CN220563479U - Ore conveying line for mine exploitation - Google Patents
Ore conveying line for mine exploitation Download PDFInfo
- Publication number
- CN220563479U CN220563479U CN202322302231.5U CN202322302231U CN220563479U CN 220563479 U CN220563479 U CN 220563479U CN 202322302231 U CN202322302231 U CN 202322302231U CN 220563479 U CN220563479 U CN 220563479U
- Authority
- CN
- China
- Prior art keywords
- plates
- outlet pipe
- water outlet
- ore
- group
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000000428 dust Substances 0.000 claims abstract description 26
- 238000004140 cleaning Methods 0.000 claims abstract description 11
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 60
- 239000007921 spray Substances 0.000 claims description 5
- 230000005540 biological transmission Effects 0.000 claims description 4
- 230000000694 effects Effects 0.000 abstract description 4
- 238000005065 mining Methods 0.000 abstract description 4
- 238000000034 method Methods 0.000 abstract description 2
- 239000011435 rock Substances 0.000 abstract description 2
- 238000009434 installation Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009792 diffusion process Methods 0.000 description 1
- 238000005507 spraying Methods 0.000 description 1
Landscapes
- Cleaning By Liquid Or Steam (AREA)
Abstract
The utility model discloses an ore conveying line for mining, and relates to the technical field of ore mining. This mine exploitation ore transfer chain, including carrying platform, dust fall cleaning assembly and adjusting part, the inside of carrying the platform is equipped with the drive belt, and dust fall cleaning assembly locates carry bench, dust fall cleaning assembly includes first outlet pipe and second outlet pipe, and the drive belt is located between first outlet pipe and the second outlet pipe. This mine exploitation ore transfer chain can be in the in-process of carrying the ore, wets the ore, avoids like this when carrying that the ore rocks and produces the condition of dust, can have certain dust fall effect to can wash the conveyer belt after carrying the ore through the second outlet pipe, avoid remaining the conveying effect that the spot influences follow-up ore on the conveyer belt, can also carry out the slope with the conveyer belt and handle, can increase the application scope of conveyer belt like this as required, improve the practicality of device.
Description
Technical Field
The utility model relates to the technical field of ore exploitation, in particular to an ore conveying line for mine exploitation.
Background
The utility model discloses a mine exploitation ore conveyor of publication No. CN218144073U, be linked together through inlet tube and outside water pump, can carry the water source to the inlet tube, and the inside water source of inlet tube passes through the inside of shunt tubes entering water storage chamber, so that follow-up ore dust fall to conveying belt body surface bottom, can carry the ore when the conveying belt body rotates, and when the conveying belt body rotates, can drive the front and back both ends of interior rotary drum through the meshing of drive rack with preceding driven rack and back driven rack and rotate simultaneously, and when interior rotary drum rotates, the water source of water storage intracavity portion passes through the shower nozzle blowout, and then can carry out dust fall operation to the ore of piling up at conveying belt body surface bottom.
According to the ore conveying device for mining, although dust fall treatment can be carried out on ores during ore conveying, dust diffusion is reduced, when ores are conveyed, the conveying angle of the conveying belt is difficult to adjust according to the on-site conveying environment, and when the conveying belt is required to incline, the lifting treatment is required to be carried out at the bottom of the device, so that the operation is not only convenient for workers, but also the stability of the conveying belt is poor after the conveying belt is lifted by using external articles, and the ores are inconvenient to convey.
Disclosure of Invention
The utility model aims to provide a mine exploitation ore conveying line which can solve the problem of adjusting the conveying angle of a conveying belt according to the on-site conveying environment.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the ore conveying line for mining comprises a conveying table, a dust fall cleaning assembly and an adjusting assembly, wherein a transmission belt is arranged in the conveying table;
the dust fall cleaning assembly is arranged on the conveying table and comprises a first water outlet pipe and a second water outlet pipe, and the driving belt is positioned between the first water outlet pipe and the second water outlet pipe;
the adjusting component is arranged on the conveying table, the adjusting component comprises fixed transverse plates, electric push rods and a fixed table, the electric push rods are fixedly arranged at the top of the fixed table, the number of the fixed transverse plates is two, one side of one group of fixed transverse plates is fixedly arranged with one side of the conveying table, the free ends of the electric push rods are hinged with the bottoms of one group of fixed transverse plates, and the electric push rods are used for driving the conveying table and the transmission belt to incline.
Preferably, the dust fall cleaning assembly further comprises side plates, support plates and connecting elbows, wherein the side plates are fixedly installed on the front side and the rear side of the conveying table, the number of the side plates is four, each two side plates are two groups, the top of one group of side plates and the bottom of the other group of side plates are fixedly installed with the support plates, the number of the support plates is four, each two support plates are one group, the opposite surface of one group of support plates is fixedly installed with a first water outlet pipe, the opposite surface of the other group of support plates is fixedly installed with a second water outlet pipe, the rear sides of the two support plates are fixedly installed with the connecting elbows, one end of each connecting elbows extends to the inside of the second water outlet pipe, and the other end of each connecting elbows extends to the inside of the first water outlet pipe.
Preferably, the adjusting component further comprises two groups of fixing plates fixedly arranged at the top of the fixing table, two groups of fixing rods are fixedly arranged on adjacent side walls of the two groups of fixing plates, sliding plates are slidably arranged on the outer walls of the two groups of fixing rods, the hinge plates are hinged to the tops of the sliding plates, the number of the fixing transverse plates is two, the tops of one group of fixing transverse plates are fixedly arranged at the bottoms of the conveying table, and the tops of the hinge plates are hinged to the bottoms of one group of fixing transverse plates.
Preferably, the bottom of the first water outlet pipe and the top of the second water outlet pipe are fixedly provided with spray heads, and the spray heads are communicated with the interiors of the first water outlet pipe and the second water outlet pipe.
Preferably, the outer wall of the connecting elbow is fixedly provided with a water inlet pipe, and the water inlet pipe is communicated with the inside of the connecting elbow.
Preferably, the number of the electric push rods is two, and the electric push rods are symmetrically arranged, so that the stability of the conveying table during lifting can be improved.
Compared with the prior art, the utility model has the beneficial effects that: this mine exploitation ore transfer chain uses through the cooperation of curb plate, the backup pad, first outlet pipe, second outlet pipe and connecting return bend, can wet the ore at the in-process of carrying the ore, avoid like this when carrying, the ore rocks and produces the condition of dust, can have certain dust fall effect, and can wash the conveyer belt after carrying the ore through the second outlet pipe, it influences the conveying effect of follow-up ore to avoid remaining the spot on the conveyer belt, in the cooperation through the fixed plate, the dead lever, the articulated slab, fixed diaphragm, electric putter and fixed station use, can carry out the tilting treatment with the conveyer belt, can increase the application scope of conveyer belt like this as required, the practicality of improvement device.
Drawings
FIG. 1 is a perspective view of the present utility model;
FIG. 2 is a top view of the present utility model;
fig. 3 is a side view of the present utility model.
In the figure: 1. a conveying table; 2. a transmission belt; 3. a dust fall cleaning assembly; 301. a side plate; 302. a support plate; 303. a first water outlet pipe; 304. a second water outlet pipe; 305. a connecting bent pipe; 4. an adjustment assembly; 401. a fixing plate; 402. a fixed rod; 403. a hinged plate; 404. fixing the transverse plate; 405. an electric push rod; 406. a fixed table.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1-3, the present utility model provides a technical solution: the utility model provides a mine exploitation ore transfer chain, including carrying platform 1, dust fall washs subassembly 3 and adjusting part 4, the inside of carrying platform 1 is equipped with drive belt 2, dust fall washs subassembly 3 locates on carrying platform 1, dust fall washs subassembly 3 and includes first outlet pipe 303 and second outlet pipe 304, drive belt 2 is located between first outlet pipe 303 and the second outlet pipe 304, adjusting part 4 locates on carrying platform 1, adjusting part 4 includes fixed diaphragm 404, electric putter 405 and fixed platform 406, the top fixed mounting of fixed platform 406 has electric putter 405, the quantity of fixed diaphragm 404 is two sets of, one side of a set of fixed diaphragm 404 and one side fixed mounting of carrying platform 1, electric putter 405's free end articulates the installation with the bottom of one set of fixed diaphragm 404 wherein, electric putter 405 is used for driving carrying platform 1 and drive belt 2 to incline.
Further, the dust fall cleaning assembly 3 further comprises side plates 301, supporting plates 302 and connecting elbows 305, the side plates 301 are fixedly installed on the front side and the rear side of the conveying table 1, the number of the side plates 301 is four, each two side plates 301 are two, the top of one group of side plates 301 and the bottom of the other group of side plates 301 are fixedly installed with the supporting plates 302, the number of the supporting plates 302 is four, each two supporting plates 302 are one, the opposite surfaces of one group of supporting plates 302 are fixedly installed with a first water outlet pipe 303, the opposite surfaces of the other group of supporting plates 302 are fixedly installed with a second water outlet pipe 304, the rear sides of the two supporting plates 302 are fixedly installed with the connecting elbows 305, one end of the connecting elbows 305 extends to the inside of the second water outlet pipe 304, the other end of the connecting elbows 305 extends to the inside of the first water outlet pipe 303, the bottom of the first water outlet pipe 303 and the top of the second water outlet pipe 304 are fixedly installed with spray heads, the outer walls of the connecting elbows 305 are fixedly installed with the water inlet pipes 303, the water inlet pipes are fixedly communicated with the inside of the connecting elbows 303, the first water outlet pipe 302 can be conveyed in the conveying belt, the second water outlet pipe 304 can be prevented from being wet, dust can be prevented from being blown down by the ore, and dust can be prevented from being washed by the second water outlet pipe 2, and the dust can be conveyed by the following the conveying belt 2.
Still further, adjusting part 4 still includes 401402 and articulated slab 403, the top fixed mounting of fixed station 406 has two sets of fixed plates 401, two sets of fixed levers 402 are installed to the adjacent lateral wall fixed mounting of two sets of fixed plates 401, the outer wall slidable mounting of two sets of fixed levers 402 has the sliding plate, the articulated slab 403 of installing in top of sliding plate, the quantity of fixed diaphragm 404 is two sets of, the top of one set of fixed diaphragm 404 and the bottom fixed mounting of delivery table 1, the top of articulated slab 403 and the bottom articulated installation of one set of fixed diaphragm 404, the quantity of electric putter 405 is two sets of and be the symmetry setting, control electric putter 405, electric putter 405 starts can drive delivery table 1 one side and rise, can carry out the tilting treatment with drive belt 2, like this can increase the application scope of drive belt 2 as required, the practicality of device is improved.
Working principle: when the device is used, the electric push rod 405 is controlled firstly, the electric push rod 405 is started to drive one side of the conveying table 1 to ascend, then after the conveying table 1 and the driving belt 2 are adjusted to a proper angle, the water inlet pipe on the connecting elbow 305 is connected with water conveying elements such as a water pump, the water is started to enter the connecting elbow 305 through the water inlet pipe, the water flows into the first water outlet pipe 303 and the second water outlet pipe 304 through the connecting elbow 305, the spraying heads are sprayed out through the first water outlet pipe 303 and the second water outlet pipe 304, the ore is placed on the driving belt 2, the driving belt 2 is controlled to start to convey the ore, when the ore passes through the lower part of the first water outlet pipe 303, the first water outlet pipe 303 can wet the ore, dust is large when the ore is prevented from moving, and when the driving belt 2 moves to the second water outlet pipe 304, the second water outlet pipe 304 can clean the driving belt 2, and stains of the driving belt 2 are reduced.
The embodiments of the present utility model have been described in detail with reference to the accompanying drawings, but the present utility model is not limited to the above embodiments, and various changes can be made within the knowledge of one of ordinary skill in the art without departing from the spirit of the present utility model.
Claims (6)
1. The utility model provides a mine exploitation ore transfer chain which characterized in that: comprising the following steps:
a conveying table (1), wherein a transmission belt (2) is arranged in the conveying table (1);
the dust fall cleaning assembly (3) is arranged on the conveying table (1), the dust fall cleaning assembly (3) comprises a first water outlet pipe (303) and a second water outlet pipe (304), and the driving belt (2) is arranged between the first water outlet pipe (303) and the second water outlet pipe (304);
the adjusting component (4) is arranged on the conveying table (1), the adjusting component (4) comprises a fixed transverse plate (404), an electric push rod (405) and a fixed table (406), the electric push rod (405) is fixedly arranged at the top of the fixed table (406), the number of the fixed transverse plates (404) is two, one side of one group of the fixed transverse plates (404) is fixedly arranged on one side of the conveying table (1), the free end of the electric push rod (405) is hinged to the bottom of one group of the fixed transverse plates (404), and the electric push rod (405) is used for driving the conveying table (1) and the driving belt (2) to incline.
2. A mine mined ore transfer line in accordance with claim 1, wherein: the dust fall cleaning assembly (3) further comprises side plates (301), support plates (302) and connecting bent pipes (305), the side plates (301) are fixedly installed on the front side and the rear side of the conveying table (1), the number of the side plates (301) is four, each two side plates (301) are divided into two groups, the support plates (302) are fixedly installed on the top of one group of side plates (301) and the bottom of the other group of side plates (301), the number of the support plates (302) is four, each two support plates (302) are divided into one group, a first water outlet pipe (303) is fixedly installed on the opposite surface of one group of support plates (302), a second water outlet pipe (304) is fixedly installed on the opposite surface of the other group of support plates (302), the connecting bent pipes (305) are fixedly installed on the rear side of the two support plates (302), one end of each connecting bent pipe (305) extends to the inside of the second water outlet pipe (304), and the other end of each connecting bent pipe (305) extends to the inside of the first water outlet pipe (303).
3. A mine mined ore transfer line as defined in claim 2, wherein: the adjusting component (4) further comprises two groups of fixing plates (401) and hinge plates (403), wherein the tops of the fixing tables (406) are fixedly provided with two groups of fixing rods (402), the adjacent side walls of the two groups of fixing plates (401) are fixedly provided with two groups of fixing rods (402), the outer walls of the two groups of fixing rods (402) are slidably provided with sliding plates, the tops of the sliding plates are hinged with the hinge plates (403), the number of the fixing transverse plates (404) is two, the tops of one group of fixing transverse plates (404) are fixedly arranged at the bottoms of the conveying tables (1), and the tops of the hinge plates (403) are hinged with the bottoms of one group of fixing transverse plates (404).
4. A mine mined ore transfer line as defined in claim 3, wherein: the bottom of the first water outlet pipe (303) and the top of the second water outlet pipe (304) are fixedly provided with spray heads, and the spray heads are communicated with the interiors of the first water outlet pipe (303) and the second water outlet pipe (304).
5. A mine mined ore transfer line in accordance with claim 4, wherein: the outer wall of the connecting elbow pipe (305) is fixedly provided with a water inlet pipe which is communicated with the inside of the connecting elbow pipe (305).
6. A mine mined ore transfer line in accordance with claim 5, wherein: the number of the electric push rods (405) is two, and the electric push rods are symmetrically arranged.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322302231.5U CN220563479U (en) | 2023-08-26 | 2023-08-26 | Ore conveying line for mine exploitation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322302231.5U CN220563479U (en) | 2023-08-26 | 2023-08-26 | Ore conveying line for mine exploitation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN220563479U true CN220563479U (en) | 2024-03-08 |
Family
ID=90087179
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202322302231.5U Active CN220563479U (en) | 2023-08-26 | 2023-08-26 | Ore conveying line for mine exploitation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN220563479U (en) |
-
2023
- 2023-08-26 CN CN202322302231.5U patent/CN220563479U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN112792660B (en) | Automatic change bilateral edging device of glass | |
CN214235407U (en) | Cleaning equipment is used in PE tubular product production | |
CN112024522A (en) | Cleaning machine for quartz glass tube | |
CN220563479U (en) | Ore conveying line for mine exploitation | |
CN111802601A (en) | Seaweed product powdering device with disassembly-free machine cleaning function and cleaning method thereof | |
CN209665894U (en) | A kind of concrete material promotion conveying equipment | |
CN111375615B (en) | Automatic cleaning machine for heat preservation barrel | |
CN206101537U (en) | Multi -functional bubble cleaning machine | |
CN214865442U (en) | Screen glass washs drying equipment | |
CN215477927U (en) | Conveying device for quartz stone plate production and processing | |
CN212333805U (en) | Feeding mechanism of light plaster | |
CN112628782B (en) | Industrial flue gas desulfurization dust removal device and implementation method thereof | |
CN209049784U (en) | One kind having cleaning function side plate conveying device | |
CN220431657U (en) | Residue conveying device for building construction engineering | |
CN107433675B (en) | Ceramic waxing production equipment | |
CN217867096U (en) | Feeding device for steelmaking furnace | |
CN221472688U (en) | Aluminum template cleaning device for building construction | |
CN218834908U (en) | Spraying type pretreatment device for aluminum single plate | |
CN217397517U (en) | Belt line conveying system capable of being automatically cleaned | |
CN114348555A (en) | Push mechanism for pipeline production | |
CN221586886U (en) | Assembly line mechanical equipment convenient to equipment | |
CN219210985U (en) | Glass cup production belt cleaning device | |
CN213825436U (en) | Coal spraying equipment | |
CN219648152U (en) | Photovoltaic board automatic cleaning device that leaves factory | |
CN217289005U (en) | Lifting type multifunctional steel pipe spraying equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |