CN220301917U CN202321486204.1U CN202321486204U CN220301917U CN 220301917 U CN220301917 U CN 220301917U CN 202321486204 U CN202321486204 U CN 202321486204U CN 220301917 U CN220301917 U CN 220301917U
Authority
CN
China
Prior art keywords
fence
strong magnet
sleeve
steel pipe
tower top
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321486204.1U
Other languages
Chinese (zh)
Inventor
韩风智
马琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Haoxiao Industry And Trade Co ltd
Original Assignee
Qingdao Haoxiao Industry And Trade Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Haoxiao Industry And Trade Co ltd filed Critical Qingdao Haoxiao Industry And Trade Co ltd
Priority to CN202321486204.1U priority Critical patent/CN220301917U/en
Application granted granted Critical
Publication of CN220301917U publication Critical patent/CN220301917U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a steel tube tower top overhaul fence which comprises a first fence sleeve, a second fence sleeve, a left strong magnet, a fixed connection rope, a sliding ring and a right strong magnet, wherein a movable rod is arranged in the first fence sleeve and the second fence sleeve, the sliding ring is arranged on the outer side of the movable rod, the upper end of the sliding ring is connected with an end fixing rod, the left strong magnet and an end connection block are arranged on the upper portion of the first fence sleeve, the right strong magnet and the end connection block are arranged on the upper portion of the second fence sleeve, and the fixed connection rope is connected on the upper portion of the end connection block.

Description

Steel pipe tower top overhauls rail
Technical Field
The utility model relates to the technical field of steel tube tower fences, in particular to a steel tube tower top overhaul fence.
Background
When overhauling the steel pipe tower, the bottom need be equipped with job site rail, this is not only the responsibility that detects constructor, but also can avoid the emergence of some accidents, prevent to appear the instrument phenomenon that drops in detecting the work progress, utilize the rail can prevent that personnel from getting into dangerous zone, also reach warning effect to pedestrian around, the effect that the rail can make the pedestrian keep away from, reduce the emergence of accident, consequently, need all use the rail to keep apart the protection in some more dangerous places at the job site, can be better when the construction to observe like this, the effect that plays warning protection that can be fine, traditional rail adopts whole installation flexibility relatively poor, and inconvenient use, be inconvenient for simultaneously installing and dismantle, also can not adjust rail whole length, and then reduced the rate of utilization.
Disclosure of Invention
The utility model aims to provide a steel pipe tower top overhaul fence, which solves the problems that the overall installation flexibility of the fence in the prior art is poor, the fence is inconvenient to use, the installation and the disassembly are inconvenient, the overall length of the fence cannot be adjusted, and the utilization rate is reduced.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides a steel pipe tower top overhauls rail, includes first rail sleeve, second rail sleeve, left side powerful magnet, fixed connection rope, slip ring and right side powerful magnet, the telescopic inside of first rail sleeve and second rail is equipped with the movable rod, the outside of movable rod is equipped with the slip ring, and its upper end of slip ring is connected with the tip dead lever, first rail telescopic upper portion is equipped with left powerful magnet and tip connecting block, the telescopic upper portion of second rail is equipped with right side powerful magnet and tip connecting block, the upper portion of tip connecting block is connected with fixed connection rope.
Preferably, the upper end of the moving rod is provided with a limiting plate, the length of the limiting plate is larger than that of the sliding ring, and the sliding ring can be prevented from moving out of the upper end of the moving rod by the limiting plate.
Preferably, the lower parts of the first fence sleeve and the second fence sleeve are fixedly connected with fence bases, and the stability of the first fence sleeve and the second fence sleeve can be improved by utilizing the fence bases.
Preferably, the sliding ring is in sliding connection with the moving rod, a fastening bolt is arranged on the upper portion of the sliding ring, and the acting force of the sliding ring can be increased by using the fastening bolt, so that the sliding ring can be conveniently fixed.
Preferably, the ends of the left strong magnet and the right strong magnet are in semicircular structures, and the upper sides of the left strong magnet and the right strong magnet are connected with metal connecting rods, so that the metal connecting rods can be fixed on the upper parts of the left strong magnet and the right strong magnet at different inclination angles.
Preferably, the end fixing rod is connected with the outer side of the sliding ring through an end fixing block, so that the end fixing rod is conveniently installed on the upper portion of the sliding ring.
Preferably, the sliding ring, the left strong magnet and the right strong magnet are all provided with a plurality of sliding rings and the strong magnets, so that the overall stability and flexibility of the fence can be improved.
Compared with the prior art, the utility model has the beneficial effects that: according to the utility model, the first fence sleeve and the second fence sleeve can be fixed through the matching of the left strong magnet, the right strong magnet and the metal connecting rod, meanwhile, the connecting angle between the fence sleeves can be changed, the overall length of the fence can be conveniently adjusted in a mutually spliced mode, meanwhile, the flexibility of the fence can be improved, the safety of the steel pipe tower can be improved, the installation can be conveniently carried out by utilizing the fixed connecting rope, the weight of the fence can be reduced, and the steel pipe tower has the characteristics of convenience in installation and high flexibility.
Drawings
Fig. 1 is a schematic diagram of a front view structure of the present utility model.
Fig. 2 is a schematic left-hand structural view of the first fence sleeve of the present utility model.
FIG. 3 is a schematic view of a metal connecting rod connection structure according to the present utility model.
In the figure: 1-fence base, 2-first fence sleeve, 3-movable rod, 4-left strong magnet, 5-end connecting block, 6-fixed connection rope, 7-metal connecting rod, 8-slip ring, 9-fastening bolt, 10-end fixed rod, 11-limiting plate, 12-second fence sleeve, 13-right strong magnet.
Description of the embodiments
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1 to 3, in an embodiment of the present utility model, a steel pipe tower top maintenance fence includes a first fence sleeve 2, a second fence sleeve 12, a left strong magnet 4, a fixed connection rope 6, a sliding ring 8 and a right strong magnet 13, wherein moving rods 3 are disposed inside the first fence sleeve 2 and the second fence sleeve 12, so that the moving rods 3 can move up and down inside the first fence sleeve 2 and the second fence sleeve 12, the sliding ring 8 is disposed outside the moving rods 3, the height of the end fixing rod 10 is conveniently adjusted by using the sliding ring 8, the upper end of the sliding ring 8 is connected with the end fixing rod 10, the upper portion of the first fence sleeve 2 is provided with the left strong magnet 4 and the end connection block 5, the fixed connection rope 6 is conveniently fixed by using the end connection block 5, the right strong magnet 13 and the end connection block 5 are disposed on the upper portion of the second fence sleeve 12, the metal connection rod 7 is conveniently fixed by using the left strong magnet 4 and the right strong magnet 13, and the upper portion of the end connection block 5 is conveniently connected with the fixed connection rope 6, and the fixed connection rope 6 can be realized by fixedly connecting the fixed connection rope 6.
Further, the upper end of the moving rod 3 is provided with a limiting plate 11, the length of the limiting plate 11 is greater than that of the sliding ring 8, and the sliding ring 8 can be prevented from moving out of the upper end of the moving rod 3 by the limiting plate 11.
Further, the lower parts of the first fence sleeve 2 and the second fence sleeve 12 are fixedly connected with the fence base 1, and the stability of the first fence sleeve 2 and the second fence sleeve 12 can be improved by using the fence base 1.
Further, the sliding ring 8 is slidably connected with the moving rod 3, a fastening bolt 9 is arranged on the upper portion of the sliding ring 8, and the acting force of the sliding ring 8 can be increased by using the fastening bolt 9, so that the sliding ring 8 can be conveniently fixed.
Further, the ends of the left strong magnet 4 and the right strong magnet 13 are in a semicircular structure, and the metal connecting rod 7 is connected to the upper sides of the left strong magnet 4 and the right strong magnet 13, so that the metal connecting rod 7 can be fixed to the upper parts of the left strong magnet 4 and the right strong magnet 13 at different inclination angles.
Further, the end fixing rod 10 is connected with the outer side of the sliding ring 8 through an end fixing block, so that the end fixing rod 10 is conveniently installed on the upper portion of the sliding ring 8.
Further, the sliding ring 8, the left strong magnet 4 and the right strong magnet 13 are all provided with a plurality of sliding rings 8 and strong magnets, so that the overall stability and flexibility of the fence can be improved.
The working principle of the utility model is as follows: when the fence is used, the movable rod 3 can move up and down in the first fence sleeve 2 and the second fence sleeve 12, the height of the fence can be improved, the height of the end fixing rod 10 can be conveniently adjusted by utilizing the sliding ring 8, the acting force of the sliding ring 8 can be increased through the fastening bolt 9, the sliding ring 8 is further conveniently fixed, the movable rod 3 can be prevented from moving downwards, the limiting plate 11 can prevent the sliding ring 8 from moving out of the upper end of the movable rod 3, the fixed connection rope 6 can be installed on the upper part of the end connecting block 5, blocking can be realized through the fixed connection rope 6, and the metal connecting rod 7 is fixed on the upper parts of the left strong magnet 4 and the right strong magnet 13 at different inclination angles, so that the angle between the first fence sleeve 2 and the second fence sleeve 12 can be changed, the first fence sleeve 2 and the second fence sleeve 12 can achieve the aim of assembling the fence.
It will be evident to those skilled in the art that the utility model is not limited to the details of the foregoing illustrative embodiments, and that the present utility model may be embodied in other specific forms without departing from the spirit or essential characteristics thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the utility model being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (7)

1. The utility model provides a steel pipe tower top overhauls rail, includes first rail sleeve (2), second rail sleeve (12), left side powerful magnet (4), fixed connection rope (6), slip ring (8) and right side powerful magnet (13), its characterized in that: the inside of first rail sleeve (2) and second rail sleeve (12) is equipped with movable rod (3), the outside of movable rod (3) is equipped with slip ring (8), and the upper end of its slip ring (8) is connected with tip dead lever (10), the upper portion of first rail sleeve (2) is equipped with left side powerful magnet (4) and tip connecting block (5), the upper portion of second rail sleeve (12) is equipped with right side powerful magnet (13) and tip connecting block (5), the upper portion of tip connecting block (5) is connected with fixed connection rope (6).
2. The steel pipe tower top maintenance fence of claim 1, wherein: the upper end of the movable rod (3) is provided with a limiting plate (11), and the length of the limiting plate (11) is greater than that of the sliding ring (8).
3. The steel pipe tower top maintenance fence of claim 1, wherein: the lower parts of the first fence sleeve (2) and the second fence sleeve (12) are fixedly connected with a fence base (1).
4. The steel pipe tower top maintenance fence of claim 1, wherein: the sliding ring (8) is connected with the moving rod (3) in a sliding manner, and a fastening bolt (9) is arranged on the upper portion of the sliding ring (8).
5. The steel pipe tower top maintenance fence of claim 1, wherein: the ends of the left strong magnet (4) and the right strong magnet (13) are of semicircular structures, and the upper sides of the left strong magnet (4) and the right strong magnet (13) are connected with a metal connecting rod (7).
6. The steel pipe tower top maintenance fence of claim 1, wherein: the end fixing rod (10) is connected with the outer side of the sliding ring (8) through an end fixing block.
7. The steel pipe tower top maintenance fence of claim 1, wherein: the sliding ring (8), the left strong magnet (4) and the right strong magnet (13) are all provided with a plurality of magnets.
CN202321486204.1U 2023-06-12 2023-06-12 Steel pipe tower top overhauls rail Active CN220301917U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321486204.1U CN220301917U (en) 2023-06-12 2023-06-12 Steel pipe tower top overhauls rail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321486204.1U CN220301917U (en) 2023-06-12 2023-06-12 Steel pipe tower top overhauls rail

Publications (1)

Publication Number Publication Date
CN220301917U true CN220301917U (en) 2024-01-05

Family

ID=89347962

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321486204.1U Active CN220301917U (en) 2023-06-12 2023-06-12 Steel pipe tower top overhauls rail

Country Status (1)

Country Link
CN (1) CN220301917U (en)

Similar Documents

Publication Publication Date Title
CN203530851U (en) Basket device for combined basket working vehicle
CN201401005Y (en) Template sliding and lifting device
CN220301917U (en) Steel pipe tower top overhauls rail
CN204625045U (en) A kind of steel structure hoisting door shaped stent formula hanging apparatus
CN218145329U (en) Steel pipe hoisting frame with damping and buffering functions
CN207158651U (en) Modular assembly formula automatic lifting tower crane attached wall workbench
CN202745353U (en) Tool-type overhanging scaffold
CN211569905U (en) Net rack short column embedded part hoisting device
CN209493853U (en) A kind of support frame structure of high-speed railway attaching scaffold
CN203354460U (en) Hanging basket oblique face moving mechanism
CN111908334A (en) Method for assembling and disassembling portal crane and auxiliary support structure
CN205532362U (en) Long stroke righting device for pylon can shirk
CN206487128U (en) A kind of Guiding Support Elevating Scaffold
CN110748140A (en) Track beam hanging basket special for stepped curtain wall
CN215595462U (en) Climbing-preventing ladder stand for steel pipe pole of power transmission line
CN214692997U (en) Safe suspension structure for high-altitude construction of building
CN215657597U (en) Improve bed-jig of prefabricated pier stud steel reinforcement cage assembly precision
CN213710301U (en) Guide diagonal bracing
CN220952977U (en) Accurate positioning and mounting device for partial cable-stayed bridge cable guide pipe
CN220767740U (en) Multifunctional vehicle suitable for installation of overlength landing stage guardrail
CN218597695U (en) Auxiliary installation mechanism of rail transit elevated section outer side guardrail
CN220849117U (en) Guardrail for construction
CN210216217U (en) Road traffic signboard
CN218493326U (en) Quick detachable protective bracket
CN218411205U (en) Building tower crane verticality detection device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant