CN219793640U - Bridge high pier steel bar operation platform - Google Patents

Bridge high pier steel bar operation platform Download PDF

Info

Publication number
CN219793640U
CN219793640U CN202320089576.4U CN202320089576U CN219793640U CN 219793640 U CN219793640 U CN 219793640U CN 202320089576 U CN202320089576 U CN 202320089576U CN 219793640 U CN219793640 U CN 219793640U
Authority
CN
China
Prior art keywords
steel bar
operation platform
bar operation
bridge high
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320089576.4U
Other languages
Chinese (zh)
Inventor
李其山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changde Baisheng Construction Technology Co ltd
Original Assignee
Changde Baisheng Construction Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changde Baisheng Construction Technology Co ltd filed Critical Changde Baisheng Construction Technology Co ltd
Priority to CN202320089576.4U priority Critical patent/CN219793640U/en
Application granted granted Critical
Publication of CN219793640U publication Critical patent/CN219793640U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/30Adapting or protecting infrastructure or their operation in transportation, e.g. on roads, waterways or railways

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to the technical field of operation platforms, and discloses a bridge high pier steel bar operation platform which comprises a bridge high pier main body, a movable mechanism, a climbing mechanism and a steel bar operation platform mechanism, wherein the movable mechanism is positioned at the outer end of the bridge high pier main body, the climbing mechanism is positioned at the outer end of the bridge high pier main body, the steel bar operation platform mechanism is positioned at the front end of the movable mechanism, and the movable mechanism comprises a mounting angle iron, a mounting hole and a mounting block I. This bridge high mound steel bar operation platform has installed movable mechanism, fixes in bridge high mound main part through the installation angle bar, and follow-up installation piece of being convenient for first, bracing piece and installation piece second are connected, and the installation and the dismantlement of steel bar operation platform mechanism of being convenient for, and convenient to use person can be better carry out the steel bar operation, and the bracing piece supports steel bar operation platform mechanism, makes steel bar operation platform mechanism more steady, and installation piece second installs steel bar operation platform mechanism, is convenient for make steel bar operation platform mechanism more firm.

Description

Bridge high pier steel bar operation platform
Technical Field
The utility model relates to the technical field of operation platforms, in particular to a bridge high pier steel bar operation platform.
Background
When the high mound steel bar operation of bridge, need the workman to climb, need carry out the steel bar operation on different heights, traditional climbing through the scaffold frame, but when the scaffold frame was built, not swift, and stability is relatively poor.
Currently, the lifting machine is used for lifting the height, so that a user can conveniently lift the lifting machine to the required height to perform the bridge high pier steel bar operation, and the operation is more convenient.
However, when the steel bar operation of a plurality of bridge high piers is needed, the lifting machine is obviously insufficient to be used simultaneously, and the cost is high, so that the lifting machine is not beneficial to any disassembly and assembly.
Disclosure of Invention
(one) solving the technical problems
The utility model aims to provide a bridge high pier steel bar operation platform, which solves the problems that in the prior art, when the steel bar operation of a plurality of bridge high piers is needed, lifting machines are obviously not used simultaneously, the cost is high, and the lifting machines are not beneficial to random disassembly and assembly.
(II) technical scheme
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides a bridge high mound steel bar operation platform, includes bridge high mound main part, movable mechanism, climbing mechanism and steel bar operation platform mechanism, movable mechanism is located the outer end of bridge high mound main part, climbing mechanism is located the outer end of beam high mound main part, steel bar operation platform mechanism is located movable mechanism's front end, movable mechanism includes installation angle bar, mounting hole, installation piece one, bracing piece and installation piece two, installation angle bar fixed mounting is in the outer end of bridge high mound main part, the quantity of installation angle bar is a plurality of, the installation angle bar is symmetric distribution.
Preferably, the mounting hole is fixed to be set up in the outer end of installation angle bar, the quantity of mounting hole is a plurality of, the mounting hole is the equidistance and arranges, first movable mounting of installation piece is in the inside of mounting hole, first and mounting hole looks adaptation, is fixed in bridge high mound main part through the installation angle bar, and follow-up installation piece of being convenient for one, bracing piece and installation piece second are connected, and the installation and the dismantlement of the steel bar operation platform mechanism of being convenient for, and convenient to use person can be better carry out the steel bar operation.
Preferably, the bracing piece fixed mounting just with steel bar operation platform mechanism fixed connection in the front end of installation piece one, installation piece two movable mounting in the inside of mounting hole and with steel bar operation platform mechanism fixed connection, installation piece two supports steel bar operation platform mechanism through the bracing piece with the mounting hole looks adaptation, makes steel bar operation platform mechanism more steady, and installation piece two installs steel bar operation platform mechanism, is convenient for make steel bar operation platform mechanism more firm.
Preferably, the climbing mechanism comprises a fixed block, a supporting rod and a climbing rod, wherein the fixed block is fixedly arranged at the outer end of the bridge high pier main body, the fixed blocks are symmetrically distributed, the supporting rod is fixedly arranged at the right end of the fixed block, the climbing rod is fixedly arranged at the right end of the supporting rod, the supporting rod is fixed through the fixed block, the climbing rod is fixed by the supporting rod, a user can climb the climbing rod conveniently, and the user can climb the steel bar operation platform mechanism to perform steel bar operation.
Preferably, the steel bar operation platform mechanism comprises a steel bar operation platform body, a telescopic protection rod, a connecting rod and a telescopic anti-falling rod, wherein the steel bar operation platform body is fixedly installed at the top end of the supporting rod and is positioned at the front end of the second installation block, the user can tread conveniently through the steel bar operation platform body, and the user can perform steel bar operation conveniently.
Preferably, the telescopic protection rod is fixedly arranged at the top end of the steel bar operation platform body, the number of the telescopic protection rods is a plurality of, the telescopic protection rods are symmetrically distributed, and a user is protected through the telescopic protection rods.
Compared with the prior art, the utility model has the beneficial effects that:
1. according to the bridge high pier steel bar operation platform, the movable mechanism is installed, the bridge high pier main body is fixed through the installation angle iron, the follow-up installation block I, the support rod and the installation block II are convenient to connect, the installation and the disassembly of the steel bar operation platform mechanism are convenient, a user can better perform steel bar operation, the support rod supports the steel bar operation platform mechanism, the steel bar operation platform mechanism is enabled to be more stable, the installation block II is used for installing the steel bar operation platform mechanism, and the steel bar operation platform mechanism is convenient to be firmer;
2. according to the bridge high pier steel bar operation platform, the climbing mechanism is arranged, the supporting rods are fixed through the fixing blocks, the climbing rods are fixed, the climbing rods are convenient for a user to climb, and the user can climb onto the steel bar operation platform mechanism to perform steel bar operation;
3. this bridge high mound steel bar operation platform has installed steel bar operation platform mechanism, is convenient for the user tramples through the steel bar operation platform body, and convenient to use person carries out the steel bar operation, and flexible guard bar protects the user, and the connecting rod is connected flexible anti-falling bar, avoids the user to fall.
Drawings
FIG. 1 is a schematic perspective view of the present utility model;
FIG. 2 is a schematic cross-sectional view of the present utility model;
FIG. 3 is an enlarged schematic view of the structure of FIG. 2A according to the present utility model;
fig. 4 is a schematic perspective view of a reinforcement work platform body according to the present utility model;
FIG. 5 is a schematic perspective view of the climbing mechanism of the present utility model.
In the figure: 1. a bridge high pier body; 2. a movable mechanism; 201. mounting angle iron; 202. a mounting hole; 203. a first mounting block; 204. a support rod; 205. a second mounting block; 3. a climbing mechanism; 301. a fixed block; 302. a support rod; 303. climbing the rod; 4. a steel bar operation platform mechanism; 401. a steel bar operation platform body; 402. a telescopic protective rod; 403. a connecting rod; 404. a telescopic anti-falling rod.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1-5, the present utility model provides a technical solution: the utility model provides a bridge high mound steel bar operation platform, including bridge high mound main part 1, movable mechanism 2, climbing mechanism 3 and steel bar operation platform mechanism 4, movable mechanism 2 is located the outer end of bridge high mound main part 1, climbing mechanism 3 is located the outer end of beam high mound main part, steel bar operation platform mechanism 4 is located the front end of movable mechanism 2, movable mechanism 2 includes installation angle bar 201, mounting hole 202, installation piece one 203, bracing piece 204 and installation piece two 205, installation angle bar 201 fixed mounting is in the outer end of bridge high mound main part 1, the quantity of installation angle bar 201 is a plurality of, installation angle bar 201 is the symmetric distribution.
The mounting hole 202 is fixed to be set up in the outer end of installation angle bar 201, the quantity of mounting hole 202 is a plurality of, the mounting hole 202 is the equidistance and arranges, installation piece one 203 movable mounting is in the inside of mounting hole 202, installation piece one 203 and mounting hole 202 looks adaptation, fix on bridge pier main part 1 through installation angle bar 201, be convenient for follow-up installation piece one 203, bracing piece 204 and installation piece two 205 are connected, be convenient for the installation and the dismantlement of bar operation platform mechanism 4, the user can be better carry out the bar operation, bracing piece 204 fixed mounting is in the front end of installation piece one 203 and with bar operation platform mechanism 4 fixed connection, installation piece two 205 movable mounting is in the inside of mounting hole 202 and with bar operation platform mechanism 4 fixed connection, installation piece two 205 and mounting hole 202 looks adaptation, support bar operation platform mechanism 4 through bracing piece 204, make bar operation platform mechanism 4 more steady, installation piece two 205 install bar operation platform mechanism 4, be convenient for make bar operation platform mechanism 4 more firm.
Climbing mechanism 3 includes fixed block 301, branch 302 and climbing pole 303, fixed block 301 fixed mounting is in the outer end of bridge pier main part 1, fixed block 301 is symmetrical distribution, branch 302 fixed mounting is in the right-hand member of fixed block 301, climbing pole 303 fixed mounting is in the right-hand member of branch 302, fixed branch 302 through fixed block 301, the fixed climbing pole 303 of branch 302, climbing pole 303 is convenient for the user climb, the user can climb to steel bar operation platform mechanism 4 through the convenience of customers, steel bar operation platform mechanism 4 includes steel bar operation platform body 401, flexible guard bar 402, connecting rod 403 and flexible anti-falling pole 404, steel bar operation platform body 401 fixed mounting is in the top of bracing piece 204 and is located the front end of installing piece two 205, be convenient for the user trample through steel bar operation platform body 401, convenient for the user carries out steel bar operation, flexible guard bar 402 fixed mounting is in the top of steel bar operation platform body 401, the quantity of flexible guard bar 402 is a plurality of, flexible guard bar 402 is symmetrical distribution, the user carries out the protection through flexible guard bar 402, connecting rod 403 is fixed mounting in the inner of connecting rod 403, the connecting rod 403 is prevented falling pole 404 through flexible anti-falling pole 404, the user is fixed by connecting rod 404.
Working principle: the installation angle bar 201 is fixed on bridge high mound main part 1, follow-up installation piece of being convenient for 203, bracing piece 204 and installation piece two 205 are connected, the installation and the dismantlement of steel bar operation platform mechanism 4 of being convenient for, convenient to use person can be better carry out the reinforcing bar and do, bracing piece 204 supports steel bar operation platform mechanism 4, make steel bar operation platform mechanism 4 more steady, installation piece two 205 install steel bar operation platform mechanism 4, be convenient for make steel bar operation platform mechanism 4 more firm, fixed block 301 fixed strut 302, strut 302 fixed climbing pole 303, climbing pole 303 facilitate the user to climb, convenient to use person can climb and carry out the steel bar operation on steel bar operation platform mechanism 4, steel bar operation platform body 401 is convenient for the user to trample, convenient to use person carries out the steel bar operation, flexible guard bar 402 protects the user, flexible anti-falling pole 404 is connected to the connecting rod 403, avoid the user to fall, convenient to use person carries out the steel bar operation simultaneously on different high mound main parts 1.
Finally, it should be noted that the above description is only for illustrating the technical solution of the present utility model, and not for limiting the scope of the present utility model, and that the simple modification and equivalent substitution of the technical solution of the present utility model can be made by those skilled in the art without departing from the spirit and scope of the technical solution of the present utility model.

Claims (7)

1. The utility model provides a bridge high mound steel bar operation platform, includes bridge high mound main part (1), movable mechanism (2), climbing mechanism (3) and steel bar operation platform mechanism (4), its characterized in that: the movable mechanism (2) is located the outer end of bridge high mound main part (1), climbing mechanism (3) are located the outer end of bridge high mound main part, reinforcing bar operation platform mechanism (4) are located the front end of movable mechanism (2), movable mechanism (2) are including installation angle bar (201), mounting hole (202), installation piece one (203), bracing piece (204) and installation piece two (205), installation angle bar (201) fixed mounting is in the outer end of bridge high mound main part (1), the quantity of installation angle bar (201) is a plurality of, installation angle bar (201) are symmetrical distribution.
2. The bridge high pier steel bar work platform according to claim 1, wherein: the mounting holes (202) are fixedly formed in the outer ends of the mounting angle irons (201), the number of the mounting holes (202) is a plurality of, the mounting holes (202) are distributed at equal intervals, the mounting blocks (203) are movably mounted in the mounting holes (202), and the mounting blocks (203) are matched with the mounting holes (202).
3. The bridge high pier steel bar work platform according to claim 2, wherein: the support rod (204) is fixedly arranged at the front end of the first installation block (203) and is fixedly connected with the steel bar operation platform mechanism (4), the second installation block (205) is movably arranged in the installation hole (202) and is fixedly connected with the steel bar operation platform mechanism (4), and the second installation block (205) is matched with the installation hole (202).
4. A bridge high pier steel bar work platform according to claim 3, wherein: the climbing mechanism (3) comprises a fixed block (301), a supporting rod (302) and a climbing rod (303), wherein the fixed block (301) is fixedly arranged at the outer end of the bridge high pier main body (1), the fixed blocks (301) are symmetrically distributed, the supporting rod (302) is fixedly arranged at the right end of the fixed block (301), and the climbing rod (303) is fixedly arranged at the right end of the supporting rod (302).
5. The bridge high pier steel bar work platform according to claim 4, wherein: the steel bar operation platform mechanism (4) comprises a steel bar operation platform body (401), a telescopic protection rod (402), a connecting rod (403) and a telescopic anti-falling rod (404), wherein the steel bar operation platform body (401) is fixedly installed at the top end of the supporting rod (204) and is located at the front end of the second installation block (205).
6. The bridge high pier steel bar work platform according to claim 5, wherein: the flexible guard bars (402) are fixedly arranged at the top ends of the steel bar operation platform bodies (401), the number of the flexible guard bars (402) is a plurality of, and the flexible guard bars (402) are symmetrically distributed.
7. The bridge high pier steel bar work platform according to claim 6, wherein: the connecting rod (403) is fixedly arranged at the inner end of the telescopic protection rod (402), and the telescopic anti-falling rod (404) is fixedly arranged at the inner end of the connecting rod (403).
CN202320089576.4U 2023-01-31 2023-01-31 Bridge high pier steel bar operation platform Active CN219793640U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320089576.4U CN219793640U (en) 2023-01-31 2023-01-31 Bridge high pier steel bar operation platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320089576.4U CN219793640U (en) 2023-01-31 2023-01-31 Bridge high pier steel bar operation platform

Publications (1)

Publication Number Publication Date
CN219793640U true CN219793640U (en) 2023-10-03

Family

ID=88186777

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320089576.4U Active CN219793640U (en) 2023-01-31 2023-01-31 Bridge high pier steel bar operation platform

Country Status (1)

Country Link
CN (1) CN219793640U (en)

Similar Documents

Publication Publication Date Title
CN219793640U (en) Bridge high pier steel bar operation platform
KR200381397Y1 (en) Foot plate safety guardrail device of mold
CN208815868U (en) A kind of construction scaffold
CN214785757U (en) Scaffold frame that building engineering used
CN213802471U (en) Guardrail is overhauld in construction elevator installation
CN112360130A (en) Splicing type adjustable anti-falling scaffold for construction of overhead building layer
CN208202632U (en) A kind of lift tunnel construction protection canopy
CN219773537U (en) Assembled construction protection platform
CN101560828A (en) Buckled type steel pipe scaffold formwork support of cross strut
CN217897219U (en) Overhanging type scaffold suitable for curtain wall indoor installation
CN207377209U (en) A kind of indirect cool tower lifts broadening platform stent
CN215717005U (en) Concrete box culvert template construction is with scaffold frame that has protective structure
CN220566880U (en) Quick installation type support for construction
CN220058765U (en) Front and rear bracket connecting and fixing device of electric hanging basket
CN214658604U (en) Scaffold for civil and industrial building engineering construction
CN218406330U (en) Building engineering construction scaffold convenient to dismantle
CN213539633U (en) Wide-angle adjustable steel structure platform
CN213297110U (en) Scaffold connecting device convenient to detach for construction
CN216276792U (en) Scaffold frame for municipal works
CN219242097U (en) Security protection net for fan mixing tower prefabricated piece assembly platform
CN219100661U (en) Portable scaffold for construction engineering installation
CN216949839U (en) Building engineering is with dismantling and enclose fender
CN217840808U (en) High-altitude construction platform
CN211007575U (en) A remove handling frame for building engineering
CN220487619U (en) Anti-cracking arch frame trolley transverse telescopic supporting leg system and arch frame trolley

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant