CN220521571U CN202322007466.1U CN202322007466U CN220521571U CN 220521571 U CN220521571 U CN 220521571U CN 202322007466 U CN202322007466 U CN 202322007466U CN 220521571 U CN220521571 U CN 220521571U
Authority
CN
China
Prior art keywords
bamboo
fixing
sliding
beam column
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322007466.1U
Other languages
Chinese (zh)
Inventor
谢智锐
黄子明
郭楠
盛叶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Tansheng Construction Engineering Co ltd
Fujian Agriculture and Forestry University
Original Assignee
Fujian Tansheng Construction Engineering Co ltd
Fujian Agriculture and Forestry University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Tansheng Construction Engineering Co ltd, Fujian Agriculture and Forestry University filed Critical Fujian Tansheng Construction Engineering Co ltd
Priority to CN202322007466.1U priority Critical patent/CN220521571U/en
Application granted granted Critical
Publication of CN220521571U publication Critical patent/CN220521571U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a combined beam column of recombined bamboo and concrete, which comprises: mix and drench the earth pillar, mix and drench four supporting shoe of fixed surface fixedly connected with of earth pillar, the surface of four supporting shoe is all overlapped and is equipped with fixed cover, mix and drench the surface cover of earth pillar and be equipped with heavy bamboo cover, one side of heavy bamboo cover is provided with heavy bamboo board, positioning assembly includes two constant head tanks and two locating pieces, and two constant head tanks are all offered in the inside of supporting shoe, and two locating pieces sliding connection are in the inside of constant head tank respectively. The utility model provides a combined beam column of recombined bamboo and concrete, which is characterized in that after a fixing sleeve is sleeved on the surface of a supporting block, a positioning assembly is driven to move to a proper position, after a limiting assembly is installed, the limiting assembly is fixed between the fixing sleeve and the supporting block, and the positioning assembly is fixed again while the limiting assembly is fixed through the fixing assembly, so that the fixing effect is improved through a double-layer fixing mode.

Description

Combined beam column of recombined bamboo and concrete
Technical Field
The utility model relates to the field of recombined bamboo beams and columns, in particular to a combined beam and column of recombined bamboo and concrete.
Background
The recombined bamboo is also called heavy bamboo, and is a new bamboo material which is formed by reorganizing and strengthening bamboo, namely, the bamboo is processed into long bamboo strips, bamboo filaments or crushed into bamboo filament bundles, and the bamboo filament bundles are dried, impregnated with glue, dried to the required water content, laid in a mould and thermally cured at high temperature and high pressure to form the section bar.
The current recombined bamboo-concrete beam column comprises: the soil main body mechanism, the clamping mechanism, the reinforcing mechanism, the connecting mechanism and the combined mechanism are arranged below the outer end of the main body mechanism, the reinforcing mechanism is arranged on the outer side of the upper end of the main body mechanism, the connecting mechanism is arranged in the main body mechanism, and the combined mechanism is arranged on the outer side of the connecting mechanism; the reinforcing mechanism comprises a mounting groove, a threaded bolt, a protruding block and reinforcing steel bars, wherein the threaded bolt is in threaded mounting at the upper end of the mounting groove, the protruding block is fixedly mounted in the mounting groove, the reinforcing steel bars are fixedly mounted at the front end of the protruding block, the cross beam and the protruding block can be tightened and reinforced through the threaded bolt, the heavy bamboo plates at the left side and the right side are reinforced and tightened through the combined rod in the combined groove, the stability of a connecting node is guaranteed, the main structure of the combined beam column is not required to be drilled during subsequent decoration, the stability of the main structure is guaranteed, and the service life of the integral structure of the combined beam column is prolonged.
However, against the factors of long-time use and wind and sun exposure, the screw bolts are loosened after rusting, so that the cross beams are loosened, the stability is reduced, and the supporting and connecting effects are reduced, so that the service life is reduced
Therefore, it is necessary to provide a composite beam column of recombined bamboo and concrete to solve the above technical problems.
Disclosure of Invention
The utility model provides a combined beam column of recombined bamboo and concrete, which solves the problem that a cross beam is loosened due to loosening after rusting occurs along with long-time use of a threaded bolt.
In order to solve the technical problems, the utility model provides a combined beam column of recombined bamboo and concrete, which comprises:
the surface of the mixed leaching soil column is fixedly connected with four supporting blocks, the surfaces of the four supporting blocks are respectively sleeved with a fixed sleeve, the surface of the mixed leaching soil column is sleeved with a heavy bamboo sleeve, and one side of the heavy bamboo sleeve is provided with a heavy bamboo plate;
the positioning assembly comprises two positioning grooves and two positioning blocks, wherein the two positioning grooves are formed in the supporting block, and the two positioning blocks are respectively and slidably connected to the inside of the positioning grooves;
the limiting assembly comprises two limiting grooves and two limiting plates, the two limiting grooves are respectively formed in the two positioning blocks and the supporting blocks, and the two limiting plates are connected in the two limiting grooves in a sliding mode;
the fixing assembly comprises four fixing holes and four fixing pins, the four fixing holes are formed in the supporting block, and the four fixing pins are respectively connected with the inside of the four fixing holes in a threaded mode.
Preferably, the fixing pin is a bolt, and the fixing hole is a threaded hole matched with the fixing pin.
Preferably, a sliding component is arranged in the heavy bamboo sleeve and comprises a sliding groove, and a sliding block is connected in the sliding groove in a sliding manner.
Preferably, the inside of sliding block is provided with stable subassembly, stable subassembly includes the stable groove, stable inslot sliding connection has stable piece.
Preferably, a fixing pad is fixedly connected to one side of the stabilizing block, and the fixing pad is made of rubber materials.
Preferably, a moving assembly is arranged in the heavy bamboo sleeve, the moving assembly comprises a moving groove, and a moving block is connected in the moving groove in a sliding manner.
Preferably, the inside of heavy bamboo board has seted up the mounting groove, the inside sliding connection of mounting groove has the movable plate.
Compared with the related art, the combined beam column of the recombined bamboo and the concrete has the following beneficial effects:
the utility model provides a combined beam column of recombined bamboo and concrete, which is characterized in that after a fixing sleeve is sleeved on the surface of a supporting block, a positioning assembly is driven to move to a proper position, after a limiting assembly is installed, the limiting assembly is fixed between the fixing sleeve and the supporting block, and the positioning assembly is fixed again while the limiting assembly is fixed through the fixing assembly, so that the fixing effect is improved through a double-layer fixing mode.
Drawings
Fig. 1 is a schematic structural view of a first embodiment of a composite beam column of a composite bamboo and concrete according to the present utility model;
FIG. 2 is an enlarged schematic view of portion A shown in FIG. 1;
FIG. 3 is a schematic view of a second embodiment of a composite beam and column made of recombined bamboo and concrete according to the present utility model
Fig. 4 is an enlarged schematic view of a portion B shown in fig. 3.
Reference numerals in the drawings: 1. mix and drench earth pillar, 2, supporting shoe, 3, fixed cover, 4, locating component, 41, constant head tank, 42, locating piece, 5, spacing subassembly, 51, spacing groove, 52, limiting plate, 6, fixed subassembly, 61, fixed orifices, 62, fixed pin, 7, heavy bamboo cover, 8, heavy bamboo board, 9, sliding subassembly, 91, sliding groove, 92, sliding block, 10, stabilizing subassembly, 101, stabilizing groove, 102, stabilizing block, 11, fixed pad, 12, moving subassembly, 121, moving groove, 122, moving block, 13, movable plate.
Detailed Description
The utility model will be further described with reference to the drawings and embodiments.
First embodiment
Referring to fig. 1 and fig. 2 in combination, fig. 1 is a schematic structural diagram of a first embodiment of a composite beam column of a composite bamboo and concrete according to the present utility model; fig. 2 is an enlarged schematic view of a portion a shown in fig. 1. A composite beam column of recombined bamboo and concrete comprising:
the concrete spraying column 1, the surface of the concrete spraying column 1 is fixedly connected with four supporting blocks 2, the surfaces of the four supporting blocks 2 are respectively sleeved with a fixed sleeve 3, the surface of the concrete spraying column 1 is sleeved with a heavy bamboo sleeve 7, and one side of the heavy bamboo sleeve 7 is provided with a heavy bamboo plate 8;
the positioning assembly 4 comprises two positioning grooves 41 and two positioning blocks 42, wherein the two positioning grooves 41 are respectively arranged in the supporting block 2, and the two positioning blocks 42 are respectively and slidably connected in the positioning grooves 41;
the limiting assembly 5 comprises two limiting grooves 51 and two limiting plates 52, the two limiting grooves 51 are respectively formed in the two positioning blocks 42 and the supporting block 2, and the two limiting plates 52 are slidably connected in the two limiting grooves 51;
the fixing assembly 6, the fixing assembly 6 includes four fixed orifices and four fixed pins, four fixed orifices all set up in the inside of supporting shoe 2, four fixed pins threaded connection respectively in the inside of four fixed orifices.
The fixing pin 62 is a bolt, and the fixing hole 61 is a threaded hole matched with the fixing pin 62.
The supporting block 2 cooperates fixed cover 3 to carry out the connection effect when supporting the junction node between a plurality of concrete drenching earth pillar 1, increases its holistic stability when increasing the aesthetic property through heavy bamboo cover 7 cooperation heavy bamboo board 8.
Positioning grooves 41 are formed in the top and the bottom of the inside of the supporting block 2, positioning blocks 42 are slidably connected in the two positioning grooves 41, the two positioning blocks 42 are fixedly connected to the top and the bottom of the inner wall of the fixed sleeve 3 respectively, two limiting grooves 51 are formed in the two positioning blocks 42, the supporting block 2 and the inside of the fixed sleeve 3, limiting plates 52 are slidably connected in the two limiting grooves 51, and the positioning blocks 42 are fixed through the limiting plates 52 after the positioning blocks 42 move to a proper position to one side in the positioning grooves 41.
The fixed orifices 61 with fixed pin 62 looks adaptation are all offered to limiting plate 52, locating piece 42, supporting shoe 2 and fixed cover 3's inside for fix locating piece 52 again in the time of fixing limiting plate 52, thereby when increasing fixed effect, because fixed pin 62 and limiting plate 52 are the cross setting, thereby make fixed pin 62 because long-time use and when the back that takes place to rust after the insolateing of blowing out, fixed cover 3 can not take place not hard up, thereby increased stability in the time of having increased fixed effect.
The working principle of the combined beam column of the recombined bamboo and the concrete provided by the utility model is as follows:
when the fixing sleeve 3 is used, the fixing sleeve 3 is sleeved on the surface of the supporting block 2, the two positioning blocks 42 are driven to move to one side in the positioning groove 41 to a proper position, the limiting plate 52 is inserted into the limiting groove 51 and then pushed to one side, so that the limiting plate 52 moves to one side in the limiting groove 51 to a proper position, and the fixing pin 62 is arranged in the fixing hole 61 to limit the limiting plate 52 and simultaneously limit the positioning blocks 42.
Compared with the related art, the combined beam column of the recombined bamboo and the concrete has the following beneficial effects:
the utility model provides a combined beam column of recombined bamboo and concrete, which is characterized in that after a fixing sleeve 3 is sleeved on the surface of a supporting block 2, a positioning component 4 is driven to move to a proper position, a limiting component 5 is installed, after the fixing sleeve 3 and the supporting block 2 are fixed, the limiting component 5 is fixed through a fixing component 6, and meanwhile, the positioning component 4 is fixed again, so that the fixing effect is improved through a double-layer fixing mode.
Second embodiment
Referring to fig. 3 and fig. 4 in combination, another composite beam and column of composite bamboo and concrete is provided according to a second embodiment of the present application. The second embodiment is merely a preferred manner of the first embodiment, and implementation of the second embodiment does not affect the implementation of the first embodiment alone.
Specifically, the second embodiment of the present application provides a composite beam column of recombinant bamboo and concrete, which is characterized in that, a composite beam column of recombinant bamboo and concrete, the inside of heavy bamboo cover 7 is provided with sliding component 9, sliding component 9 includes sliding groove 91, sliding block 92 is connected in sliding way in the inside of sliding groove 91.
The inside of the sliding block 92 is provided with a stabilizing assembly 10, the stabilizing assembly 10 comprises a stabilizing groove 101, and a stabilizing block 102 is slidably connected to the inside of the stabilizing groove 101.
One side of the stabilizing block 102 is fixedly connected with a fixing pad 11, and the fixing pad 11 is made of rubber materials.
The inside of heavy bamboo cover 7 is provided with movable assembly 12, movable assembly 12 includes removal groove 121, the inside sliding connection in removal groove 121 has movable block 122.
The inside of heavy bamboo board 8 has seted up the mounting groove, the inside sliding connection of mounting groove has movable plate 13.
Two sliding grooves 91 are formed in the heavy bamboo sleeve 7, sliding blocks 92 are slidably connected in the two sliding grooves 91, one sides of the two sliding blocks 92 are fixedly connected with one side of the heavy bamboo board 8, and the two sliding blocks are used for positioning when the heavy bamboo board 8 is installed.
The stabilizing grooves 101 are formed in the two sliding blocks 92 and the heavy bamboo sleeve 7, the stabilizing blocks 102 are slidably connected in the stabilizing grooves 101, and the stabilizing blocks 102 are driven to move to a proper position to one side in the stabilizing grooves 101 after the moving blocks 122 enter the moving grooves 121, and the sliding blocks 92 are fixed, so that the heavy bamboo boards 8 and the heavy bamboo sleeve 7 are fixed.
Four movable grooves are formed in the heavy bamboo sleeve 7, movable blocks 122 are slidably connected in the four movable grooves 121, and the four movable blocks 122 are fixedly connected to one sides of the two movable plates 13 respectively.
Two mounting grooves are formed in the heavy bamboo board 8, and movable safety 13 is connected inside the two mounting grooves in a sliding mode.
The fixed pad 11 is fixedly connected to one side of each of the plurality of stabilizing blocks 102 and used for extruding the fixed pad 11 after the movable plate 13 enters the inside of the movable groove, limiting the movable plate 13 through the elastic force of the fixed pad 11, and simultaneously increasing the friction force through the fixed pad 11 to increase the fixing effect, and simultaneously fixing the movable plate 13 through the mounting bolts under the condition of more use.
The working principle of the combined beam column of the recombined bamboo and the concrete provided by the utility model is as follows:
when the heavy bamboo sleeve 7 is used, after being sleeved on the outer side of the mixed leaching soil column 1, the heavy bamboo plate 8 is moved to one side and combined, so that after the sliding block 92 is driven to enter the sliding groove 91, the moving block 122 is driven to enter the moving groove 121 when the moving plate 13 is installed in the installation groove, the fixing pad 11 is extruded, so that after the stabilizing block 102 is driven to move to one side and enter the stabilizing groove 101, the sliding block 92 is fixed, the moving plate 13 is fixed, and the heavy bamboo plate 8 and the heavy bamboo sleeve 7 are fixed.
Compared with the related art, the combined beam column of the recombined bamboo and the concrete has the following beneficial effects:
the utility model provides a combined beam column of recombined bamboo and concrete, which is convenient to fix a heavy bamboo sleeve 7 and a heavy bamboo plate 8 by matching a sliding component 9 with a stabilizing component 10, a fixed pad 11, a moving component 12 and a moving plate 13, so that the heavy bamboo sleeve and the heavy bamboo plate 8 are convenient to install.
The foregoing description is only illustrative of the present utility model and is not intended to limit the scope of the utility model, and all equivalent structures or equivalent processes or direct or indirect application in other related technical fields are included in the scope of the present utility model.

Claims (7)

1. A composite beam column of recombined bamboo and concrete, comprising:
the surface of the mixed leaching soil column is fixedly connected with four supporting blocks, the surfaces of the four supporting blocks are respectively sleeved with a fixed sleeve, the surface of the mixed leaching soil column is sleeved with a heavy bamboo sleeve, and one side of the heavy bamboo sleeve is provided with a heavy bamboo plate;
the positioning assembly comprises two positioning grooves and two positioning blocks, wherein the two positioning grooves are formed in the supporting block, and the two positioning blocks are respectively and slidably connected to the inside of the positioning grooves;
the limiting assembly comprises two limiting grooves and two limiting plates, the two limiting grooves are respectively formed in the two positioning blocks and the supporting blocks, and the two limiting plates are connected in the two limiting grooves in a sliding mode;
the fixing assembly comprises four fixing holes and four fixing pins, the four fixing holes are formed in the supporting block, and the four fixing pins are respectively connected with the inside of the four fixing holes in a threaded mode.
2. The composite beam and column of recombined bamboo and concrete according to claim 1, wherein the fixing pin is a bolt, and the fixing hole is a threaded hole matched with the fixing pin.
3. The composite beam column of recombined bamboo and concrete according to claim 1, wherein a sliding component is arranged inside the recombined bamboo sleeve, the sliding component comprises a sliding groove, and a sliding block is connected inside the sliding groove in a sliding manner.
4. A composite beam column of recombined bamboo and concrete according to claim 3, characterized in that the interior of the sliding block is provided with a stabilizing assembly comprising a stabilizing groove, the interior of which is slidingly connected with a stabilizing block.
5. The composite beam column of recombined bamboo and concrete according to claim 4, wherein a fixing pad is fixedly connected to one side of the stabilizing block, and the fixing pad is made of rubber materials.
6. A composite beam column of recombined bamboo and concrete according to claim 3, characterized in that the interior of the heavy bamboo jacket is provided with a moving assembly comprising a moving groove, the interior of which is slidingly connected with a moving block.
7. The composite beam column of recombined bamboo and concrete according to claim 1, wherein a mounting groove is formed in the heavy bamboo plate, and a moving plate is connected to the mounting groove in a sliding manner.
CN202322007466.1U 2023-07-28 2023-07-28 Combined beam column of recombined bamboo and concrete Active CN220521571U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322007466.1U CN220521571U (en) 2023-07-28 2023-07-28 Combined beam column of recombined bamboo and concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322007466.1U CN220521571U (en) 2023-07-28 2023-07-28 Combined beam column of recombined bamboo and concrete

Publications (1)

Publication Number Publication Date
CN220521571U true CN220521571U (en) 2024-02-23

Family

ID=89924377

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322007466.1U Active CN220521571U (en) 2023-07-28 2023-07-28 Combined beam column of recombined bamboo and concrete

Country Status (1)

Country Link
CN (1) CN220521571U (en)

Similar Documents

Publication Publication Date Title
CN101851985B (en) Articulated anchor and prestress tensioning method of high strength fibre composite sheet
CN220521571U (en) Combined beam column of recombined bamboo and concrete
CN113700285A (en) Assembled steel constructs for construction support for construction
CN213412360U (en) Reinforced structure of prefabricated window mould that wafts
CN214062334U (en) Detachable deformation joint aluminum alloy template
CN211228931U (en) Basalt fiber concrete section steel combined member
CN212613920U (en) Prestressing force reinforcing apparatus
CN204826653U (en) Stupefied fixing clip of vertical back of body of aluminum mould board
CN210828432U (en) Concrete heel post later stage strengthening mechanism
CN211342975U (en) Combined grouting anchor rod made of light-cured glass fiber reinforced rib
CN112727070A (en) Steel frame GMT combined die carrier
CN215759823U (en) Back building partition wall, constructional column and bearing wall's drawknot structure
CN206913351U (en) A kind of Recombined bamboo assembly backing plate
CN219773724U (en) Reinforced structure of building structure floor
CN219196829U (en) Reinforcing and connecting device for building engineering
CN210238933U (en) Keel and keel combined structure thereof
CN216195507U (en) Steel construction is used in connection of high strength beam column
CN221219632U (en) Plastic building template
CN212613919U (en) Prestressing force reinforcing apparatus
CN219451480U (en) Combined aluminum alloy frame plastic template
CN218522228U (en) Assembled beam column node template
CN221073043U (en) Environment-friendly building curtain wall embedded part
CN220538892U (en) Firm additional strengthening of girder steel bears
CN220580510U (en) Groove square tube combined type secondary joist structure
CN212613029U (en) Connecting device for steel structure construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant