CN220414800U - Auxiliary pile is last to set up installation work platform - Google Patents

Auxiliary pile is last to set up installation work platform Download PDF

Info

Publication number
CN220414800U
CN220414800U CN202322054563.6U CN202322054563U CN220414800U CN 220414800 U CN220414800 U CN 220414800U CN 202322054563 U CN202322054563 U CN 202322054563U CN 220414800 U CN220414800 U CN 220414800U
Authority
CN
China
Prior art keywords
auxiliary pile
welded
connecting plate
base block
platform according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322054563.6U
Other languages
Chinese (zh)
Inventor
刘平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHEC Dong Meng Engineering Co Ltd
Original Assignee
CCCC SHEC Dong Meng Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHEC Dong Meng Engineering Co Ltd filed Critical CCCC SHEC Dong Meng Engineering Co Ltd
Priority to CN202322054563.6U priority Critical patent/CN220414800U/en
Application granted granted Critical
Publication of CN220414800U publication Critical patent/CN220414800U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model relates to the technical field of auxiliary pile pouring, and discloses an installation work platform arranged on an auxiliary pile. This set up installation work platform on the auxiliary pile, add the track through the rail main part inboard at installation platform, then install movable assembly fixed on the track, make movable assembly can take shielding assembly to slide along the rail main part, shielding assembly can assemble simultaneously, can install a plurality of movable assemblies and shielding assembly on the track as required, shelter from the position that needs to shelter from to work platform, can shelter from for constructor and construction equipment when meetting sleet weather, can shelter from sunshine simultaneously in high temperature weather, reduce sunshine and to constructor and construction equipment's adverse effect, movable assembly and shielding assembly's installation also very simple swift.

Description

Auxiliary pile is last to set up installation work platform
Technical Field
The utility model relates to the technical field of auxiliary pile pouring, in particular to an installation operation platform arranged on an auxiliary pile.
Background
In the construction process of large projects, the auxiliary piles are simply poured, so that the auxiliary piles are widely applied in the construction processes of electric power, water conservancy, buildings, bridges and the like, when the auxiliary piles are poured, surrounding pouring platforms are built, then the auxiliary piles are poured, the pouring process is carried out on the operation platform, the traditional installation platform is an open-air structure, the construction environment is greatly influenced by natural environment, when severe weather (such as continuous rainfall, strong sunlight, hail and the like) is met, the construction process is influenced by the environment, and meanwhile, the physical health and the working efficiency of constructors are negatively influenced when constructors are exposed to the severe environment.
Disclosure of Invention
(one) solving the technical problems
Aiming at the defects of the prior art, the utility model provides an installation operation platform arranged on an auxiliary pile, which has the advantages of rain shielding, snow, sunlight, wind, simplicity in installation and the like, and solves the problem that the construction platform is easily influenced by natural environment.
(II) technical scheme
In order to achieve the purposes of shielding rain, snow, sunlight and wind and simple installation, the utility model provides the following technical scheme:
an auxiliary pile is provided with an installation operation platform, which comprises a fence main body, a track, a movable assembly and a shielding assembly;
the movable assembly comprises a base plate, spring rods are welded and fixed at the left end and the right end of the base plate, two L-shaped plug-in posts are welded and fixed at the front of the base plate, a threaded telescopic rod is welded and fixed at the back of the base plate, and rollers are connected to the upper end and the lower end of each spring rod through shafts in a rotating mode;
the shielding assembly comprises a connecting plate, four first plugging columns are welded at the top of the connecting plate, a connecting base block is plugged at the top of the connecting plate through the four first plugging columns welded on the connecting plate, and a telescopic shielding plate is fixedly clamped at the top of the connecting base block.
As a preferable technical scheme of the utility model, the upper side and the lower side of the spring rod are provided with a section of spring structure, and the movable assembly can be firmly fixed on the track under the interaction of the spring structure and the threaded telescopic rod.
As a preferable technical scheme of the utility model, the L-shaped plug-in column is of an L-shaped structure and is used for plugging in the connecting plate.
As a preferable technical scheme of the utility model, the bottom of the connecting plate is provided with two first plug holes, and the two first plug holes can fix the connecting plate with the substrate in a plug manner through two L-shaped plug posts welded on the front surface of the substrate.
As a preferable technical scheme of the utility model, the bottom surface of the connecting base block is provided with four second plug holes, and the four second plug holes are used for being plugged with the four first plug posts.
As a preferable technical scheme of the utility model, a protrusion is arranged at the back side end of the bottom surface of the connecting base block, a through hole in the front-back direction is arranged at the lower end of the protrusion, and a bolt is inserted into the through hole.
As a preferable technical scheme of the utility model, a bolt hole is formed on the contact surface of the fence main body and the protrusion on the connecting base block, the bolt hole is used for inserting a bolt, and the bolt is inserted into the bolt hole of the fence main body after passing through the through hole of the connecting base block, so that the shielding assembly is prevented from tilting forwards.
As a preferable technical scheme of the utility model, the installation directions of two adjacent telescopic shielding plates are opposite, and the two adjacent telescopic shielding plates can be mutually clamped and fixed through a sleeve clamping structure.
(III) beneficial effects
Compared with the prior art, the utility model provides an auxiliary pile provided with an installation operation platform, which has the following beneficial effects:
this set up installation work platform on the auxiliary pile, add the track through the rail main part inboard at installation platform, then install movable assembly fixed on the track, make movable assembly can take shielding assembly to slide along the rail main part, shielding assembly can assemble simultaneously, can install a plurality of movable assemblies and shielding assembly on the track as required, shelter from the position that needs to shelter from to work platform, can shelter from for constructor and construction equipment when meetting sleet weather, can shelter from sunshine simultaneously in high temperature weather, reduce sunshine and to constructor and construction equipment's adverse effect, movable assembly and shielding assembly's installation also very simple swift.
Drawings
FIG. 1 is a schematic view of an assembled structure of the present utility model;
FIG. 2 is a schematic view of a part of the structure of the present utility model.
FIG. 3 is a schematic view of the movable assembly structure of the present utility model.
Fig. 4 is a schematic side view of a partial structure of the present utility model.
Fig. 5 is a schematic side view of the utility model in a side view.
In the figure: 1. a connection base block; 2. a plug pin; 3. a first plug-in column; 4. a connecting plate; 5. a spring rod; 6. a threaded telescopic rod; 7. a fence body; 8. a roller; 9. a track; 10. an L-shaped plug-in column; 11. a substrate; 12. a telescopic shielding plate.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
In the description of the present utility model, it should be understood that the terms "center," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," and the like indicate orientations or positional relationships based on the orientation or positional relationships shown in the drawings, merely to facilitate describing the present utility model and simplify the description, and do not indicate or imply that the devices or elements referred to must have a specific orientation, be configured and operated in a specific orientation, and thus should not be construed as limiting the present utility model.
In the description of the present utility model, it should be noted that, unless explicitly specified and limited otherwise, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be either fixedly connected, detachably connected, or integrally connected, for example; can be directly connected or indirectly connected through an intermediate medium, and can be communication between two elements. The specific meaning of the above terms in the present utility model will be understood in specific cases by those of ordinary skill in the art.
Referring to fig. 1-5, an auxiliary pile is provided with an installation work platform, which comprises a fence main body 7, a track 9, a movable component and a shielding component.
The movable assembly comprises a base plate 11, spring rods 5 are welded and fixed at the left end and the right end of the base plate 11, two L-shaped plug-in posts 10 are welded and fixed in front of the base plate 11, a threaded telescopic rod 6 is welded and fixed at the back of the base plate 11, and idler wheels 8 are connected to the upper end and the lower end of the two spring rods 5 through shaft rotation.
The shielding assembly comprises a connecting plate 4, four first plugging columns 3 are welded at the top of the connecting plate 4, a connecting base block 1 is plugged at the top of the connecting plate 4 through the four first plugging columns 3 welded on the connecting plate 4, and a telescopic shielding plate 12 is fixedly clamped at the top of the connecting base block 1.
In this embodiment, the upper and lower sides of the spring rod 5 are provided with a section of spring structure, and under the interaction of the spring structure and the threaded telescopic rod 6, the movable assembly can be firmly fixed on the track 9.
In this embodiment, the L-shaped plugging post 10 has an L-shaped structure for plugging the connecting plate 4.
In this embodiment, two first plugging holes are formed at the bottom of the connecting plate 4, and the two first plugging holes can plug and fix the connecting plate 4 with the substrate 11 through two L-shaped plugging posts 10 welded on the front surface of the substrate 11.
In this embodiment, the bottom surface of the connection base block 1 is provided with four second plugging holes, and the four second plugging holes are used for plugging with the four first plugging columns 3.
In this embodiment, a protrusion is provided at the bottom surface of the connection base block 1 near the back surface, a through hole in the front-back direction is provided at the lower end of the protrusion, and a plug pin 2 is inserted into the through hole.
In this embodiment, a bolt hole is formed on the contact surface between the fence body 7 and the protrusion located on the connection base block 1, and the bolt hole is used for inserting the bolt 2, and the bolt 2 is inserted into the bolt hole of the fence body 7 after passing through the through hole of the connection base block 1, so as to prevent the shielding component from tilting forward.
In this embodiment, the installation directions of the two adjacent telescopic shielding plates 12 are opposite, and the two adjacent telescopic shielding plates 12 can be mutually clamped and fixed through the sleeve clamping structure.
Working principle: firstly, the track 9 is fixedly arranged on the inner side of the fence main body 7, the upper fence main body 7 and the lower fence main body 7 of the movable assembly are respectively clamped into the upper connecting base block 1 and the lower connecting base block 1, the movable assembly is moved to a position to be shielded, then the threaded telescopic rod 6 is stretched, the upper end and the lower end of the threaded telescopic rod 6 are tightly propped against the connecting base block 1, the connecting base block 1 is unfolded, the movable assembly is fixed on the connecting base block 1, then the shielding assembly is arranged on the movable assembly, the telescopic shielding plate 12 is adjusted to shield, when a plurality of shielding assemblies are needed, the shielding assemblies are additionally arranged, the installation directions of the two adjacent telescopic shielding plates 12 are opposite, and then the two adjacent telescopic shielding plates 12 are clamped and fixed through the sleeve clamping structure.
To sum up, set up installation work platform on this auxiliary pile, through adding rail 9 in installation platform's rail main part 7 inboard, then install movable assembly on rail 9 fixedly, make movable assembly can take shielding assembly to slide along rail main part 7, shielding assembly can assemble simultaneously, can install a plurality of movable assemblies and shielding assembly on rail 9 as required, shelter from the position that work platform needs to shelter from, can shelter from for constructor and construction equipment when meetting sleet weather, can shelter from sunshine simultaneously in high temperature weather still, reduce the adverse effect of sunshine to constructor and construction equipment, movable assembly and shielding assembly's installation process is also very simple swift.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1. An auxiliary pile is provided with an installation operation platform, which comprises a fence main body (7), a track (9), a movable assembly and a shielding assembly;
the method is characterized in that: the movable assembly comprises a base plate (11), spring rods (5) are welded and fixed at the left end and the right end of the base plate (11), two L-shaped inserting columns (10) are welded and fixed in front of the base plate (11), a threaded telescopic rod (6) is welded and fixed at the back of the base plate (11), and idler wheels (8) are connected at the upper end and the lower end of each spring rod (5) through shaft rotation;
the shielding assembly comprises a connecting plate (4), four first plugging columns (3) are welded at the top of the connecting plate (4), a connecting base block (1) is plugged at the top of the connecting plate (4) through the four first plugging columns (3) welded on the connecting plate (4), and a telescopic shielding plate (12) is fixedly clamped at the top of the connecting base block (1).
2. An auxiliary pile mounting platform according to claim 1, wherein: the upper side and the lower side of the spring rod (5) are respectively provided with a section of spring structure, and the movable assembly can be firmly fixed on the track (9) under the interaction of the spring structure and the threaded telescopic rod (6).
3. An auxiliary pile mounting platform according to claim 1, wherein: the L-shaped plug-in column (10) is of an L-shaped structure and is used for plugging in the connecting plate (4).
4. An auxiliary pile mounting platform according to claim 1, wherein: two first plug holes are formed in the bottom of the connecting plate (4), and the connecting plate (4) can be fixedly plugged with the base plate (11) through two L-shaped plug posts (10) welded on the front surface of the base plate (11).
5. An auxiliary pile mounting platform according to claim 1, wherein: four second plug holes are formed in the bottom surface of the connecting base block (1) and are used for being plugged with the four first plug columns (3).
6. An auxiliary pile mounting platform according to claim 1, wherein: the bottom surface of the connecting base block (1) is provided with a protrusion at the back surface end, the lower end of the protrusion is provided with a through hole in the front-back direction, and a bolt (2) is inserted in the through hole.
7. An auxiliary pile mounting platform according to claim 6, wherein: the fence body (7) is provided with a bolt hole on a contact surface protruding on the connecting base block (1), the bolt hole is used for inserting a bolt (2), and the bolt (2) is inserted into the bolt hole of the fence body (7) after passing through the through hole of the connecting base block (1) so as to prevent the shielding assembly from tilting forwards.
8. An auxiliary pile mounting platform according to claim 1, wherein: the installation directions of two adjacent (12) are opposite, and the two adjacent (12) can be mutually clamped and fixed through the sleeve clamping structure.
CN202322054563.6U 2023-08-01 2023-08-01 Auxiliary pile is last to set up installation work platform Active CN220414800U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322054563.6U CN220414800U (en) 2023-08-01 2023-08-01 Auxiliary pile is last to set up installation work platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322054563.6U CN220414800U (en) 2023-08-01 2023-08-01 Auxiliary pile is last to set up installation work platform

Publications (1)

Publication Number Publication Date
CN220414800U true CN220414800U (en) 2024-01-30

Family

ID=89641041

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322054563.6U Active CN220414800U (en) 2023-08-01 2023-08-01 Auxiliary pile is last to set up installation work platform

Country Status (1)

Country Link
CN (1) CN220414800U (en)

Similar Documents

Publication Publication Date Title
CN215290700U (en) Assembly type building sealing waterproof structure
CN220414800U (en) Auxiliary pile is last to set up installation work platform
CN203387464U (en) Supporting structure for solar-energy cell assembly
CN112511080B (en) Photovoltaic panel support capable of conveniently adjusting inclination angle
CN212002568U (en) Anti-freezing power tower for cold area
CN219420663U (en) Drainage and water guide structure of photovoltaic waterproof support
CN210195358U (en) Foldable steel structure canopy
CN214942887U (en) Photovoltaic parking shed
CN213654154U (en) Lifting type construction platform for house building engineering
CN211421922U (en) House water leakage repairing structure
CN205356243U (en) Photovoltaic array loose joint device on water
CN210597607U (en) Two-layer steel structure room easy to disassemble
CN210780634U (en) Component for connecting photovoltaic module and cable structure
CN218293039U (en) Iron tower body safety device
CN220184790U (en) Special piece for awning
CN219322037U (en) High-span power bridge
CN221031302U (en) Civil engineering construction support
CN220457316U (en) Clamping structure of photovoltaic panel
CN220798117U (en) Photovoltaic panel installing support
CN219135200U (en) Protective cover of protective pool for oil field
CN219392443U (en) Rainproof device of oblique aerial photography camera
CN220653273U (en) Stable photovoltaic panel bracket connecting piece
CN220580290U (en) Reducing adjustable steel bolt connection structure
CN212453822U (en) Swimming pool steel bounding wall structure
CN218467188U (en) Civil engineering is with folding grid of protection

Legal Events

Date Code Title Description
GR01 Patent grant