CN219824931U - Length-adjustable bailey beam nondestructive reinforcing vertical rod - Google Patents

Length-adjustable bailey beam nondestructive reinforcing vertical rod Download PDF

Info

Publication number
CN219824931U
CN219824931U CN202321141231.5U CN202321141231U CN219824931U CN 219824931 U CN219824931 U CN 219824931U CN 202321141231 U CN202321141231 U CN 202321141231U CN 219824931 U CN219824931 U CN 219824931U
Authority
CN
China
Prior art keywords
adjustable
bailey beam
steel
length
vertical rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321141231.5U
Other languages
Chinese (zh)
Inventor
白万帅
周俊龙
李晓明
李晓磊
赵伟宏
赵旭
孙承林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN202321141231.5U priority Critical patent/CN219824931U/en
Application granted granted Critical
Publication of CN219824931U publication Critical patent/CN219824931U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

The utility model relates to a length-adjustable bailey beam nondestructive reinforcement vertical rod which comprises lower I-shaped steel, wherein fixed bases are arranged at the front end and the rear end of the top of the lower I-shaped steel, the fixed bases are positioned at the front side and the rear side of a bailey beam web rod, vertical steel pipes are welded at the tops of the fixed bases, adjustable jacking is arranged at the tops of the vertical steel pipes, turnbuckles are sleeved on the outer sides of the adjustable jacking, and upper I-shaped steel is arranged at the tops of the adjustable jacking. The utility model has the advantages of convenient and quick installation, no need of welding, reduced welding damage to the bailey beam, strong applicability by adjusting the jacking and the length of the reinforcing vertical rod, convenient installation and disassembly by adopting an assembled installation structure, and simultaneously avoids the phenomenon of stress concentration of the bailey beam at the beam of the pile top, and ensures the safety of the bailey beam.

Description

Length-adjustable bailey beam nondestructive reinforcing vertical rod
Technical Field
The utility model relates to the technical field of building construction, in particular to a length-adjustable bailey beam nondestructive reinforcing vertical rod.
Background
The bailey frame is a truss unit consisting of an upper chord member, a lower chord member, a vertical rod and an inclined rod, can bear a pressure structure above, is formed by connecting a plurality of bailey frames through pin shafts, and is the most widely applied and best assembled bridge in China. Has the characteristics of simple structure, convenient transportation, quick erection, large carrying capacity, good interchangeability and strong adaptability
In the bridge construction process, the Bailey beam, the steel pipe pile, the pile top beam and the like form a temporary support system, the upper load is transferred to the Bailey beam, and then the Bailey beam is transferred to the pile top beam, the steel pipe pile and the like. Under ideal conditions, the upper part of the pile top beam is opposite to the vertical rod of the Bailey beam, but is limited by bridge span and site conditions, and in actual construction, the pile top beam is usually opposite to the chord member instead of the vertical rod, so that the shearing force of the lower chord member of the Bailey beam is overlarge, stress concentration occurs, and damage is caused. In order to prevent damage, vertical bar reinforcement is performed when installing the bailey beam. The conventional bailey beam reinforcing vertical rod needs to be welded with reinforcing accessories on the bailey frame, damage can be caused to the bailey frame, and the length cannot be adjusted.
Disclosure of Invention
The utility model aims to solve the defects of the prior art and provides a length-adjustable bailey beam nondestructive reinforcing vertical rod.
The utility model adopts the following technical scheme to realize the aim: the utility model provides a nondestructive montant of strengthening of bailey beam of adjustable length, includes the I-steel down, and fixed base is all installed at both ends around the I-steel top down, and fixed base is located both sides around the bailey beam web pole, and vertical steel pipe is welded at fixed base top, and adjustable jacking is installed at vertical steel pipe top, and adjustable jacking outside cover is equipped with the nut, and the I-steel is installed at adjustable jacking top.
Further, the fixed base is a channel steel, and the groove of the channel steel is larger than the lower I-steel.
Further, the adjustable jacking is arranged on the inner side of the top of the vertical steel pipe.
Further, the diameter of the cross section of the vertical steel pipe is 60mm.
The beneficial effects of the utility model are as follows: the utility model has the advantages of convenient and quick installation, no need of welding, reduced welding damage to the bailey beam, strong applicability by adjusting the jacking and the length of the reinforcing vertical rod, convenient installation and disassembly by adopting an assembled installation structure, and simultaneously avoids the phenomenon of stress concentration of the bailey beam at the beam of the pile top, and ensures the safety of the bailey beam.
Drawings
FIG. 1 is a schematic diagram of the structure of the present utility model;
FIG. 2 is a side view of the present utility model;
in the figure: 1-feeding I-steel; 2-jacking; 3-nuts; 4-vertical steel pipes; 5-a fixed base; 6-lower I-steel; 7-bailey beams; 8-pile top cross beams; 9-steel pipe piles;
the drawings in the present utility model are schematic, and their sizes do not represent actual dimensions;
the embodiments of the present utility model will be described in detail below with reference to the accompanying drawings.
Detailed Description
The utility model is further illustrated by the following examples in conjunction with the accompanying drawings:
as shown in fig. 1-2, a length-adjustable bailey beam nondestructive reinforcement vertical rod comprises a lower I-steel 6, wherein fixed bases 5 are respectively arranged at the front end and the rear end of the top of the lower I-steel, the fixed bases 5 are positioned at the front side and the rear side of a web member of the bailey beam 7, vertical steel pipes 4 are welded at the tops of the fixed bases 5, adjustable jacking 2 are arranged at the tops of the vertical steel pipes 4, nuts 3 are sleeved outside the adjustable jacking 2, and upper I-steel 1 is arranged at the tops of the adjustable jacking 2. The fixed base 5 is a channel steel, and the groove of the channel steel is larger than the lower I-steel 6. The adjustable jacking 2 is arranged on the inner side of the top of the vertical steel pipe 4. The vertical steel pipe 4 adopts a seamless steel pipe with phi 60 multiplied by 4.5 mm.
And determining the installation position of the reinforcing vertical rod according to the design positions of the steel pipe pile 9 and the pile top cross beam 8, wherein the reinforcing vertical rod is positioned right above the pile top cross beam 8. The lower I-steel 6 is fixed on a lower chord member of the bailey beam 7, the fixed base 5 is welded with the vertical steel pipe 4 and is placed on the lower I-steel 6, the adjustable jacking 2 and the nut 3 are placed on the upper portion of the vertical steel pipe 4, pre-tightening is carried out firstly, after the upper I-steel 1 is installed, final tightening is carried out, so that the upper I-steel 1 and the lower I-steel 6 are respectively propped against the upper chord member and the lower chord member of the bailey beam 7, and the vertical reinforcement of the bailey beam 7 is realized. During the dismantling, only the nut 3 is required to be reversely rotated, the adjustable jacking 2 is loosened, the upper I-steel 1 and the lower I-steel 6 are pulled out, and the dismantling of the reinforcing vertical rod can be completed.
While the utility model has been described above with reference to the accompanying drawings, it will be apparent that the utility model is not limited to the above embodiments, but is intended to cover various modifications, either made by the method concepts and technical solutions of the utility model, or applied directly to other applications without modification, within the scope of the utility model.

Claims (4)

1. The utility model provides a nondestructive montant of strengthening of bailey beam of adjustable length, a serial communication port, including lower I-steel (6), fixed base (5) are all installed at both ends around lower I-steel (6) top, and fixed base (5) are located both sides around bailey beam (7) web member, and fixed base (5) top welding has vertical steel pipe (4), and adjustable jacking (2) are installed at vertical steel pipe (4) top, and adjustable jacking (2) outside cover is equipped with nut (3), and I-steel (1) are installed at adjustable jacking (2) top.
2. The length-adjustable bailey beam nondestructive reinforcement vertical rod according to claim 1, wherein the fixed base (5) is a channel steel, and the groove of the channel steel is larger than the lower I-steel (6).
3. The length-adjustable bailey beam nondestructive reinforcement vertical rod according to claim 2, wherein the adjustable jacking (2) is arranged on the inner side of the top of the vertical steel tube (4).
4. A length-adjustable beret beam non-destructive reinforcement vertical rod according to claim 3, characterized in that the vertical steel tube (4) has a cross-sectional diameter of 60mm.
CN202321141231.5U 2023-05-11 2023-05-11 Length-adjustable bailey beam nondestructive reinforcing vertical rod Active CN219824931U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321141231.5U CN219824931U (en) 2023-05-11 2023-05-11 Length-adjustable bailey beam nondestructive reinforcing vertical rod

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321141231.5U CN219824931U (en) 2023-05-11 2023-05-11 Length-adjustable bailey beam nondestructive reinforcing vertical rod

Publications (1)

Publication Number Publication Date
CN219824931U true CN219824931U (en) 2023-10-13

Family

ID=88284809

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321141231.5U Active CN219824931U (en) 2023-05-11 2023-05-11 Length-adjustable bailey beam nondestructive reinforcing vertical rod

Country Status (1)

Country Link
CN (1) CN219824931U (en)

Similar Documents

Publication Publication Date Title
CN108316477B (en) Node connecting structure in flat steel tube concrete column and section steel beam and construction method
CN112049028B (en) Damping and anti-overturning single-column pier bridge reinforcing device and installation method
CN216042984U (en) Collapse-prevention steel pipe tower with stable base
CN219824931U (en) Length-adjustable bailey beam nondestructive reinforcing vertical rod
CN110878524B (en) Construction method of steel pipe concrete arch bridge installation system
CN218912364U (en) Assembled steel stand bearing structure
CN111350345A (en) Pull-rod-free template reinforcing system for outer wall of buried sewage treatment plant and installation method
CN115341701B (en) Hanging formwork construction method for high-altitude overhanging steel bar truss floor support plate
CN218467092U (en) Adjustable supporting device for assembled steel bar truss floor bearing plate
CN113309366A (en) Steel structure mounting shoring system and construction process thereof
CN107142967B (en) Integral sliding structure of water area tunnel formwork supporting structure and inner formwork support
CN216765927U (en) Assembled supporting device
CN221645550U (en) Movable opposite supporting device for tower column on diamond main tower
CN220318759U (en) Truss for high-altitude side wall
CN221741552U (en) Indoor manual carrying and installing solderless bearing steel frame for house reconstruction
CN217106134U (en) Telescopic floor slab supporting truss
CN217781770U (en) Device for controlling radian line type effect of bridge arch ring
CN212358034U (en) Integrated supporting mechanism of thin-wall hollow pier
CN220266666U (en) Underpinning device of pit type steel pipe static pressure pile
CN215055275U (en) Adjustable single-side formwork supporting pull rod
CN218265945U (en) Device for improving construction progress of large pipe shed in tunnel
CN221196383U (en) Underground pipeline suspension protection device
CN216690325U (en) Scaffold frame supporting beam is encorbelmented to pre-buried formula of structure
CN216893492U (en) Be used for reinforced connection structure of concrete beam template
CN220166693U (en) Cast-in-situ bent cap assembled steel pipe support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant