CN220117027U - Positioning device for beam pier top preformed hole of tenon type anti-falling beam of high-speed railway - Google Patents

Positioning device for beam pier top preformed hole of tenon type anti-falling beam of high-speed railway Download PDF

Info

Publication number
CN220117027U
CN220117027U CN202321505189.0U CN202321505189U CN220117027U CN 220117027 U CN220117027 U CN 220117027U CN 202321505189 U CN202321505189 U CN 202321505189U CN 220117027 U CN220117027 U CN 220117027U
Authority
CN
China
Prior art keywords
adjusting
pier top
speed railway
positioning device
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321505189.0U
Other languages
Chinese (zh)
Inventor
王宗林
安东林
韩付亮
李学意
李岩
赫耀飞
张璞
王彦强
袁晓红
赵阳阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 3 Engineering Group Co Ltd
Six Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Original Assignee
China Railway No 3 Engineering Group Co Ltd
Six Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 3 Engineering Group Co Ltd, Six Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd filed Critical China Railway No 3 Engineering Group Co Ltd
Priority to CN202321505189.0U priority Critical patent/CN220117027U/en
Application granted granted Critical
Publication of CN220117027U publication Critical patent/CN220117027U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to the technical field of tenon type beam falling prevention construction, in particular to a positioning device for a reserved hole on a pier top of a tenon type beam falling prevention pier of a high-speed railway, which comprises the following components: the clamp is arranged on the pier top die and is used for clamping the integral mechanism; the transverse adjusting mechanism is used for fixing the positioning die sleeve at a preset position; the power switching mechanism is fixedly connected to the clamp and comprises a supporting end and an adjusting end, the adjusting end is fixedly connected with the transverse adjusting mechanism, and the supporting end is fixedly connected to the clamp. The setting of this switching mechanism, switching mechanism can carry out adaptability according to the actual position of location die sleeve and adjust, can make the location die sleeve remove in the direction of height, can adjust the hole degree of depth, can switch to with transverse adjustment mechanism meshing, can make it adjust in the width direction, can adjust the distance between two holes like this, it is convenient to adjust like this.

Description

Positioning device for beam pier top preformed hole of tenon type anti-falling beam of high-speed railway
Technical Field
The utility model relates to the technical field of tenon type beam falling prevention construction, in particular to a positioning device for a pier top preformed hole of a tenon type beam falling prevention of a high-speed railway.
Background
The tenon-shaped anti-falling beam is arranged between the pier top and the beam bottom, and a certain gap is reserved between the longitudinal bridge direction and the transverse bridge direction of the device, and the structure and the action mechanism can be briefly described as follows: the steel cylinder is embedded in the position corresponding to the beam body and the pier top, a solid steel tenon is inserted into the steel cylinder, the diameter of the steel tenon is smaller than the inner diameter of the steel cylinder, when the beam body and the pier body are subjected to relative displacement exceeding a preset level, the upper end and the lower end of the steel tenon are in contact with the inner wall of the steel cylinder, the steel cylinder starts to be stressed to generate elastic deformation, and then the steel cylinder is subjected to plastic deformation, so that the damping, shock insulation and limiting effects with the buffering effect are realized.
In modern high-speed railway bridge construction, the construction pier top of the tenon type anti-falling beam is provided with a large number of reserved hole sites, and the requirement on the position accuracy of the reserved hole is high. The prior art usually comprises the steps of pre-burying a PVC sleeve or an iron sleeve for forming holes before concrete pouring, wherein the pre-burying PVC sleeve or the iron sleeve is mainly bound and fixed by binding wires and filler steel bars, the pre-burying efficiency is low, and the pre-burying efficiency is easily influenced by lateral pressure of concrete and vibration to generate deflection, so that hole position errors are large, and the post-burying PVC sleeve or the iron sleeve is difficult to treat, wastes time and labor and takes time and labor.
Disclosure of Invention
In order to solve the technical problems, the utility model provides a positioning device for a reserved hole on the pier top of a tenon type beam falling prevention pier of a high-speed railway.
The technical scheme of the utility model is realized as follows:
a high-speed railway tenon type beam falling prevention pier top preformed hole positioning device comprises:
the clamp is arranged on the pier top die and is used for clamping the integral mechanism;
the transverse adjusting mechanism is used for fixing the positioning die sleeve at a preset position;
the power switching mechanism is fixedly connected to the clamp and comprises a supporting end and an adjusting end, the adjusting end is fixedly connected with the transverse adjusting mechanism, and the supporting end is fixedly connected to the clamp;
the adjusting end comprises a transverse adjusting mechanism used for fixing, the adjusting end is connected with the supporting end, and a switching mechanism is arranged in the adjusting end.
Further, a fastening bolt is arranged on the clamp, and the clamp is clamped on one side of the pier top die by the fastening bolt.
Further, a threaded hole is formed in the bottom of the inner wall of the positioning die sleeve, and an exhaust bolt is arranged in the threaded hole.
Further, the horizontal adjustment mechanism comprises a horizontal beam, an adjusting screw is arranged in the horizontal beam, a slide way is arranged on the outer side of the horizontal beam, a displacement nut on the adjusting screw moves in the slide way, two sides of the mounting ring are fixedly connected with a rotating sleeve on the displacement nut on two sides, and one end of the adjusting screw, which is located at the adjusting end, is fixedly connected with a first bevel gear.
Further, the supporting end comprises a supporting seat, an adjusting support is connected to the top of the supporting end through threads, and a second bevel gear is fixedly connected to the top end of the adjusting support.
Further, the adjusting end comprises a shell, an adjusting rod is rotatably arranged in the shell, and two limiting strips are arranged on the adjusting rod.
Further, the switching mechanism is arranged between the first bevel gear and the second bevel gear, and the switching mechanism is used for enabling the adjusting end to adjust the transverse adjusting mechanism in the height direction and the width direction during adjustment.
Further, the switching mechanism comprises two installation shaft sleeves, a third bevel gear is rotatably arranged in the installation shaft sleeves, a through channel is arranged on the third bevel gear, and limiting openings are formed in positions, corresponding to the limiting strips, on two sides of the inner wall of the through channel.
The utility model has the following beneficial effects:
1. the utility model discloses a transverse adjustment mechanism's setting can be adjusted the location die sleeve in width direction, can improve the convenience of adjusting like this, need not manual measurement operation.
2. The setting of switching mechanism, switching mechanism can carry out adaptability according to the actual position of location die sleeve and adjust, can make the location die sleeve remove in the direction of height, can adjust the hole degree of depth, can switch to with transverse adjustment mechanism meshing, can make it adjust in the width direction, can adjust the distance between two holes like this, it is convenient to adjust like this.
Drawings
FIG. 1 is a top view of the present utility model;
FIG. 2 is a perspective view of the present utility model;
FIG. 3 is a side view of the present utility model;
FIG. 4 is a schematic diagram of a switching mechanism of the present utility model;
FIG. 5 is a side view of the switching structure of the present utility model;
FIG. 6 is a partial exploded view of the switching mechanism of the present utility model;
fig. 7 is a schematic view of the lateral adjustment mechanism of the present utility model.
Detailed Description
The following description of the technical solutions in the embodiments of the present utility model will be clear and complete, and it is obvious that the described embodiments are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1 to 7, the positioning device for the reserved hole on the pier top of the tenon type beam falling prevention beam of the high-speed railway provided by the utility model comprises:
the clamp 2 is arranged on the pier top die 1, the clamp 2 is used for clamping the whole mechanism, a fastening bolt is arranged on the clamp 2, and the clamp 2 is clamped on one side of the pier top die 1 by the fastening bolt;
when the positioning device is used, the positioning device is placed in the width direction of the pier top die 1, the fastening bolts on the clamps 2 on the two sides are screwed down, one end of each bolt penetrating through the clamp 2 is in contact with the surface of the clamp 2, the bolts in the width direction are synchronously operated, the installation can be completed, the disassembly type design is realized, and the positioning device is convenient to use repeatedly during construction.
The power switching mechanism 6 is fixedly connected to the clamp 2, the power switching mechanism 6 comprises a supporting end and an adjusting end, the adjusting end is fixedly connected with the transverse adjusting mechanism 3, and the supporting end is fixedly connected to the clamp 2; the adjusting end comprises a shell, an adjusting rod 6.1 is rotatably arranged in the shell, and two limiting strips 6.4 are arranged on the adjusting rod 6.1. The supporting end comprises a supporting seat 6.2, an adjusting support is connected to the top thread of the supporting end 6.2, a second bevel gear 6.3 is fixedly connected to the top end of the adjusting support, a switching mechanism is arranged between the first bevel gear 3.4 and the second bevel gear 6.3, and the switching mechanism is used for enabling the adjusting end to adjust in the height direction and the width direction when the adjusting end is adjusted. The switching mechanism comprises two mounting shaft sleeves 6.5, a third bevel gear 6.6 is rotationally arranged in the mounting shaft sleeves 6.5, a through channel is arranged on the third bevel gear 6.6, and limiting ports 6.7 are arranged at positions, corresponding to limiting strips 6.4, on two sides of the inner wall of the through channel.
The following description is made of the present embodiment when the adjustment lever 6.1 is operated:
the adjusting lever 6.1 comprises two first stations and a second station when specifically rotating:
at the first station: before operation, the adjusting rod 6.1 needs to be pulled outwards, so that after the adjusting rod 6.1 is kept at the outermost position, the limiting rod 6.4 is rotated to the position of the limiting opening 6.7 after the adjusting rod 6.1 is slowly rotated, then the limiting rod 6.4 is clamped into the limiting opening 6.7, after the adjusting rod 6.1 is rotated, the adjusting rod 6.1 can drive the first bevel gear 3.4 to rotate, and thus the transverse adjusting mechanism 3 can be adjusted in the width direction.
At the second station: at this time, the adjusting rod 6.1 moves to the innermost position, the limiting strip 6.4 is clamped into the limiting opening 6.7 on the other third bevel gear 6.6, and thus the third bevel gear 6.6 drives the second bevel gear 6.3 to rotate, and further adjustment in the height direction can be achieved.
In one embodiment, the transverse adjusting mechanism 3 is used for fixing the positioning die sleeve 5 at a preset position; wherein, the adjustment end is used for fixed horizontal adjustment mechanism 3, and horizontal adjustment mechanism 3 includes horizontal beam 3.1, is provided with adjusting screw 3.2 in the horizontal beam 3.1, and the outside of horizontal beam 3.1 is provided with the slide, and displacement nut 3.3 on the adjusting screw 3.2 removes in the slide, and the change cover fixed connection on the displacement nut 3.3 of both sides and the both sides of collar 4, adjusting screw 3.2 are located the one end fixedly connected with first bevel gear 3.4 of adjustment end.
In order to ensure that the positioning die sleeve 5 is placed at a proper position, when the power switching mechanism 6 rotates, the transverse adjusting mechanism 3 can be operated in a linkage mode, so that the first bevel gear 3.4 can drive the adjusting screw 3.2 to rotate, and then the displacement nut 3.3 on the adjusting screw 3.2 moves in the slideway, and at the moment, the mounting ring 4 drives the positioning die sleeve 5 fixed on the mounting ring to move, so that the adjustment operation can be facilitated.
Wherein the horizontal beam 3.1 is provided with scales for observing the adjusted position of the positioning die sleeve 5, and the measuring procedure is reduced.
The screw hole is offered to location die sleeve 5 inner wall bottom, and the screw hole is provided with exhaust bolt 7.
In the cement molding process, after the positioning die sleeve 5 is rotated out through the exhaust bolt 7, the hole on the positioning die sleeve 5 is exposed, so that the positioning die sleeve 5 can be conveniently taken out from the air after internal negative pressure enters gas.
The foregoing description of the preferred embodiments of the utility model is not intended to be limiting, but rather is intended to cover all modifications, equivalents, alternatives, and improvements that fall within the spirit and scope of the utility model.

Claims (8)

1. The utility model provides a high-speed railway tenon formula prevents roof beam mound top preformed hole positioner that falls which characterized in that includes:
the fixture (2) is arranged on the pier top die (1), and the fixture (2) is used for clamping the integral mechanism;
the transverse adjusting mechanism (3) is used for fixing the positioning die sleeve (5) at a preset position;
the power switching mechanism (6), the power switching mechanism (6) is fixedly connected to the clamp (2), the power switching mechanism (6) comprises a supporting end and an adjusting end, the adjusting end is fixedly connected with the transverse adjusting mechanism (3), and the supporting end is fixedly connected to the clamp (2);
the adjusting end comprises a transverse adjusting mechanism (3) which is used for fixing, the adjusting end is connected with the supporting end, and a switching mechanism is arranged in the adjusting end.
2. The positioning device for the pier top preformed hole of the tenon type beam falling prevention of the high-speed railway according to claim 1 is characterized in that a fastening bolt is arranged on the clamp (2), and the clamp (2) is clamped on one side of the pier top die (1) by the fastening bolt.
3. The positioning device for the reserved hole on the pier top of the tenon type beam falling prevention of the high-speed railway according to claim 1 is characterized in that a threaded hole is formed in the bottom of the inner wall of the positioning die sleeve (5), and an exhaust bolt (7) is arranged in the threaded hole.
4. The positioning device for the reserved hole on the pier top of the high-speed railway tenon type beam falling prevention pier according to claim 1 is characterized in that the transverse adjusting mechanism (3) comprises a horizontal beam (3.1), an adjusting screw (3.2) is arranged in the horizontal beam (3.1), a slideway is arranged on the outer side of the horizontal beam (3.1), a displacement nut (3.3) on the adjusting screw (3.2) moves in the slideway, two sides of the mounting ring (4) are fixedly connected with rotating sleeves on the displacement nuts (3.3) on two sides, and one end of the adjusting screw (3.2) located at an adjusting end is fixedly connected with a first bevel gear (3.4).
5. The positioning device for the reserved hole on the pier top of the tenon type beam falling prevention of the high-speed railway according to claim 1 is characterized in that the supporting end comprises a supporting seat (6.2), an adjusting support is connected with the top of the supporting end (6.2) through threads, and a second bevel gear (6.3) is fixedly connected with the top end of the adjusting support.
6. The positioning device for the beam pier top preformed hole for the tenon type anti-falling beam of the high-speed railway according to claim 5, wherein the adjusting end comprises a shell, an adjusting rod (6.1) is rotationally arranged in the shell, and two limiting strips (6.4) are arranged on the adjusting rod (6.1).
7. The positioning device for the beam pier top preformed hole of the tenon type anti-falling beam of the high-speed railway according to claim 3 or 5, wherein the switching mechanism is arranged between the first bevel gear (3.4) and the second bevel gear (6.3) and is used for enabling the adjusting end to adjust the transverse adjusting mechanism (3) in the height direction and the width direction when the adjusting end is adjusted.
8. The positioning device for the beam pier top preformed hole for the tenon type anti-falling beam of the high-speed railway according to claim 5 or 7, wherein the switching mechanism comprises two mounting shaft sleeves (6.5), a third bevel gear (6.6) is rotationally arranged in the mounting shaft sleeves (6.5), a through channel is arranged on the third bevel gear (6.6), and limiting ports (6.7) are arranged at positions, corresponding to the limiting strips (6.4), on two sides of the inner wall of the through channel.
CN202321505189.0U 2023-06-13 2023-06-13 Positioning device for beam pier top preformed hole of tenon type anti-falling beam of high-speed railway Active CN220117027U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321505189.0U CN220117027U (en) 2023-06-13 2023-06-13 Positioning device for beam pier top preformed hole of tenon type anti-falling beam of high-speed railway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321505189.0U CN220117027U (en) 2023-06-13 2023-06-13 Positioning device for beam pier top preformed hole of tenon type anti-falling beam of high-speed railway

Publications (1)

Publication Number Publication Date
CN220117027U true CN220117027U (en) 2023-12-01

Family

ID=88892992

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321505189.0U Active CN220117027U (en) 2023-06-13 2023-06-13 Positioning device for beam pier top preformed hole of tenon type anti-falling beam of high-speed railway

Country Status (1)

Country Link
CN (1) CN220117027U (en)

Similar Documents

Publication Publication Date Title
CN220117027U (en) Positioning device for beam pier top preformed hole of tenon type anti-falling beam of high-speed railway
CN209244282U (en) A kind of prestressed, reinforced device
CN111590514A (en) Casting flange erection joint subassembly with adjustable butterfly valve is special
CN101691740A (en) Construction control device for pedestal pre-embedded steel plates of pre-stressed concrete box girder
CN206472007U (en) A kind of adjustable easily de- motor lines coil winding mould
CN219200890U (en) Engineering foundation pile detection fixing device for construction engineering detection
CN111496418A (en) Stagnant water steel sheet welding operation welding slag collecting box
CN215881419U (en) Automobile transmission gear assembly fixture
CN212217641U (en) A pipeline fixing device for welding desulfurizing tower
CN210797314U (en) Bridge structure reinforcing die
CN208305363U (en) A kind of internal model opening-closing locking mechanism
CN217394766U (en) Pipe tool clamp
CN219417038U (en) Reinforcing steel bar drawing experimental device for quality detection of constructional engineering
CN221031547U (en) Positioning device for foundation embedded bolt
CN218067489U (en) Concrete quality detection device for building engineering
CN213837724U (en) Anchor clamps for engineering construction
CN213794505U (en) Pipeline cutting device is used in air conditioner installation
CN214925570U (en) Template positioning mechanism is used in processing of prestressed concrete square pile
CN221134135U (en) Drilling equipment for seamless steel tube machining
CN220686513U (en) Concrete protective layer cushion block for civil construction
CN220289270U (en) Steel construction stress detection device
CN217180483U (en) Concrete permeameter for measuring water seepage resistance of concrete block
CN216371895U (en) Automatic five-axis hydraulic clamp
CN219104277U (en) Bending leakage-resistant test device for metal corrugated pipe
CN221681629U (en) Four-corner height difference control device for filler stone pouring

Legal Events

Date Code Title Description
GR01 Patent grant