CN219541251U - Building site pipeline pull throughs - Google Patents
Building site pipeline pull throughs Download PDFInfo
- Publication number
- CN219541251U CN219541251U CN202320214820.5U CN202320214820U CN219541251U CN 219541251 U CN219541251 U CN 219541251U CN 202320214820 U CN202320214820 U CN 202320214820U CN 219541251 U CN219541251 U CN 219541251U
- Authority
- CN
- China
- Prior art keywords
- main part
- pull throughs
- fixedly connected
- pipeline
- servo motor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Earth Drilling (AREA)
Abstract
The utility model provides a building site pipeline dredging device, which belongs to the technical field of buildings and comprises a dredging main body and a zigzag hose, wherein the top of the dredging main body is fixedly connected with a fixed ring, the inner wall of the fixed ring is fixedly provided with a servo motor, the output end of the servo motor is fixedly connected with a driving wheel, the outer surface of the driving wheel is in transmission connection with a belt, the inside of the dredging main body is movably connected with a rotating shaft, and a hexagonal groove is formed in the rotating shaft. This building site pipeline pull throughs, in the use, when starting servo motor, can rotate the action wheel to drive belt drive, can make the pivot rotate, the rethread hexagonal groove can rotate the tortuous hose, makes the drill bit can stretch the pipeline, can clear up the pipeline inner wall when the drill bit starts, through the setting of light, makes this pull throughs be convenient for observe when the clearance, raises the efficiency.
Description
Technical Field
The utility model belongs to the technical field of buildings, and particularly relates to a building site pipeline dredging device.
Background
The pipeline is widely used as an effective material conveying means, effective dredging maintenance is required to be carried out on the pipeline in order to prolong the service life of the pipeline and prevent accidents such as leakage, and the pipeline dredging device is used as effective pipeline dredging equipment under the condition that a plurality of defects exist in a manual dredging mode, so that more and more applications are obtained.
However, in the existing life, more mud and household garbage are often accumulated at the bottom of a large-sized pipeline, and the conventional solution is to manually clean the bottom of the pipeline or clean the bottom of the pipeline by using a high-pressure water gun, so that the time and labor are wasted, the efficiency is low, the pipeline cannot be bent generally, dead corners which cannot be cleaned are formed, the operation is inconvenient, the hand feeling is poor, and the design of the pipeline dredging device for the building site is very necessary.
Accordingly, the present utility model provides a construction site pipeline dredging apparatus
Disclosure of Invention
The utility model aims to provide a building site pipeline dredging device, and aims to solve the problems that in the prior art, time and labor are wasted, the efficiency is low, a pipeline cannot be bent generally, dead angles cannot be cleaned, the operation is inconvenient, the hand feeling is poor, and the like.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides a building site pipeline pull throughs, includes mediation main part and tortuous hose, the top fixedly connected with solid fixed ring of mediation main part, gu fixed ring's inner wall fixed mounting has servo motor, servo motor's output fixedly connected with action wheel, the surface transmission of action wheel is connected with the belt, the inside swing joint of mediation main part has the pivot, hexagonal groove has been seted up to the inside of pivot, the bottom fixed mounting of mediation main part has the light.
Preferably, a drill bit is fixedly arranged at one end of the zigzag hose, and the drill bit is made of diamond.
Preferably, a connecting handle is fixedly arranged at the other end of the zigzag hose, and a hexagonal prism is arranged on the outer side of the connecting handle.
Preferably, a grip rod is in threaded connection with one side of the dredging main body, and a rubber sleeve is arranged on the outer surface of the grip rod ().
Preferably, the bottom side of the dredging main body is fixedly connected with a handle, and the outer surface of the handle is provided with anti-skid patterns.
Preferably, an operation hand button is arranged on one side of the grip.
Preferably, one side of mediation main part top fixedly connected with metal sheet, the top of metal sheet is through bearing fixedly connected with servo motor.
Preferably, the belt penetrates through the interior of the dredging main body.
Compared with the prior art, the utility model has the beneficial effects that:
1. this building site pipeline pull throughs, in the use, when starting servo motor, can rotate the action wheel to drive belt drive, can make the pivot rotate, the rethread hexagonal groove can rotate the tortuous hose, makes the drill bit can stretch the pipeline, can clear up the pipeline inner wall when the drill bit starts, through the setting of light, makes this pull throughs be convenient for observe when the clearance, raises the efficiency.
2. This building site pipeline pull throughs for the connecting handle can be connected with the pivot, and the tortuous hose of being convenient for rotates, thereby makes this building site pipeline pull throughs play the effect of being convenient for dismantle, makes grip stick convenient to detach, and convenient to use person operates, and the rubber sleeve can increase user's comfort, through the setting of operation hand knot, through the rotation that the servo motor can be controlled to the knot of knot operation hand, the operation is more convenient.
Drawings
The accompanying drawings are included to provide a further understanding of the utility model and are incorporated in and constitute a part of this specification, illustrate the utility model and together with the embodiments of the utility model, serve to explain the utility model. In the drawings:
FIG. 1 is a schematic perspective view of the present utility model;
FIG. 2 is a second perspective view of the present utility model;
FIG. 3 is a third perspective view of the present utility model;
FIG. 4 is a schematic elevational view of the present utility model;
fig. 5 is an enlarged schematic view of the structure of fig. 2 a according to the present utility model.
In the figure: 1. dredging the main body; 2. a fixing ring; 3. a servo motor; 4. a driving wheel; 5. a belt; 6. a rotating shaft; 7. a hexagonal groove; 8. a lighting lamp; 9. a tortuous hose; 10. a drill bit; 11. a connecting handle; 12. a grip bar; 13. a grip; 14. operating a hand button; 15. a metal plate.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Examples
Referring to fig. 1-5, the present utility model provides the following technical solutions: the utility model provides a building site pipeline pull throughs, includes pull throughs main part 1 and tortuous hose 9, pull throughs main part 1's top fixedly connected with solid fixed ring 2, gu fixed ring 2's inner wall fixed mounting has servo motor 3, servo motor 3's output fixedly connected with action wheel 4, action wheel 4's surface transmission is connected with belt 5, pull throughs main part 1's inside swing joint has pivot 6, hexagonal groove 7 has been seted up to pivot 6's inside, pull throughs main part 1's bottom fixed mounting has light 8.
In the specific embodiment of the utility model, in the use process, when the servo motor 3 is started, the driving wheel 4 can be rotated, the belt 5 is driven to drive, the rotating shaft 6 can be rotated, the zigzag hose 9 can be rotated through the hexagonal groove 7, the drill bit 10 can extend to a pipeline, when the drill bit 10 is started, the inner wall of the pipeline can be cleaned, and the dredging device is convenient to observe during cleaning and improves the efficiency through the arrangement of the illuminating lamp 8.
Specifically, a drill bit 10 is fixedly installed at one end of the tortuous hose 9, and the drill bit 10 is made of diamond.
In this embodiment: in use, the drill bit 10 is arranged so that the drill bit 10 can extend into a pipeline, and the pipeline can be cleaned when the drill bit 10 is started.
Specifically, the other end of the zigzag hose 9 is fixedly provided with a connecting handle 11, and the outer side of the connecting handle 11 is provided with a hexagonal prism.
In this embodiment: in the use process, the connecting handle 11 can be connected with the rotating shaft 6, so that the bending hose 9 can be conveniently rotated.
Specifically, one side of the dredging main body 1 is connected with a grip rod 12 in a threaded manner, and a rubber sleeve is arranged on the outer surface of the grip rod 12.
In this embodiment: in the use process, the grip rod 12 can be convenient to detach, the operation of a user is convenient, and the comfort of the user can be improved through the rubber sleeve.
Specifically, the bottom side of the dredging main body 1 is fixedly connected with a grip 13, and the outer surface of the grip 13 is provided with anti-skid patterns.
In this embodiment: during use, a user holds the grip 13 for convenient operation, and comfort of the user can be enhanced through the anti-skid patterns.
Specifically, an operation handle 14 is provided on one side of the grip 13.
In this embodiment: in the use process, through the arrangement of the operation hand button 14, the rotation of the servo motor 3 can be controlled through the button operation hand button 14.
Specifically, one side of mediation main part 1 top fixedly connected with metal sheet 15, the top of metal sheet 15 is through bearing fixedly connected with servo motor 3.
In this embodiment: during use, the metal plate 15 can fix the limit of the servomotor 3.
Specifically, the belt 5 penetrates the inside of the dredging main body 1.
In this embodiment: during use, the belt 5 can be passed through the dredging main body 1.
The electrical components are all connected with an external main controller and 220V mains supply, and the main controller can be conventional known equipment for controlling a computer and the like.
The working principle and the using flow of the utility model are as follows: in the use process of the building site pipeline dredging device, when the servo motor 3 is started, the driving wheel 4 can be rotated, the belt 5 is driven to drive, the rotating shaft 6 can be rotated, the zigzag hose 9 can be rotated through the hexagonal groove 7, the drill bit 10 can extend to a pipeline, when the drill bit 10 is started, the inner wall of the pipeline can be cleaned, and the dredging device is convenient to observe during cleaning and improves efficiency through the arrangement of the illuminating lamp 8; this building site pipeline pull throughs for the connecting handle 11 can be connected with pivot 6, and the crooked hose 9 of being convenient for rotates, thereby makes this building site pipeline pull throughs play the effect of being convenient for dismantle, makes grip stick 12 can convenient to detach, and convenient to use person operates, and the rubber sleeve can increase user's comfort, through the setting of operation hand knot 14, can control servo motor 3's rotation through detaining the operation hand knot 14, and the operation is more convenient.
Finally, it should be noted that: the foregoing description is only a preferred embodiment of the present utility model, and the present utility model is not limited thereto, but it is to be understood that modifications and equivalents of some of the technical features described in the foregoing embodiments may be made by those skilled in the art, although the present utility model has been described in detail with reference to the foregoing embodiments. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present utility model should be included in the protection scope of the present utility model.
Claims (8)
1. The utility model provides a building site pipeline pull throughs, includes mediation main part (1) and tortuous hose (9), its characterized in that: the utility model discloses a dredge main part, including main part (1) and main part, the top fixedly connected with solid fixed ring (2) of dredge main part (1), the inner wall fixed mounting of solid fixed ring (2) has servo motor (3), the output fixedly connected with action wheel (4) of servo motor (3), the surface transmission of action wheel (4) is connected with belt (5), the inside swing joint of dredge main part (1) has pivot (6), hexagonal groove (7) have been seted up to the inside of pivot (6), the bottom fixedly mounted of dredge main part (1) has light (8).
2. A construction site pipe pull throughs according to claim 1, wherein: one end of the zigzag hose (9) is fixedly provided with a drill bit (10), and the drill bit (10) is made of diamond.
3. A construction site pipe pull throughs according to claim 1, wherein: the connecting handle (11) is fixedly arranged at the other end of the zigzag hose (9), and a hexagonal prism is arranged on the outer side of the connecting handle (11).
4. A construction site pipe pull throughs according to claim 1, wherein: one side threaded connection of mediation main part (1) has grip stick (12), the surface of grip stick (12) is provided with the rubber sleeve.
5. A construction site pipe pull throughs according to claim 1, wherein: the dredging device is characterized in that a handle (13) is fixedly connected to the side face of the bottom of the dredging main body (1), and anti-slip patterns are arranged on the outer surface of the handle (13).
6. A construction site pipe pull throughs as claimed in claim 5, wherein: an operation hand button (14) is arranged on one side of the grip (13).
7. A construction site pipe pull throughs according to claim 1, wherein: one side of mediation main part (1) top fixedly connected with metal sheet (15), the top of metal sheet (15) is through bearing fixedly connected with servo motor (3).
8. A construction site pipe pull throughs according to claim 1, wherein: the belt (5) penetrates through the dredging main body (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202320214820.5U CN219541251U (en) | 2023-02-15 | 2023-02-15 | Building site pipeline pull throughs |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202320214820.5U CN219541251U (en) | 2023-02-15 | 2023-02-15 | Building site pipeline pull throughs |
Publications (1)
Publication Number | Publication Date |
---|---|
CN219541251U true CN219541251U (en) | 2023-08-18 |
Family
ID=87707803
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202320214820.5U Active CN219541251U (en) | 2023-02-15 | 2023-02-15 | Building site pipeline pull throughs |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN219541251U (en) |
-
2023
- 2023-02-15 CN CN202320214820.5U patent/CN219541251U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207756577U (en) | A kind of petroleum pipeline dredger | |
CN213014097U (en) | Road surface concrete health preserving device for highway engineering construction | |
CN201260653Y (en) | Wall cleaning machine | |
CN219541251U (en) | Building site pipeline pull throughs | |
CN201710275U (en) | Electrically driven window cleaner | |
CN111927139B (en) | Sequential slurry guiding device for crack grouting and multifunctional slurry guiding device for grouting | |
CN213061624U (en) | Crack pouring equipment for road construction | |
CN207412113U (en) | Eminence glass cleaning machinery hand | |
CN111892143A (en) | Sewage treatment equipment cleaning device | |
CN108560940A (en) | A kind of high-efficiency ceramic tile floor excavating device | |
CN220959285U (en) | Bio-fertilizer cylinder drying-machine wiper mechanism | |
CN215062521U (en) | Energy-saving deep dehumidification air conditioning unit | |
CN220133568U (en) | Wall repairing device for decoration engineering | |
CN220282081U (en) | Stainless steel water tank with cleaning structure | |
CN220083272U (en) | Indoor ventilation structure of building | |
CN218613317U (en) | Angle mill with washing structure for stone processing | |
CN212078760U (en) | Wall surface spraying device for architectural decoration capable of treating wall surface smoothness | |
CN213137328U (en) | Outer wall perforating device of building for building engineering | |
CN220573046U (en) | Dust collector is produced to calcium silicate board | |
CN215963814U (en) | But sealed production of gluing of self-cleaning uses material grinder | |
CN220716993U (en) | Scrubbing machine for cleaning quartz sand | |
CN213378206U (en) | Efficient industrial chemicals rinsing device for chemical production | |
CN221001816U (en) | Spraying device for building wall surface | |
CN204112763U (en) | Brick wall mortar mortar joint cleaning plant | |
CN220747692U (en) | Concrete wall waterproof construction basic unit processing apparatus |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |