CN219931655U - Rag bolt installs positioner - Google Patents

Rag bolt installs positioner Download PDF

Info

Publication number
CN219931655U
CN219931655U CN202320606456.7U CN202320606456U CN219931655U CN 219931655 U CN219931655 U CN 219931655U CN 202320606456 U CN202320606456 U CN 202320606456U CN 219931655 U CN219931655 U CN 219931655U
Authority
CN
China
Prior art keywords
adjusting
posts
post
adjusting rod
upright
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320606456.7U
Other languages
Chinese (zh)
Inventor
肖俊
张俊华
张智康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Industrial Building Group Installation Engineering Co ltd
Original Assignee
Hubei Industrial Building Group Installation Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Industrial Building Group Installation Engineering Co ltd filed Critical Hubei Industrial Building Group Installation Engineering Co ltd
Priority to CN202320606456.7U priority Critical patent/CN219931655U/en
Application granted granted Critical
Publication of CN219931655U publication Critical patent/CN219931655U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Abstract

The utility model relates to an anchor bolt installation positioning device, which comprises four upright posts and four adjusting rods, wherein each adjusting rod is arranged between two adjacent upright posts and is vertical to the upright posts, one end of each adjusting rod is fixedly connected with one upright post, the other end of each adjusting rod penetrates through a rectangular hole formed in the other upright post, each upright post is provided with a locking mechanism at the rectangular hole, the lower ends of the four upright posts are respectively and rotatably connected with four thread sleeves, and the thread sleeves are sleeved at the upper ends of the anchor bolts through thread matching; the stand is connected with the mode of adopting the activity between the regulation pole, replaces original welded mode to be connected, but the rag bolt is after the installation is accomplished, but the distance between four stand readjustment, adapt to the rag bolt's of other pre-buried positions installation, but whole device repeatedly usable, rag bolt need not prefabricated ground cage in advance before the installation, has saved material cost, has improved rag bolt installation effectiveness.

Description

Rag bolt installs positioner
Technical Field
The utility model relates to the technical field of building construction, in particular to an anchor bolt installation positioning device.
Background
The foundation bolt is one of the structures commonly used in engineering, is embedded in the concrete foundation, and realizes the interconnection between equipment and the foundation. In order to ensure verticality and no inclination during foundation bolt installation, a cage is generally designed in advance, the size of the ground cage is designed according to the concrete position of the bolt hole for fixing the equipment base, after the ground cage is positioned and installed on the foundation bolt, the position for pre-embedding installation of the foundation bolt corresponds to the position of the bolt hole of the equipment base, however, the size of the ground cage is customized in advance, after the foundation bolt is installed, the ground cage cannot position other foundation bolts and can only be used once, so that the material waste is caused, the cost for installing the foundation bolt is improved, and the installation efficiency of the foundation bolt is reduced.
Disclosure of Invention
The utility model aims to provide an anchor bolt installation positioning device which solves the problems in the prior art.
The technical scheme for solving the technical problems is as follows:
the utility model provides an rag bolt installs positioner, including four stands and four regulation pole, every regulation pole setting is between two adjacent stands and perpendicular with the stand, the one end and the stand fixed connection of every regulation pole, the rectangular hole of seting up on another stand is run through to one end in addition, every stand is provided with locking mechanism in rectangular hole department, the lower extreme of four stands rotates respectively and is connected with four thread bush, the thread bush is used for cup jointing the upper end at rag bolt through screw-thread fit.
The beneficial effects of the utility model are as follows: the lower extreme at the stand is installed to rag bolt, adopt movable mode to connect between stand and the regulation pole, adjust rag bolt's position, make four rag bolt's positions correspond with the position of screw hole on the equipment base, rag bolt is after the installation is accomplished, rotatable thread bush makes thread bush and rag bolt separation, conveniently in the follow-up use, but the distance between four stand readjustment, adapt to the rag bolt's of other pre-buried positions installation, but whole device repeatedly usable, rag bolt does not need prefabricated ground cage in advance before the installation, material cost has been saved, rag bolt installation effectiveness has been improved.
On the basis of the technical scheme, the utility model can be improved as follows.
Further, four stands are including a reference column and three regulation post, reference column and two regulation pole fixed connection, two regulation posts adjacent with the reference column respectively with one regulation pole fixed connection to by the regulation pole of being connected with the reference column run through, the regulation post of keeping away from the reference column is run through by two regulation poles simultaneously.
Further, the locking mechanism comprises a threaded rod penetrating through the inner wall of the adjusting column and extending into the adjusting column through threaded fit and an extrusion piece rotationally connected with one end of the threaded rod in the adjusting column, and the two threaded rods are oppositely arranged and point to the axis of the adjusting column.
Further, the outer side of the adjusting rod is provided with scale marks.
Further, the outside of adjusting the pole is inlayed and is had the spirit level.
Further, stand side fixedly connected with right angle set square, bar recess has been seted up to the bottom of adjusting the pole, and the top of right angle set square slides and sets up the inside at bar recess.
Drawings
FIG. 1 is a schematic diagram of the structure of the present utility model;
FIG. 2 is a bottom view of the structure of the adjusting lever of the present utility model;
fig. 3 is a schematic structural view of the locking mechanism of the present utility model.
In the drawings, the list of components represented by the various numbers is as follows:
1. upright post, 11, positioning post, 12, adjusting post, 131, threaded sleeve, 132, right angle triangle, 133, locking mechanism, 1331, extrusion piece, 1332, threaded rod, 134, rectangular hole, 2, adjusting rod, 21, level gauge, 22, bar-shaped groove, 3, rag bolt.
Detailed Description
The principles and features of the present utility model are described below with reference to the drawings, the examples are illustrated for the purpose of illustrating the utility model and are not to be construed as limiting the scope of the utility model.
Embodiment 1, as shown in fig. 1-3, an anchor bolt installation positioning device comprises four upright posts 1 and four adjusting rods 2, wherein each adjusting rod 2 is arranged between two adjacent upright posts 1 and is perpendicular to each upright post 1, one end of each adjusting rod 2 is fixedly connected with one upright post 1, the other end of each adjusting rod penetrates through a rectangular hole 134 formed in the other upright post 1, a locking mechanism 133 is arranged at each upright post 1 at the rectangular hole 134, four thread sleeves 131 are respectively connected to the lower ends of the four upright posts 1 in a rotating mode, and the thread sleeves 131 are used for being sleeved at the upper ends of anchor bolts 3 through thread matching.
The two adjacent columns 1 are connected together through adjusting the pole 2, the inner wall of the thread bush 131 is provided with the thread groove matched with the upper end of the foundation bolt 3, the foundation bolt 3 is installed on the column 1 through the thread bush 131, concentricity is kept between the foundation bolt 3 and the column 1, one end of the adjusting rod 2 is fixedly connected with one of the columns 1, the other end of the adjusting rod passes through the other column 1 adjacent to the other end of the adjusting rod, the column 1 penetrating the adjusting rod 2 can slide on the adjusting rod 2, the distance between the two adjacent columns 1 is adjusted, the column 1 drives the foundation bolt 3 to move, the position between the foundation bolt 3 is adjusted, the positions of the four foundation bolts 3 correspond to the positions of the threaded holes on the equipment base, after the size is adjusted, the locking mechanism 133 on the column 1 locks the column 1 with the adjusting rod 2, so that the installation position of the foundation bolt is shifted in the adjusting rod 2 in the process, the movable mode is adopted between the column 1 and the adjusting rod 2 to replace the original welding mode, the foundation bolt 3 can rotate the thread bush 131 after the installation is completed, the thread bush 131 is separated from the position of the foundation bolt 3 in advance, the prefabricated cage can be installed in advance, the prefabricated cage can be conveniently, and the cost of the prefabricated cage can be saved.
Because the upright post 1 and the adjusting rod 2 are vertically arranged, the foundation bolt 3 is also in a vertical state with the adjusting rod 2 after being installed on the threaded sleeve 131, and in the process of specifically installing the foundation bolt 3, the adjusting rod 2 must be ensured to be in a horizontal state, so that the foundation bolt 3 is vertical to the ground after being installed.
Example 2, as shown in fig. 1, this example is a further improvement over example 1, which is specifically as follows:
the four upright posts 1 comprise a positioning post 11 and three adjusting posts 12, the positioning post 11 is fixedly connected with the two adjusting posts 2, the two adjusting posts 12 adjacent to the positioning post 11 are respectively fixedly connected with the one adjusting post 2 and are penetrated by the adjusting posts 2 connected with the positioning post 11, and the adjusting posts 12 far away from the positioning post 11 are penetrated by the two adjusting posts 2.
When the distance between the four upright posts 1 is adjusted, the positioning posts 11 are taken as datum points, two adjusting posts 12 adjacent to the positioning posts 11 are respectively pushed to adjust the distance between the positioning posts 11, and the adjusting posts 12 far away from the positioning posts 11 move along with the movement of the other two adjusting posts 12 to adapt to the distance between the bolt holes of the equipment base, so that the aim of installing the foundation bolts is fulfilled.
Example 3 as shown in fig. 1 and 3, this example is a further improvement on the basis of any one of examples 1 to 2, and is specifically as follows:
the locking mechanism 133 includes a threaded rod 1332 that extends through the inner wall of the adjustment column 12 into the adjustment column 12 by threaded engagement, and a pressing piece 1331 rotatably connected to one end of the threaded rod 1332 inside the adjustment column 12, and the two threaded rods 1332 are disposed opposite to each other and are directed toward the axis of the adjustment column 12.
Rotating the threaded rod 1332, the threaded rod 1332 pushes the extrusion piece 1331 to extrude the adjusting rod 2, the two extrusion pieces 1331 extrude the adjusting rod 2 simultaneously, the adjusting rod 2 is guaranteed to be firmly extruded, and therefore the adjusting rod 2 cannot move with the adjusting column 12, otherwise, when the position of the adjusting column 12 is to be adjusted, the threaded rod 1332 can be reversely rotated, the threaded rod 1332 is a hexagon bolt, and when the threaded rod 1332 is rotated, the threaded rod 1332 can be screwed by means of a wrench, and the extrusion piece 1331 can firmly extrude the adjusting rod 2.
Example 4, as shown in fig. 1, is a further improvement on any of examples 1 to 3, and is specifically as follows:
the outside of adjusting the pole 2 is provided with the scale mark, and stand 1 can slide stand 1 to the appointed distance between and adjacent stand 1 according to the length scale mark on adjusting pole 2 at specific gliding in-process to guarantee the accuracy to the distance adjustment between stand 1 and the stand 1, reduce the deviation.
Example 5, as shown in fig. 1, is a further improvement on any of examples 1 to 4, and is specifically as follows:
the outside of adjusting the pole 2 is inlayed and is had the spirit level 21, and the spirit level 21 is the bubble spirit level, through observing the spirit level 21, guarantees to adjust pole 2 and keeps the horizontality at the in-process of installation, spirit level 21 and adjusting pole 2 surface parallel and level, can not influence and adjust pole 2 and pass rectangular hole 134.
Example 6, as shown in fig. 1 and 2, this example is a further improvement on the basis of any one of examples 1 to 5, and is specifically as follows:
the side fixedly connected with right angle set square 132 of stand 1, bar recess 22 has been seted up to the bottom of adjusting pole 2, and the top slip of right angle set square 132 sets up in bar recess 22's inside, and one right angle limit and stand 1 fixed connection of right angle set square 132, another right angle limit slip setting is in bar recess of adjusting pole 2. The adjusting rod 2 is supported through the right-angle triangular plate 132, so that the upright post 1 and the adjusting rod 2 are kept in a vertical state all the time, and the accuracy of the foundation bolt 3 after being installed is improved. In particular implementation, the other right-angle side of the right-angle triangle 132 fixed with the positioning column 11 is directly welded with the bottom of the adjusting rod 2, so that the connection firmness between the positioning column 11 and the adjusting rod 2 can be enhanced.
The foregoing description of the preferred embodiments of the utility model is not intended to limit the utility model to the precise form disclosed, and any such modifications, equivalents, and alternatives falling within the spirit and scope of the utility model are intended to be included within the scope of the utility model.

Claims (4)

1. The foundation bolt installation positioning device is characterized by comprising four upright posts (1) and four adjusting rods (2), wherein each adjusting rod (2) is arranged between two adjacent upright posts (1) and is perpendicular to each upright post (1), one end of each adjusting rod (2) is fixedly connected with one upright post (1), the other end of each adjusting rod penetrates through a rectangular hole (134) formed in the other upright post (1), a locking mechanism (133) is arranged at the rectangular hole (134) of each upright post (1), four threaded sleeves (131) are respectively connected to the lower ends of the four upright posts (1) in a rotating mode, and each threaded sleeve (131) is used for being sleeved at the upper end of a foundation bolt (3) through threaded fit;
the four upright posts (1) comprise a positioning post (11) and three adjusting posts (12), wherein the positioning post (11) is fixedly connected with two adjusting posts (2), the two adjusting posts (12) adjacent to the positioning post (11) are respectively fixedly connected with one adjusting post (2) and are penetrated by the adjusting posts (2) connected with the positioning post (11), and the adjusting post (12) far away from the positioning post (11) is penetrated by the two adjusting posts (2) at the same time;
the locking mechanism (133) comprises a threaded rod (1332) penetrating through the inner wall of the adjusting column (12) in a threaded fit mode and extending into the adjusting column (12), and an extrusion piece (1331) rotatably connected with one end of the threaded rod (1332) in the adjusting column (12), wherein the two threaded rods (1332) are oppositely arranged and point to the axis of the adjusting column (12).
2. The foundation bolt installation positioning device according to claim 1, characterized in that the outer side of the adjusting rod (2) is provided with graduation marks.
3. The foundation bolt installation positioning device according to claim 1, wherein a level meter (21) is embedded on the outer side of the adjusting rod (2).
4. The foundation bolt installation positioning device according to claim 1, wherein a right-angle triangle (132) is fixedly connected to the side edge of the upright post (1), a strip-shaped groove (22) is formed in the bottom of the adjusting rod (2), and the top of the right-angle triangle (132) is slidably arranged in the strip-shaped groove (22).
CN202320606456.7U 2023-03-24 2023-03-24 Rag bolt installs positioner Active CN219931655U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320606456.7U CN219931655U (en) 2023-03-24 2023-03-24 Rag bolt installs positioner

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320606456.7U CN219931655U (en) 2023-03-24 2023-03-24 Rag bolt installs positioner

Publications (1)

Publication Number Publication Date
CN219931655U true CN219931655U (en) 2023-10-31

Family

ID=88499549

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320606456.7U Active CN219931655U (en) 2023-03-24 2023-03-24 Rag bolt installs positioner

Country Status (1)

Country Link
CN (1) CN219931655U (en)

Similar Documents

Publication Publication Date Title
JP4491030B2 (en) Anchor bolt set device
US9677276B2 (en) Support for embedding object in concrete
US20070166111A1 (en) Poured concrete column alignment and plumbing tool
JP2001059343A (en) Concrete placement method for forming slab, and support tool for guide rail used therefor
CN211262238U (en) Supporting device for building engineering measuring equipment
CN219931655U (en) Rag bolt installs positioner
CN209907531U (en) A support for rainwater pipeline construction
CN215803300U (en) Ground leveling auxiliary device for building construction
CN217420584U (en) Auxiliary device for positioning foundation bolt
CN202370264U (en) Fixing device for rapidly installing foundation bolt
CN220336541U (en) Construction engineering strutting arrangement
CN112663654A (en) Detachable location frock suitable for assembly type structure built-in fitting
CN206919877U (en) A kind of leveling rod support for being easy to regulation horizontal
JP2008150851A (en) Anchor bolt support
CN217027187U (en) Basic built-in fitting positioning tool of photovoltaic installation
CN211736444U (en) Positioning equipment for grouted rubble retaining wall
CN220789347U (en) Water stable elevation control device
CN114876214B (en) High-precision steel structure upright post installation precision control device
KR101578524B1 (en) Spacer for adjusting hight and space of rebar
CN217812412U (en) Leveling guide rail bracket for cast-in-place concrete floor
CN220301867U (en) Building construction precast floor plank strutting arrangement
CN218667914U (en) Assembled building fixed baseplate
CN215803338U (en) Foundation bolt positioning device
CN212027171U (en) Pre-buried positioner of regulation formula precast concrete stair bolt