CN219671510U CN202321203743.XU CN202321203743U CN219671510U CN 219671510 U CN219671510 U CN 219671510U CN 202321203743 U CN202321203743 U CN 202321203743U CN 219671510 U CN219671510 U CN 219671510U
Authority
CN
China
Prior art keywords
water supply
box
box body
setting
holes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321203743.XU
Other languages
Chinese (zh)
Inventor
李超
郭勋
刘岱泉
张全剑
李天润
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fourth Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
Fourth Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical Fourth Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN202321203743.XU priority Critical patent/CN219671510U/en
Application granted granted Critical
Publication of CN219671510U publication Critical patent/CN219671510U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sliding Valves (AREA)

Abstract

The utility model discloses a pre-buried temporary water supply point operation box which comprises a box body, wherein a box door is rotatably connected to the right side of the box body, fixing holes are formed in the upper side and the lower side of the box body, a fixing rod is fixedly connected to the left side in the box body, a three-way pipe is fixedly connected to the right side of the fixing rod, sealing sleeves are sleeved on the upper side and the lower side of the three-way pipe in a threaded manner, a central pipe is fixedly connected to the right side of the three-way pipe, a plurality of drain pipes are uniformly and fixedly connected to the lower side of the central pipe, valves are arranged in the drain pipes, a plurality of positioning holes are formed in the lower side of the box body, and conical rods are sleeved on the inner threads of the positioning holes. According to the utility model, through the box body, the simple protection operation on the water supply pipe is completed, the overall stability of the box body is improved under the action of the stabilizing plate, the threaded rod and the threaded cylinder, and meanwhile, the secondary limiting and fixing operation can be carried out on the conical rod, so that the structure has the advantages of low manufacturing cost, simplicity in operation and good practical effect.

Description

Pre-buried temporary water supply point operation box
Technical Field
The utility model relates to the technical field of building construction, in particular to a pre-buried temporary water supply point operation box.
Background
In the building construction process, corresponding water supply points are often set according to actual working conditions, in the actual working process, the whole structure of the water supply points is simple, the water supply pipes are mainly composed of water supply pipes, the water supply pipes are placed at high positions and are subjected to corresponding water discharge operation, the cost is low, however, no protection device for the water supply pipes exists at present, the water inlet pipes are often damaged along with long-time use of the water supply pipes, a large amount of labor and material waste is caused, the construction cost is increased, and a difficult problem is caused to maintain.
Disclosure of Invention
The utility model aims to solve the defects existing in the prior art, such as: the water supply pipe is not protected, the water inlet pipe is often damaged along with long-time use of the water supply pipe, a large amount of labor and material waste is caused, the construction cost is increased, the maintenance becomes a difficult problem, and the embedded temporary water supply point operation box is provided.
In order to achieve the above purpose, the present utility model adopts the following technical scheme:
the utility model provides a temporary water supply point operation box of pre-buried formula, includes the box, the right side of box rotates to be connected and is equipped with the chamber door, the upper and lower both sides of box all are equipped with the fixed orifices, left side fixedly connected with is equipped with the dead lever in the box, the right side fixedly connected with of dead lever is equipped with the three-way pipe, the upper and lower both sides of three-way pipe all thread bush is equipped with the seal cover, the right side fixedly connected with of three-way pipe is equipped with the center tube, the even fixedly connected of downside of center tube is equipped with a plurality of drain pipes, and is a plurality of be equipped with the valve in the drain pipe, the lower side is equipped with a plurality of locating holes, and a plurality of locating hole internal thread bush is equipped with the taper lever, the taper lever runs through in the locating hole setting.
Preferably, place from top to bottom in the box and be equipped with two steadying plates, the downside the steadying plate is located the upside and the toper pole contact connection setting of toper pole, the upside the steadying plate is connected with the interior upside contact of box and is set up, the downside the upside rotation of steadying plate is connected and is equipped with a plurality of screw thread barrels, and is a plurality of screw thread barrel internal thread cover is equipped with the threaded rod, the threaded rod runs through in screw thread barrel setting, threaded rod and upside steadying plate fixed connection setting.
Preferably, the upper sides of the two stabilizing plates are provided with through holes, the through holes and the fixing holes are oppositely arranged, arc plates are arranged in the through holes in a left-right sliding connection mode, and the arc plates and the through holes are oppositely arranged in a matching mode.
Preferably, two the lateral wall of firm board is equipped with logical groove, it is penetrating setting around the logical groove, it sets up equally through rotation hole and through-hole to lead to the groove, rotation hole internal thread cover is equipped with the dwang, the dwang runs through in rotation hole setting, dwang and arc rotate the connection setting.
Preferably, a rubber pad is fixedly connected to the inner side of the arc-shaped plate.
Compared with the prior art, the utility model has the beneficial effects that: through the box, accomplish the simple protection operation to the feed pipe, then under the effect of toper pole, accomplish the holistic simple fixed operation of device, immediately, under the effect of firm board, threaded rod and screw barrel, when improving the holistic steadiness of box, can also carry out the fixed operation of secondary restriction to the toper pole, finally, under the effect of arc and through-hole, accomplish the fixed operation of secondary to the feed pipe, the completion that can be better is to the protection operation of feed pipe, overall structure low in manufacturing cost, easy operation, the practical effect is good.
Drawings
FIG. 1 is a schematic structural diagram of a pre-buried temporary water supply point operation box according to the present utility model;
fig. 2 is a schematic side view connection diagram of a central tube of a pre-buried temporary water supply point operation box according to the present utility model;
FIG. 3 is an enlarged view of the structure at A in FIG. 1;
fig. 4 is a schematic top view connection diagram of a stabilizing plate in a pre-buried temporary water supply point operation box according to the present utility model.
In the figure: 1 box, 2 chamber door, 3 dead levers, 4 three-way pipe, 5 seal cover, 6 fixed orifices, 7 locating holes, 8 conical rod, 9 firm board, 10 screw thread section of thick bamboo, 11 threaded rod, 12 center tube, 13 drain pipe, 14 valve, 15 through-holes, 16 logical groove, 17 rotation hole, 18 dwang, 19 arc.
Description of the embodiments
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments.
Referring to fig. 1-4, a pre-buried temporary water supply point operation box comprises a box body 1, the right side rotation connection of box 1 is equipped with chamber door 2, the upper and lower both sides of box 1 all are equipped with fixed orifices 6, the left side fixed connection is equipped with dead lever 3 in the box 1, the right side fixed connection of dead lever 3 is equipped with three-way pipe 4, the upper and lower both sides of three-way pipe 4 all thread bush is equipped with seal cover 5, the right side fixed connection of three-way pipe 4 is equipped with center tube 12, the downside of center tube 12 evenly fixed connection is equipped with a plurality of drain pipes 13, be equipped with valve 14 in a plurality of drain pipes 13, the box 1 downside is equipped with a plurality of locating holes 7, a plurality of locating holes 7 internal thread bush is equipped with conical rod 8, conical rod 8 runs through locating holes 7 sets up, place about box 1 is equipped with two stabilizing plates 9, downside stabilizing plates 9 are located conical rod 8's upside and conical rod 8 contact connection setting, upside and upside stabilizing plates 9 and box 1 internal side contact connection setting, downside of connecting plate 9 is equipped with a plurality of screw thread cylinders 10, a plurality of thread cylinders 10 internal thread cylinders 10 are equipped with 11 and a plurality of thread cylinders 11 and two through-hole sets of 13, the corresponding through holes 15 are set up through hole 15, the setting up through hole 15 is set up relative to the corresponding through hole 15, the side 11, the setting up of the through hole 15 is realized, the through hole 15 is set up through hole 15, the corresponding through hole 15, the setting up of the through hole 15 is set up 15, and the corresponding through hole 15, and the setting up 15, and the 13 is set up through hole 15, and 15 is set up and 13, and set up and 15, the through groove 16 is arranged identically with the through hole 15 through the rotating hole 17, the rotating rod 18 is sleeved in the rotating hole 17 by the inner thread, the rotating rod 18 penetrates through the rotating hole 17, the rotating rod 18 and the arc plate 19 are connected in a rotating way, the movement control operation of the arc plate 19 is completed, and a rubber pad is fixedly connected on the inner side of the arc plate 19, so that the arc plate 19 and the water supply pipe are connected more tightly.
In the utility model, when the installation operation is required, the specific operation is as follows: the whole device is placed on a working position, a corresponding water supply pipe penetrates through the through hole 15 and the fixing hole 6, the corresponding sealing sleeve 5 is screwed off from the three-way pipe 4, the water inlet pipe and the three-way pipe 4 are connected together, the device is in the prior art, redundant description is not needed, the conical rod 8 is rotated, the conical rod 8 is inserted into the corresponding ground, the threaded cylinder 10 is rotated until the lower side fixing plate 9 and the conical rod 8 are tightly contacted and connected together, the upper side fixing plate 9 and the box body 1 are tightly contacted and connected together, the rotating rod 18 is rotated, the rotating rod 18 drives the arc plate 19 to move until the arc plate 19, the water supply pipe and the through hole 15 are tightly contacted and connected together, the whole assembly operation is completed, when the water discharge operation is needed, the box door 2 is opened, and the valve 14 is opened.
The foregoing is only a preferred embodiment of the present utility model, but the scope of the present utility model is not limited thereto, and any person skilled in the art, who is within the scope of the present utility model, should make equivalent substitutions or modifications according to the technical scheme of the present utility model and the inventive concept thereof, and should be covered by the scope of the present utility model.

Claims (5)

1. The utility model provides a temporary water supply point operation box of pre-buried formula, includes box (1), a serial communication port, the right side of box (1) rotates to be connected and is equipped with chamber door (2), the upper and lower both sides of box (1) all are equipped with fixed orifices (6), left side fixed connection is equipped with dead lever (3) in box (1), the right side fixed connection of dead lever (3) is equipped with three-way pipe (4), the equal thread bush in upper and lower both sides of three-way pipe (4) is equipped with seal cover (5), the right side fixed connection of three-way pipe (4) is equipped with center tube (12), the downside even fixed connection of center tube (12) is equipped with a plurality of drain pipes (13), a plurality of be equipped with valve (14) in drain pipe (13), the downside is equipped with a plurality of locating holes (7), a plurality of locating hole (7) internal thread bush is equipped with taper rod (8), taper rod (8) run through in locating hole (7) setting.
2. The temporary pre-buried water supply point operation box according to claim 1, wherein two stabilizing plates (9) are placed up and down in the box body (1), the downside the stabilizing plates (9) are located the upside of conical rod (8) and contact connection setting of conical rod (8), the upside the stabilizing plates (9) are connected with the upside in the box body (1) and are connected and set up, the downside the upside of stabilizing plates (9) is rotated and is connected and be equipped with a plurality of screw thread section of thick bamboo (10), a plurality of screw thread section of thick bamboo (10) internal thread cover is equipped with threaded rod (11), threaded rod (11) run through in screw thread section of thick bamboo (10) setting, threaded rod (11) and upside stabilizing plate (9) fixed connection setting.
3. The temporary pre-buried water supply point operation box according to claim 2, wherein through holes (15) are formed in the upper sides of the two stabilizing plates (9), the through holes (15) and the fixing holes (6) are oppositely arranged, arc-shaped plates (19) are arranged in the through holes (15) in a left-right sliding connection mode, and the arc-shaped plates (19) and the through holes (15) are oppositely arranged in a matching mode.
4. A temporary pre-buried water supply point operation box according to claim 3, characterized in that, two the lateral wall of stabilizing board (9) is equipped with logical groove (16), pass through the setting of penetrating around logical groove (16), it is the same through rotation hole (17) and through-hole (15) setting to pass through groove (16), rotation hole (17) internal thread cover is equipped with dwang (18), dwang (18) run through in rotation hole (17) setting, dwang (18) and arc (19) rotate the connection setting.
5. A temporary pre-buried water supply operating box according to claim 3, characterized in that a rubber pad is fixedly connected to the inner side of the arc-shaped plate (19).
CN202321203743.XU 2023-05-18 2023-05-18 Pre-buried temporary water supply point operation box Active CN219671510U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321203743.XU CN219671510U (en) 2023-05-18 2023-05-18 Pre-buried temporary water supply point operation box

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321203743.XU CN219671510U (en) 2023-05-18 2023-05-18 Pre-buried temporary water supply point operation box

Publications (1)

Publication Number Publication Date
CN219671510U true CN219671510U (en) 2023-09-12

Family

ID=87926280

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321203743.XU Active CN219671510U (en) 2023-05-18 2023-05-18 Pre-buried temporary water supply point operation box

Country Status (1)

Country Link
CN (1) CN219671510U (en)

Similar Documents

Publication Publication Date Title
CN219671510U (en) Pre-buried temporary water supply point operation box
CN207796179U (en) A kind of irrigation valve for general use and irrigation system
CN208675988U (en) A kind of agricultural water conservancy irrigation rig
CN210079936U (en) Dip-coating equipment for pre-impregnated coiled material platform base
CN210834584U (en) Automatic pressurization concrete impermeability instrument
CN208294486U (en) A kind of Multifunctional blowout preventer
CN210088050U (en) High pressure resistant oil is plug valve structure in pit
CN209585693U (en) A kind of Construction of Civil Engineering support device
CN102176397A (en) Counter weight for liquid level float switch
CN208996450U (en) A kind of civil construction reserving hole template
CN113756840A (en) Anti-blowout device for applying sleeve valve steel pipe in water-rich sand layer and construction method
CN203703310U (en) Remote control valve
CN211288917U (en) Groove type elastic seat sealing gate valve
CN205859308U (en) Spray irrigation system water tank water intake floating ball water stop valve
CN214838446U (en) Intelligent control's stop valve
CN201250634Y (en) Polish rod aligning and connecting device of an oil pumping unit
CN219033164U (en) Sealing door structure for construction of gravel pile
CN214838562U (en) Gate valve with anti-blocking structure
CN209146368U (en) A kind of piston-propelled water flow control valve
CN216768762U (en) Water conservancy embedded pipeline capable of effectively preventing sediment deposition
CN219210834U (en) Dust removal and maintenance device for greening plants
CN214696995U (en) Building water supply and drainage pipe embedded part
CN216382708U (en) Rubber flexible check valve
CN218991582U (en) Automatic slurry stopping connecting device for connecting grouting pipe and advance small guide pipe
CN221170821U (en) Adjustable water controller

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant