CN220504567U - Adjusting device for construction and installation of steel structure steel column - Google Patents

Adjusting device for construction and installation of steel structure steel column Download PDF

Info

Publication number
CN220504567U
CN220504567U CN202322153099.6U CN202322153099U CN220504567U CN 220504567 U CN220504567 U CN 220504567U CN 202322153099 U CN202322153099 U CN 202322153099U CN 220504567 U CN220504567 U CN 220504567U
Authority
CN
China
Prior art keywords
steel
construction
lifting
support
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322153099.6U
Other languages
Chinese (zh)
Inventor
吴艳君
张亚飞
张红民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinxiang Huifeng Steel Structure Co ltd
Original Assignee
Xinxiang Huifeng Steel Structure Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinxiang Huifeng Steel Structure Co ltd filed Critical Xinxiang Huifeng Steel Structure Co ltd
Priority to CN202322153099.6U priority Critical patent/CN220504567U/en
Application granted granted Critical
Publication of CN220504567U publication Critical patent/CN220504567U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses an adjusting device for construction and installation of a steel column with a steel structure, which belongs to the technical field of building construction and comprises a stable bottom plate, wherein a stable vertical pipe is fixedly installed on the upper surface of the stable bottom plate, a slidable lifting upright post is arranged in the stable vertical pipe, a lifting flat plate is fixedly installed on the upper surface of the lifting upright post, electric telescopic rods are fixedly installed on the left side and the right side of the lower surface of the lifting flat plate, and a lifting flat plate is fixedly installed at the output end of each electric telescopic rod. This an adjusting device for steel construction steel column construction installation drives the catch bar and removes the support through setting up electric telescopic handle and lifting flat plate and promotes movable rod and centre gripping support and drive centre gripping spring post and arc grip block and inwards remove and carry out the centre gripping fixedly to the steel construction for have better centre gripping fixed effect to the steel construction, stability when guaranteeing to adjust the steel construction that can be better has further improved the convenience of adjusting the steel construction.

Description

Adjusting device for construction and installation of steel structure steel column
Technical Field
The utility model belongs to the technical field of building construction, and particularly relates to an adjusting device for construction and installation of a steel column of a steel structure.
Background
The steel structure is a structure formed by steel materials, is one of main building structure types, mainly comprises steel beams, steel columns, steel trusses and other components made of steel sections, steel plates and the like, is light in dead weight, simple and convenient to construct and widely applied to the fields of large-scale plants, venues, super high-rise and the like; at present, the existing steel structure is generally installed by hoisting with a vehicle; the existing mounting mode of the steel structure is inconvenient, larger shaking can be generated in the mounting process, the steel structure is difficult to mount more urgently and accurately, the convenience of mounting the steel structure is reduced, and better use of people is not facilitated.
Disclosure of Invention
In order to overcome the defects in the prior art, the utility model provides the adjusting device for the construction and installation of the steel column of the steel structure, which solves the problems that the installation mode of the steel structure is inconvenient, larger shaking can be generated in the installation process, the steel structure is difficult to install more rapidly and accurately, the convenience of the installation of the steel structure is reduced, and the steel structure is not beneficial to better use of people.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides an adjusting device for steel construction steel column construction installation, includes the stable bottom plate, the last fixed surface of stable bottom plate installs stable riser, stable riser's inside is equipped with slidable lift stand, the last fixed surface of lift stand installs the lift flat board, the equal fixed mounting in left and right sides of lift flat board lower surface has electric telescopic handle, electric telescopic handle's output fixed mounting has the lifting flat board, the fixed mounting of the lower surface of lift flat board has L shape mount, the inside fixed mounting of L shape mount has elastic clamping device, the dull and stereotyped upper surface fixed mounting of lifting has the fixed bolster, the top of fixed bolster is equipped with rotatable catch bar, stable riser's surface is equipped with slidable slip sleeve, slip sleeve's medial surface fixed mounting has the installing support, the inboard of installing support is equipped with rotatable lifter, the top rotatable linking bridge that is equipped with the lower surface of lift flat board, slip sleeve's inside is run through and is pegged graft at stable riser inside locating lever.
As a further aspect of the utility model: the elastic clamping device comprises a movable support which is slidably arranged in the L-shaped fixing frame, a rotatable movable rod is arranged on the inner side of the movable support, a rotatable clamping support is arranged on the inner side of the movable rod, a clamping spring column is fixedly arranged on the inner side surface of the clamping support, and an arc-shaped clamping plate is fixedly arranged on the inner side surface of the clamping spring column.
As a further aspect of the utility model: the outer side surface of the clamping support is fixedly provided with a movable sliding block, the top of the inner wall of the L-shaped fixing frame is provided with a movable sliding groove, and the movable sliding block is in sliding connection with the movable sliding groove.
As a further aspect of the utility model: the number of the arc clamping plates is two, and friction anti-slip lines are arranged on the inner sides of the two groups of arc clamping plates.
As a further aspect of the utility model: the movable support is internally and fixedly provided with a cross sliding block, the inside of the L-shaped fixing frame is provided with a cross sliding groove, and the cross sliding block is in sliding connection with the cross sliding groove.
As a further aspect of the utility model: and the front surface of the stable vertical pipe is provided with a plurality of groups of positioning grooves, and the size of each positioning groove is matched with the size of each positioning rod.
As a further aspect of the utility model: the number of the lifting rods is two, and the lengths of the two lifting rods are eight hundred fifty millimeters.
As a further aspect of the utility model: rectangular through holes are formed in the sliding sleeve, and the sizes of the rectangular through holes are matched with the sizes of the stable vertical pipes.
Advantageous effects
Compared with the prior art, the utility model has the beneficial effects that:
this an adjusting device for steel construction steel column construction installation drives the catch bar and removes the support through setting up electric telescopic handle and lifting flat plate and promotes movable rod and centre gripping support and drive centre gripping spring post and arc grip block and inwards remove and carry out the centre gripping fixedly to the steel construction for have better centre gripping fixed effect to the steel construction, stability when guaranteeing to adjust the steel construction that can be better has further improved the convenience of adjusting the steel construction.
This an adjusting device for steel construction steel column construction installation drives lifter and linking bridge through setting up sliding sleeve along stabilizing the surface slip of riser and promote the dull and stereotyped back that reciprocates to suitable height, inserts the inside of stabilizing the riser with the locating lever through sliding sleeve and carries out the location operation for have better location effect to stable riser and lift stand, effectively improved the stability of location, help people better use.
Drawings
FIGS. 1 and 2 are schematic views of the structure of the present utility model;
FIG. 3 is a schematic view of a partial structure of the present utility model;
FIG. 4 is an exploded view of the elastic clamping device of the present utility model;
in the figure: 1. stabilizing the bottom plate; 2. stabilizing the riser; 3. lifting the upright post; 4. lifting a flat plate; 5. an electric telescopic rod; 6. lifting the flat plate; 7. an L-shaped fixing frame; 8. an elastic clamping device; 801. a movable support; 802. a moving rod; 803. a clamping bracket; 804. clamping the spring column; 805. an arc-shaped clamping plate; 9. a fixed bracket; 10. a push rod; 11. sliding the sleeve; 12. a mounting bracket; 13. a lifting rod; 14. a connecting bracket; 15. and a positioning rod.
Detailed Description
The technical scheme of the patent is further described in detail below with reference to the specific embodiments.
As shown in fig. 1-4, the present utility model provides a technical solution: the utility model provides an adjusting device for steel construction steel column construction installation, including stabilizing bottom plate 1, stabilizing bottom plate 1's upper surface fixed mounting has stable riser 2, stabilizing riser 2's inside is equipped with slidable lift stand 3, lifting plate 3's upper surface fixed mounting has lifting plate 4, lifting plate 4 lower surface's the equal fixed mounting in left and right sides has electric telescopic handle 5, electric telescopic handle 5's output fixed mounting has lifting plate 6, lifting plate 4's lower surface fixed mounting has L shape mount 7, L shape mount 7's inside fixed mounting has elastic clamping device 8, lifting plate 6's upper surface fixed mounting has fixed bolster 9, fixed bolster 9's top is equipped with rotatable catch bar 10, stabilizing riser 2's surface is equipped with slidable slide sleeve 11, slide sleeve 11's medial surface fixed mounting has installing support 12, installing support 12's inboard is equipped with rotatable lifter 13, lifting plate 13's top rotatable linking bridge 14 that is equipped with the lower surface of lifting plate 4, slide sleeve 11's inside runs through has the locating lever 15 of grafting inside stable riser 2.
The elastic clamping device 8 comprises a movable bracket 801 which is slidably arranged in the L-shaped fixing frame 7, a rotatable movable rod 802 is arranged on the inner side of the movable bracket 801, a rotatable clamping bracket 803 is arranged on the inner side of the movable rod 802, a clamping spring column 804 is fixedly arranged on the inner side of the clamping bracket 803, and an arc-shaped clamping plate 805 is fixedly arranged on the inner side of the clamping spring column 804.
Specifically, as shown in fig. 1, fig. 2 and fig. 3, the front of stable riser 2 has been seted up multiunit positioning groove, positioning groove's size and positioning rod 15's size looks adaptation, stable riser 2 positive positioning groove and positioning rod 15 mutually support, the stability of location has been improved, the quantity of lifter 13 is two sets of, the length of two sets of lifter 13 is eight hundred fifty millimeters, two sets of lifter 13 mutually support, the better lift adjustment of being convenient for, rectangular through-hole has been seted up to the inside of slip sleeve 11, rectangular through-hole's size looks adaptation with stable riser 2, the inside rectangular through-hole of slip sleeve 11 mutually support with stable riser 2, the stability of reciprocating has been improved.
Specifically, as shown in fig. 4, the outer side surface of the clamping bracket 803 is fixedly provided with a movable sliding block, the top of the inner wall of the L-shaped fixing frame 7 is provided with a movable sliding groove, the movable sliding block is in sliding connection with the movable sliding groove, the movable sliding block on the outer side surface of the clamping bracket 803 is mutually matched with the movable sliding groove on the top of the inner wall of the L-shaped fixing frame 7, the stability of movement is improved, the number of the arc clamping plates 805 is two, the inner side surfaces of the two groups of arc clamping plates 805 are respectively provided with friction anti-skid lines, the friction force of the inner side surfaces of the two groups of arc clamping plates 805 is increased, the anti-skid effect is improved, the inside of the movable bracket 801 is fixedly provided with a cross sliding groove, the inside of the L-shaped fixing frame 7 is provided with a cross sliding groove, the cross sliding block inside the movable bracket 801 is mutually matched with the cross sliding groove inside the L-shaped fixing frame 7, and the stability of movement is improved.
The working principle of the utility model is as follows:
s1, placing the device below a steel structure, controlling a sliding sleeve 11 to slide along the outer surface of a stable vertical pipe 2 to drive a lifting rod 13 and a connecting bracket 14 to push a lifting flat plate 4 to move up and down to a proper height, and inserting a positioning rod 15 into the stable vertical pipe 2 through the sliding sleeve 11 for positioning;
s2, then starting the electric telescopic rod 5, wherein the output end of the electric telescopic rod 5 drives the lifting flat plate 6 to move, the lifting flat plate 6 drives the fixed support 9 to move, the fixed support 9 drives the pushing rod 10 to move, the pushing rod 10 drives the moving support 801 to move, the moving support 801 drives the moving rod 802 to move, the moving rod 802 drives the clamping support 803 to move, the clamping support 803 drives the clamping spring column 804 to move, and the clamping spring column 804 drives the arc-shaped clamping plate 805 to move to clamp and fix the steel structure, so that the steel structure is convenient to adjust.
In the description of the present utility model, it should be noted that, unless explicitly specified and limited otherwise, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be either fixedly connected, detachably connected, or integrally connected, for example; can be mechanically or electrically connected; can be directly connected or indirectly connected through an intermediate medium, and can be communication between two elements. The specific meaning of the above terms in the present utility model can be understood by those of ordinary skill in the art in a specific case.
While the preferred embodiments of the present patent have been described in detail, the present patent is not limited to the above embodiments, and various changes may be made without departing from the spirit of the present patent within the knowledge of one of ordinary skill in the art.

Claims (8)

1. The utility model provides an adjusting device for steel construction steel column construction installation, includes stable bottom plate (1), the last fixed surface of stable bottom plate (1) installs stable riser (2), the inside of stable riser (2) is equipped with slidable lift stand (3), the last fixed surface of lift stand (3) installs lift flat board (4), its characterized in that: the lifting device is characterized in that electric telescopic rods (5) are fixedly arranged on the left side and the right side of the lower surface of the lifting flat plate (4), an lifting flat plate (6) is fixedly arranged at the output end of the electric telescopic rods (5), an L-shaped fixing frame (7) is fixedly arranged on the lower surface of the lifting flat plate (4), an elastic clamping device (8) is fixedly arranged inside the L-shaped fixing frame (7), a fixing support (9) is fixedly arranged on the upper surface of the lifting flat plate (6), a rotatable pushing rod (10) is arranged at the top of the fixing support (9), a sliding sleeve (11) is arranged on the outer surface of the stable vertical pipe (2), a mounting support (12) is fixedly arranged on the inner side of the sliding sleeve (11), a rotatable lifting rod (13) is arranged on the inner side of the mounting support (12), a connecting support (14) connected with the lower surface of the lifting flat plate (4) is rotatably arranged at the top of the lifting rod (13), and a positioning rod (15) inserted inside the stable vertical pipe (2) is penetrated inside the sliding sleeve (11).
2. The adjusting device for construction and installation of steel columns of steel structures according to claim 1, wherein: the elastic clamping device (8) comprises a movable support (801) which is slidably arranged in an L-shaped fixing frame (7), a rotatable movable rod (802) is arranged on the inner side of the movable support (801), a rotatable clamping support (803) is arranged on the inner side of the movable rod (802), a clamping spring column (804) is fixedly arranged on the inner side surface of the clamping support (803), and an arc-shaped clamping plate (805) is fixedly arranged on the inner side surface of the clamping spring column (804).
3. An adjustment device for construction installation of steel structure steel columns according to claim 2, wherein: the outer side face of the clamping support (803) is fixedly provided with a movable sliding block, the top of the inner wall of the L-shaped fixing frame (7) is provided with a movable sliding groove, and the movable sliding block is in sliding connection with the movable sliding groove.
4. An adjustment device for construction installation of steel structure steel columns according to claim 2, wherein: the number of the arc-shaped clamping plates (805) is two, and friction anti-slip lines are arranged on the inner side faces of the two groups of arc-shaped clamping plates (805).
5. An adjustment device for construction installation of steel structure steel columns according to claim 2, wherein: the movable support (801) is internally and fixedly provided with a cross slide block, the inside of the L-shaped fixing frame (7) is provided with a cross slide groove, and the cross slide block is in sliding connection with the cross slide groove.
6. The adjusting device for construction and installation of steel columns of steel structures according to claim 1, wherein: the front of the stable vertical pipe (2) is provided with a plurality of groups of positioning grooves, and the size of each positioning groove is matched with the size of each positioning rod (15).
7. The adjusting device for construction and installation of steel columns of steel structures according to claim 1, wherein: the number of the lifting rods (13) is two, and the lengths of the two lifting rods (13) are eight hundred fifty millimeters.
8. The adjusting device for construction and installation of steel columns of steel structures according to claim 1, wherein: rectangular through holes are formed in the sliding sleeve (11), and the size of each rectangular through hole is matched with the size of the stable vertical pipe (2).
CN202322153099.6U 2023-08-11 2023-08-11 Adjusting device for construction and installation of steel structure steel column Active CN220504567U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322153099.6U CN220504567U (en) 2023-08-11 2023-08-11 Adjusting device for construction and installation of steel structure steel column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322153099.6U CN220504567U (en) 2023-08-11 2023-08-11 Adjusting device for construction and installation of steel structure steel column

Publications (1)

Publication Number Publication Date
CN220504567U true CN220504567U (en) 2024-02-20

Family

ID=89865427

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322153099.6U Active CN220504567U (en) 2023-08-11 2023-08-11 Adjusting device for construction and installation of steel structure steel column

Country Status (1)

Country Link
CN (1) CN220504567U (en)

Similar Documents

Publication Publication Date Title
CN110306776B (en) Lifting platform for high-rise building elevator shaft construction
CN108673756B (en) Convenient to use's wall drilling equipment
CN220504567U (en) Adjusting device for construction and installation of steel structure steel column
CN111877719A (en) Scaffold for construction convenient to aggregate erection
CN215249006U (en) Balancing beam device with good bearing effect
CN214270147U (en) Elevator for decoration
CN114803903A (en) Plate lifting device for indoor building construction
CN211873779U (en) Climb spacing safety lock of frame
CN211691352U (en) Bearing frame for building construction
CN112941515A (en) Compact etching machine of small-size metal convenient to height-adjusting
CN216731480U (en) Oil pump combination frock
CN220686703U (en) Clamping assembly and hanging basket for building construction
CN218819524U (en) A gallows with guiding mechanism
CN220451471U (en) Support for assembly wall
CN219751637U (en) Part hoisting jig convenient to install
CN217316013U (en) Multifunctional movable ceiling drilling tool
CN221662491U (en) Fire control pipeline auxiliary construction device
CN220951029U (en) Electric installation hydraulic lifting device
CN220113153U (en) Hand-operated clamp for machining mechanical parts
CN216971886U (en) Suspension device for electric power erection
CN221723779U (en) Automatic locking fixed bolster
CN221321675U (en) Construction platform
CN216426532U (en) Movable overhaul hoisting frame
CN215830026U (en) Partition wall girder steel optimizes construction equipment in a core section of thick bamboo elevator
CN219562866U (en) Coupling assembling for swivel bearing

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant