CN219825762U - Novel mounting structure of ceramic tile curtain wall string hanging system - Google Patents

Novel mounting structure of ceramic tile curtain wall string hanging system Download PDF

Info

Publication number
CN219825762U
CN219825762U CN202320110448.3U CN202320110448U CN219825762U CN 219825762 U CN219825762 U CN 219825762U CN 202320110448 U CN202320110448 U CN 202320110448U CN 219825762 U CN219825762 U CN 219825762U
Authority
CN
China
Prior art keywords
cross beam
curtain wall
tuzhuan
tao
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320110448.3U
Other languages
Chinese (zh)
Inventor
孙晓阳
于健伟
钱禹行
宋传华
陈彬彬
赵彬
伍侠
祁伟杰
邵伟
房晓宇
高昊
李越宇
余清江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN202320110448.3U priority Critical patent/CN219825762U/en
Application granted granted Critical
Publication of CN219825762U publication Critical patent/CN219825762U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

The utility model relates to the technical field of building curtain wall construction, in particular to a novel installation structure of a ceramic tile curtain wall string hanging system, which comprises a plurality of upright posts and also comprises: the cross beams are arranged among the upright posts, one end of each cross beam is fixedly connected with a connecting bolt through threads, and the other end of each cross beam is connected with the adjacent upright post in a welding mode; the galvanized steel corner brackets are fixed on one side of the cross beam through bolts, and vertical connecting screw bars are welded and fixed at positions, close to the galvanized steel corner brackets, of one side wall of the cross beam; the utility model aims at the construction of the bottom, the suspended ceiling and the corner parts of the curtain wall, adopts the clamping piece type T-shaped Tao Tuzhuan, improves the construction efficiency, improves the integral layering sense of the ceramic brick curtain wall modeling, shortens the construction period, can effectively improve the construction efficiency, enhances the cohesiveness between bricks, and can be used for the construction of high-rise building curtain walls.

Description

Novel mounting structure of ceramic tile curtain wall string hanging system
Technical Field
The utility model relates to the technical field of building curtain wall construction, in particular to a novel installation structure of a ceramic tile curtain wall string hanging system.
Background
In recent years, along with the development of cities and the change of aesthetic ideas of buildings by people, the building facade curtain wall modeling is more endowed with innovation and artistry, in order to adapt to the changes, the materials of the building curtain wall are also developed in a changeable manner, the building materials are also important to meet the building functionality, and meanwhile, the building is endowed with good sensory effect, and especially for the artistic building curtain wall, the aesthetic texture of the materials can bring the most direct effect impact to people. The ceramic brick curtain wall is used in a plurality of famous buildings abroad, and has been stored until now, in recent years, the ceramic brick is gradually used as an outer elevation building block in China.
In the prior art, the following problems exist:
at present, the construction of the ceramic tile curtain wall in China is mostly carried out by adopting a buried plate installation construction process, the modeling third dimension is poor, the durability is weak, and the high-rise large-area construction is easy to cause insolation cracking and panel falling, so that the safety problems of hurting people and the like are caused, so the limitation exists.
Disclosure of Invention
The utility model aims to provide a novel installation structure of a ceramic tile curtain wall serial hanging system, which aims to solve the problems in the background technology.
The technical scheme of the utility model is as follows: novel mounting structure of system is hung to pottery clay brick curtain cluster, including a plurality of stands, still include:
the cross beams are arranged among the upright posts, one end of each cross beam is fixedly connected with a connecting bolt through threads, and the other end of each cross beam is connected with the adjacent upright post in a welding mode;
the galvanized steel corner brackets are fixed on one side of the cross beam through bolts, and vertical connecting screw bars are welded and fixed at positions, close to the galvanized steel corner brackets, of one side wall of the cross beam;
the steel bar meshes are fixedly arranged on the galvanized steel corner brackets;
the clay bricks are arranged on the outer sides of the posts, the posts and the galvanized steel corner brackets are fixedly connected with the clay bricks at the top, and gaps among the clay bricks are stitched by adopting mortar stitching agents.
Preferably, a plurality of rear embedded parts are arranged above the cross beam, and the rear embedded parts are fixed on the inner side of Tao Tuzhuan in a pre-buried mode.
Preferably, a conversion joint is welded on one side wall of each rear embedded part.
Preferably, the end part of the adapter is embedded with the upright post, and the adapter is fixed with the upright post through a bolt.
Preferably, the novel brick comprises a plurality of clamping type T-shaped Tao Tuzhuan, wherein a plurality of clamping type T-shaped clay bricks are fixedly arranged between a plurality of upright posts and a cross beam, a plurality of T-shaped clamping grooves are formed in the clamping type T-shaped clay bricks, gaskets are inserted into the T-shaped clamping grooves together, and the gaskets are matched with the inner side walls of the clamping type T-shaped Tao Tuzhuan.
The utility model provides a novel installation structure of a ceramic tile curtain wall string hanging system through improvement, and compared with the prior art, the installation structure has the following improvement and advantages:
the method comprises the following steps: the utility model aims at the construction of the bottom, the suspended ceiling and the corner parts of the curtain wall, adopts the clamping piece type T-shaped Tao Tuzhuan, improves the construction efficiency, improves the overall layering sense of the ceramic brick curtain wall modeling, shortens the construction period, can effectively improve the construction efficiency, enhances the cohesiveness between bricks, and can be used for the construction of high-rise building curtain walls;
and two,: the vertical connection screw thread steel bars are adopted as the string steel bars, so that the method is economical and practical, convenient to construct, and the steel bar meshes can effectively increase the cohesiveness between bricks and the masonry height of the curtain wall;
and thirdly,: the utility model has stable structure, can be widely applied to high-rise construction, ensures the integral installation effect of the curtain wall, and ensures the current safety and the uniformity among components.
Drawings
The utility model is further explained below with reference to the drawings and examples:
FIG. 1 is a schematic view of the structure of the present utility model in use;
FIG. 2 is a schematic perspective view of a rear buried member of the present utility model;
FIG. 3 is a schematic perspective view of the rear insert and adapter of the present utility model;
FIG. 4 is a schematic view of the present utility model in a column mounted state;
FIG. 5 is a schematic view of the beam mounting state of the present utility model;
fig. 6 is a schematic view showing an installation state of a vertical connection screw reinforcement and a reinforcement mesh sheet according to the present utility model;
FIG. 7 is a schematic view of the structure of the clamping type T-shaped clay brick of the utility model;
fig. 8 is a schematic view of the structure of the clay brick of the present utility model.
Reference numerals illustrate:
101. a column; 102. a rear embedded part; 103. a conversion joint; 104. a cross beam; 105. a connecting bolt; 106. vertically connecting a twisted steel; 107. clip T-shape Tao Tuzhuan; 108. reinforcing steel bar meshes; 109. galvanized steel corner brace; 110. tao Tuzhuan.
Detailed Description
The following detailed description of the present utility model clearly and fully describes the technical solutions of the embodiments of the present utility model, and it is apparent that the described embodiments are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
The utility model provides a novel installation structure of a ceramic brick curtain wall string hanging system through improvement, and the technical scheme of the utility model is as follows:
as shown in fig. 1-8, a novel installation structure of a ceramic tile curtain wall string hanging system comprises a plurality of upright posts 101, and further comprises:
the plurality of cross beams 104, the plurality of cross beams 104 are arranged among the plurality of upright posts 101, one end of each cross beam 104 is fixedly connected with a connecting bolt 105 through threads between each upright post 101, and the other end of each cross beam 104 is connected with the adjacent upright post 101 in a welding mode; the plurality of uprights 101 and cross-members 104 form keels in the present mounting structure.
The galvanized steel corner brackets 109 are fixed on one side of the cross beam 104 through bolts, and vertical connecting screw bars 106 are welded and fixed at positions, close to the galvanized steel corner brackets 109, of one side wall of the cross beam 104;
the steel bar meshes 108, wherein the steel bar meshes 108 are fixedly arranged on a plurality of galvanized steel corner brackets 109; through the structure, the vertical connecting twisted steel 106 is adopted as the string hanging steel, so that the construction is economical and practical, the construction is convenient, the cohesiveness between bricks can be effectively increased through the steel mesh 108, and the masonry height of the curtain wall can be effectively increased.
The plurality of Tao Tuzhuan, tao Tuzhuan 110 are arranged on the outer sides of the plurality of upright posts 101, the upright posts 101 and the galvanized steel corner brackets 109 are fixedly connected with the clay bricks 110 positioned on the tops, and gaps among the plurality of clay bricks 110 are stitched by adopting mortar stitching agents.
Further, a plurality of rear embedded parts 102 are arranged above the cross beam 104, and the rear embedded parts 102 are fixed on the inner side of the Tao Tuzhuan 110 in a pre-buried mode; the post-embedded part 102 adopts a Q235B anchor plate, the post-embedded part 102 is connected with the structure through an expansion bolt and a chemical anchor bolt respectively, and the post-embedded part 102 adopts corresponding anti-corrosion treatment; the post-buried member 102 repair construction drawing is implemented after the owner and design confirmation, and meanwhile, the drawing test of the chemical anchor bolts before construction is ensured, and the test can be performed on site according to a group of every three members of various specifications.
Further, a conversion joint 103 is welded to a side wall of each post-buried member 102.
Further, the end of the adapter 103 is embedded with the upright post 101, and the adapter 103 is fixed with the upright post 101 through bolts; through the structure, the post 101 is fixedly connected with the post-embedded part 102.
Further, the novel brick comprises a plurality of clamping type T-shaped clay bricks 107, wherein the clamping type T-shaped clay bricks 107 are fixedly arranged between the upright posts 101 and the cross beams 104, a plurality of T-shaped clamping grooves are formed in the clamping type T-shaped clay bricks 107, gaskets are inserted into the T-shaped clamping grooves together, and the gaskets are matched with the inner side walls of the clamping type T-shaped clay bricks 107; through the structure, the clamping piece type T-shaped Tao Tuzhuan 107 is adopted, so that the construction efficiency is improved, the overall layering sense of the clay brick curtain wall modeling is improved, the construction period is shortened, the construction efficiency can be effectively improved, the cohesiveness between bricks is enhanced, and the construction method can be used for high-rise building curtain wall construction.
Working principle: when in use, the method specifically comprises the following mounting steps:
step one: and (3) measuring and paying off: confirming the positions of reference points and lines of a first layer, setting up a standard layer, establishing a control network in the first layer of the curtain wall according to the control axis of the first layer of the total package, outwards moving the control network according to the installation requirement of the curtain wall of the inner control network to form an outer control network, and rechecking and correcting the control network according to a design drawing so as to enable the control network to meet the design and installation requirements;
step two: the post-buried member 102 is installed: the post-buried member 102 adopts a Q235B anchor plate, and the anchor plate adopts corresponding anti-corrosion treatment. The anchor plates are respectively connected with the structure through expansion bolts and chemical anchor bolts, the post-buried part 102 is implemented after the repair construction drawing of the embedded part is confirmed by owners and designs, meanwhile, the chemical anchor bolts are ensured to be subjected to a drawing test before construction, and each three parts are combined into a group according to various specifications, so that the test can be carried out on site;
step three: the adapter 103 is installed: when the adapter 103 is installed, the embedded part 102 is arranged in each layer of cast-in-place concrete floor slab or beam of the main structure, the adapter 103 is welded with the embedded part 102, and then the adapter 103 is connected with the upright post 101 by a stainless steel bolt; when in installation, the longitudinal and transverse central lines are aligned firstly, then electric welding is carried out, and the length, the height and the quality of the welding electrode are all required by structural welding lines;
step four: and (3) mounting a column 101: the upright post 101 is installed from bottom to top, the upright post 101 is connected with the connecting code, the upright post 101 is provided with a movable joint, the joint is connected with an upper post and a lower post through a core sleeve, the core sleeve is tightly connected with the upright post 101 and is in sliding fit, and the upper post and the lower post are fixed by adopting stainless steel bolts; the upright post 101 is fixed with bolts in time after being installed in place and fastened;
step five: the cross beam 104 is mounted: after the upright post 101 is installed, checking the verticality, the levelness and the spacing, installing the cross beam 104 after meeting the requirements, welding one end of the cross beam 104 with one end of the upright post 101, movably connecting the other end of the cross beam 104 with the outer edge of the finishing surface by bolts, and checking, adjusting, correcting and fixing the outer edge of the cross beam 104 when the height of one layer is installed, so that the outer edge of the finishing surface meets the quality requirements;
step six: vertical connection rebar 106 and rebar mesh 108: accurately positioning the position of the vertical connecting twisted steel 106 on the cross beam 104, and fixing the vertical connecting twisted steel 106 on the cross beam 104 by adopting a welding method; arranging the reinforcing steel mesh 108 on the galvanized steel corner bracket 109, and fixing the galvanized steel corner bracket 109 and the cross beam 104 through bolts;
step seven: tao Tuzhuan 110 large-surface installation: tao Tuzhuan 110, installing from bottom to top, and adopting a three-one masonry method, namely a masonry method of one shoveling ash, one brick and one kneading and pressing; building a first brick on the cross beam 104, wherein the vertical mortar joints of the upper and lower bricks are staggered by one third of the brick length in the building process; each brick is connected in series through vertical through steel bars, and mortar is filled in gaps between the steel bars and brick holes for fixation;
step eight: and (3) corner brick installation: the construction line perpendicular to the transverse direction Tao Tuzhuan is additionally arranged on the base layer of the installation mode of the common brick, the angle of the perpendicular line is strictly controlled, deviation cannot occur, and the corner brick is placed into the 90-degree included angle of the construction line, so that two faces of the corner brick just touch the two construction lines;
step nine: clip T Tao Tuzhuan 107 mount: the aluminum alloy hanging piece is installed in place according to the drilling space position of the keel, but is not firmly fixed; after the aluminum alloy hanging piece is mounted on the keel, inserting the typeset clamping type T-shaped clay bricks 107 into the picking piece according to the sequence and the reserved T-shaped clamping groove positions in the clamping type T-shaped clay bricks 107; the gasket plays a role in protecting the clamping type T-shaped Tao Tuzhuan 107 and increasing the friction force between the clamping type T-shaped Tao Tuzhuan and the picking piece, and meanwhile, the gasket can adjust the height error of the clamping type T-shaped clay brick 107; when the position of the clamping piece type T-shaped clay brick 107 reaches the expected position, a spanner is adopted to fix the picking piece nut;
step ten: tao Tuzhuan 110 joint cleaning: pointing by adopting special mortar pointing agent.

Claims (5)

1. Novel mounting structure of system is hung to pottery clay brick curtain cluster, including a plurality of stands (101), its characterized in that: further comprises:
the plurality of cross beams (104), the plurality of cross beams (104) are arranged among the plurality of upright posts (101), one end of each cross beam (104) is fixedly connected with a connecting bolt (105) through threads between each upright post (101), and the other end of each cross beam (104) is connected with the adjacent upright post (101) in a welding mode;
the galvanized steel corner brackets (109) are fixed on one side of the cross beam (104) through bolts, and vertical connecting screw bars (106) are welded and fixed at positions, close to the galvanized steel corner brackets (109), of one side wall of the cross beam (104);
the steel bar meshes (108) are fixedly arranged on the galvanized steel corner brackets (109);
the plurality of Tao Tuzhuan (110), clay brick (110) set up in the outside of a plurality of stand (101), stand (101) and galvanized steel angle sign indicating number (109) with be located top clay brick (110) fixed connection, the gap between a plurality of Tao Tuzhuan (110) adopts mortar pointing agent to pointing.
2. The mounting structure of the novel ceramic tile curtain wall string hanging system according to claim 1, wherein: a plurality of rear embedded parts (102) are arranged above the cross beam (104), and the rear embedded parts (102) are fixed on the inner side of the Tao Tuzhuan (110) in a pre-buried mode.
3. The mounting structure of the novel ceramic tile curtain wall string hanging system according to claim 2, wherein: a conversion joint (103) is welded on one side wall of each rear embedded part (102).
4. The mounting structure of the novel ceramic tile curtain wall string hanging system according to claim 3, wherein: the end part of the adapter (103) is embedded with the upright post (101), and the adapter (103) and the upright post (101) are fixed through bolts.
5. The mounting structure of the novel ceramic tile curtain wall string hanging system according to claim 1, wherein: the novel anti-theft device is characterized by further comprising a plurality of clamping type T-shaped Tao Tuzhuan (107), wherein the clamping type T-shaped Tao Tuzhuan (107) is fixedly arranged between the upright posts (101) and the cross beam (104), a plurality of T-shaped clamping grooves are formed in the clamping type T-shaped Tao Tuzhuan (107), gaskets are inserted into the T-shaped clamping grooves together, and the gaskets are matched with the inner side walls of the clamping type T-shaped Tao Tuzhuan (107).
CN202320110448.3U 2023-01-19 2023-01-19 Novel mounting structure of ceramic tile curtain wall string hanging system Active CN219825762U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320110448.3U CN219825762U (en) 2023-01-19 2023-01-19 Novel mounting structure of ceramic tile curtain wall string hanging system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320110448.3U CN219825762U (en) 2023-01-19 2023-01-19 Novel mounting structure of ceramic tile curtain wall string hanging system

Publications (1)

Publication Number Publication Date
CN219825762U true CN219825762U (en) 2023-10-13

Family

ID=88281939

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320110448.3U Active CN219825762U (en) 2023-01-19 2023-01-19 Novel mounting structure of ceramic tile curtain wall string hanging system

Country Status (1)

Country Link
CN (1) CN219825762U (en)

Similar Documents

Publication Publication Date Title
CN104405062A (en) Integrated column-equipped heat preservation wallboard, production and building techniques and matched equipment
CN110670867B (en) Construction method of scaffold for improving outer vertical surface of existing building
WO2011002271A2 (en) A slab formwork system
CN102644382A (en) Mounting technology of large-module wall
CN111287467B (en) Integral dry hanging process for ceramic brick curtain wall
CN110792233A (en) Construction method of large aluminum-magnesium-manganese decorative roof panel
CN204645343U (en) Prefabricated assembled concrete out-hung panel fastening devices
CN219825762U (en) Novel mounting structure of ceramic tile curtain wall string hanging system
CN218374567U (en) Can fix a position ALC wallboard reinforced structure that can exempt from to plaster
CN204001289U (en) There is the light steel keel partition that carries the arm of encorbelmenting
CN111119368A (en) Construction method for externally-hung metal rock wool sandwich board of autoclaved sand aerated concrete wallboard
CN210628812U (en) Connecting structure for installing distribution equipment on masonry wall
CN209837882U (en) Can have enough to meet need temporary enclosure
JP4027170B2 (en) External scaffold device and construction method of external scaffold device
CN111576681A (en) FS composite heat-preservation construction integrated technology construction process
CN112746704A (en) Arch type steel-concrete combined ceiling structure of large-span giant underground workshop and construction method
CN219298535U (en) Combined light partition board partition system
CN220318990U (en) Mounting structure for fixing temporary balustrade
CN217781734U (en) Auxiliary construction device for prefabricated anti-collision wall
CN212428048U (en) Outer scaffold base device of slipform construction storehouse top
CN220486939U (en) Construction structure for hoisting large-size prefabricated cantilever plates of high-rise building roof
CN214170039U (en) Interim safe cat ladder
CN114086712B (en) Alternating construction method for splicing aluminum veneers in high and large spaces
CN114575491B (en) Composite construction method for special-shaped complex secondary structure
CN216740618U (en) Steel construction protection scaffold puts up system suitable for light rail station

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant