CN220382656U - Tray type cable bridge capable of being installed rapidly - Google Patents

Tray type cable bridge capable of being installed rapidly Download PDF

Info

Publication number
CN220382656U
CN220382656U CN202320466302.2U CN202320466302U CN220382656U CN 220382656 U CN220382656 U CN 220382656U CN 202320466302 U CN202320466302 U CN 202320466302U CN 220382656 U CN220382656 U CN 220382656U
Authority
CN
China
Prior art keywords
frame body
bracket
cable bridge
plates
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320466302.2U
Other languages
Chinese (zh)
Inventor
仲明春
姜伶玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Yongjin New Material Co ltd
Original Assignee
Jiangsu Yongjin New Material Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Yongjin New Material Co ltd filed Critical Jiangsu Yongjin New Material Co ltd
Priority to CN202320466302.2U priority Critical patent/CN220382656U/en
Application granted granted Critical
Publication of CN220382656U publication Critical patent/CN220382656U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/50Reuse, recycling or recovery technologies
    • Y02W30/80Packaging reuse or recycling, e.g. of multilayer packaging

Abstract

The utility model discloses a tray type cable bridge capable of being quickly installed, which comprises a frame body and two brackets arranged at the bottom of the frame body and used for supporting the frame body, wherein the two brackets comprise vertical plates and transverse plates connected to one side of the vertical plates, the tops of the transverse plates are connected with sliding rails, and a yielding groove is formed in one side, far away from the transverse plates, of the tops of the vertical plates. According to the cable bridge, after the vertical plate is fixed through the second bolt, the frame body is pushed to slide to the bracket along the sliding rail, when the frame body is in contact with the vertical plate, the shifting plate is turned over to be turned into the abdication groove, then the first bolt is locked, the cable bridge can be fixedly installed, when the bracket is required to be separated from the frame body, the bracket is only required to slide out of the bracket after the first bolt is screwed out, the separation can be realized, the use of a large number of bolts is avoided in the whole assembly and disassembly processes, time and labor are saved, welding between the bracket and the frame body is not required, and the disassembly and the assembly are simple and quick.

Description

Tray type cable bridge capable of being installed rapidly
Technical Field
The utility model particularly relates to a tray type cable bridge capable of being installed rapidly.
Background
The cable bridge is divided into a groove type cable bridge, a tray type cable bridge, a step type cable bridge, a grid bridge and other structures, and consists of a bracket, a bracket arm, a mounting accessory and the like, and can be independently erected or laid on various buildings and pipe gallery brackets; the tray type cable bridge is the most widely applied one in petroleum, chemical industry, light industry, telecommunication and the like, has the advantages of light weight, large load, attractive appearance, simple structure, convenient installation and the like, and is suitable for the installation of power cables and the laying of control cables.
However, when the existing tray type cable bridge is actually installed, the bracket and the bracket body are often connected in a manner of welding or fixing a large number of bolts, the whole assembly process is time-consuming and labor-consuming, and the disassembly and separation during later replacement or maintenance are not facilitated, so that a plurality of inconveniences exist in use.
Therefore, it is necessary to invent a tray type cable bridge that can be quickly installed to solve the above-mentioned problems.
Disclosure of Invention
Object of the utility model
The utility model aims to provide a tray type cable bridge which can be quickly installed, after a riser is fixed through a second bolt, a frame body is pushed to slide to a bracket along a sliding rail, when the frame body is in contact with the riser, a shifting plate is turned over to be shifted into a yielding groove, then a first bolt is locked, the cable bridge can be fixedly installed, when the bracket is required to be separated from the frame body, the bracket is required to slide out of the bracket after the first bolt is screwed out, the separation can be realized, the whole assembly and disassembly processes of the tray type cable bridge avoid the use of a large number of bolts, the time and the labor are saved, the welding between the bracket and the frame body is not required, and the disassembly and the assembly are simple and quick, so that the defects in the technology are overcome.
(II) technical scheme
In order to achieve the above object, the present utility model provides the following technical solutions: a tray type cable bridge capable of being quickly installed comprises a frame body and a bracket arranged at the bottom of the frame body and used for supporting the frame body;
the bracket is provided with two brackets, each bracket comprises a vertical plate and a transverse plate connected to one side of the vertical plate, the top of the transverse plate is connected with a sliding rail, a yielding groove is formed in one side, far away from the transverse plate, of the top of the vertical plate, and a first bolt extending into the yielding groove is arranged at the top of the vertical plate;
the support body sets up to the U-shaped, and the spout of two and slide rail looks adaptations has been seted up to the bottom, the support body is close to a side wall upward extension setting of riser, and should be close to a side wall top of riser and install two dials the board, and when two dial the board upset is to the inslot of stepping down, makes dial board and riser top threaded connection through first bolt, accomplishes the installation of bracket.
Preferably, the two brackets are symmetrically distributed about the center of the frame body, and two limiting frames are mounted at the end parts of the two transverse plates of the frame body.
Preferably, the two limit frames are rectangular and are matched with the transverse plate.
Preferably, two sides of the bottom of the vertical plate are connected with inclined plates, and the top ends of the inclined plates are connected with the bottom of the transverse plate.
Preferably, a plurality of second bolts are arranged on one side, close to the transverse plate, of the two vertical plates from top to bottom, and the end parts of the second bolts penetrate through the vertical plates and extend to the other side of the vertical plates.
Preferably, a plurality of clapboards are arranged in the frame body, the clapboards are distributed at equal intervals with two side walls of the frame body, and the number of the clapboards is not less than two.
Preferably, the frame body is divided into a plurality of wire penetrating grooves by the partition plate.
Preferably, a cover plate is mounted at the top of each wire penetrating groove, and the cover plates are connected with the partition plates.
Compared with the prior art, the technical scheme of the utility model has the beneficial effects that:
according to the utility model, after the vertical plate is fixed through the second bolt, the two sliding grooves at the bottom of the frame body are aligned with the sliding rails on the bracket, the frame body is pushed to slide to the bracket along the sliding rails, when the frame body is contacted with the vertical plate, the shifting plate is turned over to be turned into the abdication groove, then the first bolt is locked, the shifting plate and the vertical plate are fixed, the bracket and the frame body are assembled into the cable bridge body for use, and meanwhile, the cable bridge is fixedly installed, when the bracket is required to be separated from the frame body, the frame body is pushed again after the first bolt is screwed out, so that the frame body slides out of the bracket along the sliding rails, the separation of the bracket and the frame body can be realized, the whole assembly and the disassembly process of the cable bridge are free from using a large number of bolts, time and labor are saved, welding between the bracket and the frame body is not required, and disassembly and assembly are simple and rapid.
Drawings
In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings that are needed in the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments described in the present utility model, and other drawings may be obtained according to these drawings for a person having ordinary skill in the art.
FIG. 1 is a schematic diagram of the overall structure of the present utility model;
FIG. 2 is a schematic view of an exploded construction of the frame and carrier of the present utility model;
FIG. 3 is a schematic view of a bracket structure according to the present utility model;
FIG. 4 is a schematic view of a frame structure according to the present utility model;
fig. 5 is an enlarged view of the structure of the portion a of fig. 1 according to the present utility model.
Reference numerals illustrate:
1 frame body, 11 spout, 12 dials board, 2 brackets, 21 riser, 22 diaphragm, 23 slide rail, 24 groove of stepping down, 25 first bolt, 3 spacing frame, 4 swash plate, 5 second bolt, 6 baffle, 7 wire through grooves, 8 apron.
Detailed Description
In order to make the technical scheme of the present utility model better understood by those skilled in the art, the present utility model will be further described in detail with reference to the accompanying drawings.
The utility model provides a tray type cable bridge capable of being quickly installed, which is shown in fig. 1-5, and comprises a frame body 1 and a bracket 2 arranged at the bottom of the frame body 1 and used for supporting the frame body 1;
the two brackets 2 are provided with two vertical plates 21, each bracket comprises a transverse plate 22 connected to one side of each vertical plate 21, the tops of the transverse plates 22 are connected with sliding rails 23, a yielding groove 24 is formed in one side, far away from the transverse plates 22, of each vertical plate 21, and a first bolt 25 extending into the yielding groove 24 is arranged at the top of each vertical plate 21;
the frame body 1 is set to the U-shaped, and two spouts 11 with slide rail 23 looks adaptation have been seted up to the bottom, the frame body 1 is close to the upwards extension setting of a side wall of riser 21, and should be close to a side wall top of riser 21 and install two dials 12, when two dials 12 upset is to the inslot of stepping down 24, makes dials 12 and riser 21 top threaded connection through first bolt 25, accomplishes the installation of bracket 2.
Specifically, after fixing riser 21 through second bolt 5, promote support body 1 and make it slide to bracket 2 along slide rail 23, when support body 1 and riser 21 contact, upset plectrum 12 makes it shift into and give way in 24, locking first bolt 25 later, can accomplish the fixed mounting of this cable testing bridge, when needs are separated support body 2 and support body 1, only need make support body 1 roll-off bracket 2 after unscrewing first bolt 25, can realize the separation, the use of a large amount of bolts has been avoided in whole equipment and its dismantlement process, labour saving and time saving, and need not weld between bracket 2 and the support body 1, the dismouting all becomes simple and fast.
Further, in the above technical scheme, two brackets 2 are symmetrically distributed about the center of the frame body 1, two limiting frames 3 are mounted at the ends of the two transverse plates 22 of the frame body 1, and the two limiting frames 3 are rectangular and are adapted to the transverse plates 22.
In this embodiment, after the frame 1 slides into the bracket 2, the two limiting frames 3 are just located at the end of the transverse plate 22, so that the frame 1 can be limited, the frame 1 is prevented from moving up and down, and the stability of the frame 1 after being connected with the bracket 2 is improved.
Furthermore, in the above technical solution, two inclined plates 4 are connected to one side of the bottom of the vertical plate 21, and the top ends of the inclined plates 4 are connected to the bottom of the transverse plate 22.
In this embodiment, the transverse plate 22 is supported, so that the bearing capacity of the transverse plate 22 is improved, and the strength of the whole cable bridge body is further improved.
Further, in the above technical solution, a plurality of second bolts 5 are installed from top to bottom on one side of the two risers 21 close to the cross plate 22, and the ends of the second bolts 5 penetrate through the risers 21 and extend to the other side of the risers 21.
In this embodiment, when the second bolt 5 is completely screwed in, the screw head is flush with the side wall surface of the riser 21, and the riser 21 can be quickly fixed with an external building or a pipe rack bracket by using the second bolt 5, so that the cable bridge is convenient to thread after being assembled.
Further, in the above technical scheme, the inside of the frame body 1 is provided with a plurality of baffle plates 6, a plurality of baffle plates 6 are distributed at equal intervals with two side walls of the frame body 1, the number of the baffle plates 6 is not less than two, the frame body 1 is divided into a plurality of threading grooves 7 by the baffle plates 6, each threading groove 7 is provided with a cover plate 8 at the top, and the cover plates 8 are connected with the baffle plates 6.
In this embodiment, the partition plate 6 can avoid unnecessary interference caused by mutual contact of different cables inside each threading slot 7, and the cover plate 8 can protect the cables penetrating into the threading slots 7 from damage in the external environment, so that the cable bridge works better.
The implementation mode specifically comprises the following steps: during installation, a worker firstly fixes the vertical plate 21 on a wall body or other supporting bodies through threads by the second bolts 5, so that limit fixation of the bracket 2 is completed, then the frame body 1 is lifted, two sliding grooves 11 at the bottom of the frame body 1 correspond to sliding rails 23 of the bracket 2, the frame body 1 is pushed to slide along the sliding rails 23 towards the vertical plate 21 until the side wall of the upward extending arrangement of the frame body 1 contacts the vertical plate 21, at the moment, two shifting plates 12 at the top of the side wall are overturned, the shifting plates 12 are overturned into the yielding grooves 24, finally the first bolts 25 are locked, the shifting plates 12 and the vertical plate 21 are fixed, the bracket 2 and the frame body 1 can be assembled into a cable bridge body for use, and meanwhile, the fixed installation of the cable bridge is completed;
at this time, the two limiting frames 3 at the bottom of the frame body 1 just move to the outer side of the end part of the transverse plate 22, the transverse plate 22 and the frame body 1 are framed together and then matched with the poking plate 12, the limiting fixation of the frame body 1 in the up-down and left-right directions is completed, and the sliding rail 23 in the sliding groove 11 can avoid the frame body 1 from finding the longitudinal direction, namely the offset in the front-back direction;
finally, a worker penetrates the cable to be laid in the threading groove 7, and the cable bridge can be put into use;
similarly, when the bracket 2 is required to be separated from the bracket body 1, the bracket body 1 is pushed again after the first bolt 25 is screwed out, so that the bracket body 1 slides out of the bracket 2 along the sliding rail 23, the bracket 2 and the bracket body 1 can be separated, and the whole assembly and disassembly processes are simple and quick, and time and labor are saved;
the embodiment specifically solves the problems that when the tray type cable bridge in the prior art is actually installed, the bracket 2 and the frame body 1 are often connected in a mode of welding or a large number of bolts for fixing, the whole assembly process is time-consuming and labor-consuming, and the disassembly and the separation during later replacement or maintenance are not facilitated, and a plurality of inconveniences exist in use.
While certain exemplary embodiments of the present utility model have been described above by way of illustration only, it will be apparent to those of ordinary skill in the art that modifications may be made to the described embodiments in various different ways without departing from the spirit and scope of the utility model. Accordingly, the drawings and description are to be regarded as illustrative in nature and not as restrictive of the scope of the utility model, which is defined by the appended claims.

Claims (8)

1. A tray type cable bridge capable of being rapidly installed, which is characterized in that: comprises a frame body (1) and a bracket (2) arranged at the bottom of the frame body (1) and used for supporting the frame body (1);
the bracket (2) is provided with two brackets, each bracket comprises a vertical plate (21), a transverse plate (22) connected to one side of the vertical plate (21), a sliding rail (23) is connected to the top of the transverse plate (22), a yielding groove (24) is formed in one side, far away from the transverse plate (22), of the top of the vertical plate (21), and a first bolt (25) extending into the yielding groove (24) is arranged at the top of the vertical plate (21);
the frame body (1) is set to the U-shaped, and two spouts (11) with slide rail (23) looks adaptation have been seted up to the bottom, the frame body (1) is close to a side wall upward extension setting of riser (21), and should be close to a side wall top of riser (21) and install two and dial board (12), when two dial board (12) upset is to in groove (24) of stepping down, makes dial board (12) and riser (21) top threaded connection through first bolt (25), accomplishes the installation of bracket (2).
2. A quickly mountable tray cable bridge according to claim 1, wherein: the two brackets (2) are symmetrically distributed about the center of the frame body (1), and two limiting frames (3) are arranged at the end parts of the two transverse plates (22) of the frame body (1).
3. A quickly mountable tray cable bridge according to claim 2, wherein: both limit frames (3) are rectangular and are matched with the transverse plates (22).
4. A quickly mountable tray cable bridge according to claim 1, wherein: the two vertical plates (21) are connected with an inclined plate (4) on one side of the bottom, and the top ends of the inclined plates (4) are connected with the bottom of a transverse plate (22).
5. A quickly mountable tray cable bridge according to claim 1, wherein: a plurality of second bolts (5) are arranged on one side, close to the transverse plate (22), of the two vertical plates (21) from top to bottom, and the end parts of the second bolts (5) penetrate through the vertical plates (21) and extend to the other side of the vertical plates (21).
6. A quickly mountable tray cable bridge according to claim 1, wherein: the novel multifunctional rack is characterized in that a plurality of partition boards (6) are arranged in the rack body (1), the partition boards (6) are distributed at equal intervals with the two side walls of the rack body (1), and the number of the partition boards (6) is not less than two.
7. The quickly mountable tray cable bridge of claim 6, wherein: the frame body (1) is divided into a plurality of threading grooves (7) by the partition plates (6).
8. The quickly mountable tray cable bridge of claim 7, wherein: and the top of each threading groove (7) is provided with a cover plate (8), and the cover plates (8) are connected with the partition plates (6).
CN202320466302.2U 2023-03-13 2023-03-13 Tray type cable bridge capable of being installed rapidly Active CN220382656U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320466302.2U CN220382656U (en) 2023-03-13 2023-03-13 Tray type cable bridge capable of being installed rapidly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320466302.2U CN220382656U (en) 2023-03-13 2023-03-13 Tray type cable bridge capable of being installed rapidly

Publications (1)

Publication Number Publication Date
CN220382656U true CN220382656U (en) 2024-01-23

Family

ID=89570424

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320466302.2U Active CN220382656U (en) 2023-03-13 2023-03-13 Tray type cable bridge capable of being installed rapidly

Country Status (1)

Country Link
CN (1) CN220382656U (en)

Similar Documents

Publication Publication Date Title
CN210105295U (en) Can have enough to meet need formula steel bar truss floor carrier plate strutting arrangement
CN220382656U (en) Tray type cable bridge capable of being installed rapidly
CN102518875B (en) The wire installation frame of a kind of dome or arc or slope use
JP2002004526A (en) Solar cell roofing module mounting structure
CN213125446U (en) High-strength cabling rack
CN209767033U (en) Combined steel structure bridge
CN211018133U (en) Cable bridge convenient to installation is maintained
CN211110971U (en) Photovoltaic board loading and unloading pulling device of photovoltaic energy storage system
CN216920948U (en) Hooking type kneading bearing keel
CN210577550U (en) Cable bridge with isolation groove
CN219247370U (en) Cable anti-winding frame
CN201787298U (en) Wall-hanging bracket
CN218586818U (en) Cable bridge
CN217692475U (en) Redundant comprehensive channel bridge
CN219498822U (en) Hanging type cable bridge bracket arm
CN217537658U (en) Novel hang and paste external wall brick
CN110158844A (en) It is a kind of without nailization module furred ceiling
CN213572598U (en) Integrated ceiling framework for architectural decoration
CN209705856U (en) A kind of commerce integration linear lighting gantry
CN213879143U (en) High-strength cable bridge
CN219282860U (en) Large liquid crystal display splicing and mounting structure
CN217545473U (en) High-strength cable bridge
CN215331400U (en) Scaffold lifting, positioning and fixing device
CN216489036U (en) GGD switch board electrical components skeleton convenient to installation
CN209994032U (en) Adjustable ladder type cable bridge

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant