CN220351419U - Wall-attached steel beam fixing device of construction lifter - Google Patents

Wall-attached steel beam fixing device of construction lifter Download PDF

Info

Publication number
CN220351419U
CN220351419U CN202321752725.7U CN202321752725U CN220351419U CN 220351419 U CN220351419 U CN 220351419U CN 202321752725 U CN202321752725 U CN 202321752725U CN 220351419 U CN220351419 U CN 220351419U
Authority
CN
China
Prior art keywords
clamping plate
fixing device
adjusting
side adjusting
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321752725.7U
Other languages
Chinese (zh)
Inventor
赵文威
聂超
罗洪
郑素娟
李洪强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Jianzhong Construction Technology Co ltd
Original Assignee
Fujian Jianzhong Construction Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Jianzhong Construction Technology Co ltd filed Critical Fujian Jianzhong Construction Technology Co ltd
Priority to CN202321752725.7U priority Critical patent/CN220351419U/en
Application granted granted Critical
Publication of CN220351419U publication Critical patent/CN220351419U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to a wall-attached steel beam fixing device of a construction lifter, which comprises an outer side adjusting and fixing device, an inner side adjusting and fixing device and a connecting port, wherein clamping plates are arranged in the two side adjusting and fixing devices. The width of the clamping plate is adjusted through the adjusting bolt, the steel pipe is inserted into the connecting port and fixed, then the inner side adjusting device fixed with the steel pipe is lifted and moved to the position required by the wall attaching of the construction lifter, the inner side adjusting device is fixed first, then the outer side adjusting device is fixed on the other side of the building column, then the inner side adjusting fixing device and the outer side adjusting fixing device are fastened through the protruding block through the bolt, the force is slowly discharged, and the wall attaching fixing steel beam device of the construction lifter is ensured to be fixed on the building column.

Description

Wall-attached steel beam fixing device of construction lifter
Technical Field
The utility model relates to a wall-attached steel beam fixing device of a construction lifter, and belongs to the technical field of building construction.
Background
The production companies of the construction elevators on the market mostly mainly produce standard components of the construction elevators, and are convenient to use in an interworking manner with other components. However, the situation of the construction site is often complicated, and various special fixing members are needed in many cases, for example, when special situations such as a hotel or a factory are met, and the building structure is specially designed or the position of a construction lifter is changed when the building is far away from the floor and cannot be attached. If the building structure is specially designed, the whole building structure needs to be redesigned by connecting with a design institute, which not only damages the whole building structure, but also causes great difficulty for site construction, thereby wasting a large amount of building materials.
Disclosure of Invention
In order to solve the problems in the prior art, the utility model provides a wall-attached steel beam fixing device for a construction lifter, which not only can effectively attach a building with a special structure, but also is simple and economical to assemble, and enhances the use safety of the construction lifter.
The technical scheme of the utility model is as follows:
the wall-attached steel beam fixing device of the construction elevator comprises an outer side adjusting and fixing device, an inner side adjusting and fixing device and a connecting port, wherein the outer side adjusting and fixing device and the inner side adjusting and fixing device are arranged in opposite directions, and fixing blocks with holes are arranged in the outer side adjusting and fixing device and the inner side adjusting and fixing device respectively; the first clamping plate and the second clamping plate are symmetrically arranged and pass through the fixing block to be fixed on the outer side adjusting and fixing device; the third clamping plate and the fourth clamping plate are symmetrically arranged and pass through the fixing block to be fixed on the inner side adjusting and fixing device; the first clamping plate, the second clamping plate, the third clamping plate and the fourth clamping plate are respectively and tightly wound on the side surface of the building column body; the connecting port is fixed on the surface of the back-to-outside adjusting and fixing device of the inner adjusting and fixing device and is used for fixedly connecting the steel pipes.
Further, the first clamping plate, the second clamping plate, the third clamping plate and the fourth clamping plate comprise side plates inserted into the holes of the fixed blocks and clamping plates vertically connected with the side plates, the clamping plates are respectively clung to two vertical side walls of the corners of the building column body, and after the first adjusting screw passes through the first clamping plate and the second clamping plate and is inserted into the side plates in the fixed blocks, the first clamping plate and the second clamping plate are fixed on the outer side adjusting and fixing device; the second adjusting screw rod penetrates through the third clamping plate and the fourth clamping plate to be inserted into the side plate in the fixing block, and then the third clamping plate and the fourth clamping plate are fixed on the inner side adjusting and fixing device.
Further, the clamping plates of the first clamping plate, the second clamping plate, the third clamping plate and the fourth clamping plate, which are clung to the side wall of the building column body, are also provided with protruding blocks, and bolt fixing hole sites penetrate through the protruding blocks.
Further, a connecting rib plate is arranged between each side face of the connecting port and the inner side adjusting and fixing device, and at least two connecting rib plates are arranged on each side face.
The utility model has the following beneficial effects:
1. the device for fixing the steel beam by the wall attached to the construction lifter effectively solves the problem that the position of the wall attached to the construction lifter is affected by a building structure.
2. The wall-attached steel beam fixing device for the construction lifter can effectively save the use cost, reduce the material loss and save the resources.
3. According to the wall-attached steel beam fixing device for the construction elevator, provided by the utility model, the device is installed and completed only by an installer in a small amount of time, so that the safety in construction of the construction elevator is greatly ensured, and the working efficiency is improved.
Drawings
FIG. 1 is a schematic view of a construction hoist wall-attached steel girder fixing device according to the present utility model;
FIG. 2 is a simulation diagram of the construction of the wall-attached fixed steel beam of the construction hoist fixed to a square column;
the reference numerals in the drawings are as follows:
1. an outside adjustment fixture; 11. a first clamping plate; 111. a second clamping plate; 12. a first adjusting screw; 2. an inside adjustment fixture; 21. a third clamping plate; 211. a fourth clamping plate; 22. a second adjusting screw; 3. a connection port; 31. a connecting bolt hole; 4. a bump; 41. bolt fixing hole sites; 5. connecting rib plates; 6. a steel pipe; 7. a side plate; 8. a fixed block; 9. building columns.
Detailed Description
The utility model will now be described in detail with reference to the drawings and to specific embodiments.
Referring to fig. 1 to 2, a wall-attached steel beam fixing device of a construction lifter comprises an outer side adjusting and fixing device 1, an inner side adjusting and fixing device 2 and a connecting port 3, wherein the outer side adjusting and fixing device 1 and the inner side adjusting and fixing device 2 are arranged in opposite directions, and fixing blocks 8 with holes are arranged in the outer side adjusting and fixing device and the inner side adjusting and fixing device; the first clamping plate 11 and the second clamping plate 111 are symmetrically arranged and pass through the fixing block 8 to be fixed on the outer side adjusting and fixing device 1; the third clamping plate 21 and the fourth clamping plate 211 are symmetrically arranged and pass through the fixing block 8 to be fixed on the inner side adjusting and fixing device 2; the first clamping plate 11, the second clamping plate 111, the third clamping plate 21 and the fourth clamping plate 211 are respectively fastened on the side surface of the building column 9 around the hoops; the connecting port 3 is fixed on the surface of the inner side adjusting and fixing device 2, which is opposite to the outer side adjusting and fixing device 1, and is used for fixedly connecting the steel pipe 6.
In this embodiment, the first clamping plate 11, the second clamping plate 111, the third clamping plate 21 and the fourth clamping plate 211 all comprise a side plate 7 inserted into the hole of the fixing block 8 and clamping plates vertically connected with the side plate 7, the clamping plates are respectively clung to two vertical side walls of the corner of the building column 9, and after the first adjusting screw 12 passes through the first clamping plate 11 and the second clamping plate 111 to be inserted into the side plate 7 in the fixing block 8, the first clamping plate 11 and the second clamping plate 111 are fixed on the outside adjusting fixing device 1; the second adjusting screw 22 is inserted through the third clamping plate 21 and the fourth clamping plate 211 to the side plate 7 in the fixing block 8, and then fixes the third clamping plate 21 and the fourth clamping plate 211 to the inside adjusting fixing device 2.
In this embodiment, the clamping plates of the first clamping plate 11, the second clamping plate 111, the third clamping plate 21 and the fourth clamping plate 211, which are tightly attached to the side wall of the building column 9, are further provided with a protruding block 4, and bolt fixing holes 41 are penetrated through the protruding block 4.
In this embodiment, a connection rib plate 5 is disposed between each side surface of the connection port 3 and the inner side adjusting and fixing device 2, and at least two connection rib plates 5 are disposed on each side surface.
The working principle of the utility model is as follows:
in the construction process, the inner side adjusting and fixing device 2 is connected with the steel pipe 6, the steel pipe 6 is inserted into the connecting port 3 of the inner side adjusting and fixing device 2, the connecting bolt is used for fixing the steel pipe 6 into the connecting port 3 by penetrating through the connecting bolt hole 31 above the connecting port 3, and the bolt is screwed to the corresponding nut after penetrating through the corresponding connecting port 3 and the connecting bolt hole 31 left on the steel pipe 6. After the connection tightness of the steel pipe 6 and the inner side adjusting and fixing device 2 is confirmed, the other end of the steel pipe 6 is fixed with the other inner side adjusting and fixing device 2 in the same way, and after the connection tightness of the two inner side adjusting and fixing devices 2 and the steel pipe 6 is confirmed, the steel pipe 6 is lifted and moved to the position required by the wall attaching of the construction lifter.
After the steel pipe 6 is adjusted to a predetermined position, the third clamping plate 21 and the fourth clamping plate 211 are closely attached to the building column 9 by adjusting the second adjusting screw 22 above the inside adjusting fixing device 2. The outside adjusting and fixing device 1 is then mounted to the same position from the other side of the building column 9, the first adjusting screw 12 above the outside adjusting and fixing device 1 is adjusted to make the first clamping plate 11 cling to the third clamping plate 21, and the rear bolts are screwed to the corresponding nuts through the two bolt fixing holes 41 on the same side protruding block 4. After the outside adjusting and fixing device 1 and the inside adjusting and fixing device 2 are confirmed to be clamped with the building column 9, the outside adjusting and fixing device 1 and the inside adjusting and fixing device 2 on the other side are fixed in the same way, and then the lifting hook is controlled to slowly release force, so that the wall-attached fixing steel beam device of the construction lifter can be fixed on the building column 9.
The foregoing description is only illustrative of the present utility model and is not intended to limit the scope of the utility model, and all equivalent structures or equivalent processes or direct or indirect application in other related technical fields are included in the scope of the present utility model.

Claims (4)

1. The utility model provides a construction elevator attaches wall fixed girder steel device which characterized in that: the device comprises an outer side adjusting and fixing device (1), an inner side adjusting and fixing device (2) and a connecting port (3), wherein the outer side adjusting and fixing device (1) and the inner side adjusting and fixing device (2) are arranged in opposite directions, and fixing blocks (8) with holes are arranged in the outer side adjusting and fixing device; the first clamping plate (11) and the second clamping plate (111) are symmetrically arranged and pass through the fixing block (8) to be fixed on the outer side adjusting and fixing device (1); the third clamping plate (21) and the fourth clamping plate (211) are symmetrically arranged and pass through the fixing block (8) to be fixed on the inner side adjusting and fixing device (2); the first clamping plate (11), the second clamping plate (111), the third clamping plate (21) and the fourth clamping plate (211) are respectively fastened on the side surface of the building column (9) around the hoops; the connecting port (3) is fixed on the surface of the inner side adjusting and fixing device (2) which is opposite to the outer side adjusting and fixing device (1) and is used for fixedly connecting the steel pipe (6).
2. The construction elevator wall-attached steel beam fixing device according to claim 1, wherein: the first clamping plate (11), the second clamping plate (111), the third clamping plate (21) and the fourth clamping plate (211) comprise side plates (7) inserted into the holes of the fixed block (8) and clamping plates vertically connected with the side plates (7), the clamping plates are respectively clung to two vertical side walls of the corner of the building column (9), and after the first adjusting screw (12) passes through the side plates (7) of the first clamping plate (11) and the second clamping plate (111) inserted into the fixed block (8), the first clamping plate (11) and the second clamping plate (111) are fixed on the outer side adjusting and fixing device (1); the second adjusting screw (22) passes through the third clamping plate (21) and the fourth clamping plate (211) to be inserted into the side plate (7) in the fixed block (8), and then the third clamping plate (21) and the fourth clamping plate (211) are fixed on the inner side adjusting and fixing device (2).
3. The construction elevator wall-attached steel beam fixing device according to claim 2, wherein: the first clamping plate (11), the second clamping plate (111), the third clamping plate (21) and the fourth clamping plate (211) are tightly attached to the clamping plates on the side wall of the building column body (9), the protruding blocks (4) are further provided with protruding blocks (4), and bolt fixing hole sites (41) penetrate through the protruding blocks (4).
4. The construction elevator wall-attached steel beam fixing device according to claim 1, wherein: connecting rib plates (5) are arranged between each side face of the connecting port (3) and the inner side adjusting and fixing device (2), and at least two connecting rib plates (5) are arranged on each side face.
CN202321752725.7U 2023-07-05 2023-07-05 Wall-attached steel beam fixing device of construction lifter Active CN220351419U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321752725.7U CN220351419U (en) 2023-07-05 2023-07-05 Wall-attached steel beam fixing device of construction lifter

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321752725.7U CN220351419U (en) 2023-07-05 2023-07-05 Wall-attached steel beam fixing device of construction lifter

Publications (1)

Publication Number Publication Date
CN220351419U true CN220351419U (en) 2024-01-16

Family

ID=89484080

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321752725.7U Active CN220351419U (en) 2023-07-05 2023-07-05 Wall-attached steel beam fixing device of construction lifter

Country Status (1)

Country Link
CN (1) CN220351419U (en)

Similar Documents

Publication Publication Date Title
CN203701350U (en) Self-reset energy consumption node for aerated concrete externally hanging wallboard
CN103835527B (en) A kind of dismountable supporting device
CN103821265A (en) Self-resetting energy dissipation node for externally hung aerated concrete wallboard and construction method thereof
CN210396247U (en) Modularization container building connected node
CN204983173U (en) Steel construction beam -column connection node
CN220351419U (en) Wall-attached steel beam fixing device of construction lifter
CN115233834B (en) High-rise modularized box structure connecting node
CN217439520U (en) Wall connecting piece for outer scaffold drawknot
CN213359489U (en) Adjustable reinforcing device for supporting construction elevator on basement roof
CN212773459U (en) Wall pouring template applied to expansion joint side
CN111364745A (en) Unsupported self-supporting profile steel platform
CN208088494U (en) A kind of assembled architecture component
CN203742200U (en) Detachable jacking and supporting device
CN110950254A (en) Quick mounting and dismounting type tower crane attachment operation platform and manufacturing method thereof
CN217172989U (en) Hoisting clamp for single-side clad plate wood shear wall
CN117071913B (en) Steel construction cantilever steel bar truss building carrier plate hanging die construction device
CN217871881U (en) Steel construction roofing bed-jig node adjustment control device that slides
CN217437595U (en) Simple vertical wall-attached seat of tower crane
CN216740304U (en) Connection node of prefabricated floor of assembled and girder steel
CN211369532U (en) Combined fixed pre-buried water stop joint template
CN215054035U (en) High-rise steel structure assembling structure
CN212153706U (en) Limiting device of steel structure truss
CN210976673U (en) Anti-falling device for steel structure engineering construction
CN218713982U (en) H-shaped steel component and concrete structure connected node structure
CN214461221U (en) Rigidity-reinforcing structure for connection of prefabricated parts

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant