CN219973587U - Assembled steel frame infilled wall - Google Patents

Assembled steel frame infilled wall Download PDF

Info

Publication number
CN219973587U
CN219973587U CN202320932794.XU CN202320932794U CN219973587U CN 219973587 U CN219973587 U CN 219973587U CN 202320932794 U CN202320932794 U CN 202320932794U CN 219973587 U CN219973587 U CN 219973587U
Authority
CN
China
Prior art keywords
steel frame
main body
connecting plate
filling
wall main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320932794.XU
Other languages
Chinese (zh)
Inventor
李庆振
王雪楠
王涛
吕吉宁
吴孝飞
封�波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Hi Speed Dejian Group Co Ltd
Original Assignee
Shandong Hi Speed Dejian Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Hi Speed Dejian Group Co Ltd filed Critical Shandong Hi Speed Dejian Group Co Ltd
Priority to CN202320932794.XU priority Critical patent/CN219973587U/en
Application granted granted Critical
Publication of CN219973587U publication Critical patent/CN219973587U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

The utility model discloses an assembled steel frame filling wall, which belongs to the field of filling walls and comprises two steel frame structures, wherein a filling wall main body is arranged between the two steel frame structures, a fixing structure is arranged in the filling wall main body, the fixing structure can move up and down in the filling wall main body, the fixing structure consists of a mounting base rod, a supporting connecting plate, a fixing base plate and fixing clamping columns, the plurality of supporting connecting plates are symmetrically arranged on the outer wall of the mounting base rod, the plurality of fixing base plates are respectively arranged at the outer ends of the plurality of supporting connecting plates, the plurality of fixing clamping columns are respectively arranged at the lower ends of the plurality of fixing base plates, and the step of assembling and connecting the steel frame structure and the filling wall main body can be simplified on the premise of ensuring the connection strength of the steel frame structure and the filling wall main body, so that the assembling and connecting efficiency of the steel frame structure and the filling wall main body can be finally improved.

Description

Assembled steel frame infilled wall
Technical Field
The utility model relates to the field of infill walls, in particular to an assembled steel frame infill wall.
Background
The filling wall is a building structure, and the wall body is divided into a bearing wall and a non-bearing wall according to different stress conditions of the structure. The non-bearing wall comprises a partition wall, a filling wall and a curtain wall. The walls of the frame structure that are filled between the columns are referred to as frame infill walls.
The infill wall in the steel frame construction often can adopt a plurality of bolts to be connected fixedly with steel frame when being connected with steel frame, and in order to guarantee the stability of infill wall and steel frame connection, the quantity of the bolt that is used for connecting fixedly infill wall and steel frame can be more to make the step that infill wall and steel frame are connected fixedly comparatively loaded down with trivial details, and then can make the efficiency of infill wall and steel frame equipment connection lower, so need an assembled steel frame infill wall that can quick assembly.
Disclosure of Invention
The utility model mainly aims to provide an assembled steel frame filling wall which can effectively solve the problems in the background technology.
In order to achieve the above purpose, the technical scheme adopted by the utility model is as follows:
the utility model provides an assembled steel frame infill wall, includes steel frame construction, steel frame construction has two, two install the infill wall main part between the steel frame construction, install fixed knot in the infill wall main part and construct, fixed knot constructs and can reciprocate in the infill wall main part, fixed knot constructs by installation basic pole, support connecting plate, fixed base plate and fixed card post and constitutes, support connecting plate has a plurality of and symmetrical the installation on the outer wall of installation basic pole, fixed base plate has a plurality of and installs the outer end at a plurality of support connecting plate respectively, fixed card post has a plurality of and installs the lower extreme at a plurality of fixed base plate respectively.
Preferably, a plurality of connecting grooves are symmetrically formed in the left end and the right end of the filling wall body, the upper end of the filling wall body is provided with a filling groove, the bottom end of the filling groove is provided with a storage blind hole, a plurality of communicating grooves are symmetrically formed in the filling wall body, and the communicating grooves are communicated with the connecting grooves and the storage blind hole.
Preferably, the steel frame structure comprises a steel frame main body and a mounting connecting plate, and the mounting connecting plate is uniformly arranged at the inner end of the steel frame main body in a plurality.
Preferably, the steel frame main body on the steel frame structure is fixedly mounted with the mounting connecting plate in a welding mode, the mounting connecting plate is provided with a mounting fixing hole, the mounting fixing hole penetrates through the upper end and the lower end of the mounting connecting plate, and the mounting connecting plate is inserted into a connecting groove symmetrically formed in the left end and the right end of the filling wall main body.
Preferably, the support connection plate on the fixing structure is fixedly connected with the installation base rod and the fixing base plate, and the fixing base plate is fixedly connected with the fixing clamping column.
Preferably, the mounting base rod is inserted into a filling groove and a storage blind hole which are formed in the filling wall main body, the support connecting plate is located in a communication groove formed in the filling wall main body, the fixing base plate is located in a connecting groove formed in the filling wall main body, the fixing base plate is located above the mounting connecting plate, and the fixing clamp column is inserted into a mounting fixing hole formed in the mounting connecting plate.
Compared with the prior art, the utility model has the following beneficial effects:
through set up fixed knot constructs in the infill wall main part, can be under the prerequisite of guaranteeing steel frame construction and infill wall main part joint strength, simplify the step of steel frame construction and infill wall main part equipment connection, thereby finally can promote steel frame construction and infill wall main part equipment connection's efficiency, when carrying out the equipment connection with steel frame construction and infill wall main part, can upwards pull fixed knot construct, make the roof contact of fixed baseplate and spread groove, then remove the infill wall main part between two steel frame constructions, make the installation connecting plate be in the spread groove, and make the installation connecting plate be located the below of fixed baseplate and fixing clip post, at last again loosen fixed knot construct, the fixed knot post can be inserted the installation fixed orifices by gravity influence this moment, then use cement mortar to fill up the infill groove, thereby fix fixed knot constructs, the equipment connection of steel frame construction and infill wall main part has been accomplished this moment promptly.
Drawings
FIG. 1 is a schematic diagram of the overall structure of the present utility model;
FIG. 2 is a cross-sectional view of the infill wall body of the present utility model;
fig. 3 is a schematic structural view of the steel frame structure of the present utility model.
In the figure: 1. a steel frame structure; 2. a filler wall body; 3. a fixed structure; 4. a steel frame body; 5. installing a connecting plate; 6. installing a fixing hole; 7. a connecting groove; 8. a communication groove; 9. filling the groove; 10. a receiving blind hole; 11. installing a base rod; 12. a support connection plate; 13. fixing the substrate; 14. and fixing the clamping column.
Detailed Description
The utility model is further described in connection with the following detailed description, in order to make the technical means, the creation characteristics, the achievement of the purpose and the effect of the utility model easy to understand.
Referring to fig. 1, 2 and 3, an assembled steel frame infill wall includes a steel frame structure 1, the steel frame structure 1 has two, the steel frame structure 1 comprises a steel frame main body 4 and an installation connecting plate 5, the installation connecting plate 5 has a plurality of and evenly installs the inner at the steel frame main body 4, steel frame main body 4 and installation connecting plate 5 on the steel frame structure 1 are in the same place through welded mode fixed mounting, installation fixed orifices 6 have been seted up on the installation connecting plate 5, the upper and lower both ends of installation connecting plate 5 link up, installation connecting plate 5 inserts in the spread groove 7 that the bilateral symmetry was seted up at the infill wall main body 2, install the infill wall main body 2 between two steel frame structures 1, a plurality of spread groove 7 has been seted up to the bilateral symmetry of infill wall main body 2, the filling groove 9 has been seted up to the upper end of infill wall main body 2, accomodate blind hole 10 has been seted up to the symmetry in the filling wall main body 2, a plurality of intercommunication groove 8 communicates spread groove 7 with accomodating blind hole 10.
Referring to fig. 1, 2 and 3, a fixing structure 3 is installed in a main body 2 of a filling wall, the fixing structure 3 can move up and down in the main body 2 of the filling wall, the fixing structure 3 is composed of a mounting base rod 11, a supporting connecting plate 12, a fixing base plate 13 and fixing clamping columns 14, the supporting connecting plate 12 is provided with a plurality of symmetrically installed on the outer wall of the mounting base rod 11, the fixing base plate 13 is provided with a plurality of respectively installed at the outer ends of the plurality of supporting connecting plates 12, the fixing clamping columns 14 are respectively installed at the lower ends of the plurality of fixing base plates 13, the supporting connecting plate 12 on the fixing structure 3 is fixedly connected with the mounting base rod 11 and the fixing base plate 13, the fixing base plate 13 is fixedly connected with the fixing clamping columns 14, the mounting base rod 11 is inserted into a filling groove 9 and a containing blind hole 10 formed in the main body 2 of the filling wall, the supporting connecting plate 12 is located in a communicating groove 8 formed in the main body 2 of the filling wall, the fixed base plate 13 is positioned in the connecting groove 7 formed on the filling wall main body 2, the fixed base plate 13 is positioned above the mounting connecting plate 5, the fixed clamping column 14 is inserted into the mounting fixing hole 6 formed on the mounting connecting plate 5, the step of assembling and connecting the steel frame structure 1 and the filling wall main body 2 can be simplified on the premise of ensuring the connection strength of the steel frame structure 1 and the filling wall main body 2 by arranging the fixed structure 3 in the filling wall main body 2, so that the efficiency of assembling and connecting the steel frame structure 1 and the filling wall main body 2 can be finally improved, when the steel frame structure 1 and the filling wall main body 2 are assembled and connected, the fixed structure 3 can be pulled upwards, the fixed base plate 13 is contacted with the top wall of the connecting groove 7, then the filling wall main body 2 is moved between the two steel frame structures 1, the mounting connecting plate 5 is positioned in the connecting groove 7, and make the installation connecting plate 5 be located the below of fixed base plate 13 and fixed card post 14, unclamp fixed knot structure 3 at last, fixed knot structure 3 can receive gravity influence downwardly moving this moment, and fixed card post 14 can insert in the installation fixed orifices 6 at last, and then use cement mortar to fill up filling slot 9 to fixed knot structure 3, the equipment connection of steel frame structure 1 and infilled wall main part 2 has been accomplished this moment.
It should be noted that, in the assembled steel frame infill wall, when the steel frame structure 1 and the infill wall main body 2 are assembled and connected, the installation base rod 11 on the fixed structure 3 can be firstly grasped, then the fixed structure 3 is pulled upwards, so that the fixed base plate 13 is in contact with the top wall of the connecting groove 7, then the infill wall main body 2 is moved between the two steel frame structures 1, at this time, the installation connecting plate 5 is required to be positioned in the connecting groove 7, and meanwhile, the installation connecting plate 5 is positioned below the fixed base plate 13 and the fixed clamping columns 14, finally the installation base rod 11 on the fixed structure 3 is loosened, at this time, the fixed structure 3 can be downwards moved under the influence of gravity, finally the fixed clamping columns 14 can be inserted into the installation fixing holes 6 formed on the installation connecting plate 5, then the infill groove 9 is filled with cement mortar, so that the fixed structure 3 is fixed, and at this time, the assembled and connected between the steel frame structure 1 and the infill wall main body 2 is completed.
The foregoing description is only a preferred embodiment of the present utility model, and is not intended to limit the present utility model, but although the present utility model has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the technical solutions described in the foregoing embodiments, or that equivalents may be substituted for part of the technical features thereof. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present utility model should be included in the protection scope of the present utility model. The scope of the utility model is defined by the appended claims and equivalents thereof.

Claims (6)

1. The utility model provides an assembled steel frame infilled wall, includes steel frame construction (1), steel frame construction (1) have two, two install infilled wall main part (2), its characterized in that between steel frame construction (1): install fixed knot construct (3) in filling wall main part (2), fixed knot constructs (3) and can reciprocate in filling wall main part (2), fixed knot constructs (3) by installation basic pole (11), support connecting plate (12), fixed base plate (13) and fixed card post (14) and constitute, support connecting plate (12) have a plurality of and symmetry install on the outer wall of installation basic pole (11), fixed base plate (13) have a plurality of and install the outer end at a plurality of support connecting plate (12) respectively, fixed card post (14) have a plurality of and install the lower extreme at a plurality of fixed base plate (13) respectively.
2. A fabricated steel framed infill wall according to claim 1, wherein: the left and right sides both ends symmetry of filling wall main part (2) has seted up a plurality of spread groove (7), filling groove (9) have been seted up to the upper end of filling wall main part (2), accomodate blind hole (10) have been seted up to the bottom of filling groove (9), a plurality of intercommunication groove (8) have been seted up to the symmetry in filling wall main part (2), intercommunication groove (8) are with spread groove (7) and accomodate blind hole (10) intercommunication.
3. A fabricated steel framed infill wall as claimed in claim 2, wherein: the steel frame structure (1) is composed of a steel frame main body (4) and mounting connecting plates (5), wherein the mounting connecting plates (5) are uniformly arranged at the inner ends of the steel frame main body (4) in a plurality.
4. A fabricated steel framed infill wall according to claim 3, wherein: the steel frame structure is characterized in that a steel frame main body (4) on the steel frame structure (1) and a mounting connecting plate (5) are fixedly mounted together in a welding mode, mounting fixing holes (6) are formed in the mounting connecting plate (5), the upper end and the lower end of the mounting connecting plate (5) are penetrated through by the mounting fixing holes (6), and the mounting connecting plate (5) is inserted into connecting grooves (7) symmetrically formed in the left end and the right end of the filling wall main body (2).
5. A fabricated steel framed infill wall according to claim 4, wherein: the support connecting plate (12) on the fixed structure (3) is fixedly connected with the mounting base rod (11) and the fixed base plate (13), and the fixed base plate (13) is fixedly connected with the fixed clamping column (14).
6. A fabricated steel framed infill wall according to claim 5, wherein: the installation base rod (11) is inserted into a filling groove (9) formed in the filling wall main body (2) and a storage blind hole (10), the support connecting plate (12) is located in a communication groove (8) formed in the filling wall main body (2), the fixing base plate (13) is located in a connecting groove (7) formed in the filling wall main body (2), the fixing base plate (13) is located above the installation connecting plate (5), and the fixing clamping column (14) is inserted into an installation fixing hole (6) formed in the installation connecting plate (5).
CN202320932794.XU 2023-04-24 2023-04-24 Assembled steel frame infilled wall Active CN219973587U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320932794.XU CN219973587U (en) 2023-04-24 2023-04-24 Assembled steel frame infilled wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320932794.XU CN219973587U (en) 2023-04-24 2023-04-24 Assembled steel frame infilled wall

Publications (1)

Publication Number Publication Date
CN219973587U true CN219973587U (en) 2023-11-07

Family

ID=88577033

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320932794.XU Active CN219973587U (en) 2023-04-24 2023-04-24 Assembled steel frame infilled wall

Country Status (1)

Country Link
CN (1) CN219973587U (en)

Similar Documents

Publication Publication Date Title
CN219973587U (en) Assembled steel frame infilled wall
CN113482152A (en) Assembled steel node
CN210374024U (en) Intelligent air conditioner easy to assemble
CN212104667U (en) Prefabricated shear force wall of assembled
CN213233925U (en) Assembled building curtain
CN210263402U (en) Arc single-layer latticed shell structure for large-scale steel structure building
CN218643548U (en) Assembly type structure component connection structure
CN216475578U (en) A assembled building supporting seat for in building work
CN216195848U (en) Prefabricated building structure of assembled architectural design
CN221276940U (en) Assembled building wall
CN211080306U (en) Precast concrete piping lane
CN218911734U (en) Prefabricated balcony that dry process is connected
CN217734583U (en) Steel column structure of assembled steel structure house
CN220868749U (en) Unperforated outer wall overhanging mounting frame
CN220265053U (en) Tower crane anchoring structure utilizing unilateral roof beam
CN213709969U (en) Assembled energy-conserving wall body
CN220666534U (en) Energy-saving wall convenient to install and detach
CN218114720U (en) Elevator pre-installation elevator car structure
CN214531161U (en) Install convenient assembly type structure coupling assembling
CN218643672U (en) Assembled steel structure crossbeam
CN214833516U (en) Assembled building connected node convenient to installation
CN210263033U (en) Pile foundation reinforcing apparatus
CN220550752U (en) Steel column assembly part
CN215977766U (en) Support seat of connecting piece
CN217054407U (en) Auxiliary device for rapid assembly of assembly type building