CN220285465U CN202321462583.0U CN202321462583U CN220285465U CN 220285465 U CN220285465 U CN 220285465U CN 202321462583 U CN202321462583 U CN 202321462583U CN 220285465 U CN220285465 U CN 220285465U
Authority
CN
China
Prior art keywords
guardrail
boss
hole
construction
groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321462583.0U
Other languages
Chinese (zh)
Inventor
范璐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Hubang Construction Engineering Co ltd
Original Assignee
Jiangsu Hubang Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Hubang Construction Engineering Co ltd filed Critical Jiangsu Hubang Construction Engineering Co ltd
Priority to CN202321462583.0U priority Critical patent/CN220285465U/en
Application granted granted Critical
Publication of CN220285465U publication Critical patent/CN220285465U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The application discloses construction guardrail belongs to building site guardrail technical field. The novel anti-collision device mainly comprises a first guardrail, wherein the end part of the first guardrail extends to form a mounting table, a mounting hole is formed in the mounting table, a second guardrail is provided with a groove in the second guardrail, the groove is matched with the first guardrail, the first guardrail is suitable for sliding in the groove, the end part of the second guardrail extends to form a connecting table, the connecting table is provided with a connecting hole, a sliding part is used for connecting the mounting table with the connecting table, the sliding part comprises a spring, the spring is fixed in the mounting hole, a boss is arranged at the top of the spring, the boss is rotatably arranged in the connecting hole, a roller is fixedly arranged on the boss, the second guardrail is provided with a groove, the first guardrail is suitable for sliding in the groove, and the second guardrail is connected with the first guardrail through the sliding part. The utility model provides a construction guardrail has solved the problem that the guardrail is inconvenient for accomodate.

Description

Building construction guardrail
Technical Field
The application relates to the technical field of construction site guardrails, in particular to a building construction guardrail.
Background
In the building construction process, the protection problem in construction is inevitably encountered, and in order to strengthen the safety measure, the construction party mostly uses fences or coamings on the whole construction site, thereby meeting the requirement of closed construction and further requiring the guardrails to isolate the building construction site;
the utility model patent with publication number CN216341454U specifically discloses a safe type construction guardrail, which comprises a protective fence and fixed columns arranged on two sides of the protective fence, wherein the protective fence is inserted on the two groups of fixed columns and supports the protective fence through the fixed columns on two sides;
in the above-mentioned publication, this construction guardrail supports the rail guard through the fixed column to keep apart construction, but the rail guard in this construction guardrail is fixed structure, thereby this rail guard size is unadjustable, when accomodating this rail guard, this construction guardrail can only accomodate through whole, and can not adjust the rail guard on it and accomodate, make this construction guardrail occupy great space, so it is necessary to provide a construction guardrail to solve above-mentioned problem.
It should be noted that the above information disclosed in this background section is only for understanding the background of the present application concept and, therefore, it may contain information that does not constitute prior art.
Disclosure of Invention
Based on the above problems existing in the prior art, the problems to be solved by the present application are: the utility model provides a construction guardrail, has solved the problem that the guardrail is inconvenient for accomodate.
The technical scheme adopted for solving the technical problems is as follows: the utility model provides a construction guardrail, includes first guardrail, and the tip of this first guardrail extends has the mount table, set up the mounting hole on the mount table, the second guardrail is seted up flutedly in this second guardrail, the recess with first guardrail assorted, first guardrail is suitable for slide in the recess, the tip of second guardrail extends has the connection platform, the connecting hole has been seted up on the connection bench, sliding part, this sliding part be used for with the mount table with connect between the platform, the sliding part includes the spring, this spring is fixed in the mounting hole, the boss, this boss install in the spring top, the boss rotate install in the connecting hole, the gyro wheel, this gyro wheel fixed mounting in on the boss, the gyro wheel is used for driving first guardrail is convenient for slide.
Further, a fixing part is further arranged between the mounting table and the connecting table, the fixing part comprises an adjusting hole formed in the mounting table, the adjusting hole is arranged around the boss, and a locking hole corresponding to the adjusting hole is formed in the connecting table.
Further, the first guardrail and the second guardrail are composed of an upper group of cross beams and a lower group of cross beams and vertical rods fixed between the two groups of cross beams.
Further, the first guardrail with one side of second guardrail is all fixed mounting has the stand, the stand is used for first guardrail with the second guardrail supports.
Further, the first guard rail and the second guard rail are both made of stainless steel materials.
The beneficial effects of this application are: the utility model provides a pair of construction guardrail sets up flutedly on the second guardrail for first guardrail is suitable for to slide in the recess, and is connected between second guardrail and the first guardrail through the sliding part, thereby has solved the problem that the guardrail is inconvenient for accomodate.
In addition to the objects, features, and advantages described above, there are other objects, features, and advantages of the present application. The present application will be described in further detail with reference to the drawings.
Drawings
The accompanying drawings, which are included to provide a further understanding of the application and are incorporated in and constitute a part of this application, illustrate embodiments of the application and together with the description serve to explain the application and do not constitute an undue limitation to the application. In the drawings:
FIG. 1 is an overall schematic view of a construction barrier of the present application;
FIG. 2 is an exploded view of the building construction barrier of FIG. 1;
FIG. 3 is an enlarged schematic view of FIG. 2 at A;
FIG. 4 is a schematic view of the construction barrier of FIG. 1 in a curved condition;
FIG. 5 is a schematic view of the construction barrier of FIG. 1 in a contracted state;
wherein, each reference sign in the figure:
1. a first guardrail; 11. a mounting table; 2. a second guardrail; 21. a groove; 22. a connection station; 3. a connecting mechanism; 31. a boss; 32. a spring; 33. an adjustment aperture; 34. a connection hole; 35. locking holes.
Detailed Description
It should be noted that, in the case of no conflict, the embodiments and features in the embodiments may be combined with each other. The present application will be described in detail below with reference to the accompanying drawings in conjunction with embodiments.
In order to make the present application solution better understood by those skilled in the art, the following description will be made in detail and with reference to the accompanying drawings in the embodiments of the present application, it is apparent that the described embodiments are only some embodiments of the present application, not all embodiments. All other embodiments, which can be made by one of ordinary skill in the art based on the embodiments herein without making any inventive effort, shall fall within the scope of the present application.
As shown in fig. 1, the application provides a building construction guardrail, which comprises a first guardrail 1 and a second guardrail 2, wherein the first guardrail 1 and the second guardrail 2 are made of stainless steel materials, the first guardrail 1 and the second guardrail 2 are composed of an upper group of cross beams, a lower group of cross beams and upright rods fixed between the two groups of cross beams, upright posts are fixedly arranged on one sides of the first guardrail 1 and the second guardrail 2, and the upright posts are used for supporting the first guardrail 1 and the second guardrail 2;
as shown in fig. 2-3, grooves 21 are formed in the upper and lower groups of cross beams of the second guardrail 2, and the grooves 21 are matched with the two groups of cross beams of the first guardrail 1, so that the first guardrail 1 can be inserted into the second guardrail 2, and the first guardrail 1 is suitable for sliding in the grooves 21;
the beam end of the first guardrail 1 is extended with a mounting table 11, the mounting table 11 is provided with a mounting hole (not shown in the figure), the beam end of the second guardrail 2 is extended with a connecting table 22, a connecting mechanism 3 is arranged between the mounting table 11 and the connecting table 22, and the connecting mechanism 3 is used for connecting and fixing the mounting table 11 and the connecting table 22
The connecting mechanism 3 comprises a sliding part, the sliding part is fixed in the mounting hole of the mounting table 11, the connecting table 22 is provided with a connecting hole 34, the sliding part is penetrated in the connecting hole 34 of the connecting table 22 so as to connect the mounting table 11 and the connecting table 22, and the sliding part is suitable for sliding in the connecting table 22;
the sliding part comprises a spring 32, the spring 32 is fixed in a mounting hole of the mounting table 11, a boss 31 is fixed at the top of the spring 32, the boss 31 is matched with the mounting hole and the connecting hole 34, so that the boss 31 is suitable for reciprocating movement in the mounting hole and the connecting hole 34, and a roller is arranged at the top of the boss 31;
when the first guardrail 1 and the second guardrail 2 need to be stored (as shown in fig. 5), the boss 31 is pressed, so that the boss 31 leaves the connecting hole 34 and moves into the mounting hole, and meanwhile, the first guardrail 1 is pushed, and the first guardrail 1 is driven to slide in the groove 21 of the second guardrail 2 through the roller on the boss 31;
when the first guardrail 1 and the second guardrail 2 are needed to be used (as shown in fig. 1), the first guardrail 1 is pulled, the first guardrail 1 is driven to slide in the groove 21 by the rollers on the boss 31, and the boss 31 is clamped into the connecting hole 34 of the connecting table 22 by the elasticity of the spring 32 to the boss 31, so that the first guardrail 1 and the second guardrail 2 are connected;
in summary, the second guardrail 2 is provided with the groove 21, so that the first guardrail 1 is suitable for sliding in the groove 21, and the second guardrail 2 and the first guardrail 1 are connected through the sliding part, thereby achieving the purpose that the second guardrail 2 and the first guardrail 1 are convenient to store;
meanwhile, the boss 31 is in rotary connection with the connecting table 22, so that the first guardrail 1 and the second guardrail 2 are suitable for rotating around the boss 31, and the effect of adjusting the angle between the first guardrail 1 and the second guardrail 2 is achieved;
the connecting mechanism 3 also comprises a locking part, and the locking part is used for fixing the first guardrail 1 and the second guardrail 2;
the locking part comprises adjusting holes 33, the adjusting holes 33 are formed in the mounting table 11 and are provided with a plurality of groups, the adjusting holes 33 are arranged around the boss 31, meanwhile, the connecting table 22 is provided with locking holes 35, and the locking holes 35 correspond to the adjusting holes 33, so that the locking holes 35 are connected with the adjusting holes 33 through bolts to fix the first guardrail 1 and the second guardrail 2;
when the angle between the first rail 1 and the second rail 2 is adjusted (as shown in fig. 4), the angle between the first rail 1 and the second rail 2 is adjusted so that the locking hole 35 corresponds to the adjusting hole 33, and then the locking hole 35 is connected with the adjusting hole 33 through a bolt, so that the first rail 1 and the second rail 2 are fixed.
The foregoing description is only of the preferred embodiments of the present application and is not intended to limit the same, but rather, various modifications and variations may be made by those skilled in the art. Any modification, equivalent replacement, improvement, etc. made within the spirit and principles of the present application should be included in the protection scope of the present application.

Claims (5)

1. A construction guardrail comprising:
the guardrail comprises a first guardrail (1), wherein an installation table (11) extends from the end part of the first guardrail (1), and an installation hole is formed in the installation table (11);
the second guardrail (2) is internally provided with a groove (21), the groove (21) is matched with the first guardrail (1), the first guardrail (1) is suitable for sliding in the groove (21), the end part of the second guardrail (2) is extended with a connecting table (22), and the connecting table (22) is provided with a connecting hole (34);
a sliding part for connecting the mounting table (11) and the connection table (22), characterized in that: the sliding portion includes:
a spring (32), the spring (32) being fixed in the mounting hole;
a boss (31), wherein the boss (31) is fixed on the top of the spring (32), and the boss (31) is rotatably installed in the connecting hole (34);
the roller is fixedly arranged on the boss (31) and is used for driving the first guardrail (1) to slide conveniently.
2. A construction guardrail according to claim 1, characterized in that: the fixing part is further arranged between the mounting table (11) and the connecting table (22), the fixing part comprises an adjusting hole (33) formed in the mounting table (11), the adjusting hole (33) is arranged around the boss (31), and a locking hole (35) corresponding to the adjusting hole (33) is formed in the connecting table (22).
3. A construction guardrail according to claim 1, characterized in that: the first guardrail (1) and the second guardrail (2) are composed of an upper group of cross beams and a lower group of cross beams and vertical rods fixed between the two groups of cross beams.
4. A construction guardrail according to claim 3, characterized in that: the first guardrail (1) and one side of the second guardrail (2) are fixedly provided with upright posts, and the upright posts are used for supporting the first guardrail (1) and the second guardrail (2).
5. A construction guardrail according to claim 4, characterized in that: the first guardrail (1) and the second guardrail (2) are both made of stainless steel materials.
CN202321462583.0U 2023-06-09 2023-06-09 Building construction guardrail Active CN220285465U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321462583.0U CN220285465U (en) 2023-06-09 2023-06-09 Building construction guardrail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321462583.0U CN220285465U (en) 2023-06-09 2023-06-09 Building construction guardrail

Publications (1)

Publication Number Publication Date
CN220285465U true CN220285465U (en) 2024-01-02

Family

ID=89341004

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321462583.0U Active CN220285465U (en) 2023-06-09 2023-06-09 Building construction guardrail

Country Status (1)

Country Link
CN (1) CN220285465U (en)

Similar Documents

Publication Publication Date Title
CN210970834U (en) Transportation strutting arrangement that can quick fixed precast segment roof beam
CN220285465U (en) Building construction guardrail
DE59905925D1 (en) Guard rail arrangement
CN210798483U (en) Construction fence for building based on environmental protection
CN220747853U (en) Outdoor construction rail guard
CN111535658A (en) Road construction safety protective guard
CN210460172U (en) Combined type isolation gate
CN220166770U (en) Rail guard for municipal works
CN219604231U (en) Novel guardrail of municipal building
CN215561968U (en) Combined pier column protective net for bridge engineering
CN219691255U (en) Protective fence with good protective effect
CN218715713U (en) Highway maintenance warning fence
CN220889762U (en) Railing assembly with anti-toppling structure
CN216476703U (en) Rail guard is used in public road bridge roof beam construction
CN211691808U (en) Assembled landscape construction is with warning rail
CN211691795U (en) Construction guardrail
CN218715729U (en) Retractable construction guardrail
CN215758709U (en) Public road bridge roof beam buffer stop
CN215978837U (en) Road bridge tunnel construction rail guard
CN219931837U (en) Foundation pit excavation supporting structure
CN220813587U (en) Municipal administration guardrail
CN220550960U (en) Bridge foundation pit protection device
CN220869004U (en) Municipal construction rail guard
CN218563277U (en) Safety protective guard for building engineering
CN213391301U (en) Edge-facing multifunctional protective fence for building construction

Legal Events