CN219475720U - Energy control system test meter - Google Patents
Energy control system test meter Download PDFInfo
- Publication number
- CN219475720U CN219475720U CN202320611593.XU CN202320611593U CN219475720U CN 219475720 U CN219475720 U CN 219475720U CN 202320611593 U CN202320611593 U CN 202320611593U CN 219475720 U CN219475720 U CN 219475720U
- Authority
- CN
- China
- Prior art keywords
- metering chip
- shell
- control system
- energy control
- system test
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
Abstract
The utility model discloses an energy control system test meter, comprising: a housing; the metering chip is arranged in the shell and is used for monitoring and storing the power consumption voltage, the power consumption current and the power consumption amount in unit time of the electric equipment; the display is arranged on the shell and connected with the metering chip and used for displaying the power consumption voltage, the power consumption quantity in unit time and the real-time power consumption of the electric equipment; the alarm is arranged on the shell and is connected with the metering chip; the first wiring terminal is arranged on the shell and connected with the metering chip and used for connecting a power line of electric equipment; the second wiring terminal is arranged on the shell and is connected with the metering chip and used for connecting with the mains supply; the transmission interface is arranged on the shell and is connected with the metering chip and used for supplying power or transmitting data to the metering chip. The utility model has the characteristics of monitoring the power consumption of the electric equipment in real time and improving the accuracy.
Description
Technical Field
The utility model relates to the technical field of energy management, in particular to an energy control system test meter.
Background
The energy consumption of the production equipment is monitored in real time and the abnormal energy consumption is detected, so that the development trend of manufacturing automation and further cost reduction is realized, in addition, the whole production energy-saving condition of an enterprise is evaluated by the energy consumption condition of single equipment, and the abnormal energy consumption phenomena of energy leakage, long standby time, overhigh energy consumption in a certain link of a production workshop and the like can be effectively reduced.
At present, most of the production energy metering of enterprises adopts a manual metering mode, workers are required to walk through each production device to record meter data, and not only the energy consumption data can be timely monitored due to overlarge workshop area of the enterprises, but also the problem of abnormal energy consumption of the devices in production can not be timely processed; in addition, the electricity consumption of the whole enterprise is counted by the ammeter in many enterprises, and the real-time monitoring of single equipment cannot be realized.
Disclosure of Invention
The utility model designs and develops an energy control system test meter, the energy consumption of electric equipment is monitored in real time through the combination of two wiring terminals and a metering chip, the hysteresis of energy consumption data is effectively avoided, and the monitoring accuracy is improved through the combination of an alarm and a transmission interface.
The technical scheme provided by the utility model is as follows:
an energy control system test meter comprising:
a housing; and
the metering chip is arranged in the shell and is used for monitoring and storing the power consumption voltage, the power consumption current and the power consumption amount in unit time of the electric equipment;
the display is arranged on the shell, is connected with the metering chip and is used for displaying the power utilization voltage, the power utilization quantity in unit time and the real-time power consumption of the electric equipment;
the alarm is arranged on the shell and is connected with the metering chip;
the first wiring terminal is arranged on the shell and connected with the metering chip and used for connecting a power line of the electric equipment;
the second wiring terminal is arranged on the shell and is connected with the metering chip and used for connecting with the mains supply;
the transmission interface is arranged on the shell and connected with the metering chip and used for supplying power or transmitting data to the metering chip.
Preferably, the method further comprises:
and the manager is arranged on the shell and is used for switching display data on the display and managing an energy control system test sheet.
Preferably, the manager includes:
the power key is arranged on the shell and connected with the metering chip and used for switching on or switching off the energy control system test meter;
the reset key is arranged on the shell and connected with the metering chip and used for resetting the metering chip;
an alarm silencing key connected with the alarm for closing the alarm;
and the function key is arranged on the shell and connected with the display and used for adjusting the data displayed on the display.
Preferably, the method further comprises:
the indicating device is arranged on the shell, is connected with the metering chip and is used for displaying the states of the energy control system test meter and the electric equipment.
Preferably, the indicating device includes:
the power supply lamp is connected with the metering chip and used for displaying whether the metering chip is electrified or not;
the reset lamp is connected with the metering chip and the reset key and is used for displaying whether the metering chip is reset or not;
the alarm lamp is connected with the metering chip and used for displaying an alarm;
and the fault lamp is connected with the metering chip and is used for displaying whether the metering chip has faults or not.
Preferably, the method further comprises:
the carrier communication module is arranged in the shell and is connected with the metering chip for remote transmission of data.
Preferably, the method further comprises:
and the upper hanging lug is arranged on one side of the shell and is used for fixing the energy control system test meter.
Preferably, the method further comprises:
the lower hanging lugs are arranged on the other side of the shell opposite to the lower hanging lugs and are used for fixing the energy control system test meter.
The beneficial effects of the utility model are as follows:
according to the energy control system test meter provided by the utility model, the energy consumption of the electric equipment is monitored in real time through the combination of the two wiring terminals and the metering chip, so that the hysteresis of energy consumption data is effectively avoided, and the electricity is conveniently saved; meanwhile, the alarm can quickly respond when the electric equipment fails, the transmission interface is set, the redundancy of data transmission can be realized, and the monitoring accuracy is improved by supplying power to the energy control system test meter.
Drawings
Fig. 1 is a schematic diagram of an axial measurement structure of a test meter of an energy control system according to the present utility model.
Fig. 2 is a schematic diagram of a front view structure of a test meter of the energy control system according to the present utility model.
Detailed Description
The present utility model is described in further detail below with reference to the drawings to enable those skilled in the art to practice the utility model by referring to the description.
As shown in fig. 1 and 2, the present utility model provides an energy control system test meter, including: the device comprises a shell 100, a metering chip (not shown in the figure), a manager, an indicating device, a display 110, a first wiring terminal 141, a second wiring terminal 142, a transmission interface 150 and an alarm 160, wherein the shell 100 is of a detachable structure, a rear cover of the shell 100 can be mutually clamped with the shell 100, the metering chip is arranged in the shell 100, and can monitor the power consumption voltage, the power consumption current and the power consumption per unit time of electric equipment in real time and can store in the metering chip; a display 110 is arranged on the front surface of the shell 100, and the display 110 is connected with the metering chip and is used for selectively displaying the power consumption voltage, the power consumption current, the power consumption in unit time and the real-time power consumption of the electric equipment monitored by the metering chip; the front of the shell is also provided with a manager and an indicating device, the indicating device is arranged at the lower side of the display, and the indicating device is connected with the metering chip and is used for displaying the states of the energy control system test meter and the electric equipment; the manager is arranged at the lower side of the indicating device and is used for switching display data on the display and managing an energy control system test table; two groove structures are respectively arranged at the upper end and the lower end of the shell 100, the first wiring terminal 141 and the alarm 160 are arranged at the groove structures at the upper end of the shell 100, the second wiring terminal 142 and the transmission interface 150 are arranged at the groove structures at the lower end of the shell 100, the first wiring terminal 141, the second wiring terminal 142, the transmission interface 150 and the alarm 160 are all mutually connected with a metering chip, the first wiring terminal is used for connecting a power line of electric equipment, and the second wiring terminal 142 is used for connecting commercial power; the alarm 160 gives an alarm when the power consumption of the electric equipment is detected to be suddenly increased, and the transmission interface 150 is used for supplying power to the metering chip, the alarm 160 and the display 110.
In this embodiment, the metering chip is commercially available, and can set the power consumption of the monitoring electric equipment in unit time according to the user demand.
In this embodiment, further comprising: a carrier communication module (not shown) is disposed in the housing 100, and the carrier communication module is connected to the metering chip, so as to remotely transmit the data monitored by the metering chip.
In this embodiment, when the carrier communication module fails, the data in the metering chip may be exported through a transmission interface.
The manager includes: the power key 121, the reset key 122, the alarm silencing key 123 and the function key 124, wherein the power key 121 and the reset key 122 are connected with the metering chip, the alarm silencing key 123 is connected with the alarm 160, the function key 124 is connected with the display 110, and the power key 121 is used for starting or closing the energy control system test table after the transmission interface is connected with the mains supply; the reset key 122 resets the metering chip when the device needs to be monitored again; the alarm silencing key is used for turning off the alarm 160 after monitoring personnel know that the electric equipment has problems after the alarm alarms; the display 110 only displays the power voltage, the power current, the power consumption per unit time or the real-time power consumption of the electric equipment monitored by the metering chip, and the function key is used for switching and adjusting the data displayed on the display 110.
The indicating device includes: the power supply lamp 131, the reset lamp 132, the alarm lamp 133 and the fault lamp 134 are all connected with the metering chip, the power supply lamp 131 is used for displaying whether the metering chip is electrified, and the power supply lamp 131 is turned on after the metering chip is electrified; the reset lamp 132 is used for displaying whether the metering chip is reset, and after the reset key 122 is pressed, the reset lamp is turned on until the reset is completed, and the reset lamp 132 is turned off; the alarm lamp 133 is used for displaying an alarm, the alarm lamp 133 is triggered to light up when the alarm 160 alarms, and the fault lamp 134 is lighted up when the metering chip breaks down.
In this embodiment, the energy control system test table of the present utility model is directly connected to the power line of the electric device.
An upper hanging lug 101 and a lower hanging lug 102 are respectively arranged at the upper end and the lower end of the shell 100 close to the rear cover and are used for portable fixing of the energy control system test meter.
According to the energy control system test meter provided by the utility model, the energy consumption of the electric equipment is monitored in real time through the combination of the two wiring terminals and the metering chip, so that the hysteresis of energy consumption data is effectively avoided, and the electricity is conveniently saved; meanwhile, the alarm can quickly respond when the electric equipment fails, the transmission interface is set, the redundancy of data transmission can be realized, and the monitoring accuracy is improved by supplying power to the energy control system test meter.
Although embodiments of the present utility model have been disclosed above, it is not limited to the details and embodiments shown and described, it is well suited to various fields of use for which the utility model would be readily apparent to those skilled in the art, and accordingly, the utility model is not limited to the specific details and illustrations shown and described herein, without departing from the general concepts defined in the claims and their equivalents.
Claims (8)
1. An energy control system test meter, comprising:
a housing; and
the metering chip is arranged in the shell and is used for monitoring and storing the power consumption voltage, the power consumption current and the power consumption amount in unit time of the electric equipment;
the display is arranged on the shell, is connected with the metering chip and is used for displaying the power utilization voltage, the power utilization quantity in unit time and the real-time power consumption of the electric equipment;
the alarm is arranged on the shell and is connected with the metering chip;
the first wiring terminal is arranged on the shell and connected with the metering chip and used for connecting a power line of the electric equipment;
the second wiring terminal is arranged on the shell and is connected with the metering chip and used for connecting with the mains supply;
the transmission interface is arranged on the shell and connected with the metering chip and used for supplying power or transmitting data to the metering chip.
2. The energy control system test meter of claim 1, further comprising:
and the manager is arranged on the shell and is used for switching display data on the display and managing an energy control system test sheet.
3. The energy control system test meter of claim 2, wherein the manager comprises:
the power key is arranged on the shell and connected with the metering chip and used for switching on or switching off the energy control system test meter;
the reset key is arranged on the shell and connected with the metering chip and used for resetting the metering chip;
an alarm silencing key connected with the alarm for closing the alarm;
and the function key is arranged on the shell and connected with the display and used for adjusting the data displayed on the display.
4. The energy control system test meter of claim 3, further comprising:
the indicating device is arranged on the shell, is connected with the metering chip and is used for displaying the states of the energy control system test meter and the electric equipment.
5. The energy control system test meter of claim 4, wherein said indicating means comprises:
the power supply lamp is connected with the metering chip and used for displaying whether the metering chip is electrified or not;
the reset lamp is connected with the metering chip and the reset key and is used for displaying whether the metering chip is reset or not;
the alarm lamp is connected with the metering chip and used for displaying an alarm;
and the fault lamp is connected with the metering chip and is used for displaying whether the metering chip has faults or not.
6. The energy control system test meter of claim 5, further comprising:
the carrier communication module is arranged in the shell and is connected with the metering chip for remote transmission of data.
7. The energy control system test meter of claim 6, further comprising:
and the upper hanging lug is arranged on one side of the shell and is used for fixing the energy control system test meter.
8. The energy control system test meter of claim 7, further comprising:
the lower hanging lugs are arranged on the other side of the shell opposite to the lower hanging lugs and are used for fixing the energy control system test meter.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202320611593.XU CN219475720U (en) | 2023-03-27 | 2023-03-27 | Energy control system test meter |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202320611593.XU CN219475720U (en) | 2023-03-27 | 2023-03-27 | Energy control system test meter |
Publications (1)
Publication Number | Publication Date |
---|---|
CN219475720U true CN219475720U (en) | 2023-08-04 |
Family
ID=87468010
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202320611593.XU Active CN219475720U (en) | 2023-03-27 | 2023-03-27 | Energy control system test meter |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN219475720U (en) |
-
2023
- 2023-03-27 CN CN202320611593.XU patent/CN219475720U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100596331C (en) | High pressure measurement device and antitheft electric method for high-low pressure electric quantity measurement contrast | |
CN210274117U (en) | Intelligent gateway and system | |
CN205453696U (en) | Real -time on -line monitoring system of optical cable based on GIS | |
CN211426740U (en) | Power module state self-diagnosis device of distribution network automation terminal | |
CN200996970Y (en) | Charge-evasion preventer for comparing high-voltage end and low-voltage end quantity | |
CN105932770A (en) | Intelligent electric meter box | |
CN203119619U (en) | Microcomputer harmonic elimination device | |
CN107144750A (en) | A kind of low-voltage platform area down Monitor Unit device and alarm method | |
CN207456618U (en) | A kind of ring-main unit temperature of cable junction monitoring device | |
CN219475720U (en) | Energy control system test meter | |
CN102768075A (en) | Temperature early-warning centralized display system | |
CN205665568U (en) | Electrical safety remote control and measurement communication device based on thing networking | |
CN111313376A (en) | Rural power grids block terminal phase failure warning protection device | |
CN208350888U (en) | Low voltage equipment intelligent power monitor | |
CN102798416A (en) | Monitoring system for power environment in machine room | |
CN212849008U (en) | Modular freely-assembled intelligent charging device | |
CN215064712U (en) | NB-IoT intelligent water meter data acquisition terminal | |
CN214409153U (en) | Operating state monitor for oil fume purifier | |
CN212229020U (en) | Three-phase safety electric meter | |
CN211236021U (en) | Water immersion protection system based on low-power-consumption Bluetooth Mesh network | |
CN212304097U (en) | Intelligent power line plug | |
CN205210161U (en) | Optical fiber temperature fault indicator | |
CN209296809U (en) | Distribution supervision and energy-consumption monitoring system | |
CN205583848U (en) | Intelligent ammeter cabinet | |
CN110988731A (en) | Power module state self-diagnosis device of distribution network automation terminal |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||