CN219931559U - Simple track gauge adjusting construction platform - Google Patents

Simple track gauge adjusting construction platform Download PDF

Info

Publication number
CN219931559U
CN219931559U CN202320968203.4U CN202320968203U CN219931559U CN 219931559 U CN219931559 U CN 219931559U CN 202320968203 U CN202320968203 U CN 202320968203U CN 219931559 U CN219931559 U CN 219931559U
Authority
CN
China
Prior art keywords
rack plate
construction platform
fixing rod
rack
positioning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320968203.4U
Other languages
Chinese (zh)
Inventor
廖宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGZHOU GUANGRI LOGISTICS CO Ltd
Original Assignee
GUANGZHOU GUANGRI LOGISTICS CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGZHOU GUANGRI LOGISTICS CO Ltd filed Critical GUANGZHOU GUANGRI LOGISTICS CO Ltd
Priority to CN202320968203.4U priority Critical patent/CN219931559U/en
Application granted granted Critical
Publication of CN219931559U publication Critical patent/CN219931559U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Types And Forms Of Lifts (AREA)

Abstract

The utility model discloses a simple track gauge adjusting construction platform, which comprises a bracket body, wherein two upper beam assemblies are respectively arranged right above the left side and the right side of the bracket, two lower beam assemblies are respectively arranged right below the left side and the right side of the bracket body, and the simple track gauge adjusting construction platform further comprises: the first rack plate is arranged between the upper beam assemblies, the first rack plate is provided with a plurality of first positioning ports which are sequentially arranged at intervals along the length direction of the first rack plate, the second rack plate is arranged between the lower beam assemblies, the second rack plate is provided with a plurality of second positioning ports which are sequentially arranged at intervals along the length direction of the second rack plate; the first fixing rod and the second fixing rod are respectively fixed on the first rack plate and the second rack plate through the matching of the screw rod and the nut. The utility model has the advantages of being capable of adjusting the transverse size of the construction platform at any time according to the actual distance between the guide rails on the installation site and having stability.

Description

Simple track gauge adjusting construction platform
Technical Field
The utility model relates to the technical field of construction platforms, in particular to a simple track adjusting construction platform for elevator shafts or elevator installation.
Background
In the society of the present high-rise building, an elevator becomes an indispensable equipment for each high-rise building, but when installing an elevator shaft or an elevator, the elevator shaft or the elevator is difficult to construct due to the excessively high floor, so that an installer often needs to install the elevator shaft or the elevator by means of a construction platform. In the prior art, people often simply build a construction platform or install an elevator shaft or an elevator using a construction platform with a bidirectional screw structure.
The following drawbacks exist in the prior art: 1-2, a support body 1 is used, two upper beam assemblies 2 are respectively arranged right above the left side and the right side of the support, two lower beam assemblies 3 are respectively arranged right below the left side and the right side of the support body 1, and the transverse size of the construction platform cannot be adjusted at any time according to the actual distance between guide rails on an installation site; when the construction platform with the bidirectional screw structure is used, the transverse size of the construction platform is not easy to adjust and is easy to loosen.
Disclosure of Invention
In order to overcome the technical defects, the utility model provides a simple track gauge adjusting construction platform which can solve the problems that the transverse size of the construction platform cannot be adjusted at any time according to the actual distance between guide rails on an installation site and the construction platform is not stable.
In order to solve the problems, the utility model is realized according to the following technical scheme: the utility model provides a simple and easy gauge adjustment construction platform, includes the support body, be equipped with two entablature subassemblies directly over the support body left and right sides respectively, be equipped with two entablature subassemblies directly under the support body left and right sides respectively, its characterized in that still includes:
the first rack plate is arranged between the upper beam assemblies, a plurality of first positioning ports are formed in the first rack plate, and the first positioning ports are sequentially arranged at intervals along the length direction of the first rack plate;
the second rack plate is arranged between the lower beam assemblies, a plurality of second positioning ports are formed in the second rack plate, and the second positioning ports are sequentially arranged at intervals along the length direction of the second rack plate;
the first fixing rod is fixed at one first positioning opening of the first rack plate through the matching of the screw rod and the nut;
the second fixing rod is fixed at one second positioning opening of the second rack plate through the matching of the screw rod and the nut.
In one embodiment, the ends of the upper beam assembly and the lower beam assembly are respectively provided with a first through hole, and the first through holes are respectively sleeved with a movable supporting column.
In one embodiment, the number of the first rack plate and the second rack plate is two, the two first rack plates are respectively and symmetrically arranged between the two upper beam assemblies, and the two second rack plates are respectively and symmetrically arranged between the two lower beam assemblies.
In one embodiment, the first fixing rod, the second fixing rod and the supporting column are all fixed on the elevator guide rail through fixing devices, the fixing devices comprise fasteners and connecting plates, and the first fixing rod, the second fixing rod and the supporting column are fixed on the connecting plates through threads.
In one embodiment, the support body is vertically provided with a support plate, and the support plate is provided with a second through hole or a screw hole.
In one embodiment, the first positioning opening and the second positioning opening are both circular in shape.
In one embodiment, a plurality of the first positioning ports and the second positioning ports are arranged at equal intervals.
In one embodiment, the first rack plate and the second rack plate are integrally formed with the first positioning port and the second positioning port, respectively.
In one embodiment, the bracket body, the upper beam assembly, the lower beam assembly, the first rack plate, the second rack plate, the first fixing rod, the second fixing rod, the support column and the support plate are all metal material pieces.
Compared with the prior art, the utility model has the beneficial effects that:
through adjusting the position of first dead lever at first location mouth to and adjust the position of second dead lever at the second location mouth, make construction platform can be according to the convenient distance adjustment transverse length between the scene guide rail, and first dead lever and second dead lever pass through the cooperation of screw rod and nut and fix respectively at first rack board and first rack board, increase construction platform's steadiness, can reduce the potential safety hazard.
Drawings
The utility model is described in further detail below with reference to the attached drawing figures, wherein:
FIG. 1 is a top view of a prior art construction platform;
FIG. 2 is a front view of the present utility model;
FIG. 3 is a top view of the present utility model;
FIG. 4 is a side view of the present utility model;
FIG. 5 is a top view of a schematic of the use of the present utility model;
fig. 6 is a front view of a schematic of the use of the present utility model.
In the figure: 1. a bracket body; 2. an upper beam assembly; 3. a lower beam assembly; 4. a first rack plate; 5. a second rack plate; 6. a first positioning port; 7. a first fixing rod; 8. a second fixing rod; 9. a first through hole; 10. a support column; 11. a fixing device; 12. a fastener; 13. a connecting plate; 14. a support plate; 15. a second through hole; 16. a screw hole; 17. an elevator guide rail.
Detailed Description
The following description of the preferred embodiments of the present utility model will be made with reference to the accompanying drawings, it being understood that the preferred embodiments described herein are for illustration and explanation only, and are not intended to limit the utility model thereto, and the terms "upper" and "lower" etc. are used herein for convenience of description only, and are not to be construed as limitations on the technical solution, and the terms "first" and "second" … … "used merely serve to distinguish between names and not represent a particular number or order.
As shown in fig. 2-5, the simple track gauge adjusting construction platform of the utility model comprises a bracket body 1, two upper beam assemblies 2 are respectively arranged right above the left side and the right side of the bracket body 1, first rack plates 4 are arranged at the end parts between the two upper beam assemblies 2, the first rack plates 4 have the function of adjusting the transverse length of the operation platform, two lower beam assemblies 3 are respectively arranged right below the left side and the right side of the bracket body 1, second rack plates 5 are arranged at the end parts between the two lower beam assemblies 3, the second rack plates 5 have the function of adjusting the transverse length of the operation platform, the first rack plates 4 and the second rack plates 5 are arranged on the same side of the bracket body 1, in particular, a plurality of first positioning ports 6 are arranged on the first rack plates 4, the plurality of first positioning ports 6 are orderly arranged at intervals along the length direction of the first rack plates 4, the second rack plate 5 is provided with a plurality of second positioning ports (not shown in the figure), the second positioning ports are sequentially arranged at intervals along the length direction of the first rack plate 5, the end part between the two upper beam assemblies 2 is provided with a first fixing rod 7, one end of the first fixing rod 7 is fixed at one first positioning port 6 of the first rack plate 4 through the cooperation of a screw and a nut, the other end of the first fixing rod 7 is fixed at an elevator guide rail 17 of a construction site, the end part between the two lower beam assemblies 3 is provided with a second fixing rod 8, one end of the second fixing rod 8 is fixed at one second positioning port of the second rack plate 5 through the cooperation of the screw and the nut, the other end of the second fixing rod 8 is fixed at the elevator guide rail 17 of the construction site, under the combined action of the bracket body 1, the upper beam assemblies 2 and the lower beam assemblies 3, a common construction platform is formed, through adjusting the position of the first dead lever of homonymy at first location mouth to and adjust the position of second dead lever at the second location mouth, the length of first dead lever 7 and second dead lever 8 in support body 1 also can be along with increasing or reducing, make construction platform can adjust horizontal length according to the convenient distance between the on-the-spot guide rail, and first dead lever 7 and second dead lever 8 fix at first rack board 4 and second rack board 5, be difficult for taking off to increase construction platform's steadiness, can reduce the potential safety hazard.
In specific embodiments, the ends of the two upper beam assemblies 2 and the two lower beam assemblies 3 are respectively provided with a first through hole 9, the first through holes 9 are respectively sleeved with a movable support column 10, the support columns 10 can be stretched and shortened in the upper beam assemblies 2 and the lower beam assemblies 3, one ends of the support columns 10 far away from the first through holes 9 are fixed on the elevator guide rails 17, so that the number of the support columns 10 fixed on the elevator guide rails 17 can be adjusted according to the required bearing weight of an operation platform, the stability of the construction platform can be further enhanced, and the operation platform can bear larger weight.
In specific embodiments, the number of the first rack plates 4 and the second rack plates 5 is two, the two first rack plates 4 are respectively symmetrically arranged at two ends between the two upper beam assemblies 2, the two second rack plates 5 are respectively symmetrically arranged at two ends between the two lower beam assemblies 3, through the arrangement of the structure, not only the left lateral length of the operation platform but also the right lateral length of the construction platform can be adjusted according to the actual requirements of the construction site, but also the lateral distance of the construction platform can be simultaneously adjusted when the distance between the guide rails of the construction site is larger, so that the operation platform can be suitable for the construction site with larger guide rail distance.
In specific embodiments, the first fixing rod 7, the second fixing rod 8 and the supporting column 10 are all fixed on the elevator guide rail 17 through the fixing device 11, the fixing device 11 comprises a fastening piece 12 and a connecting plate 13, the fastening piece 12 belongs to a common technology, namely, the distance between two clamping pieces in the fastening piece 12 is adjusted by rotating an adjusting nut, so that the fixing on the elevator guide rail 17 is realized, the first fixing rod 7, the second fixing rod 8 and the supporting column 10 are fixed on the connecting plate 13 through threads, when the elevator guide rail 17 is used, the first fixing rod 7, the second fixing rod 8 and the supporting column 10 cannot be respectively fixed on the elevator guide rail 17, and only the fixing device 11 is required to be fixed on the elevator guide rail 17, so that a certain time can be saved, and the working efficiency is improved.
In specific embodiments, the support body 1 is vertically provided with the support plate 14, the safety of a construction platform can be enhanced through the support plate 14, the support plate 14 is provided with the second through hole 15 or the screw hole 16, and tools can be bound on the second through hole 15 or fixed on the screw hole 16 during construction, so that the tools can be prevented from falling, and potential safety hazards are further reduced.
In specific embodiments, the shapes of the first positioning opening 6 and the second positioning opening are circular, the first positioning openings 6 and the second positioning openings are arranged at equal intervals, the transverse distance of the construction platform can be better controlled and adjusted through the arrangement of equal intervals, the first rack plate 4 and the second rack plate 5 are integrally formed with the first positioning openings 6 and the second positioning openings respectively, and the firmness of the first rack plate 4 and the second rack plate 5 can be enhanced through the integrated structure.
In specific embodiments, the bracket body 1, the upper beam assembly 2, the lower beam assembly 3, the first rack plate 4, the second rack plate, the first fixing rod 7, the second fixing rod 8, the support column 10 and the support plate 14 are all metal material pieces, so that not only can the stability of the construction platform be enhanced, but also the durability of the construction platform can be improved.
The application principle of the utility model is as follows: at the job site, according to actual demand, through the position of adjusting the first dead lever 7 of homonymy and second dead lever 8 at locating slot 6, thereby adjust the lateral length of construction platform, and first dead lever 7 and second dead lever 8 pass through the cooperation of bolt and nut and fix respectively at first rack board 4 and second rack board 5, the other end of first dead lever 7 and second dead lever 8 is fixed at elevator guide rail 17, thereby increase the steadiness of construction platform, can reduce the potential safety hazard, if construction platform need bear great weight, can pass through the support column 10 that upper beam assembly 2 and lower beam assembly 3 set up, and fix support column 10 at elevator guide rail 17, can further strengthen construction platform's steadiness, make operation platform can bear great weight, when the construction, can tie up the instrument on the second through-hole 15 of extension board 14 or fix on screw 16 of extension board 14, can prevent that the instrument from dropping, the potential safety hazard has been further reduced.
The above is only a preferred embodiment of the present utility model, and is not limited in any way, so any modification, equivalent variation and modification made to the above embodiment according to the technical substance of the present utility model still fall within the scope of the technical solution of the present utility model.

Claims (9)

1. The utility model provides a simple and easy gauge adjustment construction platform, includes support body (1), be equipped with two entablature subassembly (2) respectively directly over support body (1) left and right sides, be equipped with two bottom end rail subassembly (3) respectively under support body (1) left and right sides, its characterized in that still includes:
the first rack plate (4) is arranged between the upper beam assemblies (2), the first rack plate (4) is provided with a plurality of first positioning ports (6), and the first positioning ports (6) are sequentially arranged at intervals along the length direction of the first rack plate (4);
the first rack plate (5) is arranged between the lower beam assemblies (3), a plurality of second positioning ports are formed in the second rack plate (5), and the second positioning ports are sequentially arranged at intervals along the length direction of the second rack plate (5);
the first fixing rod (7) is fixed at one first positioning opening (6) of the first rack plate (4) through the matching of a screw and a nut;
the second fixing rod (8) is fixed at one second positioning opening of the second rack plate (5) through the matching of the screw rod and the nut.
2. Construction platform according to claim 1, characterized in that the ends of both the upper beam assembly (2) and the lower beam assembly (3) are provided with a first through hole (9), the first through holes (9) are each provided with a movable support column (10).
3. Construction platform according to claim 2, wherein the number of the first rack plates (4) and the second rack plates (5) is two, the two first rack plates (4) are symmetrically arranged between the two upper beam assemblies (2), and the two second rack plates (5) are symmetrically arranged between the two lower beam assemblies (3).
4. A construction platform according to claim 3, characterized in that the first fixing rod (7), the second fixing rod (8) and the supporting column (10) are all fixed to the elevator guide rail (17) by means of fixing means (11), the fixing means (11) comprise fastening means (12) and a connecting plate (13), and the first fixing rod (7), the second fixing rod (8) and the supporting column (10) are fixed to the connecting plate (13) by means of threads.
5. Construction platform according to any one of claims 1-4, characterized in that the bracket body (1) is vertically provided with a support plate (14), the support plate (14) being provided with a second through hole (15) or screw hole (16).
6. Construction platform according to claim 5, characterized in that the first positioning opening (6) and the second positioning opening are both circular in shape.
7. The construction platform according to claim 6, wherein the plurality of first positioning ports (6) and second positioning ports are arranged at equal intervals.
8. The construction platform according to claim 7, wherein the first rack plate (4) and the second rack plate (5) are integrally formed with the first positioning opening (6) and the second positioning opening, respectively.
9. The construction platform according to claim 2, wherein the bracket body (1), the upper beam assembly (2), the lower beam assembly (3), the first rack plate (4), the second rack plate (5), the first fixing rod (7), the second fixing rod (8) and the support column (10) are all metal material pieces.
CN202320968203.4U 2023-04-26 2023-04-26 Simple track gauge adjusting construction platform Active CN219931559U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320968203.4U CN219931559U (en) 2023-04-26 2023-04-26 Simple track gauge adjusting construction platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320968203.4U CN219931559U (en) 2023-04-26 2023-04-26 Simple track gauge adjusting construction platform

Publications (1)

Publication Number Publication Date
CN219931559U true CN219931559U (en) 2023-10-31

Family

ID=88493039

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320968203.4U Active CN219931559U (en) 2023-04-26 2023-04-26 Simple track gauge adjusting construction platform

Country Status (1)

Country Link
CN (1) CN219931559U (en)

Similar Documents

Publication Publication Date Title
CN219931559U (en) Simple track gauge adjusting construction platform
EP0247962A3 (en) Shoring of a carrier
CN215258969U (en) Encoder support that can multi-direction adjust
CN219753904U (en) Construction platform telescopic leg ejector rod assembly
CN216641354U (en) Protector that electromechanical installation construction used
CN207633607U (en) Aluminum alloy combination support type unit stone curtain wall
CN220218502U (en) Track seat positioning device of robot
CN217734512U (en) Assembled superimposed sheet board holds in palm
CN211736264U (en) Civil engineering construction support
CN216428585U (en) Steel column installation device
CN214696682U (en) Auxiliary device for door leaf installation
CN212024513U (en) Automatic staircase returns rail bearing structure
CN220838079U (en) Aluminium mould C groove trompil location frock
CN215906622U (en) Road and bridge engineering is with adjustable building truss structure
CN210067481U (en) Three-dimensional adjustable unit type energy-saving curtain wall assembly platform structure
CN216543210U (en) Anti-breaking supporting vertical plate of electrical cabinet
CN209797376U (en) multifunctional lifting platform
CN220972789U (en) Precast beam field steel bar binding rack
CN218503113U (en) Angle steel frock of punching a hole
CN212298175U (en) Horizontal adjusting device of bearing type coating chamber body equipment
CN218149639U (en) Adjustable scaffold
CN220366018U (en) Quick deviation correcting device of push pipe
CN213615022U (en) Welding tool for tower cylinder built-in part
CN220377891U (en) Auxiliary connection tool for assembled steel structure beam column
CN201645356U (en) Column assembly

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant