CN220226393U CN202321800721.1U CN202321800721U CN220226393U CN 220226393 U CN220226393 U CN 220226393U CN 202321800721 U CN202321800721 U CN 202321800721U CN 220226393 U CN220226393 U CN 220226393U
Authority
CN
China
Prior art keywords
plate
hall
water blocking
support
steel structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321800721.1U
Other languages
Chinese (zh)
Inventor
郑兆欣
刘文峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Chemical Transportation Construction Group Operation Management Shandong Co ltd
Original Assignee
China Chemical Transportation Construction Group Operation Management Shandong Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Chemical Transportation Construction Group Operation Management Shandong Co ltd filed Critical China Chemical Transportation Construction Group Operation Management Shandong Co ltd
Priority to CN202321800721.1U priority Critical patent/CN220226393U/en
Application granted granted Critical
Publication of CN220226393U publication Critical patent/CN220226393U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Building Environments (AREA)

Abstract

The utility model discloses a hall steel structure, which mainly comprises hall steel columns and connecting plates, wherein foundation bolts are needed to be embedded on the ground before the hall is built, the hall is not convenient to install after the building is built, when the hall rains, accumulated water at the top of the hall flows down to two sides and the front, pedestrians enter the hall and are easy to be sprayed by the accumulated water flowing down.

Description

Hall steel structure
Technical Field
The utility model belongs to the technical field of steel structures, and particularly relates to a hall steel structure.
Background
Compared with concrete, the steel structure has the characteristics of light weight and high structural strength, and is widely applied to building decoration, factory building construction and bridge construction, wherein the application of the steel structure for building decoration is fastest, the steel structure for building decoration only has burglary-resisting windows and burglary-resisting doors, the steel structure is rapidly developed in the building decoration industry along with popularization of the green building concept, and the construction of bird nest gymnasiums is an important witness, so that the halls of a large number of buildings adopt the steel structure.
However, the existing steel structure of the hall mainly comprises hall steel columns and connecting plates, foundation bolts are needed to be embedded in the ground before the hall is built, the hall is not convenient to install after the building is built, accumulated water at the top of the hall flows down to two sides and the front when raining, and pedestrians enter the hall and are easily sprayed by the accumulated water flowing down.
Disclosure of Invention
Aiming at the situation, in order to overcome the defects of the prior art, the utility model provides the steel structure of the hall, which effectively solves the problems that the steel structure of the hall mainly comprises hall steel columns and connecting plates, foundation bolts are needed to be embedded in the ground before the hall is built, the hall is not convenient to be additionally arranged after the building is built, accumulated water at the top of the hall flows down to two sides and the front when raining, and pedestrians enter the hall and are easy to be sprayed by the accumulated water flowing down.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides a hall steel construction, includes first support, first support bottom is fixed with first breakwater, the roof is installed on first support top, the roof top is connected with the buckled plate, the fixed plate is installed at first support top, the fixed plate top is connected with the third support, the toggle plate is installed at the third support top, the fixed plate middle part is connected with the sleeve pipe, sleeve pipe one end is kept away from to the fixed plate is fixed with the nut, the sleeve pipe inboard has cup jointed the second spliced pole, second spliced pole one end is connected with first spliced pole, the second spliced pole is kept away from first spliced pole one end and is seted up flutedly, the second support is installed to the fixed plate bottom, the sliding tray has been seted up to the second support bottom, the water blocking curtain is installed to the sliding tray bottom.
Preferably, the water blocking curtain comprises a second water blocking plate and a third water blocking plate, wherein the third water blocking plate is arranged at one end of the second water blocking plate, and the width of the second water blocking plate is four times that of the third water blocking plate.
Preferably, a rubber strip is mounted at the top of the sliding groove.
Preferably, five reinforcing ribs are uniformly distributed and fixed at the bottom end of the top plate, and the reinforcing ribs are made of steel.
Preferably, a waist round hole is formed in the middle of the sleeve.
Compared with the prior art, the utility model has the beneficial effects that:
the utility model has convenient installation, can be additionally installed after building, has small construction quantity, meets the development requirement of green buildings, has the flow guiding function on the accumulated water by the corrugated plates arranged at the top, ensures that the accumulated water only flows out of two sides of a hall, and pedestrians enter from the front of the hall, thereby avoiding being sprayed by the accumulated water.
The water blocking curtain is arranged, so that the water blocking curtain can be pulled to enable the top of the water blocking curtain to move to the top of the sliding groove when the water blocking curtain meets heavy rainfall weather, and the water blocking curtain and the first water blocking plate can play a role in blocking water to prevent accumulated water outside a building from entering the building.
Drawings
The accompanying drawings are included to provide a further understanding of the utility model and are incorporated in and constitute a part of this specification, illustrate the utility model and together with the embodiments of the utility model, serve to explain the utility model. In the drawings:
FIG. 1 is a schematic diagram of the overall structure of the present utility model;
FIG. 2 is a schematic view of the installation structure of the reinforcing rib of the present utility model;
FIG. 3 is a schematic view of a first connector post mounting structure according to the present utility model;
fig. 4 is a schematic view of a second water baffle installation structure of the present utility model.
In the figure: 1. a first water baffle; 2. a first bracket; 3. a sliding groove; 4. a second bracket; 5. a sleeve; 6. a toggle plate; 7. a third bracket; 8. corrugated plates; 9. a water blocking curtain; 10. a top plate; 11. reinforcing ribs; 12. a first connection post; 13. a second connection post; 14. a nut; 15. a groove; 16. a fixing plate; 91. a second water baffle; 92. and a third water baffle.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
As shown in fig. 1, fig. 2, fig. 3 and fig. 4, an embodiment of the present utility model provides a hall steel structure, which comprises a first bracket 2, a first water baffle 1 is fixed at the bottom of the first bracket 2, a top plate 10 is installed at the top end of the first bracket 2, a corrugated plate 8 is connected at the top end of the top plate 10, a fixing plate 16 is installed at the top of the first bracket 2, a third bracket 7 is connected at the top end of the fixing plate 16, a toggle plate 6 is installed at the top of the third bracket 7, a sleeve 5 is connected in the middle of the fixing plate 16, a nut 14 is fixed at one end of the fixing plate 16 far from the sleeve 5, a second connecting column 13 is sleeved at the inner side of the sleeve 5, a first connecting column 12 is connected at one end of the second connecting column 13 far from the first connecting column 12, a groove 15 is provided at one end of the bottom of the fixing plate 16, a second bracket 4 is installed at the bottom of the second bracket 4, a sliding groove 3 is provided at the bottom of the sliding groove 3, and a water blocking curtain 9 is installed at the bottom of the sliding groove 3.
The water blocking curtain 9 comprises a second water blocking plate 91 and a third water blocking plate 92, the third water blocking plate 92 is arranged at one end of the second water blocking plate 91, and the width of the second water blocking plate 91 is four times of that of the third water blocking plate 92
Specifically, a rubber strip is arranged at the top of the sliding groove 3.
Specifically, five reinforcing ribs 11 are uniformly distributed and fixed at the bottom end of the top plate 10, and the reinforcing ribs 11 are made of steel.
Specifically, a waist round hole is formed in the middle of the sleeve 5.
First, given by fig. 1, fig. 2 and fig. 3, nut 14 and fixed plate 16 are fixed through the welding mode, the internal thread has been seted up to nut 14 inboard, the external screw thread has been seted up in the second spliced pole 13 outside, rotatory second spliced pole 13 can make second spliced pole 13 take place for nut 14, nut 14 can drive first spliced pole 12 and remove, intensive lug is installed in the sleeve pipe 5 outside, can ensure that sleeve pipe 5 atress is out of shape after, can produce stable frictional force, buckled plate 8 can play the effect of leading water, three toggle plates 6 are evenly installed at third support 7 top, can strengthen the effect to steel construction atress, first breakwater 1 is also installed to second support 4 and the symmetrical position of first support 2, first breakwater 1 is kept away from first support 2 one end and is fixed with sealed rubber slab, first breakwater 1 bottom also is fixed with the rubber slab, play sealed effect, the rubber strip is installed at the sliding groove 3 top, can ensure that when water blocking curtain 9 removes to sliding groove 3 top, the frictional force that produces is fixed water blocking curtain 9, the ripple plate 8 is a glass curtain that is equipped with when guaranteeing that the effect is still can be passed through in the groove, when guaranteeing that the effect is opened.
In the second embodiment, the same features as those of the first embodiment are not described in detail, and the different features of the first embodiment are as follows: given by fig. 1 and 4, in this embodiment, the buckled plate 8 is formed by having rectangular sheet metal hinged joint, makes buckled plate 8 can fold, can adjust buckled plate 8 expansion length as required, and manger plate curtain 9 comprises a second manger plate 91 and polylith third manger plate 92, and the rubber strip has been pressed from both sides between second manger plate 91 and the third manger plate 92, also has pressed from both sides the rubber strip between third manger plate 92 and the third manger plate 92, connects through the socket joint mode between second manger plate 91 and the third manger plate 92, can ensure that the angle can be produced between second manger plate 91 and the third manger plate 92, ensures can remove in sliding tray 3.
Working principle: when using a hall steel construction, first support 2 and second support 4 place subaerial at the level, insert sleeve pipe 5, first spliced pole 12 and second spliced pole 13 in the hole that building wall offered, the hole that building wall offered should slightly be greater than sleeve pipe 5 external diameter, second spliced pole 13 and nut 14 pass through threaded connection, rotatory second spliced pole 13 can make second spliced pole 13 remove in nut 14, nut 14 and fixed plate 16 are fixed through the welding mode, nut 14 can not rotate and remove, second spliced pole 13 removes and can make first spliced pole 12 also remove, first spliced pole 12 and fixed plate 16 begin extrusion sleeve pipe 5, the waist round hole has been offered at sleeve pipe 5 middle part and is more easily by the extrusion deformation, can fill up the hole that building wall offered at the instantaneous speed, play fixed effect, the toggle plate 6 can play the effect that the structure is strengthened, building buckled plate 8 can be in rainy, make the ponding flow down both sides from the low-lying department of buckled plate 8, avoid ponding to flow out from the hall place ahead, meet the weather and keep off, can make water bar 9 and the top be moved to the top 9, can slide to the top 9, the top is fixed to the top is realized to the top by the high-friction strip, the top is avoided, the top is reached to the top is fixed 9, the top is reached to the top is fixed to the top is reached to the top is can be moved to the top is 9.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. Hall steel structure, including first support (2), its characterized in that: the utility model discloses a waterproof curtain, including first support (2), first bracket (2), roof (10) are installed on first support (2) top, roof (10) top is connected with buckled plate (8), fixed plate (16) are installed at first support (2) top, fixed plate (16) top is connected with third support (7), toggle plate (6) are installed at third support (7) top, fixed plate (16) middle part is connected with sleeve pipe (5), sleeve pipe (5) one end is kept away from to fixed plate (16) is fixed with nut (14), second spliced pole (13) have been cup jointed to sleeve pipe (5) inboard, second spliced pole (13) one end is connected with first spliced pole (12), recess (15) are seted up to second spliced pole (13) one end of keeping away from first spliced pole (12), second support (4) are installed to fixed plate (16) bottom, sliding tray (3) are seted up to second support (4) bottom, water-blocking curtain (9) are installed to sliding tray (3) bottom.
2. A lobby steel structure according to claim 1, wherein: the water blocking curtain (9) comprises a second water blocking plate (91) and a third water blocking plate (92), the third water blocking plate (92) is arranged at one end of the second water blocking plate (91), and the width of the second water blocking plate (91) is four times that of the third water blocking plate (92).
3. A lobby steel structure according to claim 1, wherein: the top of the sliding groove (3) is provided with a rubber strip.
4. A lobby steel structure according to claim 1, wherein: five reinforcing ribs (11) are uniformly distributed and fixed at the bottom end of the top plate (10), and the reinforcing ribs (11) are made of steel.
5. A lobby steel structure according to claim 1, wherein: a waist round hole is formed in the middle of the sleeve (5).
CN202321800721.1U 2023-07-11 2023-07-11 Hall steel structure Active CN220226393U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321800721.1U CN220226393U (en) 2023-07-11 2023-07-11 Hall steel structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321800721.1U CN220226393U (en) 2023-07-11 2023-07-11 Hall steel structure

Publications (1)

Publication Number Publication Date
CN220226393U true CN220226393U (en) 2023-12-22

Family

ID=89193884

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321800721.1U Active CN220226393U (en) 2023-07-11 2023-07-11 Hall steel structure

Country Status (1)

Country Link
CN (1) CN220226393U (en)

Similar Documents

Publication Publication Date Title
CN220226393U (en) Hall steel structure
CN103352549B (en) A kind of steel-structure backflow-type double-layer colorful-plate rain tent
CN206408806U (en) A kind of glass sunlight house
CN201671190U (en) Flashing device of roof pipeline of steel structure building
CN209742033U (en) Rainwater hopper for urban road
CN106968418A (en) A kind of cell underground garage ventilation and lighting well construction
CN210086678U (en) Ancient building flying rafter structure constructed by metal plates
CN206219981U (en) A kind of Selection of Urban Pedestrian Overpass water guide discharge structure
CN206917105U (en) A kind of eaves structure with mine dam
CN206267005U (en) A kind of overpass with guiding gutter
CN209891519U (en) Reinforced concrete storage bin top cover plate structure
CN214301242U (en) Bridge expansion joint waterproofing mechanism
CN218324485U (en) Waterproof construction is used in villa decoration
CN210766980U (en) Gardens design is with preventing waterlogging rainwater collector convenient to installation
CN214531591U (en) Modeling awning and high-through stainless steel stand column
CN219773304U (en) Grid stone curtain wall connection structure with waterproof function
CN218176088U (en) Novel well lid
CN209855089U (en) Canopy of first floor self-remaining courtyard of house
CN220487226U (en) Photovoltaic bicycle shed beneficial to drainage
CN217325696U (en) Special-shaped dome drain pipe
CN217104510U (en) Drainage structure for plugging drainage hole of high-speed railway
CN214786374U (en) Workshop factory building steelframe
CN220267039U (en) Efficient streamline roof ventilation and cooling device
CN112177253B (en) Door and window aluminum alloy eaves mouth knot formula structure
CN215167356U (en) Steel construction of canopy