CN219384250U - Paying-off auxiliary equipment for cable construction - Google Patents

Paying-off auxiliary equipment for cable construction Download PDF

Info

Publication number
CN219384250U
CN219384250U CN202222961929.3U CN202222961929U CN219384250U CN 219384250 U CN219384250 U CN 219384250U CN 202222961929 U CN202222961929 U CN 202222961929U CN 219384250 U CN219384250 U CN 219384250U
Authority
CN
China
Prior art keywords
movable block
auxiliary equipment
spool
groups
cable construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222961929.3U
Other languages
Chinese (zh)
Inventor
方家文
吴伟
叶海青
汪海红
张志伟
王洁莹
汪育良
杜勇
王荀勇
罗丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuancheng Nantian Power Engineering Co ltd Ningguo Kaiyuan Branch
Original Assignee
Ningguo Power Supply Co of State Grid Anhui Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningguo Power Supply Co of State Grid Anhui Electric Power Co Ltd filed Critical Ningguo Power Supply Co of State Grid Anhui Electric Power Co Ltd
Priority to CN202222961929.3U priority Critical patent/CN219384250U/en
Application granted granted Critical
Publication of CN219384250U publication Critical patent/CN219384250U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/50Reuse, recycling or recovery technologies
    • Y02W30/82Recycling of waste of electrical or electronic equipment [WEEE]

Landscapes

  • Storing, Repeated Paying-Out, And Re-Storing Of Elongated Articles (AREA)

Abstract

The utility model discloses paying-off auxiliary equipment for cable construction, which comprises a base and a fixed seat, wherein a handle is arranged on the right side of the base, a reciprocating screw rod is arranged on the left side of the handle, a movable block is arranged outside the reciprocating screw rod, a limiting block is arranged at the bottom of the movable block and is positioned in a limiting groove, a shell of a roller is arranged at the top of the movable block, a spool is arranged above the roller, a clamping column is arranged on the left side of the spool, a rotating rod is arranged at the left end of the clamping column, a driven wheel is arranged outside the rotating rod, and a speed change gear set is arranged below the driven wheel. The paying-off work can be accelerated according to the work requirement, the work of rotating can be completed without the need of using huge effort by workers or the joint of a plurality of workers, the labor capacity of the workers is reduced, and the labor is saved, so that the practicability is enhanced.

Description

Paying-off auxiliary equipment for cable construction
Technical Field
The utility model relates to the technical field of cable construction, in particular to paying-off auxiliary equipment for cable construction.
Background
As is known, a cable is generally a rope-like cable formed by several or several groups of wires [ each group of at least two twisted wires, each group of wires is insulated from each other, an insulated wire formed by arranging one or more conductive wire cores insulated from each other in a sealed sheath, and is often twisted around a center, the whole outside is covered with a highly insulating cover layer, and the whole is erected in the air or underground or under the water for telecommunication or power transmission, distribution of electric energy or transmission of electric signals, and the difference between the cable and a common wire is mainly that the cable is large in size and complex in structure, so that the cable needs to be used as auxiliary equipment in the field of construction when paying off, and thus a paying-off auxiliary equipment for cable construction is needed;
the existing paying-off auxiliary equipment for cable construction comprises a spool and a bracket, wherein U-shaped grooves are formed in the middle of the left side and the right side of the top end of the bracket, and the left end and the right end of the spool are respectively clamped with the two groups of U-shaped grooves; when the existing paying-off auxiliary equipment for cable construction is used, a bracket is required to be put at a designated position, then a spool is put on the bracket by using a carrying tool, and finally a worker drags one end to move and rotates the spool to carry out paying-off operation when required;
however, the conventional paying-off auxiliary equipment for cable construction generally has the following problems when in use;
1. when the spool is too heavy, the spool needs to consume huge effort or a plurality of workers need to normally finish the rotation, so that the manpower is wasted, the labor capacity of the workers is too great, and the body is damaged to a certain extent, so that the practicability is poor;
2. the distance between the bobbins is determined according to the length of the cable and the number of turns of the winding, and the distance of the drum arranged by the existing paying-off auxiliary equipment for cable construction cannot be adjusted, so that the paying-off auxiliary equipment is only suitable for paying-off operation of the cable wound by the bobbins with fixed distance, and has certain limitation.
Disclosure of Invention
The utility model aims to provide paying-off auxiliary equipment for cable construction, which is used for solving the problems that the prior paying-off auxiliary equipment for cable construction in the market is poor in practicability because the distance between bobbins is determined according to the length of a cable and the number of turns of winding, and a roller arranged by the prior paying-off auxiliary equipment for cable construction cannot be used for distance adjustment, so that the paying-off auxiliary equipment is only suitable for paying-off work of a cable wound by bobbins with fixed distance and has certain limitation because the bobbins are too heavy and require a plurality of workers to normally finish rotation when the bobbins rotate, so that manpower is wasted and the labor capacity of the workers is too great.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides a unwrapping wire auxiliary assembly for cable construction, includes base and fixing base, the right side of base is provided with the handle, and the left side of handle is provided with reciprocating screw, reciprocating screw's outside is provided with movable block, and the bottom of movable block is provided with the stopper to the stopper is located the inside of spacing groove, the top of movable block is provided with the shell of cylinder, and the top of cylinder is provided with the spool, the left side of spool is provided with the card post, and the left end of card post is provided with the bull stick, the outside of bull stick is provided with from the driving wheel, and the below from the driving wheel is provided with gear set, gear set's below is provided with the gear, and the left side of gear is provided with the motor, the motor is located the inside of installing the shell.
Preferably, the movable block is in threaded connection with the reciprocating screw rod, the length of the multifilament rod is greater than two thirds of the length of the base, the movable block and the limiting block are of an integrated structure, the limiting block and the limiting groove are of an integrated structure, and the length of the limiting groove is greater than the length of the multifilament rod.
Preferably, the movable block is fixedly connected with the shell of the roller, 2 groups of rollers are arranged on the roller, the 2 groups of rollers are identical in size, the 2 groups of rollers are symmetrically distributed, and the surfaces of the 2 groups of rollers are made of smooth materials.
Preferably, the bottom of fixing base is provided with the slider, and the slider is located the spout inside, slider and spout constitute sliding structure, and the spout is provided with 2 groups to 2 groups of spouts are about the horizontal center pin symmetric distribution of spacing groove.
Preferably, the fixing base top is provided with the installation shell, and fixing base and installation shell are fixed connection, the fixing base inner wall is connected with the bull stick through the bearing, and bull stick and card post are fixed connection, card post and the inside draw-in groove of horizontal spool block each other.
Preferably, the gear is intermeshed with a pinion gear of the speed change gear set, and the pinion gear and the bull gear are coaxially rotated, and the bull gear of the speed change gear set is intermeshed with the driven wheel.
Compared with the prior art, the utility model has the beneficial effects that: the paying-off auxiliary equipment for the cable construction is arranged;
1. the position of the installation shell is adjusted through the sliding structure of the sliding block at the bottom of the fixing seat and the sliding groove, so that the clamping column is better clamped and fixed with the clamping groove in the spool, the adjustment is performed according to the spool position, the motor is used for driving the gear to be meshed with the speed change gear set for rotation, meanwhile, the speed change gear set is meshed with the driven wheel for rotation, the driven wheel drives the inner rotating rod to rotate, and the rotating rod is fixedly connected with the clamping column, so that the spool can be driven to perform the speed change gear set for paying off operation, the paying off operation can be accelerated according to the working requirement, the work of rotation can be completed without the need of using huge effort by workers or the labor capacity of multiple workers together, the labor is saved, and the practicability is enhanced;
2. through staff's rotation handle drive for drive two sets of cylinders through reciprocating lead screw threaded connection's movable block and remove in opposite directions, thereby can adjust according to the distance between the spool of cable length winding, thereby make the cylinder be applicable to the unwrapping wire work of multiple spool, application scope enlarges, and it is comparatively convenient to operate.
Drawings
FIG. 1 is a schematic diagram of the overall front cross-sectional structure of the present utility model;
FIG. 2 is a schematic side sectional view of the present utility model;
FIG. 3 is a schematic top view of the drum and base of the present utility model;
FIG. 4 is a schematic top view of the bobbin driving structure and base of the present utility model;
FIG. 5 is a schematic side view of the clamping groove of the clamping column and the spool.
In the figure: 1. a base; 2. a spool; 3. a roller; 4. a movable block; 5. a reciprocating screw rod; 6. a handle; 7. a limiting block; 8. a limit groove; 9. a chute; 10. a slide block; 11. a fixing seat; 12. a motor; 13. a gear; 14. a speed change gear set; 15. driven wheel; 16. a rotating rod; 17. a clamping column; 18. and (5) mounting the shell.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1-5, the present utility model provides a technical solution: the utility model provides a unwrapping wire auxiliary assembly for cable construction, including base 1 and fixing base 11, the right side of base 1 is provided with handle 6, and the left side of handle 6 is provided with reciprocating screw 5, the outside of reciprocating screw 5 is provided with movable block 4, and the bottom of movable block 4 is provided with stopper 7, and stopper 7 is located the inside of spacing groove 8, the top of movable block 4 is provided with the shell of cylinder 3, and the top of cylinder 3 is provided with spool 2, the left side of spool 2 is provided with card post 17, and the end of card post 17 is provided with bull stick 16, the outside of bull stick 16 is provided with from driving wheel 15, and the below from driving wheel 15 is provided with gear set 14, gear 13 is provided with to the below of gear set 14, and the left side of gear 13 is provided with motor 12, motor 12 is located the inside of installation shell 18.
The movable block 4 is in threaded connection with the reciprocating screw rod 5, the length of the reciprocating screw rod 5 is greater than two thirds of the length of the base 1, the movable block 4 and the limiting block 7 are of an integrated structure, the limiting block 7 and the limiting groove 8 are of an integrated structure, and the length of the limiting groove 8 is greater than the length of the reciprocating screw rod 5, so that the roller 3 can perform position adjustment better;
the movable block 4 is fixedly connected with the shell of the roller 3, the roller 3 is provided with 2 groups, the 2 groups of rollers 3 have the same size, the 2 groups of rollers 3 are symmetrically distributed, and the surfaces of the 2 groups of rollers 3 are made of smooth materials, so that the spool paying-off is more labor-saving;
the bottom of the fixed seat 11 is provided with the sliding block 10, the sliding block 10 is positioned in the sliding groove 9, the sliding block 10 and the sliding groove 9 form a sliding structure, the sliding groove 9 is provided with 2 groups, and the 2 groups of sliding grooves 9 are symmetrically distributed about the transverse central axis of the limit groove 8, so that the driving structure of the spool 2 can be more convenient to adjust along with the different positions and the different sizes of the spool 2;
the top of the fixed seat 11 is provided with a mounting shell 18, the fixed seat 11 is fixedly connected with the mounting shell 18, the inner wall of the fixed seat 11 is connected with the rotating rod 16 through a bearing, the rotating rod 16 is fixedly connected with the clamping column 17, and the clamping column 17 is mutually clamped with a clamping groove in the transverse spool 2, so that the spool 2 is stably driven by a driving structure to carry out paying-off work, and falling is avoided;
the gear 13 is meshed with a pinion of the speed change gear set 14, the pinion and the large gear rotate coaxially, the large gear of the speed change gear set 14 is meshed with the driven wheel 15, and the speed change gear can be adjusted according to the requirement of paying-off speed, so that the operation is very convenient;
working principle: when the auxiliary paying-off equipment for cable construction is used, firstly, the equipment is moved to a position required by a user, then the position of the roller 3 is adjusted according to the distance between the two vertical bobbins 2, the handle 6 is driven by manual rotation of the handle 6 by a worker, the reciprocating screw rod 5 is driven by the handle 6 to be in threaded connection with the movable block 4 to rotate, meanwhile, the movable block 4 slides in the limit groove 8 through the limit block 7 to carry out position adjustment, the movable block 4 drives the roller 3 integrated shell to move and adjust the position because the movable block 4 is fixedly connected with the bottom of the roller 3 shell, and the distance between the two groups of rollers 3 is equal to the distance between the two groups of vertical bobbins 2, because the contact surface of the handle 6 and the reciprocating screw rod 5 is of a polygonal structure and is made of rough material, the reciprocating screw rod is fixed without driving force, at this time, the staff is placed on the two groups of rollers 3 through the spool 2 wound by the cable, then the staff slides in the chute 9 by pushing the slide block 10 with the integrated structure at the bottom of the fixed seat 11, so that the clamping post 17 and the clamping groove inside the transverse spool 2 are mutually clamped and fixed, as the surface of the clamping post 17 is provided with a plurality of groups of bumps made of rough materials, the clamping groove is convenient to clamp and firm, finally, the motor 12 is driven by the starting motor 12, the motor 12 drives the gear 13 to rotate in meshed mode with the speed-changing gear set 14 through the rotating rod 16 connected at the top, meanwhile, the speed-changing gear set 14 rotates in meshed mode with the driven wheel 15, the driven wheel 15 drives the clamping post 17 fixedly connected with the rotating rod 16 to rotate, and the clamping post 17 and the spool 2 are clamped and firm, so that the transverse spool 2 is driven to rotate, thereby the paying-off process is realized, the operation is very convenient, what is not described in detail in this specification is prior art known to those skilled in the art.
Although the present utility model has been described with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described, or equivalents may be substituted for elements thereof, and any modifications, equivalents, improvements and changes may be made without departing from the spirit and principles of the present utility model.

Claims (6)

1. Paying-off auxiliary equipment for cable construction comprises a base (1) and a fixing seat (11), and is characterized in that: the right side of base (1) is provided with handle (6), and the left side of handle (6) is provided with reciprocating screw (5), the outside of reciprocating screw (5) is provided with movable block (4), and the bottom of movable block (4) is provided with stopper (7) to stopper (7) are located the inside of spacing groove (8), the top of movable block (4) is provided with the shell of cylinder (3), and the top of cylinder (3) is provided with spool (2), the left side of spool (2) is provided with card post (17), and the left end of card post (17) is provided with bull stick (16), the outside of bull stick (16) is provided with from driving wheel (15), and the below from driving wheel (15) is provided with gear set (14), the below of gear set (14) is provided with gear (13), and the left side of gear (13) is provided with motor (12), motor (12) are located the inside of installing shell (18).
2. The pay-off auxiliary equipment for cable construction according to claim 1, wherein: the movable block (4) is in threaded connection with the reciprocating screw rod (5), the length of the reciprocating screw rod (5) is greater than two thirds of the length of the base (1), the movable block (4) and the limiting block (7) are of an integrated structure, the limiting block (7) and the limiting groove (8) are of an integrated structure, and the length of the limiting groove (8) is greater than the length of the reciprocating screw rod (5).
3. The pay-off auxiliary equipment for cable construction according to claim 1, wherein: the movable block (4) is fixedly connected with the shell of the roller (3), the roller (3) is provided with 2 groups, the 2 groups of rollers (3) are identical in size, the 2 groups of rollers (3) are symmetrically distributed, and the surfaces of the 2 groups of rollers (3) are made of smooth materials.
4. The pay-off auxiliary equipment for cable construction according to claim 1, wherein: the bottom of fixing base (11) is provided with slider (10), and slider (10) are located inside spout (9), slider (10) and spout (9) constitute sliding structure, and spout (9) are provided with 2 groups to 2 groups of spouts (9) are about spacing groove (8) horizontal center pin symmetry distribution.
5. The pay-off auxiliary equipment for cable construction according to claim 1, wherein: the utility model discloses a transverse spool (2) is characterized in that an installation shell (18) is arranged at the top of the fixed seat (11), the fixed seat (11) is fixedly connected with the installation shell (18), the inner wall of the fixed seat (11) is connected with a rotating rod (16) through a bearing, the rotating rod (16) is fixedly connected with a clamping column (17), and the clamping column (17) is mutually clamped with a clamping groove in the transverse spool (2).
6. The pay-off auxiliary equipment for cable construction according to claim 1, wherein: the gear (13) is meshed with a pinion of the speed change gear set (14), the pinion and the bull gear rotate coaxially, and the bull gear of the speed change gear set (14) is meshed with the driven wheel (15).
CN202222961929.3U 2022-11-07 2022-11-07 Paying-off auxiliary equipment for cable construction Active CN219384250U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222961929.3U CN219384250U (en) 2022-11-07 2022-11-07 Paying-off auxiliary equipment for cable construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222961929.3U CN219384250U (en) 2022-11-07 2022-11-07 Paying-off auxiliary equipment for cable construction

Publications (1)

Publication Number Publication Date
CN219384250U true CN219384250U (en) 2023-07-21

Family

ID=87165888

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222961929.3U Active CN219384250U (en) 2022-11-07 2022-11-07 Paying-off auxiliary equipment for cable construction

Country Status (1)

Country Link
CN (1) CN219384250U (en)

Similar Documents

Publication Publication Date Title
CN110589609A (en) Winding device for aluminum high-voltage wire
CN213568871U (en) Cable processing is with pulling take-up device
CN216311447U (en) Cable production stranded conductor device
CN110038980A (en) A kind of wire and cable smoothes out with the fingers straight cutter machine
CN106876047A (en) A kind of cable produces stranded wire apparatus
CN111599534A (en) Cable tubular stranded conductor device is used in processing of five metals alternating current equipment
CN212769112U (en) Galvanized steel wire rope production is with winding equipment of getting and putting of being convenient for
CN112660922A (en) Coiling mechanism for cable manufacture
CN219384250U (en) Paying-off auxiliary equipment for cable construction
CN213923574U (en) Tension control device of winding equipment for cable production
CN216971575U (en) Cable processing winding equipment with positioning and stopping functions
CN217769285U (en) Wire arranging device for cable laying
CN113690795B (en) 220 kilovolt transmission line wire repairing device
CN212387448U (en) Electric power construction kinking device
CN211310401U (en) Automatic wire arranging device suitable for cable production
CN209052226U (en) Drawing cable clamping device and drawing cable equipment
CN216889512U (en) Cable reel convenient to cable storage is stacked
CN220201055U (en) Take-up and pay-off mechanism for power transmission and distribution
CN214152564U (en) A high-efficient stranded conductor device for cable production and processing
CN220702921U (en) Vertical reel of cable
CN212953505U (en) Winding equipment for processing cable for power engineering
CN219971502U (en) Cable winding and unwinding devices
CN212799102U (en) Pay-off rack for electric power construction
CN215815299U (en) Novel withstand voltage tensile cable armor is with steel band clad structure
CN214053515U (en) Cable cutting device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20231009

Address after: Building 2, No. 22 Shuanglong Lane, Jinhe West Road, Ningguo City, Xuancheng City, Anhui Province, 242300

Patentee after: Xuancheng Nantian Power Engineering Co.,Ltd. Ningguo Kaiyuan Branch

Address before: 242300 No.17, Qinghua East Road, Ningguo City, Xuancheng City, Anhui Province

Patentee before: STATE GRID ANHUI ELECTRIC POWER CO., LTD., NINGGUO POWER SUPPLY Co.

TR01 Transfer of patent right