CN220394783U - Municipal administration water supply and drainage pipeline connection structure - Google Patents

Municipal administration water supply and drainage pipeline connection structure Download PDF

Info

Publication number
CN220394783U
CN220394783U CN202321518016.2U CN202321518016U CN220394783U CN 220394783 U CN220394783 U CN 220394783U CN 202321518016 U CN202321518016 U CN 202321518016U CN 220394783 U CN220394783 U CN 220394783U
Authority
CN
China
Prior art keywords
fixer
connection structure
connecting pipe
baffle
water supply
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321518016.2U
Other languages
Chinese (zh)
Inventor
赵世海
王金奎
吴光进
张慧增
颜睿敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Construction Group Co Ltd
Original Assignee
CCCC Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Construction Group Co Ltd filed Critical CCCC Construction Group Co Ltd
Priority to CN202321518016.2U priority Critical patent/CN220394783U/en
Application granted granted Critical
Publication of CN220394783U publication Critical patent/CN220394783U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sink And Installation For Waste Water (AREA)

Abstract

The utility model relates to the technical field of pipeline connection, in particular to a municipal water supply and drainage pipeline connection structure which comprises a base, wherein a left baffle and a right baffle are respectively arranged on the left side and the right side of the base, grooves are formed in the inner walls of the upper ends of the left baffle and the right baffle, a protective cover is arranged between the left baffle and the right baffle, metal blocks corresponding to the grooves are connected on the two sides of the protective cover, a fixer assembly is arranged on the upper surface of the base, an auxiliary connecting pipe is arranged in the fixer assembly, and a first connecting pipe and a second connecting pipe are respectively arranged on the left side and the right side of the auxiliary connecting pipe. Through baffle and the visor that set up in the base both sides, can protect drainage pipe's connection structure, prevent to drip the rainwater that falls from top and both sides and cause the erosion to drainage pipe's connection structure, extension drainage pipe connection structure's life reduces the cost of frequently changing drainage pipe connection structure, also can reduce the degree of difficulty of constructor when changing drainage pipe connection structure.

Description

Municipal administration water supply and drainage pipeline connection structure
Technical Field
The utility model relates to the technical field of pipeline connection, in particular to a municipal water supply and drainage pipeline connection structure.
Background
The drain pipe refers to a system composed of a pipe channel for collecting and discharging sewage, wastewater and rainwater and auxiliary facilities thereof. Including main pipes, branch pipes and pipes to the treatment plant, whether built on the street or elsewhere, should be taken as drainage pipe statistics as long as the pipes function as drainage.
With the development of cities, people are more and more dense, the water supply amount in cities is increasingly increased, the establishment of drainage pipelines is becoming increasingly important, but various problems are exposed when the drainage pipelines are connected, when the connection structure of the drainage pipelines is used for a long time, parts on the connection structure can be corroded by substances such as rainwater, the stability of the connection structure is further affected, and the corroded parts are not easy to clean, so that great difficulty is brought to constructors.
Disclosure of Invention
The utility model aims to provide a municipal water supply and drainage pipeline connecting structure so as to solve the problems in the background technology.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides a municipal administration water supply and drainage pipeline connection structure, includes the base, the base left and right sides is provided with left baffle and right baffle respectively, left side baffle and right baffle upper end inner wall are seted up flutedly, be provided with the visor between left baffle and the right baffle, the visor both sides are connected with the corresponding metal block of recess, the base upper surface is provided with the fixer subassembly, the inside auxiliary connection pipe that is provided with of fixer subassembly, auxiliary connection pipe left and right sides has first connecting pipe and second connecting pipe respectively, the inner wall connection of left side baffle front end and right baffle rear end has first pipeline load carrier and second pipeline load carrier
Preferably, the lower surface of the base is fixedly provided with four support columns, and the four support columns are arranged at four corners of the lower surface of the base in a rectangular array.
Preferably, the holder assembly is composed of a first holder, a second holder, a third holder, and a fourth holder, respectively, the first holder being opposite to the fourth holder, and the second holder being opposite to the third holder.
Preferably, the surface of the first fixer is provided with an upper connecting block, a side connecting block and a lower connecting block respectively, connecting holes are formed in the surfaces of the upper connecting block, the side connecting block and the lower connecting block, and the second fixer, the third fixer and the fourth fixer are identical to the first fixer in structure.
Preferably, six steel bars are respectively arranged at two ends of the auxiliary connecting pipe, six steel bars are distributed at one end of the auxiliary connecting pipe in a circumferential array mode, and communication grooves matched with the steel bars are formed in two ends of the first connecting pipe and the second connecting pipe.
Preferably, the first pipeline load carrier comprises dead lever and semicircle type ring, the one end fixed connection of dead lever is on the inner wall of left baffle front end, semicircle type ring connects another section at the dead lever, the second pipeline load carrier structure is unanimous with first pipeline load carrier.
Advantageous effects
The utility model provides a municipal water supply and drainage pipeline connecting structure, which has the following beneficial effects:
1. this municipal administration water supply and drainage pipeline connection structure through baffle and the visor that sets up in the base both sides, can protect drainage pipeline's connection structure, prevents to drop down from top and both sides the rainwater that comes and cause the erosion to drainage pipeline's connection structure, prolongs drainage pipeline connection structure's life, reduces the cost of frequently changing drainage pipeline connection structure, also can reduce the degree of difficulty of constructor when changing drainage pipeline connection structure simultaneously.
2. This municipal administration water supply and drainage pipeline connection structure through the first pipeline load-carrying device and the second pipeline load-carrying device that set up, can make people more convenient installation drainage pipeline connection structure, when not being connected between fixer and fixer, the load-carrying device can be used as temporary support, lets the pipeline fix the position before connecting, prevents that the pipeline from rocking the connection that influences the fixer subassembly.
Drawings
FIG. 1 is a schematic diagram of the structure of the present utility model;
FIG. 2 is a schematic view of an auxiliary connection pipe according to the present utility model;
FIG. 3 is a schematic view of a structural retainer assembly of the present utility model;
FIG. 4 is a schematic view of a structural retainer of the present utility model;
fig. 5 is a schematic view of a structural duct load carrier of the present utility model.
In the figure: 1. a base; 2. a left baffle; 3. a right baffle; 4. a groove; 5. a protective cover; 6. a metal block; 7. a holder assembly; 8. an auxiliary connection pipe; 9. a first connecting pipe; 10. a second connecting pipe; 11. a first pipe load carrier; 1101. a fixed rod; 1102. a semicircular ring; 12. a second pipe load carrier; 13. a support column; 14. a first holder; 1401. an upper connecting block; 1402. a side connecting block; 1403. a lower connecting block; 1404. a connection hole; 15. a second holder; 16. a third holder; 17. a fourth holder; 18. steel drill rod; 19. and a communicating groove.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1-5, the present utility model provides a technical solution: the utility model provides a municipal administration water supply and drainage pipeline connection structure, including base 1, base 1 left and right sides is provided with left baffle 2 and right baffle 3 respectively, and recess 4 has been seted up to left baffle 2 and right baffle 3 upper end inner wall, is provided with visor 5 between left baffle 2 and the right baffle 3, and visor 5 both sides are connected with the metal piece 6 corresponding with recess 4, and the lower surface fixed mounting of base 1 has four support columns 13, and four support columns 13 are rectangular array setting in the four corners department of base 1 lower surface. The baffle and the protective cover 5 can effectively protect the parts on the connecting structure from being corroded and infringed by the rainwater substances.
The base 1 upper surface is provided with fixer subassembly 7, and fixer subassembly 7 comprises first fixer 14, second fixer 15, third fixer 16 and fourth fixer 17 respectively, and first fixer 14 is relative with fourth fixer 17, and second fixer 15 is relative with third fixer 16, and first fixer 14 surface is provided with upper connecting block 1401, side connecting block 1402 and lower connecting block 1403 respectively, and upper connecting block 1401, side connecting block 1402 and lower connecting block 1403 surface all have seted up connecting hole 1404, and second fixer 15, third fixer 16 and fourth fixer 17 are the same with first fixer 14 structure. When four fixtures are used to fix the pipeline, the problem of leakage caused by the fact that the joint is not tightly sealed can be reduced.
The inside auxiliary connection pipe 8 that is provided with of fixer subassembly 7, auxiliary connection pipe 8 both ends are provided with six drill steel 18 respectively, and six drill steel 18 are circumference array distribution in the one end of auxiliary connection pipe 8, and the intercommunication groove 19 with drill steel 18 looks adaptation has been seted up at the both ends of first connecting pipe 9 and second connecting pipe 10, and auxiliary connection pipe 8 left and right sides has first connecting pipe 9 and second connecting pipe 10 respectively. The internal auxiliary connecting pipe 8 can further make the connection between the pipelines more compact, and reduce the occurrence of leakage to the greatest extent.
The inner walls of the front end of the left baffle plate 2 and the rear end of the right baffle plate 3 are connected with a first pipeline bearing device 11 and a second pipeline bearing device 12, the first pipeline bearing device 11 is composed of a fixed rod 1101 and a semicircular ring 1102, one end of the fixed rod 1101 is fixedly connected to the inner wall of the front end of the left baffle plate 2, the semicircular ring 1102 is connected to the other section of the fixed rod 1101, and the structure of the second pipeline bearing device 12 is identical to that of the first pipeline bearing device 11. When the fixing device is not connected with the fixing device, the bearing device can be used as a temporary support, so that the pipeline is fixed in position before connection, and the pipeline is prevented from shaking to influence the connection of the fixing device assembly 7.
Working principle: when a constructor needs to construct the drainage pipe connection structure, the steel bars 18 at the left and right sides of the auxiliary connection pipe 8 are aligned with the communication grooves 19 of the first connection pipe 9 and the second connection pipe 10, the auxiliary connection pipe 8, the first connection pipe 9 and the second connection pipe 10 are tightly connected with each other, the connected pipes are lifted to the first pipe load bearing device 11 and the second pipe load bearing device 12, the pipes are fixed, the pipes are prevented from shaking to affect the connection of the fixer assembly 7, then the first fixer 14 corresponds to the upper connection block 1401 and the lower connection block 1403 of the fourth fixer 17, the threaded rods penetrate through the connection holes 1404 of the first fixer 14 and the fourth fixer 17, the threaded rods are fixed by nuts, the corresponding connection holes 1404 of the first fixer 14 and the fourth fixer 17 are all fixed by the threaded rods and the nuts according to the steps described above, after the connection is completed, the second and third holders 15 and 16 are fixedly connected according to the method, and meanwhile, it should be noted that the side connection block 1402 of the first holder 14 corresponds to the side connection block 1402 of the second holder 15, and the upper connection block 1401 is parallel to the lower connection block 1403, and similarly, the third and fourth holders 16 and 17 are correspondingly connected according to the method, and after all the four holders are fixed by threaded rods and nuts, the whole holder assembly 7 is formed, and finally, the metal block 6 of the protective cover 5 corresponds to the grooves 4 formed on the inner walls of the left and right baffles 2 and 3, so as to protect the whole drainage pipe connection structure, avoid erosion of the drainage pipe connection structure caused by rainwater dropping from above and from both sides, prolong the service life of the drainage pipe connection structure, reduce the cost of frequently replacing the drainage pipe connection structure, meanwhile, the difficulty of constructors in replacing the drainage pipeline connecting structure can be reduced.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. Municipal administration water supply and drainage pipeline connection structure, including base (1), its characterized in that: the novel pipeline weight bearing device is characterized in that a left baffle (2) and a right baffle (3) are respectively arranged on the left side and the right side of the base (1), grooves (4) are formed in the inner walls of the upper ends of the left baffle (2) and the right baffle (3), a protective cover (5) is arranged between the left baffle (2) and the right baffle (3), metal blocks (6) corresponding to the grooves (4) are connected to the two sides of the protective cover (5), a fixer assembly (7) is arranged on the upper surface of the base (1), an auxiliary connecting pipe (8) is arranged in the fixer assembly (7), a first connecting pipe (9) and a second connecting pipe (10) are respectively arranged on the left side and the right side of the auxiliary connecting pipe (8), and a first pipeline weight bearing device (11) and a second pipeline weight bearing device (12) are connected to the inner walls of the front end of the left baffle (2) and the rear end of the right baffle (3).
2. The municipal water supply and drainage pipeline connection structure according to claim 1, wherein: four support columns (13) are fixedly arranged on the lower surface of the base (1), and the four support columns (13) are arranged at four corners of the lower surface of the base (1) in a rectangular array.
3. The municipal water supply and drainage pipeline connection structure according to claim 1, wherein: the fixer assembly (7) is respectively composed of a first fixer (14), a second fixer (15), a third fixer (16) and a fourth fixer (17), wherein the first fixer (14) is opposite to the fourth fixer (17), and the second fixer (15) is opposite to the third fixer (16).
4. A municipal water supply and drainage pipeline connection structure according to claim 3, wherein: the fixing device is characterized in that an upper connecting block (1401), a side connecting block (1402) and a lower connecting block (1403) are respectively arranged on the surface of the first fixing device (14), connecting holes (1404) are formed in the surfaces of the upper connecting block (1401), the side connecting block (1402) and the lower connecting block (1403), and the second fixing device (15), the third fixing device (16) and the fourth fixing device (17) are identical to the first fixing device (14) in structure.
5. The municipal water supply and drainage pipeline connection structure according to claim 1, wherein: six steel drills (18) are respectively arranged at two ends of the auxiliary connecting pipe (8), the six steel drills (18) are distributed at one end of the auxiliary connecting pipe (8) in a circumferential array mode, and communication grooves (19) matched with the steel drills (18) are formed in two ends of the first connecting pipe (9) and the second connecting pipe (10).
6. The municipal water supply and drainage pipeline connection structure according to claim 1, wherein: the first pipeline load bearing device (11) is composed of a fixed rod (1101) and a semicircular ring (1102), one end of the fixed rod (1101) is fixedly connected to the inner wall of the front end of the left baffle (2), the semicircular ring (1102) is connected to the other section of the fixed rod (1101), and the structure of the second pipeline load bearing device (12) is identical to that of the first pipeline load bearing device (11).
CN202321518016.2U 2023-06-14 2023-06-14 Municipal administration water supply and drainage pipeline connection structure Active CN220394783U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321518016.2U CN220394783U (en) 2023-06-14 2023-06-14 Municipal administration water supply and drainage pipeline connection structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321518016.2U CN220394783U (en) 2023-06-14 2023-06-14 Municipal administration water supply and drainage pipeline connection structure

Publications (1)

Publication Number Publication Date
CN220394783U true CN220394783U (en) 2024-01-26

Family

ID=89598370

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321518016.2U Active CN220394783U (en) 2023-06-14 2023-06-14 Municipal administration water supply and drainage pipeline connection structure

Country Status (1)

Country Link
CN (1) CN220394783U (en)

Similar Documents

Publication Publication Date Title
CN220394783U (en) Municipal administration water supply and drainage pipeline connection structure
CN102942252A (en) Combined zoology purifying cage
CN210263631U (en) Inverted triangular pipe truss
CN210423992U (en) Building pipe for building water supply and drainage pipeline
CN214424094U (en) Assembled steel construction house reinforcing apparatus
CN212896301U (en) Hydraulic engineering retaining wall drainage structures
CN211080485U (en) Municipal administration is pipeline fixing device for water supply and drainage
CN215568735U (en) Placer is used in construction of city rain sewage pipe network
CN210117279U (en) A dephosphorization denitrogenation constructed wetland device for sewage treatment
CN218931743U (en) Wastewater barrel of domestic water purifier
CN219529923U (en) Deposit-proof check valve
CN214274894U (en) Be applied to municipal administration drainage sewage pipes's underslung
CN220827867U (en) Pipeline for drainage engineering
CN220433914U (en) Assembled steel structure building
CN213061662U (en) Bridge both ends connection structure
CN212534397U (en) Double-deck drainage canal of reposition of redundant personnel of rain and sewage
CN212292999U (en) Inverted A2O process container type sewage treatment integrated equipment
CN213805754U (en) Emergent rainwater collecting system well lid
CN219491218U (en) Construction drain pipe
CN219035850U (en) Municipal administration road water supply and drainage pipeline connecting piece
CN220727423U (en) Connecting structure for municipal drainage pipe
CN219712619U (en) Municipal administration water supply and drainage pipeline connection structure
CN219732022U (en) Foundation pit supporting structure of ecological hydraulic engineering
CN220268665U (en) Municipal administration water supply and drainage pipeline strutting arrangement
CN221345474U (en) Water conservancy rapid trough

Legal Events

Date Code Title Description
GR01 Patent grant