CN219528620U CN202222563666.0U CN202222563666U CN219528620U CN 219528620 U CN219528620 U CN 219528620U CN 202222563666 U CN202222563666 U CN 202222563666U CN 219528620 U CN219528620 U CN 219528620U
Authority
CN
China
Prior art keywords
groups
device based
construction site
engineering management
upright posts
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222563666.0U
Other languages
Chinese (zh)
Inventor
王海涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202222563666.0U priority Critical patent/CN219528620U/en
Application granted granted Critical
Publication of CN219528620U publication Critical patent/CN219528620U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a construction site enclosing device based on construction engineering management, which belongs to the technical field of construction enclosing, and comprises two groups of upright posts with the same structure, wherein bottom cross beams are arranged at the bottoms of opposite sides of the two groups of upright posts, and top cross beams are arranged at the tops of opposite sides of the two groups of upright posts; the bottom of the top beam is connected with a surrounding baffle plate which is jointed with the bottom beam; the fixed subassembly, including laminating connect two sets of the dead lever of stand opposite side, two sets of the slot has all been seted up at the top of dead lever, the both sides of enclosing the baffle all peg graft in the slot, pull down the dead lever back through the locking screw, can directly take off the enclosing the baffle from the slot of dead lever and change, then support the bottom of dead lever through the recess of bottom crossbeam, can install the dead lever through the locking screw.

Description

Construction site enclosure device based on building engineering management
Technical Field
The utility model relates to the technical field of construction enclosure, in particular to a construction site enclosure device based on construction engineering management.
Background
In building construction management, safety management is a serious issue, and then a surrounding fence needs to be arranged at the periphery of a site in building construction, and the engineering surrounding fence is a facility which enables the construction site to be a relatively closed isolation space in order to isolate the construction site from the external environment.
The prior engineering enclosure is generally composed of an upright post, a cross beam and a color steel baffle plate, wherein the color steel baffle plate is generally clamped between the upright post and the cross beam through a clamping groove, so that when the color steel baffle plate is subjected to accidental impact and deformation damage occurs, the replacement efficiency is low, and therefore, the construction site enclosure device based on the construction engineering management is provided.
Disclosure of Invention
The utility model aims to provide a construction site enclosure device based on construction engineering management so as to solve the problems in the background technology.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the construction site enclosure device based on the construction engineering management comprises two groups of upright posts with the same structure, wherein bottom cross beams are arranged at the bottoms of opposite sides of the two groups of upright posts, and top cross beams are arranged at the tops of opposite sides of the two groups of upright posts; the bottom of the top beam is connected with a surrounding baffle plate which is jointed with the bottom beam; the fixed subassembly, including laminating connect two sets of the dead lever of stand opposite side, two sets of the slot has all been seted up at the top of dead lever, the both sides of enclosing the baffle all peg graft in the slot, the both ends of bottom cross beam front side all be provided with respectively with two sets of the recess of dead lever bottom laminating, two sets of all be provided with on the dead lever respectively with two sets of stand fixed connection's mounting structure.
As a preferable scheme of the construction site enclosure device based on the construction engineering management, the utility model comprises the following steps: the bottom ends of the two groups of upright posts are provided with flange plates.
As a preferable scheme of the construction site enclosure device based on the construction engineering management, the utility model comprises the following steps: the mounting structure comprises two groups of connecting plates with the same structure, the two groups of connecting plates are respectively arranged on two sides of the fixed rod, and locking screws connected with the stand columns are respectively arranged on the two groups of connecting plates.
As a preferable scheme of the construction site enclosure device based on the construction engineering management, the utility model comprises the following steps: the connecting plate is of an L-shaped structure.
As a preferable scheme of the construction site enclosure device based on the construction engineering management, the utility model comprises the following steps: the bending part of the connecting plate is attached to the bending part of the upright post.
As a preferable scheme of the construction site enclosure device based on the construction engineering management, the utility model comprises the following steps: the surrounding baffle is a color steel surrounding baffle.
Compared with the prior art, the utility model has the beneficial effects that: after the fixing rod is detached through the locking screw, the surrounding baffle plate can be directly taken down from the slot of the fixing rod to be replaced, then the bottom of the fixing rod is supported through the groove of the bottom cross beam, and the fixing rod can be installed through the locking screw, so that the surrounding baffle plate can be replaced quickly.
Drawings
FIG. 1 is a schematic diagram of the overall structure of a construction site enclosure device based on construction engineering management;
FIG. 2 is a schematic front view of a structure of a fixed assembly and a bottom beam of a construction site enclosure device based on construction engineering management of the present utility model;
FIG. 3 is a schematic side view of a fixed assembly and bottom beam structure of a construction site enclosure device based on construction engineering management of the present utility model;
fig. 4 is a schematic top view of a fixing assembly and a bottom beam structure of a construction site enclosure device based on construction engineering management.
In the figure: 1. a column; 2. a flange plate; 3. a top beam; 4. a bottom cross beam; 5. a surrounding baffle; 6. a fixed rod; 7. a groove; 8. a connecting plate; 9. locking the screw.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Example 1
Referring to fig. 1 to 4, a construction site enclosure device based on construction engineering management includes two groups of upright posts 1 with the same structure, bottom cross beams 4 are arranged at the bottoms of opposite sides of the two groups of upright posts 1, top cross beams 3 are arranged at the tops of opposite sides of the two groups of upright posts 1, which is the prior art;
the bottom of the top beam 3 is connected with a surrounding baffle 5 which is jointed with the bottom beam 4, and the surrounding baffle 5 is a color steel surrounding baffle;
fixed subassembly, including laminating connection at the dead lever 6 of two sets of stand 1 opposite sides, the slot has all been seted up at the top of two sets of dead levers 6, the slot is seted up at the top, the bottom of dead lever 6 is closed condition, the both sides of surrounding board 5 all peg graft in the slot, and the bottom of surrounding board is the laminating state with bottom crossbeam 4, the bottom inner wall and the bottom crossbeam 4 parallel and level of slot promptly, all be provided with respectively with the recess 7 of two sets of dead lever 6 bottoms laminating at the both ends of bottom crossbeam 4 front side, be convenient for impel in the recess 7 with dead lever 6 bottom closed part, all be provided with respectively with the mounting structure of two sets of stand 1 fixed connection on two sets of dead levers 6.
The bottom ends of the two groups of upright posts 1 are respectively provided with a flange plate 2, and the flange plates 2 are fixed on the ground through expansion screws.
The mounting structure comprises two groups of connecting plates 8 with the same structure, the two groups of connecting plates 8 are respectively arranged on two sides of the fixed rod 6, locking screws 9 connected with the upright posts 1 are arranged on the two groups of connecting plates 8, the connecting plates 8 are fixed on the upright posts 1 through the locking screws 9, and the fixed rod 6 can be fixed.
Example 2
Referring to fig. 1 to 4, the connecting plate 8 is of an L-shaped structure, so that the bending part of the connecting plate 8 is attached to the bending part of the upright 1, and after the fixing rod 6 is pushed backwards on the groove 7 in place, the connecting plate 8 is just clamped by the upright 1, so that the locking screw 9 can be conveniently installed.
The rest of the structure is the same as in embodiment 1.
When the surrounding baffle 5 is damaged and needs to be replaced, the locking screw 9 is firstly taken down, then the connecting plate 8 is pulled forward, two groups of fixing rods 6 are pulled forward, the damaged surrounding baffle 5 can be taken out upwards from the slot, then a new surrounding baffle 5 is inserted into the slot, at the moment, the surrounding baffle 5 can be supported and limited through the fixing rods 6 so as to move the surrounding baffle 5, then the bottom of the fixing rods 6 is pushed into the groove 7 of the bottom cross beam 4 until the fixing rods are pushed to be still, at the moment, the connecting plate 8 is just clamped by the upright posts 1, the locking screw 9 can be installed, the fixing rods 6 are installed, the replacement of the surrounding baffle 5 is completed, the purpose of conveniently replacing and moving the surrounding baffle 5 is achieved through the slots with the top openings and the bottom closed on the fixing rods 6, and therefore the replacement efficiency of the surrounding baffle 5 is improved.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. Construction site encloses fender device based on building engineering management, its characterized in that: comprising the steps of (a) a step of,
two groups of upright posts (1) with the same structure, bottom cross beams (4) are arranged at the bottoms of opposite sides of the two groups of upright posts (1), and top cross beams (3) are arranged at the tops of opposite sides of the two groups of upright posts (1);
the bottom of the top beam (3) is connected with a surrounding baffle plate (5) which is jointed with the bottom beam (4);
the fixing assembly comprises two groups of fixing rods (6) which are connected to the opposite sides of the upright (1) in a fitting mode, slots are formed in the tops of the fixing rods (6), two sides of the surrounding baffle plates (5) are inserted into the slots, two ends of the front side of the bottom cross beam (4) are respectively provided with two groups of grooves (7) which are respectively attached to the bottoms of the fixing rods (6), and two groups of fixing structures which are respectively fixedly connected with the upright (1) are respectively arranged on the fixing rods (6).
2. A construction site enclosure device based on construction engineering management according to claim 1, wherein: the bottom ends of the two groups of upright posts (1) are provided with flange plates (2).
3. A construction site enclosure device based on construction engineering management according to claim 1, wherein: the mounting structure comprises two groups of connecting plates (8) with the same structure, the two groups of connecting plates (8) are respectively arranged on two sides of the fixed rod (6), and locking screws (9) connected with the upright posts (1) are respectively arranged on the two groups of connecting plates (8).
4. A construction site enclosure device based on construction engineering management according to claim 3, wherein: the connecting plate (8) is of an L-shaped structure.
5. The construction site enclosure device based on construction engineering management according to claim 4, wherein: the bending part of the connecting plate (8) is attached to the bending part of the upright post (1).
6. A construction site enclosure device based on construction engineering management according to claim 1, wherein: the surrounding baffle (5) is a color steel surrounding baffle.
CN202222563666.0U 2022-09-27 2022-09-27 Construction site enclosure device based on building engineering management Active CN219528620U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222563666.0U CN219528620U (en) 2022-09-27 2022-09-27 Construction site enclosure device based on building engineering management

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222563666.0U CN219528620U (en) 2022-09-27 2022-09-27 Construction site enclosure device based on building engineering management

Publications (1)

Publication Number Publication Date
CN219528620U true CN219528620U (en) 2023-08-15

Family

ID=87582048

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222563666.0U Active CN219528620U (en) 2022-09-27 2022-09-27 Construction site enclosure device based on building engineering management

Country Status (1)

Country Link
CN (1) CN219528620U (en)

Similar Documents

Publication Publication Date Title
CN219528620U (en) Construction site enclosure device based on building engineering management
CN217693228U (en) Structure of light and thin type solar photovoltaic module
CN216841016U (en) Oil gas field ground engineering construction safety protection isolating device
CN214657789U (en) Lap joint assembly type energy-saving building
CN220190716U (en) Photovoltaic bracket convenient to install
CN213075056U (en) Anti-drop formula novel goods shelves layer board back shelves mounting structure
CN202068702U (en) Modularized frame
CN215394755U (en) Tool for integrally positioning metal embedded part of engine room cover
CN220908682U (en) Steel construction beam column connection structure
CN217711904U (en) Connection structure and protection canopy
CN220139449U (en) Solar power generation photovoltaic panel fixing device
CN215101331U (en) Steel structure derrick of elevator
CN220359062U (en) Solar tracking bracket
CN219181139U (en) Bus duct with stable connection
CN218376122U (en) Domestic door of rigidity concatenation
CN216245638U (en) Reinforcing device for air cooling island
CN221012605U (en) Sofa bed skeleton texture
CN214227669U (en) Line support for municipal works
CN221324117U (en) High-strength angle steel
CN220850265U (en) Corner supporting mechanism and aluminum profile cabinet frame
CN220848030U (en) Device is built in room
CN216157330U (en) Make things convenient for quick assembly disassembly's civil engineering construction with enclosing fender
CN219931224U (en) Building steel structure convenient to installation
CN219684370U (en) Welding deformation preventing device for multi-rib structure of thin plate
CN221119120U (en) Firmly assembled scaffold