CN219904673U - Mobile pump ship for lowering ecological water - Google Patents

Mobile pump ship for lowering ecological water Download PDF

Info

Publication number
CN219904673U
CN219904673U CN202320932591.0U CN202320932591U CN219904673U CN 219904673 U CN219904673 U CN 219904673U CN 202320932591 U CN202320932591 U CN 202320932591U CN 219904673 U CN219904673 U CN 219904673U
Authority
CN
China
Prior art keywords
water
pipe
pump
ecological
water pump
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320932591.0U
Other languages
Chinese (zh)
Inventor
党海霞
宋俊熙
黄艳飞
陈松林
曹宣辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Xinzhongshui Engineering Co ltd
Original Assignee
Guizhou Xinzhongshui Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Xinzhongshui Engineering Co ltd filed Critical Guizhou Xinzhongshui Engineering Co ltd
Priority to CN202320932591.0U priority Critical patent/CN219904673U/en
Application granted granted Critical
Publication of CN219904673U publication Critical patent/CN219904673U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Structures Of Non-Positive Displacement Pumps (AREA)

Abstract

The utility model relates to the technical field of water conservancy and hydropower engineering, and particularly discloses a mobile pump boat for lowering ecological water, which comprises a pump boat body, wherein the pump boat body is formed by horizontally, fixedly splicing a plurality of hollow rods with both ends in a sealing state in parallel, a water pump unit is fixedly arranged on the pump boat body, the top end of the water pump unit is movably communicated with a rocker arm pipe, the other end of the rocker arm pipe is movably communicated with one end of a fixed pipe, the other end of the fixed pipe is communicated with a connecting pipe, and the connecting pipe is communicated with an ecological drain pipe. The fixed pipe is fixedly arranged on the appropriate river bank edge at the upstream, the pump boat body is placed in an upstream river channel, the pump boat body and the water pump unit can float on the upstream water surface under the traction of the rocker pipe, the water pump unit is started, the water pump unit pumps water in the upstream into the fixed pipe through the rocker pipe, the water in the fixed pipe flows into the ecological water drain pipe through the connecting pipe, finally flows out of the ecological water drain pipe and enters a downstream river channel, and the ecological water flow of the downstream river channel is ensured not to be cut off.

Description

Mobile pump ship for lowering ecological water
Technical Field
The utility model relates to the technical field of water conservancy and hydropower engineering, in particular to a mobile pump ship for lowering ecological water.
Background
The water resource provides important support for the development of human society, and in order to improve the utilization rate of the water resource, the water retaining dam is usually built in a natural river to store the water resource, so that the water resource is convenient for human production and living use.
In the construction engineering of the barrage, a temporary cofferdam is firstly constructed at the upstream and downstream of the barrage to ensure that the barrage is constructed in a dry environment, and meanwhile, in order to ensure that the downstream river of the barrage is not broken, a diversion facility is required to be constructed between the upstream and downstream of the cofferdam to guide the water flow in the upstream river to the downstream, so that the ecological water flow is ensured; when the barrage is built and has water storage capacity, the barrage is required to store water, in order not to influence the existence of downstream ecological species, the barrage is set as a downstream water drainage facility, the water flow of the water drainage facility is extremely small, the influence on water storage is small, because the water drainage facility is generally much higher than the diversion facility, after the barrage is blocked by the diversion facility, the water level of the barrage does not reach the water drainage facility elevation, namely, the water level is in the elevation section of the diversion facility and the water drainage facility, at this time, the water drainage facility in the barrage cannot drain water to the downstream river, the downstream ecological water flow is cut off, and because the barrage with medium and large scale can last for a plurality of months or longer in the water storage period, the living environment of downstream residents and organisms of the barrage is seriously influenced.
In order to solve the problem of ecological water flow at the downstream of the barrage, people generally adopt temporary modes of water pump pressurizing from upstream to downstream to lift water or siphon pipe and the like, because the ecological water flow required by the barrage of medium and large scale is larger, the elevation from a diversion facility to a drainage facility is higher, the water pump is fixed at the river bank, the theoretical suction range of the water pump is 10m, and the water pump pressurizing water lifting is adopted, so that a certain difficulty is brought to specific implementation; when siphon measures are adopted, and water is stored in the initial stage of upstream, the siphon is also required to be arranged to be large because the height difference between the upstream water level and the downstream water level is not large and the ecological water flow is required to be large, so that the implementation is difficult.
Disclosure of Invention
The utility model aims to provide a mobile pump ship for lowering ecological water, which is used for solving the problem that when the water level is in the elevation section from a diversion facility to a water discharge facility, water is difficult to drain from upstream to downstream.
In order to solve the problems, the technical scheme is as follows:
the utility model provides a mobile pump ship of ecological water of transferring, includes the pump ship body, the pump ship body is by the hollow pole level that a plurality of both ends all are in sealing state fixedly concatenation side by side forms, fixedly installs the water pump unit on the pump ship body, and water pump unit top activity intercommunication has the rocking arm pipe, and the fixed pipe one end of rocking arm pipe other end activity intercommunication, fixed pipe other end intercommunication connecting pipe, connecting pipe intercommunication ecological drain pipe.
The basic principle of the technical scheme is as follows: the fixed pipe is fixedly arranged on the appropriate upstream river bank side, the pump boat body is placed in an upstream river channel, the pump boat body and the water pump unit can float on the upstream water surface under the traction of the rocker pipe, the water pump unit is started, the water pump unit pumps water in the upstream into the fixed pipe through the rocker pipe, the water in the fixed pipe flows into the ecological water drain pipe through the connecting pipe, finally flows out of the ecological water drain pipe and enters a downstream river channel, and the ecological water flow of the downstream river channel is guaranteed not to be cut off.
The beneficial effect of this scheme lies in:
1. compared with the existing mode of directly adopting a water pump to pump water from upstream to downstream, the scheme adopts the combination of the water pump unit and the pump ship body, and because the pump ship body is formed by splicing hollow rod water, the pump ship body can bear the water pump unit to float on the surface of upstream river water, and can rise along with the rising of the upstream water level, so that the water pump unit borne on the pump ship body always floats on the water surface along with the pump ship body, the water pump unit floating on the water surface can easily pump the upstream water into the rocker arm pipe by only needing very small pressure, and then flows through the fixed pipe, the connecting pipe and the ecological water discharge pipe, and finally flows into a downstream river channel.
2. After the upstream water level of the barrage reaches the elevation of a water drainage facility and ecological water flow can be normally drained, the rocker arm pipe is pulled to take out the pump boat body in the upstream river together with the water pump unit from the upstream river, and then the pump boat body and the water pump unit are recycled on different hydraulic engineering projects.
Further, the water pump unit comprises a water pump, the water pump extends from the inlet end of the water pump to the position below the pump ship body, the outlet end of the water pump is movably communicated with the rocker arm pipe through the universal spherical joint, and the outlet end of the water pump is provided with a flow regulating valve. The flow regulating valve can control the water lifting flow of the water pump, so that the hydraulic loss of the outlet of the water pump is avoided from being increased excessively when the lift is low, and the normal operation of the water pump is influenced.
Further, a water pump variable frequency control cabinet positioned at one side of the water pump unit is fixedly arranged on the pump ship body, and the water pump variable frequency control cabinet is electrically connected with the water pump unit. The water pump variable frequency control cabinet reduces the running rotation speed of the water pump by reducing the frequency of the power end, and properly widens the running range of the water pump.
Further, the other end of the rocker arm pipe is movably communicated with one end of the fixed pipe through a universal spherical joint. In the process that the pump ship body rises along with the water level, the universal spherical joint can enable the rocker arm pipe to deflect freely so as to adjust to a proper angle.
Further, the fixed pipe is a cross-shaped joint, the left end and the right end of the joint are respectively communicated with the rocker pipe and the connecting pipe, the upper end of the joint is in a sealing state, and the upper end of the joint is fixedly connected with the mounting seat. The installation seat is fixedly arranged on the river bank side, and the joint can be fixedly arranged on the river bank side.
Further, an ecological drain gate is arranged at the end of the ecological drain pipe. The ecological water drain gate controls the opening and closing of the ecological water drain pipe.
Drawings
FIG. 1 is a schematic top view of a mobile pump vessel positioned in a river;
FIG. 2 is a schematic front view of the mobile pump vessel not positioned in a river;
FIG. 3 is a schematic front view of a mobile pump vessel mated with a stationary tube;
fig. 4 is a schematic top view of a mobile pump vessel.
Reference numerals in the drawings of the specification include: diversion tunnel shutoff gate 1, diversion tunnel 2, connecting pipe 3, barrage 4, ecological drain pipe 5, ecological drain gate 6, downstream cofferdam 7, pump boat body 8, hollow pole 81, upstream cofferdam 9, water pump 10, flow control valve 11, universal ball joint 12, rocking arm pipe 13, fixed pipe 14, mount pad 141, water pump variable frequency control cabinet 15.
Detailed Description
The following is a further detailed description of the embodiments:
the embodiment is basically as shown in the accompanying figures 1-4:
as shown in fig. 1 and 3, the pump body 8 is formed by horizontally welding 5 square hollow rods 81 with both ends in a sealing state in parallel, a water pump 10 is fixedly arranged on the pump body 8 through a flange, the water pump 10 extends from an inlet end of a belt to below the pump body 8, the water pump 10 is movably communicated with one end of a rocker arm pipe 13 through a universal spherical joint 12 from an outlet end of the belt, a flow regulating valve 11 is connected with the outlet end of the water pump 10 through threads of the belt, the other end of the rocker arm pipe 13 is movably communicated with one end of a fixed pipe 14 through the universal spherical joint 12, the fixed pipe 14 is a cross-shaped joint, the left end and the right end of the joint are respectively communicated with the rocker arm pipe 13 and a connecting pipe 3, the upper end of the joint is in a sealing state, the lower end of the joint is fixedly connected with a square mounting seat 141, the mounting seat 141 is fixedly arranged on a river bank side, the connecting pipe 3 is communicated with an ecological water drain pipe 5, the ecological water drain pipe 5 transversely penetrates through and is arranged in a barrage 4, and the end of the ecological water drain pipe 5 is in threaded connection with an ecological water drain 6; as shown in fig. 4, a water pump variable frequency control cabinet 15 positioned at one side of the water pump 10 is fixedly arranged on the pump ship body 8 through a flange, and the water pump variable frequency control cabinet 15 is electrically connected with the water pump 10.
The specific implementation process is as follows:
as shown in fig. 1, temporary upstream cofferdam 9 and temporary downstream cofferdam 7 are respectively built at the upstream and downstream of the barrage 4, the upstream cofferdam 9 and the downstream cofferdam 7 break the river course, in order not to influence the survival of downstream ecological species, diversion tunnels 2 are built between the upstream and downstream of the cofferdam separation to communicate upstream and downstream, the diversion tunnels 2 can guide the water flow in the upstream river course to the downstream, diversion tunnel 2 ends in the upstream river course are provided with diversion tunnel plugging gates 1, and the diversion tunnel plugging gates 1 can control the opening and closing of the diversion tunnels 2; as shown in fig. 2, the ecological water discharge pipe 5 is transversely arranged in the barrage 4 in a penetrating way, and the level of the ecological water discharge pipe 5 is higher than that of the diversion tunnel 2.
When the barrage 4 is built and water storage begins, the diversion tunnel blocking gate 1 needs to be closed to block the diversion tunnel 2, when the upstream water level is between the level of the ecological water discharge pipe 5 and the level of the diversion tunnel 2, the mounting seat 141 of the fixing pipe 14 is fixedly arranged on the side of an upstream proper river bank, the pump ship body 8 is placed in an upstream river channel, the distance from the deck of the pump ship body 8 to the water surface is about one meter, the pump ship body 8 and the water pump 10 group can float on the upstream water surface under the traction of the rocker arm pipe 13, the pump ship body 8 can rise along with the rising of the upstream water level, the water pump 10 group is started, the water pump 10 group pumps water in the upstream into the fixing pipe 14 through the rocker arm pipe 13, the water in the fixing pipe 14 flows into the ecological water discharge pipe 5 through the connecting pipe 3, and finally flows out of the ecological water discharge pipe 5 into a downstream river channel, and the ecological water flow of the downstream river channel is prevented from being cut off.
The foregoing is merely exemplary embodiments of the present utility model, and specific structures and features that are well known in the art are not described in detail herein. It should be noted that modifications and improvements can be made by those skilled in the art without departing from the structure of the present utility model, and these should also be considered as the scope of the present utility model, which does not affect the effect of the implementation of the present utility model and the utility of the patent. The protection scope of the present utility model is subject to the content of the claims, and the description of the specific embodiments and the like in the specification can be used for explaining the content of the claims.

Claims (6)

1. The utility model provides a mobile pump ship of ecological water of transfer, includes pump ship body, its characterized in that: the pump boat body is formed by horizontally, fixedly and parallelly splicing hollow rods with two ends in a sealing state, a water pump unit is fixedly arranged on the pump boat body, the top end of the water pump unit is movably communicated with a rocker pipe, the other end of the rocker pipe is movably communicated with one end of a fixed pipe, the other end of the fixed pipe is communicated with a connecting pipe, and the connecting pipe is communicated with an ecological water drain pipe.
2. A mobile pumping vessel for lowering ecological water as claimed in claim 1, wherein: the water pump unit comprises a water pump, the water pump extends from the inlet end of the water pump to the position below the pump ship body, the outlet end of the water pump is movably communicated with the rocker arm pipe through the universal spherical joint, and the outlet end of the water pump is provided with a flow regulating valve.
3. A mobile pumping vessel for lowering ecological water according to claim 1 or 2, characterized in that: the pump boat body is fixedly provided with a water pump variable frequency control cabinet positioned at one side of the water pump unit, and the water pump variable frequency control cabinet is electrically connected with the water pump unit.
4. A mobile pumping vessel for lowering ecological water as claimed in claim 1, wherein: the other end of the rocker arm pipe is movably communicated with one end of the fixed pipe through a universal spherical joint.
5. A mobile pumping vessel for lowering ecological water as claimed in claim 1, wherein: the fixing pipe is a cross-shaped joint, the left end and the right end of the joint are respectively communicated with the rocker pipe and the connecting pipe, the upper end of the joint is in a sealing state, and the upper end of the joint is fixedly connected with the mounting seat.
6. A mobile pumping vessel for lowering ecological water as claimed in claim 1, wherein: an ecological drain gate is arranged at the end of the ecological drain pipe.
CN202320932591.0U 2023-04-23 2023-04-23 Mobile pump ship for lowering ecological water Active CN219904673U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320932591.0U CN219904673U (en) 2023-04-23 2023-04-23 Mobile pump ship for lowering ecological water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320932591.0U CN219904673U (en) 2023-04-23 2023-04-23 Mobile pump ship for lowering ecological water

Publications (1)

Publication Number Publication Date
CN219904673U true CN219904673U (en) 2023-10-27

Family

ID=88432945

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320932591.0U Active CN219904673U (en) 2023-04-23 2023-04-23 Mobile pump ship for lowering ecological water

Country Status (1)

Country Link
CN (1) CN219904673U (en)

Similar Documents

Publication Publication Date Title
CN209703536U (en) A kind of marine traffic engineering foundation pit siphon pumping drain combined assembly
CN219904673U (en) Mobile pump ship for lowering ecological water
CN212896607U (en) Pump station is from filling formula siphon diversion system
CN202441640U (en) Pump station air inlet/outlet valve type self-sealing water tank filling equipment
CN113789763B (en) Step-type discharge regulation and control system based on reservoir ecology construction
CN205035774U (en) Two flotation tank formula water conservancy flap gates
CN203175746U (en) Hydrodynamic water elevator
CN203729376U (en) Water intake well pipe structure used for hydraulic and hydropower engineering
CN212336278U (en) Large-scale underground type hydropower station factory building leakage drainage system combined with slope shaft
CN111827218B (en) Ecological drainage device for dam in alpine region
CN111395398B (en) Immersed tube structure suitable for high flow velocity and construction method thereof
CN211922550U (en) Improve power station tailrace tunnel open-full flow influence's adverse slope weir structure
CN209194485U (en) Diversion tunnel structure
CN206220200U (en) A kind of flushing device for toilet and overboard courage
CN219974841U (en) Floating ship type diesel-driven multi-outlet drainage pump station
CN206681070U (en) A kind of multi-functional discharge pump works
CN216973584U (en) Novel integrated pump station
CN221461065U (en) Siphon type water inlet structure for pressure pipeline water return
CN219974846U (en) Floating external power supply drainage pump set
CN211773393U (en) Novel rubber dam water filling and draining system on overflow weir
CN219840155U (en) Buried centrifugal pump station
CN204728289U (en) Pond and retaining dams syphon low-tension supply water replanishing device
CN204738281U (en) Electroless energy -conserving moisturizing device of diversion siphon
CN215165356U (en) Energy dissipation and emptying structure for small and medium-sized hydraulic buildings
CN219825451U (en) River water intake system along with water level change