- CN219386639U CN219386639U CN202320875273.5U CN202320875273U CN219386639U CN 219386639 U CN219386639 U CN 219386639U CN 202320875273 U CN202320875273 U CN 202320875273U CN 219386639 U CN219386639 U CN 219386639U
- Authority
- CN
- China
- Prior art keywords
- frame
- concrete pile
- inner frame
- fixedly connected
- positioning
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/50—Photovoltaic [PV] energy
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
本实用新型公开了一种装配式混凝土预制框架,包括上混凝土桩和下混凝土桩,所述上混凝土桩的底端设置有下混凝土桩,所述上混凝土桩内部的底端固定连接有第一内框。该装配式混凝土预制框架通过设置有限位插槽、第一内框、第二内框和限位插销,在对上混凝土桩和下混凝土桩进行连接时,将上混凝土桩安装在下混凝土桩的顶端,并使上混凝土桩内部的第一内框和下混凝土桩内部的第二内框相贴合,同时第二内框顶端的限位插销会插入第一内框底端的限位插槽内部,从而通过限位插槽和限位插销对第一内框和第二内框进入,以防止上混凝土桩和下混凝土桩在连接之后出现错位,解决的是无法有效对框架进行定位的问题。
The utility model discloses an assembled concrete prefabricated frame, which comprises an upper concrete pile and a lower concrete pile. The bottom of the upper concrete pile is provided with a lower concrete pile, and the bottom of the upper concrete pile is fixedly connected with a first inner frame. The prefabricated concrete frame is provided with a limit slot, a first inner frame, a second inner frame and a limit pin. When connecting the upper concrete pile and the lower concrete pile, the upper concrete pile is installed on the top of the lower concrete pile, and the first inner frame inside the upper concrete pile and the second inner frame inside the lower concrete pile are fitted together. At the same time, the limit pin at the top of the second inner frame is inserted into the limit slot at the bottom of the first inner frame, so that the first inner frame and the second inner frame can be inserted through the limit slot and the limit pin to prevent the upper concrete pile. After the connection with the lower concrete pile, there is a dislocation, which solves the problem that the frame cannot be effectively positioned.
Description
技术领域technical field
本实用新型涉及混凝土预制框架技术领域,具体为一种装配式混凝土预制框架。The utility model relates to the technical field of concrete prefabricated frames, in particular to an assembled concrete prefabricated frame.
背景技术Background technique
装配式混凝土构件是通过预先浇注的方式制成指定尺寸外型的混凝土构件,在施工时可以快速的连接安装,具有使用方便、施工周期短、标准性高的优势,在现在的建筑施工领域应用广泛,其中装配式混凝土预制框架是使用较多的一种预制构件,但是用于建筑施工领域的装配式混凝土预制框架在使用中仍存在一些缺陷;Prefabricated concrete components are made of concrete components of specified size and shape by pre-casting. They can be quickly connected and installed during construction. They have the advantages of convenient use, short construction period, and high standardization. They are widely used in the current building construction field. Among them, the prefabricated concrete frame is a kind of prefabricated component that is used more, but the prefabricated concrete frame used in the construction field still has some defects in use;
根据中国专利申请号CN202221982668.7提出的一种装配式混凝土预制框架,具体内容为本实用新型涉及装配式建筑技术领域,且公开了一种装配式混凝土预制框架,包括混凝土柱,混凝土柱的表面开设有若干个固定孔,固定孔的内部插接有A钢筋柱,A钢筋柱的一端固定连接有A顶板,A顶板上表面的两侧通过螺栓螺纹连接有B顶板,B顶板的上表面固定连接有若干个B钢筋柱,B顶板表面的两侧均固定连接有转动组件;According to the Chinese patent application number CN202221982668.7, a prefabricated concrete frame is proposed. The specific content is that the utility model relates to the technical field of prefabricated buildings, and discloses a prefabricated concrete frame, which includes concrete columns. There are several fixing holes on the surface of the concrete columns. A steel bar columns are inserted into the fixing holes. One end of the A steel bar columns is fixedly connected to the A top plate. Reinforced columns, both sides of the top plate surface of B are fixedly connected with rotating components;
该实用新型提出的装配式混凝土预制框架,在连接安装时不能有效的对框架进行定位,从而防止连接之后框架之间出现错位的现象;The assembled concrete prefabricated frame proposed by this utility model cannot effectively position the frame during connection and installation, so as to prevent the phenomenon of misalignment between the frames after connection;
现在提出一种新型的装配式混凝土预制框架来解决上述的问题。A new type of fabricated concrete prefabricated frame is now proposed to solve the above problems.
实用新型内容Utility model content
本实用新型的目的在于提供一种装配式混凝土预制框架,以解决上述背景技术中提出无法有效对框架进行定位的问题。The purpose of this utility model is to provide an assembled concrete prefabricated frame to solve the problem that the frame cannot be effectively positioned in the above-mentioned background technology.
为实现上述目的,本实用新型提供如下技术方案:一种装配式混凝土预制框架,包括上混凝土桩和下混凝土桩,所述上混凝土桩的底端设置有下混凝土桩,所述上混凝土桩内部的底端固定连接有第一内框,所述下混凝土桩内部的顶端固定连接有第二内框;In order to achieve the above object, the utility model provides the following technical solutions: an assembled concrete prefabricated frame, comprising an upper concrete pile and a lower concrete pile, the bottom of the upper concrete pile is provided with a lower concrete pile, the bottom of the upper concrete pile is fixedly connected with a first inner frame, and the top of the lower concrete pile is fixedly connected with a second inner frame;
所述第一内框的底端开设有限位插槽,所述第二内框的顶端固定连接有限位插销,所述限位插销与限位插槽活动连接,所述第一内框与第二内框活动连接,所述第一内框的底端和第二内框的顶端分别固定连接有一组外框。The bottom end of the first inner frame is provided with a limit slot, the top of the second inner frame is fixedly connected with a limit pin, the limit pin is movably connected with the limit slot, the first inner frame is movably connected with the second inner frame, and a group of outer frames are respectively fixedly connected to the bottom end of the first inner frame and the top end of the second inner frame.
优选的,所述第一内框底端开设的限位插槽呈等间距排布,所述第二内框顶端固定的限位插销呈等间距排布。Preferably, the limit slots opened at the bottom of the first inner frame are arranged at equal intervals, and the limit pins fixed at the top of the second inner frame are arranged at equal intervals.
优选的,所述外框外部的一端固定连接有连接框,所述连接框一端的四个拐角处分别开设有一组通孔,所述通孔的内部活动连接有连接螺纹杆,所述连接螺纹杆外部的两端分别固定连接有一组挡板,所述挡板与连接框活动连接,所述连接框一端的四个拐角分别活动连接有一组固定螺栓,所述连接框的一端固定连接有支撑板,所述支撑板与外框固定连接。Preferably, one end outside the outer frame is fixedly connected with a connecting frame, and four corners at one end of the connecting frame are respectively provided with a group of through holes, and the inside of the through hole is movably connected with a connecting threaded rod, and the two ends outside the connecting threaded rod are respectively fixedly connected with a set of baffles, the baffles are movably connected with the connecting frame, the four corners at one end of the connecting frame are movably connected with a set of fixing bolts, one end of the connecting frame is fixedly connected with a support plate, and the support plate is fixedly connected with the outer frame.
优选的,所述固定螺栓与连接螺纹杆螺纹连接,所述连接框的中心线与外框的中心线在同一垂直面上。Preferably, the fixing bolt is screwed to the connecting threaded rod, and the centerline of the connecting frame and the centerline of the outer frame are on the same vertical plane.
优选的,所述第一内框外部的一端固定连接有定位框,所述上混凝土桩和下混凝土桩的内部分别开设有一组定位槽,所述外框的内部固定连接有定位插块,所述上混凝土桩和下混凝土桩的外部开设有定位孔,所述定位插块与定位孔固定连接,所述定位框与定位槽固定连接。Preferably, one end outside the first inner frame is fixedly connected with a positioning frame, and a set of positioning grooves are respectively opened inside the upper concrete pile and the lower concrete pile, and a positioning plug is fixedly connected to the inside of the outer frame, and positioning holes are opened outside the upper concrete pile and the lower concrete pile, and the positioning plug is fixedly connected with the positioning hole, and the positioning frame is fixedly connected with the positioning groove.
优选的,所述定位框的中心线与第一内框的中心线在同一垂直面上,所述外框内部的定位插块呈等间距排布。Preferably, the centerline of the positioning frame and the centerline of the first inner frame are on the same vertical plane, and the positioning inserts inside the outer frame are arranged at equal intervals.
与现有技术相比,本实用新型的有益效果是:该装配式混凝土预制框架不仅实现了可以方便对框架进行定位,实现了可以方便连接,而且实现了可以提高连接件与混凝土件之间的牢固性;Compared with the prior art, the utility model has the beneficial effects that: the prefabricated concrete frame can not only realize the convenient positioning of the frame, realize the convenient connection, but also realize the improvement of the firmness between the connecting piece and the concrete piece;
(1)通过设置有限位插槽、第一内框、第二内框和限位插销,在对上混凝土桩和下混凝土桩进行连接时,将上混凝土桩安装在下混凝土桩的顶端,并使上混凝土桩内部的第一内框和下混凝土桩内部的第二内框相贴合,同时第二内框顶端的限位插销会插入第一内框底端的限位插槽内部,从而通过限位插槽和限位插销对第一内框和第二内框进入,以防止上混凝土桩和下混凝土桩在连接之后出现错位,实现了可以有效对上混凝土桩和下混凝土桩定位,防止安装后错位影响建筑强度;(1) By setting the limit slot, the first inner frame, the second inner frame and the limit pin, when the upper concrete pile and the lower concrete pile are connected, the upper concrete pile is installed on the top of the lower concrete pile, and the first inner frame inside the upper concrete pile and the second inner frame inside the lower concrete pile are fitted together, and the limit pin at the top of the second inner frame is inserted into the limit slot at the bottom of the first inner frame, so that the first inner frame and the second inner frame can be entered through the limit slot and the limit pin to prevent the upper concrete pile and the lower concrete pile Dislocation occurs after connection, so that the upper concrete pile and the lower concrete pile can be effectively positioned to prevent the dislocation after installation from affecting the building strength;
(2)通过设置有外框、连接框、连接螺纹杆、挡板、固定螺栓和支撑板,在需要对上混凝土桩和下混凝土桩进行连接时,将上混凝土桩和下混凝土桩一端的外框贴合在一起,之后将连接螺纹杆穿过连接框一端的通孔的内部,并使连接螺纹杆外部的挡板贴合在连接框的一端,并将固定螺栓套接在连接螺纹杆外部的两端,固定螺栓可以通过连接螺纹杆对两组连接框进行连接,从而通过外框对上混凝土桩和下混凝土桩进行连接,实现了可以方便的对上混凝土桩和下混凝土桩进行连接;(2) By being provided with an outer frame, a connecting frame, a connecting threaded rod, a baffle plate, a fixing bolt and a supporting plate, when the upper concrete pile and the lower concrete pile need to be connected, the outer frame at one end of the upper concrete pile and the lower concrete pile is pasted together, and then the connecting threaded rod is passed through the inside of the through hole at one end of the connecting frame, and the baffle plate outside the connecting threaded rod is attached to one end of the connecting frame, and the fixing bolts are sleeved on the two ends outside the connecting threaded rod. The upper concrete pile and the lower concrete pile are connected, so that the upper concrete pile and the lower concrete pile can be connected conveniently;
(3)通过设置有第一内框、外框、第二内框、定位孔、定位槽、定位框和定位插块,该结构的第一内框外部固定有定位框,定位框与上混凝土桩和下混凝土桩内部开设的定位槽相连接,可以提高第一内框与上混凝土桩和下混凝土桩之间连接的牢固性,且外框内部的定位插块与定位孔连接,可以提高外框与上混凝土桩和下混凝土桩之间的牢固性,实现了可以提高连接组件与上混凝土桩和下混凝土桩之间连接的稳定性。(3) By being provided with a first inner frame, an outer frame, a second inner frame, a positioning hole, a positioning groove, a positioning frame and a positioning insert, the first inner frame of the structure is fixed with a positioning frame outside, and the positioning frame is connected with the positioning groove provided inside the upper concrete pile and the lower concrete pile, which can improve the firmness of the connection between the first inner frame and the upper concrete pile and the lower concrete pile, and the positioning inserts inside the outer frame are connected with the positioning holes, which can improve the firmness between the outer frame and the upper concrete pile and the lower concrete pile, and realize that the connection assembly can be improved with the upper concrete pile and the lower concrete pile Stability of connections between piles.
附图说明Description of drawings
图1为本实用新型的正视剖面结构示意图;Fig. 1 is the front view sectional structure schematic diagram of the utility model;
图2为本实用新型的连接框仰视结构示意图;Fig. 2 is the structural schematic diagram of the connection frame of the present utility model looking up;
图3为本实用新型的图1中A处局部剖面放大结构示意图;Fig. 3 is a schematic diagram of a partial section enlarged structure at A in Fig. 1 of the present utility model;
图4为本实用新型的第二内框俯视结构示意图。Fig. 4 is a schematic top view structure diagram of the second inner frame of the present invention.
图中:1、上混凝土桩;2、限位插槽;3、第一内框;4、外框;5、连接框;6、连接螺纹杆;7、挡板;8、第二内框;9、限位插销;10、下混凝土桩;11、固定螺栓;12、支撑板;13、通孔;14、定位孔;15、定位槽;16、定位框;17、定位插块。Among the figure: 1, upper concrete pile; 2, limit slot; 3, first inner frame; 4, outer frame; 5, connecting frame; 6, connecting threaded rod; 7, baffle plate; 8, second inner frame; 9, limit bolt;
具体实施方式Detailed ways
下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. example. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.
实施例1:请参阅图1-4,一种装配式混凝土预制框架,包括上混凝土桩1和下混凝土桩10,上混凝土桩1的底端设置有下混凝土桩10,上混凝土桩1内部的底端固定连接有第一内框3,下混凝土桩10内部的顶端固定连接有第二内框8;Embodiment 1: Please refer to Fig. 1-4, an assembled concrete prefabricated frame includes an upper concrete pile 1 and a lower concrete pile 10, the bottom of the upper concrete pile 1 is provided with a lower concrete pile 10, the bottom of the upper concrete pile 1 is fixedly connected with a first inner frame 3, and the top of the lower concrete pile 10 is fixedly connected with a second inner frame 8;
第一内框3的底端开设有限位插槽2,第二内框8的顶端固定连接有限位插销9,限位插销9与限位插槽2活动连接,第一内框3与第二内框8活动连接,第一内框3的底端和第二内框8的顶端分别固定连接有一组外框4;The bottom of the first inner frame 3 is provided with a limit slot 2, the top of the second inner frame 8 is fixedly connected with a limit pin 9, the limit pin 9 is movably connected with the limit slot 2, the first inner frame 3 is movably connected with the second inner frame 8, and a group of outer frames 4 are respectively fixedly connected to the bottom of the first inner frame 3 and the top of the second inner frame 8;
第一内框3底端开设的限位插槽2呈等间距排布,第二内框8顶端固定的限位插销9呈等间距排布;The limit slots 2 provided at the bottom of the first inner frame 3 are arranged at equal intervals, and the limit pins 9 fixed at the top of the second inner frame 8 are arranged at equal intervals;
具体地,如图1、图2和图4所示,在对上混凝土桩1和下混凝土桩10进行连接时,将上混凝土桩1安装在下混凝土桩10的顶端,并使上混凝土桩1内部的第一内框3和下混凝土桩10内部的第二内框8相贴合,同时第二内框8顶端的限位插销9会插入第一内框3底端的限位插槽2内部,从而通过限位插槽2和限位插销9对第一内框3和第二内框8进入,以防止上混凝土桩1和下混凝土桩10在连接之后出现错位,实现了可以有效对上混凝土桩1和下混凝土桩10定位,防止安装后错位影响建筑强度。Specifically, as shown in Fig. 1, Fig. 2 and Fig. 4, when the upper concrete pile 1 and the lower concrete pile 10 are connected, the upper concrete pile 1 is installed on the top of the lower concrete pile 10, and the first inner frame 3 inside the upper concrete pile 1 and the second inner frame 8 inside the lower concrete pile 10 are fitted together. , to prevent the dislocation of the upper concrete pile 1 and the lower concrete pile 10 after the connection, realize the effective positioning of the upper concrete pile 1 and the lower concrete pile 10, and prevent the dislocation after installation from affecting the building strength.
实施例2:外框4外部的一端固定连接有连接框5,连接框5一端的四个拐角处分别开设有一组通孔13,通孔13的内部活动连接有连接螺纹杆6,连接螺纹杆6外部的两端分别固定连接有一组挡板7,挡板7与连接框5活动连接,连接框5一端的四个拐角分别活动连接有一组固定螺栓11,连接框5的一端固定连接有支撑板12,支撑板12与外框4固定连接;Example 2: One end of the outer frame 4 is fixed with the connection box 5, and the four corners of the connection box 5 are opened with a set of pores 13. The internal activity connection of the pores 13 is connected to the threaded pole 6. The four corners are connected to a set of fixed bolts 11, a fixed connection connection of the connection box 5 has a support board 12, the support board 12 and the outer frame 4 are fixed;
固定螺栓11与连接螺纹杆6螺纹连接,连接框5的中心线与外框4的中心线在同一垂直面上;The fixing bolt 11 is threadedly connected with the connecting threaded rod 6, and the centerline of the connecting frame 5 and the centerline of the outer frame 4 are on the same vertical plane;
具体地,如图1和图2所示,在需要对上混凝土桩1和下混凝土桩10进行连接时,将上混凝土桩1和下混凝土桩10一端的外框4贴合在一起,之后将连接螺纹杆6穿过连接框5一端的通孔13的内部,并使连接螺纹杆6外部的挡板7贴合在连接框5的一端,并将固定螺栓11套接在连接螺纹杆6外部的两端,固定螺栓11可以通过连接螺纹杆6对两组连接框5进行连接,从而通过外框4对上混凝土桩1和下混凝土桩10进行连接,实现了可以方便的对上混凝土桩1和下混凝土桩10进行连接。Specifically, as shown in Figures 1 and 2, when the upper concrete pile 1 and the lower concrete pile 10 need to be connected, the outer frame 4 at one end of the upper concrete pile 1 and the lower concrete pile 10 is pasted together, and then the connecting threaded rod 6 is passed through the inside of the through hole 13 at one end of the connecting frame 5, and the baffle plate 7 outside the connecting threaded rod 6 is attached to one end of the connecting frame 5, and the fixing bolts 11 are sleeved on both ends of the connecting threaded rod 6. The fixing bolts 11 can be connected to two groups of connecting frames 5 through the connecting threaded rod 6. , so that the upper concrete pile 1 and the lower concrete pile 10 are connected through the outer frame 4, so that the upper concrete pile 1 and the lower concrete pile 10 can be connected conveniently.
实施例3:第一内框3外部的一端固定连接有定位框16,上混凝土桩1和下混凝土桩10的内部分别开设有一组定位槽15,外框4的内部固定连接有定位插块17,上混凝土桩1和下混凝土桩10的外部开设有定位孔14,定位插块17与定位孔14固定连接,定位框16与定位槽15固定连接;Embodiment 3: One end outside the first inner frame 3 is fixedly connected with a positioning frame 16, the inside of the upper concrete pile 1 and the lower concrete pile 10 are respectively provided with a set of positioning grooves 15, the inside of the outer frame 4 is fixedly connected with a positioning plug 17, the outside of the upper concrete pile 1 and the lower concrete pile 10 is provided with a positioning hole 14, the positioning plug 17 is fixedly connected with the positioning hole 14, and the positioning frame 16 is fixedly connected with the positioning groove 15;
定位框16的中心线与第一内框3的中心线在同一垂直面上,外框4内部的定位插块17呈等间距排布;The centerline of the positioning frame 16 is on the same vertical plane as the centerline of the first inner frame 3, and the positioning inserts 17 inside the outer frame 4 are arranged at equal intervals;
具体地,如图1、图2和图3所示,该结构的第一内框3外部固定有定位框16,定位框16与上混凝土桩1和下混凝土桩10内部开设的定位槽15相连接,可以提高第一内框3与上混凝土桩1和下混凝土桩10之间连接的牢固性,且外框4内部的定位插块17与定位孔14连接,可以提高外框4与上混凝土桩1和下混凝土桩10之间的牢固性,实现了可以提高连接组件与上混凝土桩1和下混凝土桩10之间连接的稳定性。Specifically, as shown in Fig. 1, Fig. 2 and Fig. 3, the outside of the first inner frame 3 of this structure is fixed with a positioning frame 16, and the positioning frame 16 is connected with the positioning groove 15 provided inside the upper concrete pile 1 and the lower concrete pile 10, which can improve the fastness of the connection between the first inner frame 3 and the upper concrete pile 1 and the lower concrete pile 10, and the positioning plug 17 inside the outer frame 4 is connected with the positioning hole 14, which can improve the stability between the outer frame 4 and the upper concrete pile 1 and the lower concrete pile 10. Stability of the connection between the upper concrete pile 1 and the lower concrete pile 10.
工作原理:本实用新型在使用时,首先,在需要对上混凝土桩1和下混凝土桩10进行连接时,将上混凝土桩1和下混凝土桩10一端的外框4贴合在一起,之后将连接螺纹杆6穿过连接框5一端的通孔13的内部,并使连接螺纹杆6外部的挡板7贴合在连接框5的一端,并将固定螺栓11套接在连接螺纹杆6外部的两端,固定螺栓11可以通过连接螺纹杆6对两组连接框5进行连接,从而通过外框4对上混凝土桩1和下混凝土桩10进行连接,在对上混凝土桩1和下混凝土桩10进行连接时,将上混凝土桩1安装在下混凝土桩10的顶端,并使上混凝土桩1内部的第一内框3和下混凝土桩10内部的第二内框8相贴合,同时第二内框8顶端的限位插销9会插入第一内框3底端的限位插槽2内部,从而通过限位插槽2和限位插销9对第一内框3和第二内框8进入,以防止上混凝土桩1和下混凝土桩10在连接之后出现错位,该结构的第一内框3外部固定有定位框16,定位框16与上混凝土桩1和下混凝土桩10内部开设的定位槽15相连接,可以提高第一内框3与上混凝土桩1和下混凝土桩10之间连接的牢固性,且外框4内部的定位插块17与定位孔14连接,可以提高外框4与上混凝土桩1和下混凝土桩10之间的牢固性。Working principle: when the utility model is in use, firstly, when the upper concrete pile 1 and the lower concrete pile 10 need to be connected, the outer frame 4 at one end of the upper concrete pile 1 and the lower concrete pile 10 is pasted together, and then the connecting threaded rod 6 is passed through the inside of the through hole 13 at one end of the connecting frame 5, and the baffle 7 outside the connecting threaded rod 6 is attached to one end of the connecting frame 5, and the fixing bolts 11 are sleeved on both ends of the connecting threaded rod 6. The fixing bolts 11 can be connected to two groups of connecting frames through the connecting threaded rod 6 5 to connect the upper concrete pile 1 and the lower concrete pile 10 through the outer frame 4. When the upper concrete pile 1 and the lower concrete pile 10 are connected, the upper concrete pile 1 is installed on the top of the lower concrete pile 10, and the first inner frame 3 inside the upper concrete pile 1 and the second inner frame 8 inside the lower concrete pile 10 fit together, and the limit pin 9 at the top of the second inner frame 8 will be inserted into the limit slot 2 at the bottom of the first inner frame 3. The inner frame 3 and the second inner frame 8 enter to prevent the upper concrete pile 1 and the lower concrete pile 10 from being misaligned after being connected. The first inner frame 3 of the structure is fixed with a positioning frame 16 outside. Firmness between piles 10.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202320875273.5U CN219386639U (en) | 2023-04-19 | 2023-04-19 | Prefabricated frame of assembled concrete |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202320875273.5U CN219386639U (en) | 2023-04-19 | 2023-04-19 | Prefabricated frame of assembled concrete |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN219386639U true CN219386639U (en) | 2023-07-21 |
Family
ID=87166192
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202320875273.5U Expired - Fee Related CN219386639U (en) | 2023-04-19 | 2023-04-19 | Prefabricated frame of assembled concrete |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN219386639U (en) |
-
2023
- 2023-04-19 CN CN202320875273.5U patent/CN219386639U/en not_active Expired - Fee Related
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN207794465U (en) | A kind of assembled stair for building | |
| CN113482152A (en) | Assembled steel node | |
| CN111677107A (en) | A new type of assembled connection node | |
| CN219386639U (en) | Prefabricated frame of assembled concrete | |
| CN207131089U (en) | A kind of aluminum dipping form board supporting structure | |
| CN219138358U (en) | External corner template fixing assembly for shear wall pouring | |
| CN215564447U (en) | Reinforcing die of windowsill coping template | |
| CN223281656U (en) | Wind-resistant scaffolding for construction | |
| CN219175923U (en) | A construction engineering protection net with high structural strength | |
| CN223497550U (en) | A reinforced plastic building formwork | |
| CN216405701U (en) | A prefabricated steel structure frame | |
| CN221810748U (en) | Wallboard support frame is used in shed installation | |
| CN217420650U (en) | A triangular independent support device | |
| CN215253645U (en) | Building construction assembled shear wall structure | |
| CN216766252U (en) | Cross-floor and cross-column rod piece structure in steel structure assembly type house | |
| CN224016592U (en) | A connection device for steel structure curtain walls | |
| CN219451063U (en) | High wind pressure regional tower crown convenient to vertical transportation | |
| CN215631681U (en) | Plugging mold for grouting of assembled PC wall | |
| CN217537341U (en) | A positioning connection structure of a prefabricated structure | |
| CN219011536U (en) | Adjacent wallboard connecting structure for assembled building | |
| CN212154133U (en) | External angle and building formwork system using the same | |
| CN219826119U (en) | Steel-plastic combined template for concrete decorative column | |
| CN222771635U (en) | Lattice column connection structure | |
| CN217268167U (en) | Stable device of regional dimension of steel house room wall dog-ear | |
| CN223414822U (en) | Truss type connecting piece |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20230721 |