CN219931656U - Steel construction installation locating support - Google Patents

Steel construction installation locating support Download PDF

Info

Publication number
CN219931656U
CN219931656U CN202320932676.9U CN202320932676U CN219931656U CN 219931656 U CN219931656 U CN 219931656U CN 202320932676 U CN202320932676 U CN 202320932676U CN 219931656 U CN219931656 U CN 219931656U
Authority
CN
China
Prior art keywords
plates
steel structure
close
rods
supporting plates
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320932676.9U
Other languages
Chinese (zh)
Inventor
李伟丽
李鹏飞
于培焕
吴会丹
杨紫影
张崇林
王庆雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shiyan Tengzhuo Industry And Trade Co ltd
Original Assignee
Xinaoyuan Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinaoyuan Construction Engineering Co ltd filed Critical Xinaoyuan Construction Engineering Co ltd
Priority to CN202320932676.9U priority Critical patent/CN219931656U/en
Application granted granted Critical
Publication of CN219931656U publication Critical patent/CN219931656U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

The utility model discloses a steel structure installation positioning bracket, and mainly relates to the field of steel structure installation. Comprises a limiting mechanism and a clamping mechanism arranged above the limiting mechanism; the limiting mechanism comprises two symmetrically arranged supporting plates, the two supporting plates are respectively provided with a fence, and the outer sides of the two fences are respectively provided with a first screw rod and a first threaded pipe; the fixture is including setting up the mounting panel in two backup pads respectively, all is equipped with sliding connection's connecting rod on the mounting panel, and the one end that two connecting rods are close to all is equipped with splint, and the one end that two connecting rods kept away from all is equipped with the baffle, and the baffle outside all is equipped with second screw rod, second screwed pipe. The utility model has the beneficial effects that: the two surrounding baffles and the clamping plates do the movement of approaching or keeping away from simultaneously, thereby being convenient for adjustment operation, ensuring the same displacement distance at two sides, avoiding the deviation of the installation position of the steel structure, and the adjustment distance is determined by the rotation number of turns of the threaded pipe, and being better applicable to the installation and the positioning of the steel structure with different diameters.

Description

Steel construction installation locating support
Technical Field
The utility model relates to the field of steel structure installation, in particular to a steel structure installation positioning bracket.
Background
Steel structures are structures composed of steel materials, and are one of the main types of building structures. The structure mainly comprises steel beams, steel columns, steel trusses and other components made of section steel, steel plates and the like, and rust removal and prevention processes such as silanization, pure manganese phosphating, washing, drying, galvanization and the like are adopted. The components or parts are typically joined by welds, bolts or rivets. Because the self weight is lighter, and the construction is simple and convenient, the method is widely applied to the fields of large-scale factory buildings, venues, super high-rise buildings and the like.
The prior utility model patent CN218092144U discloses a steel structure installation positioning bracket, which can move the device to a designated working position when a person uses the steel structure installation positioning bracket through the arrangement of a fixed block, a connecting rod and a ground pricking cone, then the device is adjusted to a proper position by using the connecting rod, and then the device is fixed on the ground by using the ground pricking cone, thereby playing a role of conveniently reinforcing the device for fixing by the person.
Above-mentioned prior art is fixed the steel construction circle through the fixed block concatenation after when using, need remove the fixed block of unilateral respectively and adjust fixed area, but because this kind of fixed mode can't guarantee that two unilateral fixed blocks can have the same displacement distance at every turn, will lead to final fixed position and the fixed orifices position that determines in advance to deviate to some extent, easily cause the skew of installation, and the adjustment process is also more loaded down with trivial details, at least two people are required to promote the fixed block respectively and dock, and the interval of pinhole also can't guarantee that every steel construction of different diameters can both be fixed by fine laminating, just also can not the steel construction installation location of the different diameters of better adaptation uses.
Disclosure of Invention
The utility model aims to provide a steel structure installation positioning bracket, which is used for enabling two surrounding baffles and clamping plates to move close to or away from each other simultaneously through threaded connection of a threaded pipe and two threaded rods with opposite rotation directions, thereby being convenient for adjustment operation, ensuring the same displacement distance on two sides, avoiding the deviation of the installation position of a steel structure, and being better suitable for the installation positioning of steel structures with different diameters due to the fact that the adjustment distance is determined by the rotation number of the threaded pipe.
The utility model aims to achieve the aim, and the aim is achieved by the following technical scheme:
the steel structure installation positioning bracket comprises a limiting mechanism and a clamping mechanism arranged above the limiting mechanism;
the limiting mechanism comprises two symmetrically arranged supporting plates, wherein two surrounding blocks are respectively arranged on the two supporting plates, the two surrounding blocks can surround a pipeline, first screw rods are respectively arranged on the outer sides of the two surrounding blocks, the screw threads of the two first screw rods are opposite in rotation direction, one ends of the two first screw rods on the same side, which are close to each other, are connected through a first screw thread pipe, an operation hole is formed in the bottom of one side, which is close to each supporting plate, of the two supporting plates, and a centering mechanism is respectively arranged at the bottoms of the two supporting plates;
the fixture is including setting up the mounting panel in two backup pads respectively, all be equipped with on the mounting panel and run through the mounting panel and with mounting panel sliding connection's connecting rod, two the one end that the connecting rod is close to all is equipped with splint, two the one end that the connecting rod kept away from all is equipped with the baffle, the baffle outside all is equipped with the second screw rod, two the screw thread of second screw rod revolves to opposite, homonymy two the one end that the second screw rod is close to is through second screwed connection.
Further, centering mechanism is including setting up the riser in the backup pad bottom respectively, all be equipped with on the riser run through the riser and with riser sliding connection's ejector pin, two the one end that the ejector pin is close to is equipped with the clamp plate, two the one end that the ejector pin kept away from is equipped with the limiting plate, the ejector pin all overlaps outward has first spring, first spring is located between clamp plate and the riser.
Further, a plurality of balls are arranged at the bottoms of the two supporting plates.
Further, one side of the two clamping plates, which is close to each other, is an arc-shaped surface.
Further, the connecting rods are sleeved with second springs, and the second springs are located between the mounting plates and the baffle plates.
Compared with the prior art, the utility model has the beneficial effects that:
the two support plates are respectively placed on two sides of the surface of the steel structure base, the centers of the limiting mechanism and the clamping mechanism are aligned with the installation position of the center of the steel structure base through the centering mechanism, the steel pipe or the steel cylinder is hoisted above the steel structure base and then inserted into the limiting mechanism and the clamping mechanism, the first threaded pipe and the second threaded pipe are respectively rotated, the two fences move towards the middle to surround the steel pipe to limit, the inner side surfaces of the two clamping plates are tightly pressed and fixed against the outer surface of the steel pipe, the installation of the steel structure can be fixed, the clamping plates on the two sides and the fences synchronously move towards the center, the synchronous movement towards the center of the installation position can be ensured, the final installation position of the pipeline is ensured to be identical with the predetermined fixed position, the stable installation is ensured, the synchronous movement of the two clamping plates and the fence can be realized by rotating the threaded pipe, the operation is more convenient and quick, the adjustment of a smaller distance can be realized, the size of the pin hole interval is not limited, and the installation, the positioning and the application range of the steel structure with different apertures can be really adapted.
Drawings
Fig. 1 is a schematic diagram of the front view structure of the present utility model.
Fig. 2 is a schematic top view of the limiting mechanism of the present utility model.
Fig. 3 is a schematic top view of the clamping mechanism of the present utility model.
The reference numbers shown in the drawings:
1. a support plate; 2. a surrounding baffle; 3. a first screw; 4. a first threaded pipe; 5. an operation hole; 6. a mounting plate; 7. a connecting rod; 8. a clamping plate; 9. a baffle; 10. a second screw; 11. a second threaded tube; 12. a riser; 13. a push rod; 14. a pressing plate; 15. a limiting plate; 16. a first spring; 17. a ball; 18. and a second spring.
Detailed Description
The utility model will be further illustrated with reference to specific examples. It is to be understood that these examples are illustrative of the present utility model and are not intended to limit the scope of the present utility model. Further, it will be understood that various changes and modifications may be made by those skilled in the art after reading the teachings of the utility model, and equivalents thereof fall within the scope of the utility model as defined by the claims.
The utility model relates to a steel structure installation positioning bracket, which comprises a main body structure and a positioning mechanism, wherein the main body structure comprises a limiting mechanism and a clamping mechanism arranged above the limiting mechanism;
the limiting mechanism comprises two symmetrically arranged supporting plates 1, wherein the two supporting plates 1 are respectively positioned at two sides of a steel structure base, the two supporting plates 1 are respectively provided with a surrounding baffle 2, one sides of the two surrounding baffles 2 close to each other are butted and can surround a pipeline for limiting, the outer sides of the two surrounding baffles 2 are respectively provided with a first screw rod 3, the threads of the two first screw rods 3 are opposite in rotation direction, one ends of the two same sides, close to the first screw rods 3, are connected through a first threaded pipe 4, namely, two ends of the first threaded pipe 4 are respectively in threaded connection with the two first screw rods 3, the two first screw rods 3 can be driven to move towards a direction close to or away from each other simultaneously by rotating the first threaded pipe 4, therefore, the distance between the two enclosing baffles 2 is adjusted, the limiting function is realized, the operation is convenient and quick, the steel pipe with more pipe diameters can be matched for installation and use, the operation holes 5 are formed in the bottoms of the two supporting plates 1 close to one side, workers can weld the positioned pipelines through the operation holes 5, the operation holes 5 penetrate through the front and the rear of the enclosing baffles 2 and can completely weld the steel pipes along the pipe diameters of the steel pipes, the bottom parts of the two supporting plates 1 are respectively provided with a centering mechanism, the middle areas of the limiting mechanisms and the clamping mechanisms are ensured to be positioned on the central line of the steel structure base, so that the position of the central point of the limiting mechanism is inconvenient no matter how the distance between the limiting mechanisms and the clamping mechanisms is adjusted, and the installation position of the final fixed position offset center is avoided;
the fixture is including setting up the mounting panel 6 on two backup pads 1 respectively, all be equipped with on the mounting panel 6 run through mounting panel 6 and with mounting panel 6 sliding connection's connecting rod 7, the quantity of connecting rod 7 is minimum two, plays restriction pivoted effect each other, two the one end that connecting rod 7 is close to all is equipped with splint 8, and two splint 8 are fixed the steel pipe centre gripping, two the one end that connecting rod 7 kept away from all is equipped with baffle 9, and baffle 9 plays the spacing effect of keeping apart, avoids connecting rod 7 landing, the baffle 9 outside all is equipped with second screw rod 10, two the screw thread of second screw rod 10 revolves to opposite, and the homonymy two the one end that second screw rod 10 is close to is passed through second screwed pipe 11 and is connected, and the both ends of second screwed pipe 11 are respectively with two second screw rod 10 threaded connection, rotate second screwed pipe 11 can drive two second screw rods 10 and move to the direction that is close to or keep away from each other simultaneously to realize the adjustment of distance between two splint 8 through the transmission of baffle 9, realize the centre gripping function, convenient operation is swift, can adapt to more pipe diameters and install and do not have a practical limitation in the scope between adjacent big scope.
Preferably, the centering mechanism comprises vertical plates 12 respectively arranged at the bottoms of the supporting plates 1, the vertical plates 12 are respectively provided with a push rod 13 penetrating through the vertical plates 12 and in sliding connection with the vertical plates 12, one ends, close to the two push rods 13, of the two push rods are provided with pressing plates 14, one ends, far away from the two push rods 13, of the two push rods are provided with limiting plates 15, first springs 16 are sleeved outside the push rods 13, the first springs 16 are positioned between the pressing plates 14 and the vertical plates 12, the push rods 13 are pulled to compress the first springs 16, so that the distance between the two pressing plates 14 is increased, the two supporting plates 1 are placed on the steel structure base, the two pressing plates 14 are respectively positioned at two sides of the steel structure base, then the push rods 13 are loosened, the pressing plates 14 are firmly extruded at two sides of the steel structure base under the action of the first springs 16, the elastic force of the two first springs 16 is identical, the two supporting plates 1 are symmetrical relative to the steel structure base, and the centers of the limiting mechanism and the clamping mechanism are overlapped with the center of the installation position, so that the centering effect is achieved.
Preferably, a plurality of balls 17 are arranged at the bottoms of the two supporting plates 1, friction force between the bottom surface of the supporting plate 1 and the steel structure base is reduced, when the distance between the two surrounding baffles 2 and the two clamping plates 8 is adjusted, the two supporting plates 1 can smoothly move on the steel structure base, and the use range of the limiting mechanism and the clamping mechanism is convenient to adjust.
Preferably, two sides that splint 8 are close to are the arcwall face, can be better with the outside arcwall face laminating of steel pipe, guarantee the fastness of centre gripping.
Preferably, the connecting rod 7 is all overlapped outward and is had the second spring 18, the second spring 18 is located between mounting panel 6 and the baffle 9, plays the effort that a reverse support to connecting rod 7 through the second spring 18, cooperates with second screwed pipe 11 and can tensioning splint 8, avoids second screwed pipe 11 and second screw rod 10 screw thread complex clearance to lead to splint 8 to rock, further improves the stability of centre gripping.
The splint 8, the enclosing of this patent both sides keep off 2 and remove to the center in step, can ensure to remove to the center of mounted position promptly in step, can avoid final fixed position offset center's mounted position, guarantee that pipeline final mounted position is the same with the fixed position of advance determination, guarantee stable installation, the operation is convenient and fast more, can realize the adjustment of less distance moreover, need not be limited to pinhole spaced size, thereby really accomplish the steel construction installation location of adaptation different apertures and use, application scope is wider.

Claims (5)

1. A steel construction installation locating support, its characterized in that: comprises a limiting mechanism and a clamping mechanism arranged above the limiting mechanism;
the limiting mechanism comprises two symmetrically arranged supporting plates (1), wherein the two supporting plates (1) are respectively provided with a surrounding baffle (2), the two surrounding baffles (2) can surround a pipeline, the outer sides of the two surrounding baffles (2) are respectively provided with a first screw (3), the threads of the two first screws (3) are opposite in rotation direction, one ends, close to the first screws (3) on the same side, of the two supporting plates are connected through a first threaded pipe (4), the bottoms, close to one side, of the two supporting plates (1) are provided with operation holes (5), and the bottoms of the two supporting plates (1) are respectively provided with a centering mechanism;
the clamping mechanism comprises mounting plates (6) which are respectively arranged on two support plates (1), connecting rods (7) which penetrate through the mounting plates (6) and are in sliding connection with the mounting plates (6) are arranged on the mounting plates (6), two clamping plates (8) are arranged at one ends, close to the connecting rods (7), of the connecting rods, baffle plates (9) are arranged at one ends, far away from the connecting rods (7), of the connecting rods, second screw rods (10) are arranged at the outer sides of the baffle plates (9), threads of the second screw rods (10) are opposite in rotation direction, and two ends, close to the second screw rods (10), of the same side are connected through second threaded pipes (11).
2. A steel structure mounting and positioning bracket according to claim 1, wherein: the centering mechanism comprises vertical plates (12) which are respectively arranged at the bottoms of the supporting plates (1), ejector rods (13) which penetrate through the vertical plates (12) and are in sliding connection with the vertical plates (12) are arranged on the vertical plates (12), one ends, close to the ejector rods (13), of the two ejector rods are provided with pressing plates (14), one ends, far away from the ejector rods (13), of the two ejector rods are provided with limiting plates (15), first springs (16) are sleeved outside the ejector rods (13), and the first springs (16) are located between the pressing plates (14) and the vertical plates (12).
3. A steel structure mounting and positioning bracket according to claim 1, wherein: the bottoms of the two supporting plates (1) are respectively provided with a plurality of balls (17).
4. A steel structure mounting and positioning bracket according to claim 1, wherein: one side of the two clamping plates (8) close to each other is an arc-shaped surface.
5. A steel structure mounting and positioning bracket according to claim 1, wherein: the connecting rods (7) are sleeved with second springs (18), and the second springs (18) are located between the mounting plates (6) and the baffle plates (9).
CN202320932676.9U 2023-04-23 2023-04-23 Steel construction installation locating support Active CN219931656U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320932676.9U CN219931656U (en) 2023-04-23 2023-04-23 Steel construction installation locating support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320932676.9U CN219931656U (en) 2023-04-23 2023-04-23 Steel construction installation locating support

Publications (1)

Publication Number Publication Date
CN219931656U true CN219931656U (en) 2023-10-31

Family

ID=88504398

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320932676.9U Active CN219931656U (en) 2023-04-23 2023-04-23 Steel construction installation locating support

Country Status (1)

Country Link
CN (1) CN219931656U (en)

Similar Documents

Publication Publication Date Title
CN110324736B (en) Stereo set installation aluminium pipe support
CN219931656U (en) Steel construction installation locating support
CN214738845U (en) Connecting structure of steel structure concrete column
CN216343241U (en) Pipeline is assembly workstation in advance
CN214738756U (en) Steel construction building connecting device
CN212406135U (en) Positioning support for pre-assembling steel structural member
CN220127961U (en) Steel construction welding shaping mounting fixture of arranging
CN219945159U (en) Butt joint device for welding steel pipes
CN111822926A (en) Adjustable fixing device for steel structure welding
CN220204911U (en) Building construction installation component
CN217272383U (en) Pipeline support for building engineering is buckled
CN220451099U (en) Supporting steel structure building assembly
CN110744256A (en) Clamp for welding U-shaped pipeline and method for welding U-shaped pipeline
CN216606786U (en) Bending device for steel structure production
CN219837367U (en) Simple steel rail structure clamp
CN220792290U (en) Pumping pipeline supporting bracket for super high-rise building
CN220361852U (en) Fixed stable bending device
CN217653378U (en) Pipeline construction equipment that municipal works were used
CN219887168U (en) Adjustable connection structure among various civil engineering steel beams
CN221054454U (en) Equipment fastening structure and I-steel beam type support and hanger
CN219638377U (en) Scaffold connecting and locking structure
CN219901887U (en) Steel construction prevents empting anchor clamps
CN214942278U (en) Supporting and connecting device for assembly type building external hanging rack
CN210597612U (en) Assembled I-steel beam clamp connecting piece
CN220688245U (en) Water supply and drainage pipeline locating support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20231123

Address after: 442000 Shuanglong Industrial Park, Liuliping Industrial Park, Danjiangkou City, Shiyan City, Hubei Province

Patentee after: Shiyan Tengzhuo Industry and Trade Co.,Ltd.

Address before: No. 356, South Side, West End of Puxi Great Wall Avenue, Changyuan City, Xinxiang City, Henan Province, 453400

Patentee before: Xinaoyuan Construction Engineering Co.,Ltd.

TR01 Transfer of patent right