CN219343912U - Building construction platform - Google Patents

Building construction platform Download PDF

Info

Publication number
CN219343912U
CN219343912U CN202320453631.3U CN202320453631U CN219343912U CN 219343912 U CN219343912 U CN 219343912U CN 202320453631 U CN202320453631 U CN 202320453631U CN 219343912 U CN219343912 U CN 219343912U
Authority
CN
China
Prior art keywords
groove
building construction
construction platform
spring
sliding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320453631.3U
Other languages
Chinese (zh)
Inventor
赵安合
胡海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202320453631.3U priority Critical patent/CN219343912U/en
Application granted granted Critical
Publication of CN219343912U publication Critical patent/CN219343912U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Ladders (AREA)

Abstract

The utility model discloses a building construction platform, which relates to the technical field of building construction and comprises a building construction platform, wherein two sliding grooves are formed in the top of the building construction platform, the structures in the two sliding grooves are the same, a safety protection mechanism is arranged in each sliding groove, the safety protection mechanism comprises sliding bars, the sliding bars are fixedly connected in the sliding grooves, the surfaces of the sliding bars are slidably connected with moving plates, workers move to the edges of the building construction platform, and then the moving plates are stepped on to finally enable the extending plates to pop out of the moving grooves under the action of the elastic force of third springs, so that the protection height of guardrails on the building construction platform is effectively prolonged, the workers can efficiently pop out of the extending plates when working to the edges of the building construction platform, the protection effect of the workers is achieved, the safety coefficient of the workers in working on the building construction platform is effectively improved, and the use completeness of the whole device is further improved.

Description

Building construction platform
Technical Field
The utility model relates to the technical field of building construction, in particular to a building construction platform.
Background
The building construction platform refers to peripheral protection facilities which are operated by workers and are erected for vertical and horizontal transportation at a construction site, and the general term of the building world refers to places which cannot be directly constructed when the building platform is used on an outer wall, an inner decoration or a high storey height.
In the work of construction, need use the construction platform to provide the mode of being convenient for to the workman to provide comparatively convenient to construction process, in the use of current construction platform, for the workman of being convenient for carry out construction operation in the eminence, construction platform's protection railing can not be too high, for preventing to block workman's operation sight, however, when the workman is under construction, because the too serious can not voluntarily remove to construction platform's edge position of work, when current construction platform does not possess the ability of carrying out safety protection warning to the workman this moment, at this moment because self construction platform's guardrail height is lower, and then probably cause the workman to take care of the risk that causes the slope from construction platform, at this moment then can reduce workman's factor of safety in using construction platform, further reduce construction platform's safety protection performance and the perfection in use.
Disclosure of Invention
The utility model aims to at least solve one of the technical problems in the prior art and can solve the problems proposed by the background art.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the building construction platform comprises a building construction platform, wherein two sliding grooves are formed in the top of the building construction platform, the structures in the two sliding grooves are identical, and a safety protection mechanism is arranged in each sliding groove;
the safety protection mechanism comprises a sliding rod, the sliding rod is fixedly connected with the inside of the sliding groove, a moving plate is connected to the surface of the sliding rod in a sliding manner, the left side of the top of the moving plate is an inclined surface, a first spring is movably sleeved on the surface of the sliding rod, and two ends of the first spring are fixedly connected between the moving plate and the sliding groove respectively.
Preferably, the right side of spout has seted up the removal groove, and the inside rotation of removal groove is connected with the pivot, and the top fixedly connected with rotor plate of pivot rotates in the spout.
Preferably, the right side fixedly connected with push pedal of pivot, the push pedal rotates in the inside of removing the groove and connects, and the surface activity of pivot has cup jointed the second spring, and the both ends of second spring are fixed connection respectively between pivot and spout.
Preferably, the extension plate is slidably connected in the moving groove, the top of the moving groove extends to the top of the building construction platform, and the extension plate and the moving groove are both in a shape of Chinese character 'zhong'.
Preferably, the surface activity of extension board has cup jointed the third spring, and the both ends of third spring are fixed connection respectively between extension board and removal groove, and the draw-in groove has been seted up on the right side of extension board.
Preferably, the right wall of the movable groove is provided with a groove, a clamping block is connected in the groove in a sliding manner, one side, far away from the groove, of the clamping block is semicircular and is matched with the clamping groove in shape, and a fourth spring is fixedly connected between the clamping block and the groove.
Compared with the prior art, the utility model has the beneficial effects that:
(1) This building construction platform removes to building construction platform's edge through the workman, and then finally makes the extension board pop out from the shifting chute under the elasticity effect of third spring through stepping on the movable plate, and then effectually prolonged the protection height of guardrail on the building construction platform, make the workman can be effectual pop out through the extension board and then play the effect of protection to the workman when working to building construction platform edge, the effectual factor of safety who has improved the workman in work on building construction platform, further improved the use perfection of whole device in use.
(2) This building construction platform, because the top left side of movable plate is the inclined plane, and then when the workman removes to building construction platform's edge, can be more smooth step on the top of movable plate, prevent that the movable plate from causing the influence to the removal of workman when not using, effectually improved the stability of workman work on building construction platform.
(3) This construction platform, because the fixture block is kept away from the shape of recess and draw-in groove and is semicircle form and identical, and then when the fixture block removes to reset to the draw-in groove inside, can be more smoothly enter into the inside of draw-in groove, the effectual extension board that prevents produces the condition of card dun when resetting, has further improved the smoothness nature of whole device in operation.
Drawings
The utility model is further illustrated by the following examples in conjunction with the accompanying drawings:
FIG. 1 is a schematic view of a construction platform of the present utility model;
FIG. 2 is a schematic cross-sectional view of the interior of the building construction platform of the present utility model;
FIG. 3 is a schematic view of a spindle according to the present utility model.
Reference numerals: 1. a building construction platform; 2. a chute; 3. a slide bar; 4. a moving plate; 5. a first spring; 6. a rotating shaft; 7. a rotating plate; 8. a push plate; 9. a second spring; 10. a moving groove; 11. an extension plate; 12. a third spring; 13. a clamping groove; 14. a groove; 15. a clamping block; 16. and a fourth spring.
Detailed Description
Referring to fig. 1-3, the present utility model provides a technical solution: the utility model provides a building construction platform, includes building construction platform 1, and two spouts 2 have been seted up at building construction platform 1's top, and the structure in two spouts 2 is the same all, and the inside fixedly connected with slide bar 3 of spout 2, the surface sliding connection of slide bar 3 has movable plate 4, and the top left side of movable plate 4 is the inclined plane, and the surface activity of slide bar 3 has cup jointed first spring 5, and the both ends of first spring 5 are fixed connection respectively between movable plate 4 and spout 2.
The right side of spout 2 has been seted up and has been removed groove 10, and the inside rotation in removal groove 10 is connected with pivot 6, and the top fixedly connected with rotor plate 7 of pivot 6, rotor plate 7 are in spout 2 internal rotation, and the right side fixedly connected with push pedal 8 of pivot 6, push pedal 8 are in the inside rotation in removal groove 10 and are connected, and the surface activity of pivot 6 has cup jointed second spring 9, and the both ends of second spring 9 are fixed connection respectively between pivot 6 and spout 2.
In the initial state, under the elastic force of the second spring 9, the rotating plate 7 is located at the top, when a worker approaches the edge of the building construction platform 1 in the process of performing construction on the building construction platform 1, the worker steps on the top of the moving plate 4, the moving plate 4 starts to move towards the inside of the sliding groove 2 after receiving pressure, the moving plate 4 moves downwards to start compressing the first spring 5, meanwhile, the moving plate 4 starts to push the rotating plate 7 to rotate downwards when moving downwards, at the moment, the rotating plate 7 rotates to drive the rotating shaft 6 to rotate, the rotating shaft 6 rotates to drive the second spring 9 to rotate and deform, and meanwhile, the rotating shaft 6 rotates to drive the pushing plate 8 to rotate upwards.
Because the top left side of movable plate 4 is the inclined plane, and then when the workman removes to the edge of building construction platform 1, can step on the top of movable plate 4 more smoothly, prevent that movable plate 4 from causing the influence to the removal of workman when not using, effectually improved the stability of workman's work on building construction platform 1.
The extension plate 11 is connected in the sliding manner in the moving groove 10, the top of the moving groove 10 extends to the top of the building construction platform 1, the extension plate 11 and the moving groove 10 are in a shape of a Chinese character 'zhong', the moving range of the extension plate 11 is effectively limited, the extension plate 11 is prevented from sliding off from the moving groove 10, the stability of the extension plate 11 in moving is improved, a third spring 12 is movably sleeved on the surface of the extension plate 11, and two ends of the third spring 12 are fixedly connected between the extension plate 11 and the moving groove 10 respectively.
The right side of extension board 11 has seted up draw-in groove 13, and recess 14 has been seted up to the right wall of removal groove 10, and the inside sliding connection of recess 14 has fixture block 15, and the shape of the one side that fixture block 15 kept away from recess 14 and draw-in groove 13 is semicircle form and identical, fixedly connected with fourth spring 16 between fixture block 15 and the recess 14.
In the initial state, the elasticity of the fourth spring 16 is greater than the elasticity of the third spring 12, the third spring 12 is in a compressed state, at this time, the clamping block 15 is located in the clamping groove 13 and limits the extension plate 11, the extension plate 11 is located in the moving groove 10, the extension plate 11 is located at the top of the push plate 8, when the push plate 8 rotates upwards, the extension plate 11 is smoothly pushed to move upwards, the extension plate 11 moves upwards to drive the clamping groove 13 to move upwards, at this time, the clamping groove 13 and the clamping block 15 cancel blocking each other, at this time, the third spring 12 is not blocked by the clamping block 15 on the extension plate 11, the extension plate 11 moves upwards out of the top of the building construction platform 1 under the action of the elasticity of the third spring 12, at this time, the extension plate 11 pops out from the moving groove 10, and then safety protection when a worker moves to the edge of the building construction platform is completed.
Through the workman remove to the edge of building construction platform 1, and then through stepping on the travelling plate 4 and finally make extension board 11 pop out from the removal inslot 10 under the elasticity effect of third spring 12, and then effectually prolonged the protection height of guardrail on the building construction platform, make the workman can be effectual when working to building construction platform 1 edge through the popping out of extension board 11 and then play the effect of protection to the workman, effectually improved the factor of safety of workman in the work on building construction platform 1, further improved the use perfection of whole device in use. After the extension plate 11 pops up to remind the protection to the workman, need to reset extension plate 11 in order to use extension plate 11 next time, at this moment downward movement extension plate 11, extension plate 11 downward movement begins compressing third spring 12, simultaneously extension plate 11 downward movement drives draw-in groove 13 downward movement, because promote fixture block 15 to recess 14 internal movement in the upward movement of extension plate 11, simultaneously fixture block 15 moves compression fourth spring 16 inwards recess 14, after extension plate 11 fully moves and resets to remove in the inslot 10, at this moment fixture block 13 moves to the left side of fixture block 15, fixture block 15 is not being blocked, fixture block 15 moves and resets under the elasticity effect of fourth spring 16 and gets into the inside of draw-in groove 13, at this moment fixture block 15 and draw-in groove 13 resume each other, and then make extension plate 11 accomodate in the inside of removal groove 10 accomplish the reset in order to be convenient for next time to the removal of extension plate 11.
Because the shape of one side of fixture block 15 that keeps away from recess 14 and draw-in groove 13 is semicircle and identical, and then when fixture block 15 removes to reset to draw-in groove 13 inside, can be more smoothly enter into the inside of draw-in groove 13, the effectual condition that prevents extension board 11 and produce the card and stop when resetting has further improved the smoothness nature of whole device in operation.
Working principle: in the initial state, the elasticity of the fourth spring 16 is greater than the elasticity of the third spring 12, the third spring 12 is in a compressed state, at this time, the clamping block 15 is located in the clamping groove 13 and limits the extension plate 11, the extension plate 11 is located in the moving groove 10, the extension plate 11 is located at the top of the push plate 8, when the push plate 8 rotates upwards, the extension plate 11 is smoothly pushed to move upwards, the extension plate 11 moves upwards to drive the clamping groove 13 to move upwards, at this time, the clamping groove 13 and the clamping block 15 cancel blocking each other, at this time, the third spring 12 is not blocked by the clamping block 15 on the extension plate 11, the extension plate 11 moves upwards out of the top of the building construction platform 1 under the action of the elasticity of the third spring 12, at this time, the extension plate 11 pops out from the moving groove 10, and then safety protection when a worker moves to the edge of the building construction platform is completed.
The embodiments of the present utility model have been described in detail with reference to the accompanying drawings, but the present utility model is not limited to the above embodiments, and various changes can be made within the knowledge of one of ordinary skill in the art without departing from the spirit of the present utility model.

Claims (6)

1. Building construction platform, including building construction platform (1), its characterized in that: two sliding grooves (2) are formed in the top of the building construction platform (1), the structures in the two sliding grooves (2) are the same, and a safety protection mechanism is arranged in the sliding groove (2);
the safety protection mechanism comprises a sliding rod (3), the sliding rod (3) is fixedly connected with the inside of the sliding groove (2), a movable plate (4) is slidably connected to the surface of the sliding rod (3), the left side of the top of the movable plate (4) is an inclined surface, a first spring (5) is movably sleeved on the surface of the sliding rod (3), and two ends of the first spring (5) are fixedly connected between the movable plate (4) and the sliding groove (2) respectively.
2. A building construction platform according to claim 1 wherein: the right side of spout (2) has seted up removal groove (10), and the inside rotation of removal groove (10) is connected with pivot (6), and the top fixedly connected with rotor plate (7) of pivot (6), rotor plate (7) rotate in spout (2).
3. A building construction platform according to claim 2 wherein: the right side fixedly connected with push pedal (8) of pivot (6), push pedal (8) are in the inside rotation connection of removal groove (10), and second spring (9) have been cup jointed in the surface activity of pivot (6), and the both ends of second spring (9) are fixed connection respectively between pivot (6) and spout (2).
4. A building construction platform according to claim 3 wherein: the extension plate (11) is connected in a sliding manner in the movable groove (10), the top of the movable groove (10) extends to the top of the building construction platform (1), and the extension plate (11) and the movable groove (10) are in a shape of Chinese character 'zhong'.
5. A building construction platform according to claim 4 wherein: the surface activity of extension board (11) has cup jointed third spring (12), and the both ends of third spring (12) are fixed connection respectively between extension board (11) and mobile groove (10), and draw-in groove (13) have been seted up on the right side of extension board (11).
6. A building construction platform according to claim 5 wherein: the right wall of the movable groove (10) is provided with a groove (14), a clamping block (15) is connected inside the groove (14) in a sliding mode, one side, far away from the groove (14), of the clamping block (15) is semicircular and matched with the clamping groove (13), and a fourth spring (16) is fixedly connected between the clamping block (15) and the groove (14).
CN202320453631.3U 2023-03-07 2023-03-07 Building construction platform Active CN219343912U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320453631.3U CN219343912U (en) 2023-03-07 2023-03-07 Building construction platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320453631.3U CN219343912U (en) 2023-03-07 2023-03-07 Building construction platform

Publications (1)

Publication Number Publication Date
CN219343912U true CN219343912U (en) 2023-07-14

Family

ID=87100518

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320453631.3U Active CN219343912U (en) 2023-03-07 2023-03-07 Building construction platform

Country Status (1)

Country Link
CN (1) CN219343912U (en)

Similar Documents

Publication Publication Date Title
CN219343912U (en) Building construction platform
CN107876473A (en) A kind of photovoltaic power generation equipment cleaning device position-limit mechanism
CN111515457B (en) Portable iron sheet cutting machine based on metal processing
CN208753815U (en) A kind of substation equipment maintenance and repair frame convenient for adjusting
CN208228601U (en) A kind of computer cabinet dust-extraction unit
CN109132781B (en) Protective lift car buffer device in elevator shaft capable of achieving stable buffering
CN215407396U (en) Tall formwork support structure
CN217947601U (en) Auxiliary lifting platform structure capable of preventing falling for stage equipment
CN211092827U (en) Portable garden outdoor chair
CN209009930U (en) A kind of escape structure on elevator decoration top
CN211496861U (en) Ascending device for optical fiber communication installation and construction
CN209619929U (en) It is a kind of to facilitate the snow removing cart for adjusting angle
CN112727037A (en) Beam frame device for building construction
CN209024159U (en) A kind of elevator with extendable platform
CN208319933U (en) A kind of Automatic Code ball machine and its automatic billiards container structure
CN214326129U (en) Carton packing recovery plant
CN219249614U (en) Street view seat
CN108979119A (en) A kind of construction coherent-wall scaffolding cantilever arrangement easy to use
CN114541942B (en) Civil air defense door
CN219654236U (en) Safety protection device
CN115075528A (en) Static and static combined structure of construction operation platform
CN221346216U (en) Novel movable construction frame
CN110970825B (en) Auxiliary device for outdoor maintenance of power distribution station
CN220555336U (en) Low-rise building feeding equipment for building house construction
CN221664274U (en) Form removing device for building construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant