CN219607837U - Rubber ball cleaning system for steam turbine condenser - Google Patents

Rubber ball cleaning system for steam turbine condenser Download PDF

Info

Publication number
CN219607837U
CN219607837U CN202223092449.4U CN202223092449U CN219607837U CN 219607837 U CN219607837 U CN 219607837U CN 202223092449 U CN202223092449 U CN 202223092449U CN 219607837 U CN219607837 U CN 219607837U
Authority
CN
China
Prior art keywords
pipe
drain
condenser
ball
water inlet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223092449.4U
Other languages
Chinese (zh)
Inventor
白红涛
于红伟
王敏
丁小平
赵广川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Power Investment Group Jingmen Green Power Energy Co ltd
Original Assignee
State Power Investment Group Jingmen Green Power Energy Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Power Investment Group Jingmen Green Power Energy Co ltd filed Critical State Power Investment Group Jingmen Green Power Energy Co ltd
Priority to CN202223092449.4U priority Critical patent/CN219607837U/en
Application granted granted Critical
Publication of CN219607837U publication Critical patent/CN219607837U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Cleaning In General (AREA)
  • Cleaning By Liquid Or Steam (AREA)

Abstract

The utility model discloses a rubber ball cleaning system for a steam turbine condenser, which relates to the technical field of cleaning systems and comprises a condenser, wherein a first water inlet pipe and a second water inlet pipe are respectively arranged at the bottom ends of two sides of the condenser. According to the utility model, the rubber ball in the ball loading chamber is introduced into the first water inlet pipe and the second water inlet pipe through the third connecting pipe and the fourth connecting pipe by starting the rubber ball pump, then water is injected into the first water inlet pipe and the second water inlet pipe to bring the rubber ball into the condenser, the rubber ball is pushed to squeeze the pipeline in the condenser to clean impurities, then the cleaned water is discharged through the first water outlet pipe and the second water outlet pipe, the rubber ball flows into the first ball collecting net and the second ball collecting net, and the rubber ball in the first ball collecting net and the second ball collecting net is sucked into the ball loading chamber through the first connecting pipe, the second connecting pipe and the conveying pipe again by the rubber ball pump so as to be convenient for conveying the rubber ball to the first water outlet pipe and the second water outlet pipe again.

Description

Rubber ball cleaning system for steam turbine condenser
Technical Field
The utility model relates to the technical field of cleaning systems, in particular to a rubber ball cleaning system for a steam turbine condenser.
Background
The condenser is a heat exchanger for condensing steam discharged by a steam turbine into water, is also called a water re-heater, is mainly used in a power device of the steam turbine, is internally provided with a plurality of pipelines, and can generate impurities during operation, and when the pipelines are blocked by the impurities, the heat exchange effect of the condenser can be deteriorated, so that the vacuum degree of a unit is reduced, the power generation coal consumption is increased, and the problem is solved.
Disclosure of Invention
The utility model aims to overcome the defects of the prior art and provides a rubber ball cleaning system for a steam turbine condenser, which is designed aiming at the rubber ball cleaning system for the steam turbine condenser.
The aim of the utility model is realized by the following technical scheme:
a steam turbine condenser rubber ball cleaning system comprising:
the condenser is characterized in that a first water inlet pipe and a second water inlet pipe are respectively arranged at the bottom ends of two sides of the condenser, and a first water outlet pipe and a second water outlet pipe are respectively arranged at the top ends of two sides of the condenser;
one end of the first water outlet pipe and one end of the second water outlet pipe are respectively connected with a first ball collecting net and a second ball collecting net, the outer wall of the first ball collecting net is connected with a first connecting pipe, one end of the first connecting pipe is connected with a rubber ball pump, one end of the rubber ball pump is connected with a ball loading chamber through a conveying pipe, the outer wall of the second ball collecting net is connected with a second connecting pipe, and one end of the second connecting pipe is communicated with the first connecting pipe;
one end of the ball loading chamber is provided with a third connecting pipe and a second connecting pipe respectively, the third connecting pipe is connected with the first water inlet pipe, and the fourth connecting pipe is connected with the second water inlet pipe.
In the above summary, further, the first water inlet pipe and the second water inlet pipe are both provided with a first valve.
In the above summary of the utility model, further, the first water outlet pipe, the second water outlet pipe and the ball-loading chamber are provided with exhaust pipes.
In the above summary, further, the bottom end of the first ball collecting net is connected with a first drain pipe, the bottom end of the second ball collecting net is connected with a second drain pipe, and the first drain pipe and the second drain pipe are both provided with a second valve.
In the above summary, further, the first connection pipe and the second connection pipe are both provided with a third valve.
In the above summary, further, a drain pit is provided at one side of the second drain pipe, a drain pump is provided in the drain pit, and a drain pipe is provided outside the drain pit.
In the above summary, further, a first drain pipe and a second drain pipe are disposed at the bottom end of the condenser, the first drain pipe and the second drain pipe are symmetrically disposed at two sides of the bottom surface of the condenser, the first drain pipe is connected to the upper part of the condenser, the second drain pipe is connected to the bottom surface of the condenser, the first drain pipe and the second drain pipe are both provided with fourth valves, the bottom ends of the first drain pipe and the second drain pipe are both connected with a third drain pipe, and one end of the third drain pipe is connected with the drain pit.
In the above summary, further, a fourth drain pipe is disposed outside the first drain pipe, the first water inlet pipe, the second water inlet pipe, and the second drain pipe, and one end of the fourth drain pipe is connected to the drain pit.
In the above summary, further, a fifth drain pipe is connected to the outer wall of the ball loading chamber, and one end of the fifth drain pipe is connected to the drain pit.
The beneficial effects of the utility model are as follows:
according to the utility model, the rubber ball in the ball loading chamber is introduced into the first water inlet pipe and the second water inlet pipe through the third connecting pipe and the fourth connecting pipe by starting the rubber ball pump, then water is injected into the first water inlet pipe and the second water inlet pipe to bring the rubber ball into the condenser, the rubber ball is pushed to squeeze the pipeline in the condenser to clean impurities, then the cleaned water is discharged through the first water outlet pipe and the second water outlet pipe, the rubber ball flows into the first ball collecting net and the second ball collecting net, and the rubber ball in the first ball collecting net and the second ball collecting net is sucked into the ball loading chamber through the first connecting pipe, the second connecting pipe and the conveying pipe again by the rubber ball pump so as to be convenient for conveying the rubber ball to the first water outlet pipe and the second water outlet pipe again.
Drawings
Fig. 1 is a schematic diagram of the overall structure of the present utility model.
In the figure, the condenser 1, the first water outlet pipe 101, the exhaust pipe 102, the first ball collecting net 103, the first connecting pipe 104, the rubber ball pump 105, the ball loading chamber 106, the conveying pipe 107, the fifth sewage discharging pipe 108, the third connecting pipe 109, the fourth connecting pipe 110, the second water outlet pipe 111, the second ball collecting net 112, the second connecting pipe 113, the first sewage discharging pipe 114, the second sewage discharging pipe 115, the third sewage discharging pipe 116, the first water inlet pipe 2, the first water discharging pipe 3, the second water inlet pipe 4, the second water discharging pipe 5, the sewage discharging pit 6, the sewage discharging pump 601, the sewage discharging pipe 602 and the fourth sewage discharging pipe 603.
Detailed Description
Other advantages and effects of the present utility model will become apparent to those skilled in the art from the following disclosure, which describes the embodiments of the present utility model with reference to specific examples. The utility model may be practiced or carried out in other embodiments that depart from the specific details, and the details of the present description may be modified or varied from the spirit and scope of the present utility model. It should be noted that the following embodiments and features in the embodiments may be combined with each other without conflict.
Examples
Referring to fig. 1, a rubber ball cleaning system for a steam turbine condenser 1 includes a condenser 1, a water inlet pipe and a water outlet pipe;
the bottom ends of the two sides of the condenser 1 are respectively provided with a first water inlet pipe 2 and a second water inlet pipe 4, the top ends of the two sides of the condenser 1 are respectively provided with a first water outlet pipe 101 and a second water outlet pipe 111, one ends of the first water outlet pipe 101 and the second water outlet pipe 111 are respectively connected with a first ball collecting net 103 and a second ball collecting net 112, the outer wall of the first ball collecting net 103 is connected with a first connecting pipe 104, one end of the first connecting pipe 104 is connected with a rubber ball pump 105, one end of the rubber ball pump 105 is connected with a ball loading chamber 106 through a conveying pipe 107, the outer wall of the second ball collecting net 112 is connected with a second connecting pipe 113, one end of the second connecting pipe 113 is communicated with the first connecting pipe 104, one end of the ball loading chamber 106 is respectively provided with a third connecting pipe 109 and a fourth connecting pipe 110, the third connecting pipe 109 is connected with the first water inlet pipe 2, the fourth connecting pipe 110 is connected with the second water inlet pipe 4, the bottom end of the first ball collecting net 103 is connected with a first water outlet pipe 3, the bottom end of the second ball collecting net 112 is connected with a second water discharging pipe 5, the first water inlet pipe 2 and the second water inlet pipe 4 are respectively provided with a first valve, the first water outlet pipe 101, the second water outlet pipe 111 and the ball collecting chamber 106 are respectively provided with an exhaust pipe 102, the bottom end of the first ball collecting net 103 is connected with a first water discharging pipe 3, the bottom end of the second ball collecting net 112 is connected with a second water discharging pipe 5, the first water discharging pipe 3 and the second water discharging pipe 5 are respectively provided with a second valve, the first valve and the second valve are firstly opened to open the first water inlet pipe 2, the second water inlet pipe 4, the first water discharging pipe 3 and the second water discharging pipe 5, then water is injected into the first water inlet pipe 2 and the second water inlet pipe 4, water is allowed to enter the condenser 1 for heating, the heated water flows into the first ball collecting net 103 and the second ball collecting net 112 through the first water outlet pipe 101 and the second water outlet pipe 111, then the water is discharged through the first water discharging pipe 3 and the second water discharging pipe 5, then, the rubber ball pump 105 is started to feed the rubber ball in the ball loading chamber 106 into the first water inlet pipe 2 and the second water inlet pipe 4 through the third connecting pipe 109 and the fourth connecting pipe 110 respectively, so that the first water inlet pipe 2 and the second water inlet pipe 4 convey water into the pipeline of the condenser 1 while conveying the water into the condenser 1, the rubber ball is pushed to extrude the pipeline in the condenser 1 through the rubber ball to clean impurities, then the cleaned impurities are discharged through the first water outlet pipe 101 and the second water outlet pipe 111 together with the rubber ball, the rubber ball falls into the first ball collecting net 103 and the second ball collecting net 112, the cleaned water is discharged through the first water outlet pipe 3 and the second water outlet pipe 5, the cleaned rubber ball is sucked into the rubber ball pump 105 through the first connecting pipe 104 and the second connecting pipe 113, and the rubber ball is brought into the ball loading chamber 106 through the conveying pipe 107, and the rubber ball is convenient to enter the first water inlet pipe 2 and the second water inlet pipe 4 through the third connecting pipe 109 and the fourth connecting pipe 110 again for circulation cleaning.
The first water outlet pipe 101, the second water outlet pipe 111 and the ball loading chamber 106 are provided with an exhaust pipe 102, and hot air in the first water outlet pipe 101, the second water outlet pipe 111 and the ball loading chamber 106 is conveniently discharged through the exhaust pipe 102.
The first connecting pipe 104 and the second connecting pipe 113 are both provided with a third valve, one side of the second water draining pipe 5 is provided with a sewage pit 6, a sewage pump 601 is arranged in the sewage pit 6, a sewage pipe 602 is arranged outside the sewage pit 6, the bottom end of the condenser 1 is provided with a first sewage pipe 114 and a second sewage pipe 115, the first sewage pipe 114 and the second sewage pipe 115 are symmetrically arranged on two sides of the bottom surface of the condenser 1, the first sewage pipe 114 is connected to the upper part of the interior of the condenser 1, the second sewage pipe 115 is connected to the bottom surface of the condenser 1, the first sewage pipe 114 and the second sewage pipe 115 are both provided with a fourth valve, the bottom ends of the first sewage pipe 114 and the second sewage pipe 115 are both connected with a third sewage pipe 116, one end of the third sewage pipe 116 is connected with the sewage pit 6, after the condenser 1 is cleaned, the first valve, the second valve and the third valve are closed, and then the fourth valve are opened, so that waste water in the condenser 1 can flow into the third sewage pipe 116 through the first sewage pipe 114 and the second sewage pipe 115, the sewage pump is started, and the sewage pump is sucked into the sewage pit 6, and then, and the sewage is discharged into the sewage pit 6.
The first drain pipe 3, the first water inlet pipe 2, the second water inlet pipe 4 and the second drain pipe 5 are all provided with a fourth drain pipe 603, one end of the fourth drain pipe 603 is connected into the drain pit 6, and residual sewage in the first drain pipe 3, the first water inlet pipe 2, the second water inlet pipe 4 and the second drain pipe 5 is sucked into the drain pit 6 by starting the drain pump 601 and then is discharged through the sewage pipe 602.
A fifth drain pipe 108 is connected to the outer wall of the ball loading chamber 106, one end of the fifth drain pipe 108 is connected to the drain pit 6, and a drain pump 601 is started to suck the wastewater in the ball loading chamber 106 into the drain pit 6 through the fifth drain pipe 108 and then discharge the wastewater through a sewage pipe 602.
The working principle is as follows; the device firstly opens a first valve, a second valve and a third valve to open a first water inlet pipe 2, a second water inlet pipe 4, a first water outlet pipe 3 and a second water outlet pipe 5, then closes a fourth valve to seal a first water outlet pipe 114 and a second water outlet pipe 115, then injects water into the first water inlet pipe 2 and the second water inlet pipe 4 to enable the water to enter the condenser 1 for heating, the heated water flows into a first ball collecting net 103 and a second ball collecting net 112 through a first water outlet pipe 101 and a second water outlet pipe 111, then discharges the water through the first water outlet pipe 3 and the second water outlet pipe 5, then starts a rubber ball pump 105 to respectively send rubber balls in a ball loading chamber 106 into the first water inlet pipe 2 and the second water inlet pipe 4 through a third connecting pipe 109 and a fourth connecting pipe 110, enables the rubber balls to be brought into pipes of the condenser 1 while conveying water into the condenser 1, and the rubber balls are pushed through the pipes of the condenser 1 for cleaning impurities, then the cleaned impurities are discharged along with the rubber balls through the first water outlet pipe 101 and the second water outlet pipe 111, the rubber balls fall into the first ball collecting net 103 and the second ball collecting net 112, the cleaned water is discharged through the first water outlet pipe 3 and the second water outlet pipe 5, the cleaned rubber balls are sucked into the rubber ball pump 105 through the first connecting pipe 104 and the second connecting pipe 113, the rubber balls are brought into the ball loading chamber 106 through the conveying pipe 107 by the rubber ball pump 105, the rubber balls are conveniently and circularly cleaned in the first water inlet pipe 2 and the second water inlet pipe 4 through the third connecting pipe 109 and the fourth connecting pipe 110 again, then hot air in the first water outlet pipe 101, the second water outlet pipe 111 and the ball loading chamber 106 is conveniently discharged through the exhaust pipe 102, and then the first valve is closed after the condenser 1 is cleaned, the second valve and the third valve are opened, then the fourth valve is opened, so that the waste water in the condenser 1 flows into the third drain pipe 116 through the first drain pipe 114 and the second drain pipe 115, then the drain pump 601 is started to suck the waste water in the third drain pipe 116 into the drain pit 6, then the waste water is discharged through the drain pipe 602, then the residual waste water in the first drain pipe 3, the first water inlet pipe 2, the second water inlet pipe 4 and the second drain pipe 5 is sucked into the drain pit 6 through the drain pump 601, then the waste water is discharged through the drain pipe 602, and finally the waste water in the ball loading chamber 106 is sucked into the drain pit 6 through the fifth drain pipe 108 by the drain pump 601, and then the waste water is discharged through the drain pipe 602.
In the description of the present utility model, it should be understood that the directions or positional relationships indicated by the terms "upper", "lower", "left", "right", etc. are based on the directions or positional relationships shown in the drawings, are merely for convenience of describing the present utility model and simplifying the description, and do not indicate or imply that the apparatus or element in question must be provided with a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as limiting the present utility model.
The foregoing examples merely illustrate specific embodiments of the utility model, which are described in greater detail and are not to be construed as limiting the scope of the utility model. It should be noted that it will be apparent to those skilled in the art that several variations and modifications can be made without departing from the spirit of the utility model, which are all within the scope of the utility model.

Claims (9)

1. A steam turbine condenser rubber ball cleaning system, comprising:
the condenser is characterized in that a first water inlet pipe and a second water inlet pipe are respectively arranged at the bottom ends of two sides of the condenser, and a first water outlet pipe and a second water outlet pipe are respectively arranged at the top ends of two sides of the condenser;
one end of the first water outlet pipe and one end of the second water outlet pipe are respectively connected with a first ball collecting net and a second ball collecting net, the outer wall of the first ball collecting net is connected with a first connecting pipe, one end of the first connecting pipe is connected with a rubber ball pump, one end of the rubber ball pump is connected with a ball loading chamber through a conveying pipe, the outer wall of the second ball collecting net is connected with a second connecting pipe, and one end of the second connecting pipe is communicated with the first connecting pipe;
one end of the ball loading chamber is provided with a third connecting pipe and a fourth connecting pipe respectively, the third connecting pipe is connected with the first water inlet pipe, and the fourth connecting pipe is connected with the second water inlet pipe.
2. The steam turbine condenser rubber ball cleaning system of claim 1, wherein,
the first water inlet pipe and the second water inlet pipe are respectively provided with a first valve.
3. The steam turbine condenser rubber ball cleaning system of claim 1, wherein,
the first water outlet pipe, the second water outlet pipe and the ball loading chamber are all provided with exhaust pipes.
4. The steam turbine condenser rubber ball cleaning system of claim 1, wherein,
the bottom of first net is connected with first drain pipe, the bottom of second net is connected with the second drain pipe, and this first drain pipe and second drain pipe all are equipped with the second valve.
5. The steam turbine condenser rubber ball cleaning system of claim 1, wherein,
the first connecting pipe and the second connecting pipe are both provided with a third valve.
6. The steam turbine condenser rubber ball cleaning system of claim 4, wherein,
a drain pit is arranged on one side of the second drain pipe, a drain pump is arranged in the drain pit, and a sewage pipe is arranged outside the drain pit.
7. The steam turbine condenser rubber ball cleaning system of claim 1, wherein,
the bottom of condenser is equipped with first blow off pipe and second blow off pipe, first blow off pipe and second blow off pipe are in the bottom surface bilateral symmetry of condenser sets up, and this first blow off pipe is connected to the inside top of condenser, and this second blow off pipe is connected to the inside bottom surface of condenser, first blow off pipe and second blow off pipe all are equipped with the fourth valve, the bottom of first blow off pipe and second blow off pipe all is connected with the third blow off pipe, the one end and the blow off pit internal connection of third blow off pipe.
8. The steam turbine condenser rubber ball cleaning system of claim 4, wherein,
the first drain pipe, the first water inlet pipe, the second water inlet pipe and the second drain pipe are all provided with fourth drain pipes, and one ends of the fourth drain pipes are all connected into the drain pits.
9. The steam turbine condenser rubber ball cleaning system of claim 1, wherein,
the outer wall of the ball loading chamber is connected with a fifth blow-down pipe, and one end of the fifth blow-down pipe is connected with the blow-down pit.
CN202223092449.4U 2022-11-17 2022-11-17 Rubber ball cleaning system for steam turbine condenser Active CN219607837U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223092449.4U CN219607837U (en) 2022-11-17 2022-11-17 Rubber ball cleaning system for steam turbine condenser

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223092449.4U CN219607837U (en) 2022-11-17 2022-11-17 Rubber ball cleaning system for steam turbine condenser

Publications (1)

Publication Number Publication Date
CN219607837U true CN219607837U (en) 2023-08-29

Family

ID=87743380

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223092449.4U Active CN219607837U (en) 2022-11-17 2022-11-17 Rubber ball cleaning system for steam turbine condenser

Country Status (1)

Country Link
CN (1) CN219607837U (en)

Similar Documents

Publication Publication Date Title
CN102183007A (en) Waste heat recovering system of boiler
CN206803549U (en) A kind of integrated form waste heat recovery sewage source heat pump unit
CN106761921A (en) A kind of equipment system based on efficient weary wind source heat pump
CN103322728B (en) Energy improvement system of blockage-preventing descaling crude sewage heat pump
CN202012904U (en) Boiler waste heat recovery system
CN108286913B (en) Rubber ball cleaning multipoint ball system with high-pressure condenser and low-pressure condenser
CN219607837U (en) Rubber ball cleaning system for steam turbine condenser
CN110285440A (en) A kind of recycle device of coal fired boiler of power plant smoke discharging residual heat
CN2127480Y (en) Air heater of drying tower
CN202030983U (en) Steam corrugated paper production line
CN204227989U (en) On-line cleaner of heat exchanger
CN204420978U (en) A kind of energy saving drainage system of boiler hydrophobic development unit
CN102374516B (en) High-temperature tail-gas heat-recovering energy-saving device
CN106186128B (en) Waste water treatment device
CN2302495Y (en) Automatic cleaning device for heat exchanger
CN207214898U (en) A kind of high-pressure heater electromagnetic pulse chemical cleaning system
CN214406487U (en) Biomass double-layer hot water boiler
CN211120215U (en) Energy-saving improved circulating water cooling system of power generation unit
CN216011811U (en) Exhaust steam recovery and heat energy conversion device of rubber production vulcanizing machine
CN213873155U (en) Combined automatic recycling device for air conditioner condensate water
CN216953609U (en) Heat pump set for waste water waste heat recovery
CN215305652U (en) Dish washer with pipeline heat exchanger and water tank
CN212252574U (en) Heat power type energy-saving drainage flash tank
CN204006766U (en) A kind of refrigeration system
CN108825467A (en) A kind of residual heat recycling system of air compressor

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant