure according to claim 1, characterized in that the lowermost ring vertical rib cage (5) is based, and the ring vertical rib cages (5) of each section are further connected in an upward extending manner by connection or sleeving.
CN202322122591.7U 2023-08-08 2023-08-08 Fast-assembling ground beam column structure Active CN220598703U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322122591.7U CN220598703U (en) 2023-08-08 2023-08-08 Fast-assembling ground beam column structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322122591.7U CN220598703U (en) 2023-08-08 2023-08-08 Fast-assembling ground beam column structure

Publications (1)

Publication Number Publication Date
CN220598703U true CN220598703U (en) 2024-03-15

Family

ID=90165728

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322122591.7U Active CN220598703U (en) 2023-08-08 2023-08-08 Fast-assembling ground beam column structure

Country Status (1)

Country Link
CN (1) CN220598703U (en)

Similar Documents

Publication Publication Date Title
CN106703197A (en) Longspan multilayer anti-seismic frame structure system and construction method thereof
CN102418381B (en) Building structure system combined with steel beam and pre-tensioned prestressing superposed beam and construction method for building structure system
CN106149868A (en) Prefabricated buildings architectural structure system and assembly method thereof
CN114790757A (en) Cover-excavation top-down construction V-shaped column structure and construction method thereof
CN102966113A (en) Shallow buried steel column base and construction method thereof
CN220598703U (en) Fast-assembling ground beam column structure
CN216616975U (en) Reinforced structure with existing reinforced concrete column of space steel framework restraint
CN216920677U (en) First-layer supporting structure of large rockery outer package
CN109914616A (en) A kind of dry construction connection structure of assembling frame structural construction corner post and beam
CN115928682A (en) Modular drilling platform and construction method
CN216042835U (en) Layer adding device with light wall board for raising frame structure
CN212389051U (en) Stair connection application device made of different materials
CN210067063U (en) Connecting structure of side column or center column and beam for fabricated frame structure building
CN212426749U (en) Hybrid reinforced concrete joint section
CN209941913U (en) Assembled frame construction housing construction
CN217678621U (en) Foundation structure of standard H-shaped steel tower
CN109914614A (en) A kind of connection structure of assembling frame structural construction side column or center pillar and beam
CN111764505A (en) Connecting structure of concrete precast beam and cast-in-place column and construction method thereof
CN110016965A (en) Steel column foot connection structure
CN220504665U (en) Ectopic assembled H-shaped steel tower
CN220725378U (en) Novel assembled equivalent steel-concrete combined structure
CN220550677U (en) Profile steel concrete composite structure
CN218060396U (en) A recoverable shaped steel beam type base for elevator construction
CN113356647B (en) Double-limb overhanging type steel column system
CN216275800U (en) Face combination cross steel box girder tower crane foundation structure forever

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant