CN220304809U - Electrolytic cell diffusion layer flow resistance detection device - Google Patents

Electrolytic cell diffusion layer flow resistance detection device Download PDF

Info

Publication number
CN220304809U
CN220304809U CN202321842403.1U CN202321842403U CN220304809U CN 220304809 U CN220304809 U CN 220304809U CN 202321842403 U CN202321842403 U CN 202321842403U CN 220304809 U CN220304809 U CN 220304809U
Authority
CN
China
Prior art keywords
detection
jacking
fixedly connected
detection device
diffusion layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321842403.1U
Other languages
Chinese (zh)
Inventor
李洋
韩雨君
郭维平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Hesheng Chuanghe Energy Technology Co ltd
Original Assignee
Shanghai Hesheng Chuanghe Energy Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Hesheng Chuanghe Energy Technology Co ltd filed Critical Shanghai Hesheng Chuanghe Energy Technology Co ltd
Priority to CN202321842403.1U priority Critical patent/CN220304809U/en
Application granted granted Critical
Publication of CN220304809U publication Critical patent/CN220304809U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Monitoring And Testing Of Nuclear Reactors (AREA)

Abstract

The utility model relates to the technical field of electrolytic tank detection, and discloses an electrolytic tank diffusion layer resistance detection device which comprises a detection base component, wherein an electric lifting jack is fixedly arranged at the upper end of the detection base component, a pressing plate component is fixedly arranged at the upper end of the electric lifting jack, and a hydraulic lifting cylinder is fixedly arranged at the upper end of the pressing plate component. This electrolytic tank diffusion laminar flow hinders detection device, through electronic jack-up with clamp plate subassembly jacking certain height, electronic jack-up safe and reliable, the reaction can improve the jacking pressure board efficiency fast, later put into wait to examine diffusion layer spare part, later promote clamp plate subassembly through hydraulic jack-up hydro-cylinder and push down, when pressure reaches a definite value, hydraulic jack-up hydro-cylinder stops the action, hydraulic jack-up hydro-cylinder can realize great down force, satisfies required clamp force when spare part inspection, later connects water inlet pipe joint and water outlet pipe joint and lets in liquid, through external inspection equipment inspection liquid flow resistance.

Description

Electrolytic cell diffusion layer flow resistance detection device
Technical Field
The utility model relates to the technical field of electrolytic tank detection, in particular to an electrolytic tank diffusion layer flow resistance detection device.
Background
An electrolytic cell is an apparatus for carrying out an electrolytic process and generally consists of a container, electrodes and electrolyte. During electrolysis, an electrolyte solution is placed in an electrolytic cell, into which both electrodes of the cell are immersed. One electrode is referred to as the anode and the other is referred to as the cathode. The cell diffusion layer flow resistance refers to the resistance to electrolyte ion transport by the diffusion layer formed in the cell. During electrolysis, ions migrate in the electrolyte solution, but due to the presence of the diffusion layer, the ions form a relatively stable region near the cell surface, which is called the diffusion layer, the flow resistance of which has a significant impact on the electrolysis process. The larger flow resistance of the diffusion layer increases the resistance in the electrolysis process, so that the efficiency of the electrolytic tank is reduced, and monitoring is needed during the production of the electrolytic tank, so that the resistance of fluid in the flow passage holes of the diffusion layer parts of the electrolytic tank is solved, the processing problem of the flow passage is helped to be identified, unqualified parts of the flow resistance are prevented from being used for the assembly of products, and the one-time offline qualification rate of the products is improved.
Disclosure of Invention
(one) solving the technical problems
Aiming at the defects of the prior art, the utility model provides an electrolytic cell diffusion layer flow resistance detection device for solving the problems in the background.
(II) technical scheme
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides an electrolytic cell diffusion laminar flow resistance detection device, includes detects the base subassembly, detect the upper end fixed mounting of base subassembly and have electric jack, the upper end fixed mounting of electric jack has the clamp plate subassembly, the upper end fixed mounting of clamp plate subassembly has hydraulic jack, the upper end fixed mounting of hydraulic jack has the roof, the upper end fixedly connected with gallows of roof, the hanging hole has been seted up on the right side of gallows, the upper end fixed mounting of roof has hydraulic pump station;
the detection base assembly comprises a detection base body, a jacking groove, a jacking column, a detection table, a limiting ring and an end cover, wherein the jacking groove is formed in the upper end of the detection base body, the jacking column is fixedly connected to the upper end of the detection base body, the detection table is fixedly connected to the upper end of the detection base body, the limiting ring is connected to the outer side of the jacking column, and the end cover is fixedly mounted on the top end of the jacking column;
the clamp plate subassembly is including clamp plate body, guiding hole, water inlet pipe joint, water outlet pipe joint and detection platform, the guiding hole has been seted up to the upper end of clamp plate body, the upper end fixedly connected with inlet tube joint of clamp plate body, the upper end fixedly connected with outlet pipe joint of clamp plate body, the lower extreme fixedly connected with of clamp plate body detects the platform.
Preferably, four electric jacking jacks are fixedly arranged at the upper end of the detection base assembly, and the electric jacking jacks are positioned in the jacking groove.
Through above-mentioned technical scheme, through electronic jack-up jack with the clamp plate subassembly jacking certain height, electronic jack-up safe and reliable, the reaction can improve the jack-up board efficiency fast, has reduced the manpower, satisfies the ergonomic requirement.
Preferably, the upper end fixedly connected with four roof truss posts of detection base body, the outside of roof truss post all fixedly connected with spacing ring, the top of roof truss post all fixedly mounted has the end cover.
Through above-mentioned technical scheme, the spacing ring can be spacing to the clamp plate subassembly, and the end cover can be convenient for fix the roof.
Preferably, four guide holes are formed in the upper end of the pressing plate body, and the guide holes are matched with the top frame column.
Through above-mentioned technical scheme, through guiding hole and roof truss post looks adaptation structure, the clamp plate subassembly of can being convenient for moves on the roof truss post, improves the stability that compresses tightly and jack-up.
Preferably, the detection pressing table corresponds to the detection table in position, and four hydraulic jacking cylinders are fixedly arranged at the upper end of the pressing plate assembly.
Through the technical scheme, the hydraulic jacking oil cylinder can realize larger downward pressure, and the required pressing force during component inspection is met.
Preferably, the upper end fixedly connected with two gallows of roof, three hanging hole has all been seted up on the right side of gallows.
Through above-mentioned technical scheme, can be convenient for the hoist and mount of equipment through two gallows and a plurality of hanging hole, convenient transportation removes and installs.
Compared with the prior art, the utility model provides an electrolytic tank diffusion layer flow resistance detection device, which has the following beneficial effects: this electrolytic tank diffusion laminar flow hinders detection device, through electronic jack-up jack with clamp plate subassembly jacking certain height, electronic jack-up safe and reliable, the reaction can improve the jacking board efficiency fast, the manpower has been reduced, satisfy the ergonomic requirement, later put into wait to examine diffusion layer spare part, later push down through hydraulic jack-up hydro-cylinder promotion clamp plate subassembly, when pressure reaches a definite value, hydraulic jack-up hydro-cylinder stop action, hydraulic jack-up hydro-cylinder can realize great down force, required closing force when satisfying spare part inspection, through guiding hole and jacking post looks adaptation structure, can be convenient for clamp plate subassembly activity on the jacking post, improve the stability that compresses tightly and jack-up, later connect the water inlet pipe joint and go out the water pipe joint and let in liquid, through external inspection equipment inspection liquid flow resistance.
Drawings
FIG. 1 is a schematic perspective view of the first embodiment of the present utility model;
FIG. 2 is a schematic diagram of a second perspective structure of the present utility model;
FIG. 3 is a schematic diagram of the front view of the present utility model;
FIG. 4 is a schematic perspective view of a test base assembly according to the present utility model;
FIG. 5 is a schematic perspective view of a platen assembly according to the present utility model;
fig. 6 is a schematic perspective view of a platen assembly according to the present utility model.
Wherein: 1. detecting a base assembly; 101. detecting a base body; 102. a jacking groove; 103. a roof rack column; 104. a detection table; 105. a limiting ring; 106. an end cap; 2. an electric jack; 3. a platen assembly; 301. a platen body; 302. a guide hole; 303. a water inlet pipe joint; 304. a water outlet pipe joint; 305. detecting a pressing table; 4. a hydraulic jack-up cylinder; 5. a top plate; 6. a hanging bracket; 7. a hanging hole; 8. and a hydraulic pump station.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Embodiment one:
as shown in fig. 1-6, the utility model provides an electrolytic cell diffusion layer resistance detection device, which comprises a detection base component 1, wherein an electric jacking jack 2 is fixedly arranged at the upper end of the detection base component 1, a pressing plate component 3 is fixedly arranged at the upper end of the electric jacking jack 2, a hydraulic jacking oil cylinder 4 is fixedly arranged at the upper end of the pressing plate component 3, a top plate 5 is fixedly arranged at the upper end of the hydraulic jacking oil cylinder 4, a hanging bracket 6 is fixedly connected at the upper end of the top plate 5, a hanging hole 7 is formed at the right side of the hanging bracket 6, and a hydraulic pump station 8 is fixedly arranged at the upper end of the top plate 5;
the detection base assembly 1 comprises a detection base body 101, a jacking groove 102, a top frame column 103, a detection table 104, a limiting ring 105 and an end cover 106, wherein the jacking groove 102 is formed in the upper end of the detection base body 101, the top frame column 103 is fixedly connected to the upper end of the detection base body 101, the detection table 104 is fixedly connected to the upper end of the detection base body 101, the limiting ring 105 is connected to the outer side of the top frame column 103, and the end cover 106 is fixedly mounted on the top end of the top frame column 103;
the pressing plate assembly 3 comprises a pressing plate body 301, a guide hole 302, a water inlet pipe connector 303, a water outlet pipe connector 304 and a detection pressing table 305, wherein the guide hole 302 is formed in the upper end of the pressing plate body 301, the water inlet pipe connector 303 is fixedly connected to the upper end of the pressing plate body 301, the water outlet pipe connector 304 is fixedly connected to the upper end of the pressing plate body 301, and the detection pressing table 305 is fixedly connected to the lower end of the pressing plate body 301.
Specifically, detect the upper end fixed mounting of base subassembly 1 and have four electric jack-up jacks 2, electric jack-up jacks 2 are located the jacking groove 102, and the advantage is, through electric jack-up jacks 2 with clamp plate subassembly 3 jacking certain height, electric jack-up safe and reliable, the quick efficiency that can improve the top booster plate of reaction has reduced the manpower, satisfies the ergonomic requirement.
Specifically, detect four roof-rack posts 103 of upper end fixedly connected with of base body 101, the equal fixedly connected with spacing ring 105 in the outside of roof-rack post 103, the equal fixedly mounted on top of roof-rack post 103 has end cover 106, and the advantage is, spacing ring 105 can be spacing to clamp plate assembly 3, and end cover 106 can be convenient for fix roof 5.
Specifically, four guiding holes 302 have been seted up to clamp plate body 301's upper end, and guiding hole 302 and roof-rack post 103 looks adaptation, and the advantage is, through guiding hole 302 and roof-rack post 103 looks adaptation structure, can be convenient for clamp plate assembly 3 activity on roof-rack post 103, improves the stability that compresses tightly and jack-up.
Embodiment two:
as shown in fig. 2-6, as an improvement over the previous embodiment. Specifically, the position of the detection pressing table 305 corresponds to that of the detection table 104, and four hydraulic jacking cylinders 4 are fixedly arranged at the upper end of the pressing plate assembly 3.
Specifically, the upper end fixedly connected with two gallows 6 of roof 5, three hanging hole 7 have all been seted up on the right side of gallows 6, and the advantage is, through the hoist and mount of two gallows 6 and a plurality of hanging hole 7 can be convenient for equipment, convenient transportation removes and installs.
Working principle: when the hydraulic lifting jack is used, firstly, the pressure plate assembly 3 is lifted to a certain height through the electric lifting jack 2, the electric lifting jack is safe and reliable, the efficiency of lifting the pressure plate can be improved quickly in reaction, manpower is reduced, the requirements of man-machine engineering are met, then, components of a diffusion layer to be inspected are placed in the hydraulic lifting jack, the pressure plate assembly 3 is pushed to be pressed down through the hydraulic lifting cylinder 4, when the pressure reaches a certain value, the hydraulic lifting cylinder 4 stops acting, the hydraulic lifting cylinder 4 can achieve larger pressing force, the required pressing force during component inspection is met, the pressure plate assembly 3 can conveniently move on the top frame column 103 through the guide hole 302 and the top frame column 103, the pressing and lifting stability is improved, the water inlet pipe connector 303 and the water outlet pipe connector 304 are connected and liquid is introduced, and the liquid flow resistance is inspected through external inspection equipment.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides an electrolysis trough diffusion laminar flow hinders detection device, includes detection base subassembly (1), its characterized in that: the automatic detection device is characterized in that an electric jacking jack (2) is fixedly arranged at the upper end of the detection base assembly (1), a pressing plate assembly (3) is fixedly arranged at the upper end of the electric jacking jack (2), a hydraulic jacking oil cylinder (4) is fixedly arranged at the upper end of the pressing plate assembly (3), a top plate (5) is fixedly arranged at the upper end of the hydraulic jacking oil cylinder (4), a hanging bracket (6) is fixedly connected to the upper end of the top plate (5), a hanging hole (7) is formed in the right side of the hanging bracket (6), and a hydraulic pump station (8) is fixedly arranged at the upper end of the top plate (5);
the detection base assembly (1) comprises a detection base body (101), a jacking groove (102), a top frame column (103), a detection table (104), a limiting ring (105) and an end cover (106), wherein the jacking groove (102) is formed in the upper end of the detection base body (101), the top frame column (103) is fixedly connected to the upper end of the detection base body (101), the detection table (104) is fixedly connected to the upper end of the detection base body (101), the limiting ring (105) is connected to the outer side of the top frame column (103), and the end cover (106) is fixedly mounted on the top end of the top frame column (103);
the clamp plate subassembly (3) is including clamp plate body (301), guiding hole (302), inlet tube joint (303), outlet pipe joint (304) and detection platform (305), guiding hole (302) have been seted up to the upper end of clamp plate body (301), the upper end fixedly connected with inlet tube joint (303) of clamp plate body (301), the upper end fixedly connected with outlet pipe joint (304) of clamp plate body (301), the lower extreme fixedly connected with detection platform (305) of clamp plate body (301).
2. The electrolytic cell diffusion layer resistance detection device according to claim 1, wherein: four electric jacking jacks (2) are fixedly arranged at the upper end of the detection base assembly (1), and the electric jacking jacks (2) are located in the jacking groove (102).
3. The electrolytic cell diffusion layer resistance detection device according to claim 1, wherein: the detecting base comprises a detecting base body (101), wherein four top frame posts (103) are fixedly connected to the upper end of the detecting base body (101), limiting rings (105) are fixedly connected to the outer sides of the top frame posts (103), and end covers (106) are fixedly installed on the top ends of the top frame posts (103).
4. The electrolytic cell diffusion layer resistance detection device according to claim 1, wherein: four guide holes (302) are formed in the upper end of the pressing plate body (301), and the guide holes (302) are matched with the top frame column (103).
5. The electrolytic cell diffusion layer resistance detection device according to claim 1, wherein: the detection pressing table (305) corresponds to the detection table (104), and four hydraulic jacking cylinders (4) are fixedly arranged at the upper end of the pressing plate assembly (3).
6. The electrolytic cell diffusion layer resistance detection device according to claim 1, wherein: the upper end of the top plate (5) is fixedly connected with two hanging brackets (6), and three hanging holes (7) are formed in the right side of each hanging bracket (6).
CN202321842403.1U 2023-07-13 2023-07-13 Electrolytic cell diffusion layer flow resistance detection device Active CN220304809U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321842403.1U CN220304809U (en) 2023-07-13 2023-07-13 Electrolytic cell diffusion layer flow resistance detection device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321842403.1U CN220304809U (en) 2023-07-13 2023-07-13 Electrolytic cell diffusion layer flow resistance detection device

Publications (1)

Publication Number Publication Date
CN220304809U true CN220304809U (en) 2024-01-05

Family

ID=89346327

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321842403.1U Active CN220304809U (en) 2023-07-13 2023-07-13 Electrolytic cell diffusion layer flow resistance detection device

Country Status (1)

Country Link
CN (1) CN220304809U (en)

Similar Documents

Publication Publication Date Title
CN220304809U (en) Electrolytic cell diffusion layer flow resistance detection device
CN111811742A (en) Engine rear end cover air tightness test device
CN218621087U (en) Electroplating device and electroplating equipment for solar cell
CN205235774U (en) Hollow fiber curtain formula membrane module detection device
CN110082041B (en) Fire extinguisher gas tightness verifying attachment
CN217071344U (en) Welding tool for upper transfer block of battery
CN214096503U (en) Air tightness detection device for rubber sealing element
CN213275278U (en) A infiltration detection device for concrete
CN210802798U (en) Intercooler core group air tightness test device
CN213289223U (en) Fixing mechanism for welding liquid distributor of tubular free radical reactor
CN203572748U (en) Tool for detecting hydrophobicity of air filtering piece
CN212275167U (en) Engine rear end cover air tightness test device
CN220893687U (en) Elbow air tightness detection device
CN111595528A (en) Device for detecting sealing performance of oil filter
CN210974628U (en) Liquid pumping mechanism
CN215975118U (en) Chemical wastewater pH value adjusting device
CN218766413U (en) Water pressure detection device in suspension insulator
CN214780105U (en) A wire rope oil tank oil mass detection device for elevator dimension is protected
CN214694281U (en) Electroplating water quenching tank
CN220952054U (en) Simple saw blade blackening frame
CN215178395U (en) Car terminal gas tightness detection device
CN217271174U (en) Oil collecting tank of bus lifting frame hydraulic station
CN214040802U (en) Water quality testing sampler with adjustable degree of depth
CN218271245U (en) Leakproofness detection device of tinplate round can
CN213985554U (en) Air tightness detection device for lithium battery pack box

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant