CN220395115U CN202320485771.9U CN202320485771U CN220395115U CN 220395115 U CN220395115 U CN 220395115U CN 202320485771 U CN202320485771 U CN 202320485771U CN 220395115 U CN220395115 U CN 220395115U
Authority
CN
China
Prior art keywords
wall
supporting
building construction
rod
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320485771.9U
Other languages
Chinese (zh)
Inventor
贾硕
张建伟
陈连生
丁福宁
张飞
崔鸿儒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Bureau Development and Construction Co Ltd
Original Assignee
China Construction Eighth Bureau Development and Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Bureau Development and Construction Co Ltd filed Critical China Construction Eighth Bureau Development and Construction Co Ltd
Priority to CN202320485771.9U priority Critical patent/CN220395115U/en
Application granted granted Critical
Publication of CN220395115U publication Critical patent/CN220395115U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a building construction frame which comprises a supporting table, a sleeve and a first support plate, wherein the sleeve is arranged at the top of the supporting table in a penetrating mode, the first support plate is arranged at the top of the supporting table, a clamping rod is arranged at the inner wall of the sleeve in a penetrating mode, a pull head is arranged at one end of the clamping rod, and a support block is arranged at the inner wall of the supporting table. According to the utility model, the effect of improving the working efficiency of quick installation of the building construction frame is realized by installing the pull head, the first spring and the clamping rod, the pull head is pulled to drive the first supporting rod to move, the first supporting rod is driven to move by the first supporting rod, the clamping rod is driven to open the opening by the first spring to open the opening, the clamping head is clamped into the supporting table at the moment, the pull head is loosened, the first supporting rod is driven to move by the first spring, the clamping rod is driven to move by the first supporting rod, the clamping rod is driven to move by the clamping rod to enable the clamping rod to pass through the through hole and be clamped into the first bayonet, so that the working efficiency of quick installation of the building construction frame is improved, and the function of improving the working efficiency of quick installation of the building construction frame is realized.

Description

Building construction frame
Technical Field
The utility model relates to the technical field of building construction, in particular to a building construction frame.
Background
Building construction frames are temporary building tools erected at construction sites for workers to operate and to address vertical and horizontal transport. The high-altitude construction frame is mainly used in places where interior decoration or high storey height cannot be directly constructed, mainly aims at maintenance of constructors on dry or active safety nets or peripheral safety nets, high-altitude installation components and the like, and the existing building construction frame needs to be connected and fixed by using tools when in use, and is slow to install and low in efficiency.
The existing building construction frame has the following defects:
patent document CN212002140U discloses a building construction support, including building construction supporting platform, building construction supporting platform's last fixed surface installs the protection network, and the protection network is located building construction supporting platform's all around and the protection network upwards perpendicular to building construction supporting platform, and building construction supporting platform's bottom surface is provided with the supporting leg, and the supporting leg is the cuboid structure, and the supporting leg is made by the metal, and the inside of supporting leg is hollow, and the section of supporting leg is the structure of falling U-shaped, and the supporting leg is four sets of altogether. According to the utility model, when a user arrives at the upper surface of the building construction supporting platform, the weight of the user presses the building construction supporting platform to enable the building construction supporting platform to drive the movable rod to move downwards, and at the moment, the concave clamping block fixedly connected with the bottom surface of the movable rod moves downwards to be directly above the roller to be tightly attached to the upper surface of the roller, so that the effect that the building construction support is automatically fixed when the user uses the building construction support is achieved.
The building construction support of the above publication achieves the effect of automatically fixing the building construction support when a user uses the building construction support, and the problem of slow installation efficiency of the building construction support is not considered.
In view of this, it is necessary to develop a construction work frame, and thus, the construction work frame is rapidly installed to improve work efficiency.
Disclosure of Invention
The utility model aims to provide a building construction frame, which solves the problem that the slow installation efficiency of the building construction frame is not considered in the prior art.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the building construction frame comprises a supporting table, a sleeve and a first support plate, wherein the sleeve is arranged at the top of the supporting table in a penetrating manner, and the first support plate is arranged at the top of the supporting table;
the inner wall of the sleeve is provided with a clamping rod in a penetrating manner, one end of the clamping rod is provided with a pull head, the inner wall of the supporting table is provided with a supporting block, and the outer wall of the supporting block is provided with a first bayonet;
the outer wall of supporting bench installs the support, the chuck is installed to the outer wall of support, the second extension board is installed at the top of supporting bench.
Preferably, the outer wall of the clamping rod is provided with a first supporting rod, the outer wall of the first supporting rod is provided with a first spring, and one end of the first spring is connected with the inner wall of the supporting table.
Preferably, the outer wall of first extension board runs through and installs a section of thick bamboo, and the inner wall of a section of thick bamboo runs through and installs the crank, and the threaded rod is installed to the outer wall of crank, and the thread bush is installed to the outer wall of threaded rod, and the cardboard is installed to the outer wall of thread bush, and the one end of threaded rod passes through the bearing and the outer wall connection of second extension board, and the guide bar is installed to the outer wall of first extension board, and the slide is installed to the outer wall of guide bar, and the outer wall of thread bush and the outer wall connection of slide.
Preferably, the outer wall of the bracket is provided with a supporting rod.
Preferably, the outer wall of the chuck is provided with a through hole.
Preferably, a friction pad is mounted on the outer wall of the second support plate.
Preferably, the protection pad is installed at the top of supporting bench, and the outer wall of supporting bench is equipped with the opening.
Compared with the prior art, the utility model has the beneficial effects that:
1. according to the utility model, the effect of improving the working efficiency of quick installation of the building construction frame is realized by installing the pull head, the first spring and the clamping rod, the pull head is pulled to drive the first supporting rod to move, the first supporting rod is driven to move by the first supporting rod, the clamping rod is driven to open the opening by the first spring to open the opening, the clamping head is clamped into the supporting table at the moment, the pull head is loosened, the first supporting rod is driven to move by the first spring, the clamping rod is driven to move by the first supporting rod, the clamping rod is driven to move by the clamping rod to enable the clamping rod to pass through the through hole and be clamped into the first bayonet, so that the working efficiency is improved, and the function of improving the working efficiency of quick installation of the building construction frame is realized;
2. according to the utility model, the crank, the thread sleeve and the clamping plate are arranged, so that the effect of fixing building construction materials and preventing the materials from accidentally falling and injuring people is realized, the guide rod has the function of providing a moving place for the sliding cylinder, placing the building construction materials at the first support plate, rotating the crank to drive the threaded rod to move, the threaded rod to move drives the thread sleeve to move, the thread sleeve to move drives the sliding cylinder to move, the thread sleeve to move drives the clamping plate to move, the clamping plate to move drives the building construction materials to move, and the building construction materials are contacted with the friction pad to fix the building construction materials and prevent the materials from accidentally falling and injuring people, so that the safety is improved, and the function of fixing the building construction materials and preventing the materials from accidentally falling and injuring people is realized.
Drawings
FIG. 1 is a schematic diagram of the overall structure of the present utility model;
FIG. 2 is a schematic elevational view of the present utility model;
FIG. 3 is a schematic view of the threaded rod portion of the present utility model;
FIG. 4 is a schematic view of a sleeve portion of the present utility model;
fig. 5 is a schematic view of a first support plate according to the present utility model.
In the figure: 1. a support table; 101. a protective pad; 2. a sleeve; 201. a clamping rod; 202. a pull head; 203. a support block; 204. a first bayonet; 205. a first strut; 206. a first spring; 3. a first support plate; 301. a support cylinder; 302. a crank; 303. a threaded rod; 304. a thread sleeve; 305. a guide rod; 306. a slide cylinder; 307. a clamping plate; 4. a bracket; 401. a support rod; 5. a chuck; 501. a through hole; 6. a second support plate; 601. friction pad.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
In the description of the present utility model, it should be noted that the directions or positional relationships indicated by the terms "upper", "lower", "inner", "outer", "front", "rear", "both ends", "one end", "the other end", etc. are based on the directions or positional relationships shown in the drawings, are merely for convenience of describing the present utility model and simplifying the description, and do not indicate or imply that the devices or elements referred to must have a specific direction, be configured and operated in the specific direction, and thus should not be construed as limiting the present utility model. Furthermore, the terms "first," "second," and the like, are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present utility model, it should be noted that, unless explicitly specified and limited otherwise, the terms "mounted," "provided," "connected," and the like are to be construed broadly, and may be fixedly connected, detachably connected, or integrally connected, for example; can be mechanically or electrically connected; can be directly connected or indirectly connected through an intermediate medium, and can be communication between two elements. The specific meaning of the above terms in the present utility model will be understood in specific cases by those of ordinary skill in the art.
Referring to fig. 1, 2 and 3, a building construction frame includes a supporting table 1, a sleeve 2 and a first supporting plate 3, the supporting table 1 is used for providing a place for building construction, the sleeve 2 is used for providing support for a clamping rod 201, the first supporting plate 3 is used for providing support for a supporting cylinder 301, the sleeve 2 is installed at the top of the supporting table 1 in a penetrating manner, the first supporting plate 3 is installed at the top of the supporting table 1, a support 4 is installed at the outer wall of the supporting table 1, the support 4 is used for providing support for the supporting table 1, a clamping head 5 is installed at the outer wall of the support 4, the clamping head 5 is used for facilitating connection of the supporting table 1 and the support 4, a second supporting plate 6 is installed at the top of the supporting table 1, the second supporting plate 6 is used for facilitating fixation of building construction materials, a supporting rod 401 is installed at the outer wall of the support rod 401 is used for improving stability of the building construction frame, a protection pad 101 is installed at the top of the supporting table 1, a protection pad 101 is used for providing an operator, an opening is arranged at the outer wall of the supporting table 1, and the clamping head 5 is used for facilitating clamping into the supporting table 1.
Referring to fig. 2 and 4, a clamping rod 201 is installed on the inner wall of the sleeve 2 in a penetrating manner, a pull head 202 is installed at one end of the clamping rod 201, a supporting block 203 is installed on the inner wall of the supporting table 1, a first bayonet 204 is arranged on the outer wall of the supporting block 203, a first supporting rod 205 is installed on the outer wall of the clamping rod 201, a first spring 206 is installed on the outer wall of the first supporting rod 205, one end of the first spring 206 is connected with the inner wall of the supporting table 1, a through hole 501 is formed in the outer wall of the clamping head 5, the pull head 202 is pulled to drive the first supporting rod 205 to move, the first supporting rod 205 is pulled to drive the clamping head 5 to be clamped into the supporting table 1 at the moment, the pull head 202 is released to drive the first supporting rod 205 to move by the first spring 206, the clamping rod 201 is moved to drive the clamping rod 201 to pass through the through hole 501 to be clamped into the first bayonet 204, the quick installation of the building construction frame is improved, and the quick installation of the building construction frame is improved in working efficiency is realized.
Referring to fig. 2 and 5, a support tube 301 is installed on the outer wall of the first support plate 3, a crank 302 is installed on the inner wall of the support tube 301, a threaded rod 303 is installed on the outer wall of the crank 302, a threaded sleeve 304 is installed on the outer wall of the threaded rod 303, a clamping plate 307 is installed on the outer wall of the threaded sleeve 304, one end of the threaded rod 303 is connected with the outer wall of the second support plate 6 through a bearing, a guide rod 305 is installed on the outer wall of the first support plate 3, a sliding tube 306 is installed on the outer wall of the guide rod 305, the outer wall of the threaded sleeve 304 is connected with the outer wall of the sliding tube 306, a friction pad 601 is installed on the outer wall of the second support plate 6, the guide rod 305 is used for providing a moving place for the sliding tube 306, building construction materials are placed at the first support plate 3, the crank 302 is rotated to drive the threaded rod 303 to move, the threaded rod 303 is driven to move, the threaded sleeve 304 is driven to move, the threaded sleeve 306 moves, the clamping plate 307 is driven to move, the building construction materials are contacted with the friction pad 601 to be fixed, the building construction materials are prevented from falling down accidentally, the safety of the building materials is improved, and the safety is improved, and the accidental falling of the safety of the materials is prevented.
The supporting platform 1 is used for providing a place for building construction, the sleeve 2 is used for providing support for the clamping rod 201, the first supporting plate 3 is used for providing support for the supporting cylinder 301, the support 4 is used for providing support for the supporting platform 1, the clamping head 5 is used for facilitating connection of the supporting platform 1 and the support 4, the second supporting plate 6 is used for facilitating fixation of building construction materials, the pull head 202 is pulled to drive the first supporting rod 205 to move, the first supporting rod 205 is moved to drive the first spring 206 to move, the clamping rod 201 is opened, the clamping head 5 is clamped into the supporting platform 1 at the moment, the pull head 202 is loosened to drive the first supporting rod 205 to move by the first spring 206, the clamping rod 201 is moved to drive the clamping rod 201 to move, the clamping rod 201 is clamped into the first bayonet 204 by the through hole 501, the building construction frame is quickly installed to improve working efficiency, the guide rod 305 is used for providing movement for the sliding cylinder 306, the building construction materials is placed at the first supporting plate 3, the sliding rod 302 is rotated to drive the threaded rod 306 to move, the sliding sleeve is driven by the threaded rod 307 to move, and the sliding sleeve is accidentally to move, the sliding sleeve is driven by the sliding rod 304 to move, and the sliding sleeve is prevented from moving, and the sliding sleeve 304 is accidentally to move, and the sliding sleeve is accidentally caused by the sliding sleeve is driven by the sliding rod 304 to move, and the sliding sleeve 304 is prevented from moving.
It will be evident to those skilled in the art that the utility model is not limited to the details of the foregoing illustrative embodiments, and that the present utility model may be embodied in other specific forms without departing from the spirit or essential characteristics thereof. The present embodiments are, therefore, to be considered in all respects as illustrative and not restrictive, the scope of the utility model being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (7)

1. The utility model provides a building construction frame, includes brace table (1), sleeve (2) and first extension board (3), its characterized in that: the top of the supporting table (1) is provided with a sleeve (2) in a penetrating manner, and the top of the supporting table (1) is provided with a first support plate (3);
the inner wall of the sleeve (2) is provided with a clamping rod (201) in a penetrating manner, one end of the clamping rod (201) is provided with a pull head (202), the inner wall of the supporting table (1) is provided with a supporting block (203), and the outer wall of the supporting block (203) is provided with a first bayonet (204);
the outer wall of supporting bench (1) is installed support (4), chuck (5) are installed to the outer wall of support (4), second extension board (6) are installed at the top of supporting bench (1).
2. A building construction rack according to claim 1, wherein: the outer wall of the clamping rod (201) is provided with a first supporting rod (205), the outer wall of the first supporting rod (205) is provided with a first spring (206), and one end of the first spring (206) is connected with the inner wall of the supporting table (1).
3. A building construction rack according to claim 1, wherein: the outer wall of first extension board (3) runs through and installs a section of thick bamboo (301), the inner wall of a section of thick bamboo (301) runs through and installs crank (302), threaded rod (303) is installed to the outer wall of crank (302), threaded sleeve (304) is installed to the outer wall of threaded rod (303), cardboard (307) is installed to the outer wall of threaded sleeve (304), and the one end of threaded rod (303) is passed through the bearing and is connected with the outer wall of second extension board (6), guide bar (305) is installed to the outer wall of first extension board (3), slide (306) are installed to the outer wall of guide bar (305), and the outer wall of threaded sleeve (304) is connected with the outer wall of slide (306).
4. A building construction rack according to claim 1, wherein: the outer wall of the bracket (4) is provided with a supporting rod (401).
5. A building construction rack according to claim 1, wherein: the outer wall of the clamping head (5) is provided with a through hole (501).
6. A building construction rack according to claim 1, wherein: and a friction pad (601) is arranged on the outer wall of the second support plate (6).
7. A building construction rack according to claim 1, wherein: the top of supporting bench (1) is installed protection pad (101), and the outer wall of supporting bench (1) is equipped with the opening.
CN202320485771.9U 2023-03-14 2023-03-14 Building construction frame Active CN220395115U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320485771.9U CN220395115U (en) 2023-03-14 2023-03-14 Building construction frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320485771.9U CN220395115U (en) 2023-03-14 2023-03-14 Building construction frame

Publications (1)

Publication Number Publication Date
CN220395115U true CN220395115U (en) 2024-01-26

Family

ID=89597466

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320485771.9U Active CN220395115U (en) 2023-03-14 2023-03-14 Building construction frame

Country Status (1)

Country Link
CN (1) CN220395115U (en)

Similar Documents

Publication Publication Date Title
CN220395115U (en) Building construction frame
CN112780057A (en) Climbing type building construction operation platform outside building
CN216840536U (en) Scaffold cross rod convenient to install
CN2771380Y (en) Tall building out-of-window operation safety scaffold
CN220225830U (en) Spliced low-carbon decoration curtain wall
CN221168791U (en) Detachable telescopic safety support
CN216283475U (en) Simple and convenient detection device for scaffold upright rod
CN218754694U (en) Adjustable fixing device for front beam of hanging basket support
CN221119126U (en) Construction frame for construction site
CN219739849U (en) Horizontal bridge fixing structure
CN220550842U (en) Scaffold support base
CN216840118U (en) Adjustable steel construction that building curtain used
CN220989502U (en) Quick telescopic fire control extension post
CN111515907B (en) Vertical hydroelectric set magnetic pole lower wind screen bolt dismantles auxiliary device
CN220645138U (en) Wind-proof structure of hanging basket
CN216380487U (en) Telescopic scaffold suitable for indoor use
CN220666854U (en) Adjustable construction frame
CN220868740U (en) Construction bearing frame
CN217676701U (en) Installing support device for curtain wall engineering
CN217027979U (en) Protection device for house construction
CN220080690U (en) Steel construction lower support formula assembly device
CN212562401U (en) Device for installing and overhauling air conditioner external unit of existing building
CN215212268U (en) House building curtain high altitude hanging flower basket device with safety protection function
CN216603859U (en) Safety belt hanging device for disassembling and assembling oil drilling derrick
CN215430381U (en) Indoor roof cleaning device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant