CN219569480U - Leveling and plastering device for heat-insulating wall construction - Google Patents

Leveling and plastering device for heat-insulating wall construction Download PDF

Info

Publication number
CN219569480U
CN219569480U CN202320645215.3U CN202320645215U CN219569480U CN 219569480 U CN219569480 U CN 219569480U CN 202320645215 U CN202320645215 U CN 202320645215U CN 219569480 U CN219569480 U CN 219569480U
Authority
CN
China
Prior art keywords
fixed
glue
box
leveling
heat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320645215.3U
Other languages
Chinese (zh)
Inventor
许翼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Jinchuan Water Proofing Anticorrosion Decoration Engineering Co ltd
Original Assignee
Shenzhen Jinchuan Water Proofing Anticorrosion Decoration Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Jinchuan Water Proofing Anticorrosion Decoration Engineering Co ltd filed Critical Shenzhen Jinchuan Water Proofing Anticorrosion Decoration Engineering Co ltd
Priority to CN202320645215.3U priority Critical patent/CN219569480U/en
Application granted granted Critical
Publication of CN219569480U publication Critical patent/CN219569480U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P70/00Climate change mitigation technologies in the production process for final industrial or consumer products
    • Y02P70/10Greenhouse gas [GHG] capture, material saving, heat recovery or other energy efficient measures, e.g. motor control, characterised by manufacturing processes, e.g. for rolling metal or metal working

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The utility model relates to the technical field of wall construction and discloses a leveling and plastering device for heat-insulating wall construction, which comprises a transport vehicle and a placement box, wherein a lifting frame is fixed at the top of the transport vehicle, a lifting structure is fixed between the placement box and the lifting frame, connecting rods are fixed on two sides of the front surface of the placement box, and a cavity plate is fixed on the front surface of the connecting rods; according to the utility model, the cavity plate is matched with the glue spray head, so that glue can be uniformly smeared on a wall, the glue brushing roller can realize uniform glue smearing, the scraping plate can scrape residual glue on the surface of the glue brushing roller in the glue smearing process, the smoothness of the glue brushing roller can be ensured, the scraped glue can be conveniently collected and treated by the treatment box in the collection box, and the problems that the residual glue is on the glue brushing roller, uneven situation can occur when the heat-insulating wall is stuck, and the residual glue is very troublesome to manually clean by workers are solved by the aid of the treatment box in the collection box.

Description

Leveling and plastering device for heat-insulating wall construction
Technical Field
The utility model relates to the technical field of wall construction, in particular to a leveling and plastering device for heat-insulating wall construction.
Background
The heat-insulating wall is formed by compounding polymer mortar, glass fiber mesh cloth, flame-retardant molded polystyrene foam board or extruded sheet and other materials, and is subjected to on-site bonding construction. With the development of constructional engineering, more and more heat-insulating building walls are in life of people. When the heat-insulating wall is constructed, a layer of glue is coated on the wall surface, then the heat-insulating plate or the heat-insulating material is bonded and connected with the wall body, and finally the heat-insulating plate or the heat-insulating material is fixed through bolts.
Through the search, for example, chinese patent literature discloses a thermal insulation wall construction device [ application number: CN201921910598.2; publication No.: CN211286125U ]. This kind of heat preservation wall body construction equipment, including construction frame, base and construction box, the construction box is located the base top, the construction frame is located base one side, construction frame outer wall one side has the hourglass groove through hinged joint, the removal lead screw is installed to the construction frame inboard, remove the lead screw top and install first motor, and first motor is located construction frame inner wall top, remove lead screw outer wall threaded connection and have the removal seat, remove seat outside fixedly connected with movable support.
The heat preservation wall construction device disclosed in the patent can not be completely coated on a heat preservation wall in the actual use process, and residual glue is always on a glue brushing roller, and if the heat preservation wall is not cleaned, uneven conditions can appear when the heat preservation wall is pasted, the next glue smearing work is affected, if the manual cleaning of workers is very troublesome after the glue smearing is completed, the glue can be solidified, and the cleaning difficulty is increased.
Disclosure of Invention
The utility model aims to provide a leveling and plastering device for heat-insulating wall construction, which not only can realize uniform plastering, but also can scrape and collect residual glue on the surface of a rubber-covered roller in the plastering process, and can ensure the leveling of the rubber-covered roller.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides a heat preservation wall construction is with leveling device of gluing, includes the transport vechicle and places the case, the top of transport vechicle is fixed with lifting frame, be fixed with elevation structure between placing case and the lifting frame, place positive both sides of case and all be fixed with the connecting rod, the front of connecting rod is fixed with the cavity board, the front intercommunication of cavity board has a plurality of glue shower nozzles, the inside of placing the case is fixed with the storage tank, the front intercommunication of storage tank has the take out the gum pump, the intercommunication has the connecting pipe between take out the gum pump and the storage tank, place positive both sides of case all and be fixed with the telescopic link, the front of telescopic link is fixed with the fixed plate, rotate between the fixed plate and be connected with the brush rubber roll, the surface cover of telescopic link is equipped with the spring, be fixed with the scraper blade between the fixed plate, the bottom of fixed plate is fixed with the collecting box, the inside sliding connection of collecting box has the processing box, be fixed with limit structure between processing box and the collecting box.
Preferably, the lifting structure comprises a motor, the motor is fixed at the top of the lifting frame, an output shaft of the motor penetrates through the lifting frame and is fixedly provided with a threaded column, the surface of the threaded column is connected with a connecting block in a threaded manner, and the placing box is fixed at the front face of the connecting block.
Preferably, guide posts are fixed on two sides of the inner wall of the lifting frame, guide blocks are fixed on two sides of the back of the placement box, and the guide blocks are in sliding connection with the guide posts.
Preferably, the limit structure comprises a fixed block and a mounting block, wherein the fixed block is fixed on the front surface of the collecting box, the mounting block is fixed on the front surface of the processing box, and a fixing pin is connected between the fixed block and the mounting block in a threaded manner.
Preferably, a tightening block is fixed at the top of the fixing pin, and the tightening block is made of rubber materials.
Preferably, a storage box is fixed at the top of the transport vehicle, and the width of the storage box is the same as that of the transport vehicle.
Compared with the prior art, the utility model has the following beneficial effects:
according to the utility model, the cavity plate is matched with the glue spray head, so that glue can be uniformly smeared on a wall, the glue brushing roller can realize uniform glue smearing, the scraping plate can scrape residual glue on the surface of the glue brushing roller in the glue smearing process, the smoothness of the glue brushing roller can be ensured, the scraped glue can be conveniently collected and treated by the treatment box in the collection box, and the problems that the residual glue is on the glue brushing roller, uneven situation can occur when the heat-insulating wall is stuck, and the residual glue is very troublesome to manually clean by workers are solved by the aid of the treatment box in the collection box.
Drawings
FIG. 1 is a schematic perspective view of the present utility model;
FIG. 2 is a schematic view of a partial perspective structure of the present utility model;
FIG. 3 is a schematic view of a partial perspective structure of the present utility model;
fig. 4 is an enlarged view of a portion of fig. 2 a in accordance with the present utility model.
In the figure: 1. a transport vehicle; 2. placing a box; 3. a lifting frame; 4. a lifting structure; 41. a motor; 42. a threaded column; 43. a connecting block; 5. a connecting rod; 6. a cavity plate; 7. a glue spray head; 8. a glue storage tank; 9. a glue pump; 10. a connecting pipe; 11. a telescopic rod; 12. a fixing plate; 13. brushing a rubber roller; 14. a spring; 15. a scraper; 16. a collection box; 17. a treatment box; 18. a limit structure; 181. a fixed block; 182. a mounting block; 183. a fixing pin; 19. a guide post; 20. a guide block; 21. tightening the block; 22. a storage box.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1-4, a leveling and plastering device for construction of a thermal insulation wall body comprises a transport vehicle 1 and a placement box 2, wherein a lifting frame 3 is fixed at the top of the transport vehicle 1, a lifting structure 4 is fixed between the placement box 2 and the lifting frame 3, connecting rods 5 are fixed at two sides of the front surface of the placement box 2, a cavity plate 6 is fixed at the front surface of the connecting rods 5, a plurality of glue spray heads 7 are communicated with the front surface of the cavity plate 6, a glue storage tank 8 is fixed inside the placement box 2, a glue suction pump 9 is communicated with the front surface of the glue storage tank 8, a connecting pipe 10 is communicated between the glue suction pump 9 and the glue storage tank 8, telescopic rods 11 are fixed at two sides of the front surface of the placement box 2, a fixed plate 12 is rotatably connected with glue brushing rollers 13, springs 14 are sleeved on the surfaces of the telescopic rods 11, scraping plates 15 are fixed between the fixed at the bottom of the fixed plates 12, a collecting box 16 is slidably connected inside the collecting box 16, a processing box 17 is slidably connected with the collecting box 16, and a limiting structure 18 is fixed between the processing box 17 and the collecting box 16; this level and smooth device of plastering can evenly smear glue on the wall through cavity board 6 cooperation glue shower nozzle 7, brush rubber roll 13 can realize even plastering, scraper blade 15 can scrape down brush rubber roll 13 surface remaining glue at the in-process of plastering, can guarantee brush rubber roll 13's level and smooth, and the processing box 17 in the collection box 16 conveniently collect and handle the glue of scraping, the current insulation wall construction device of having solved can remain glue on brush rubber roll 13, the insulation wall will appear the uneven condition when pasting, the manual very troublesome problem of clearance of workman of residual glue adoption.
The lifting structure 4 comprises a motor 41, the motor 41 is fixed at the top of the lifting frame 3, an output shaft of the motor 41 penetrates through the lifting frame 3 and is fixedly provided with a threaded column 42, a connecting block 43 is connected to the surface of the threaded column 42 in a threaded manner, the placing box 2 is fixed on the front face of the connecting block 43, the motor 41 can drive the rubber brushing roller 13 to automatically lift, labor can be saved, the wall plastering efficiency is increased, guide posts 19 are fixed on two sides of the inner wall of the lifting frame 3, guide blocks 20 are fixed on two sides of the back face of the placing box 2, the guide blocks 20 are in sliding connection with the guide posts 19, and the guide posts 19 can guide the placing box 2 to improve the lifting stability of the placing box 2.
Limit structure 18 includes fixed block 181 and installation piece 182, and fixed block 181 is fixed in the front of collecting box 16, and installation piece 182 is fixed in the front of handling case 17, and threaded connection has fixed pin 183 between fixed block 181 and the installation piece 182, and fixed block 181 and installation piece 182 can be connected to fixed pin 183, fixes handling case 17, and the top of fixed pin 183 is fixed with and screws up the piece 21, screws up the piece 21 and adopts rubber material to make, screws up the piece 21 and can laminate the finger, improves rotatory speed, and rubber material has increased the frictional force of screwing up.
The top of transport vechicle 1 is fixed with bin 22, and bin 22's width is the same with transport vechicle 1, and the tool that the plastering needs can be stored to bin 22, has improved the convenience of plastering.
Working principle: when the glue smearing operation is carried out, a worker starts the motor 41 and the glue sucking pump 9 firstly, the motor 41 can drive the threaded column 42 to rotate, the threaded column 42 can drive the connecting block 43 and the placing box 2 to move up and down, the placing box 2 can drive the glue brushing roller 13 and the cavity plate 6 to move upwards, at the moment, the glue sucking pump 9 can suck glue out of the glue storage tank 8, the glue enters the cavity plate 6 through the connecting pipe 10 and finally coats the heat-insulating wall surface through the glue spray head 7, the glue brushing roller 13 can uniformly coat the glue in the upward moving process, the scraping plate 15 can scrape the glue on the surface of the glue brushing roller 13 when the glue brushing roller 13 rotates, the scraped glue can flow into the treatment box 17, and when the residual glue needs to be treated, the worker only needs to suck the fixing pin 183 to pull the treatment box 17 out of the inside of the collection box 16.
It is noted that relational terms such as first and second, and the like are used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Moreover, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising one … …" does not exclude the presence of other like elements in a process, method, article, or apparatus that comprises the element.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a heat preservation wall body construction is with leveling device of gluing, includes transport vechicle (1) and places case (2), its characterized in that: the utility model discloses a collection box, including collection box (16), collection box (16) and collection box (16), collection box (16) are fixed with the top of transport vechicle (1), be fixed with lifting frame (3) at the top of transport vechicle (1), place and be fixed with elevation structure (4) between case (2) and lifting frame (3), place positive both sides of case (2) and all be fixed with connecting rod (5), the front of connecting rod (5) is fixed with cavity board (6), the front intercommunication of cavity board (6) has a plurality of glue shower nozzles (7), place the inside of case (2) and be fixed with glue storage tank (8), the front intercommunication of glue storage tank (8) has take out glue pump (9), the intercommunication has connecting pipe (10) between glue pump (9) and glue storage tank (8), place positive both sides of case (2) all be fixed with telescopic link (11), the front of telescopic link (11) is fixed with fixed plate (12), rotate between fixed plate (12) and be connected with brush rubber roller (13), the surface cover of telescopic link (11) is equipped with spring (14), be fixed with scraper blade (15) between fixed plate (12), bottom fixed plate (12) and collection box (16) have collection box (16) to handle between collection box (16).
2. The leveling and plastering device for heat-insulating wall construction according to claim 1, wherein: the lifting structure (4) comprises a motor (41), the motor (41) is fixed at the top of the lifting frame (3), an output shaft of the motor (41) penetrates through the lifting frame (3) and is fixedly provided with a threaded column (42), the surface of the threaded column (42) is connected with a connecting block (43) in a threaded manner, and the placing box (2) is fixed on the front face of the connecting block (43).
3. The leveling and plastering device for heat-insulating wall construction according to claim 2, wherein: guide posts (19) are fixed on two sides of the inner wall of the lifting frame (3), guide blocks (20) are fixed on two sides of the back of the placement box (2), and the guide blocks (20) are in sliding connection with the guide posts (19).
4. The leveling and plastering device for heat-insulating wall construction according to claim 1, wherein: the limiting structure (18) comprises a fixed block (181) and a mounting block (182), wherein the fixed block (181) is fixed on the front surface of the collecting box (16), the mounting block (182) is fixed on the front surface of the processing box (17), and a fixing pin (183) is connected between the fixed block (181) and the mounting block (182) in a threaded manner.
5. The leveling and plastering device for heat preservation wall construction according to claim 4, wherein: the top of fixed pin (183) is fixed with and screws up piece (21), screw up piece (21) and adopt rubber material to make.
6. The leveling and plastering device for heat-insulating wall construction according to claim 1, wherein: the top of transport vechicle (1) is fixed with bin (22), the width of bin (22) is the same with transport vechicle (1).
CN202320645215.3U 2023-03-29 2023-03-29 Leveling and plastering device for heat-insulating wall construction Active CN219569480U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320645215.3U CN219569480U (en) 2023-03-29 2023-03-29 Leveling and plastering device for heat-insulating wall construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320645215.3U CN219569480U (en) 2023-03-29 2023-03-29 Leveling and plastering device for heat-insulating wall construction

Publications (1)

Publication Number Publication Date
CN219569480U true CN219569480U (en) 2023-08-22

Family

ID=87672609

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320645215.3U Active CN219569480U (en) 2023-03-29 2023-03-29 Leveling and plastering device for heat-insulating wall construction

Country Status (1)

Country Link
CN (1) CN219569480U (en)

Similar Documents

Publication Publication Date Title
CN113492350A (en) Steel construction is rust cleaning device for routine maintenance
CN219569480U (en) Leveling and plastering device for heat-insulating wall construction
CN210935578U (en) Real stone bionic composite thermal insulation material production equipment
CN219442595U (en) End face cleaning device for stacking squeeze plates
CN213391044U (en) Tile gum brushing device
CN213671944U (en) Punching device for stainless steel pipe
CN213670157U (en) Continuous compounding machine for sandwich boards
CN210508285U (en) Ceramic tile pointing device for building device
CN211974210U (en) Cement smearing device capable of preventing cement from dripping for building construction
CN217476167U (en) Cladding machine is used in wood moulding production
CN216276739U (en) Putty device is scraped with wall body to construction
CN219255930U (en) Prefabricated plate mould convenient to clearance
CN214726318U (en) Film coating machine for filling flame-retardant colloid of plastic flooring
CN213143773U (en) A outer wall whitewashes auxiliary device for construction
CN217018817U (en) Nonrust steel pipe cutting machine is with clearance drying device
CN220331984U (en) Film pressing machine
CN215354875U (en) Asphalt recycling device for waterproof coiled material
CN211286125U (en) Heat preservation wall body construction equipment
CN217664169U (en) Glue spreader capable of being automatically cleaned
CN216323498U (en) Novel template for building materials washs device
CN213886926U (en) Gluing mechanism for producing anti-theft wooden door
CN218567872U (en) Building engineering environment monitoring device
CN220631383U (en) Scraper blade convenient to clean
CN216756922U (en) Spreading machine capable of being cleaned quickly
CN218410615U (en) Drying device convenient to take and place

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant