CN219298779U - Building construction pouring template - Google Patents

Building construction pouring template Download PDF

Info

Publication number
CN219298779U
CN219298779U CN202320172462.6U CN202320172462U CN219298779U CN 219298779 U CN219298779 U CN 219298779U CN 202320172462 U CN202320172462 U CN 202320172462U CN 219298779 U CN219298779 U CN 219298779U
Authority
CN
China
Prior art keywords
template
groove
telescopic link
dwang
rotating rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320172462.6U
Other languages
Chinese (zh)
Inventor
张元鹏
杨永
刘艳峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Chengming Construction Co ltd
Original Assignee
Hangzhou Chengming Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Chengming Construction Co ltd filed Critical Hangzhou Chengming Construction Co ltd
Priority to CN202320172462.6U priority Critical patent/CN219298779U/en
Application granted granted Critical
Publication of CN219298779U publication Critical patent/CN219298779U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a building construction pouring template, which comprises a first template, a second template and a positioning rod, wherein the first template is arranged on the first template; the clamping block is clamped into the clamping groove, so that the connection of the first template and the second template can be completed, and the operation is simple, convenient and quick; through with first dwang follow first side inslot roll-out, then pulling first telescopic link for first firm foot can with ground contact, thereby support first template through first dwang, first telescopic link and first firm foot, strengthen the stability of first template, roll-out from the second side inslot through with the second dwang, then pulling second telescopic link, make the second firm foot can with ground contact, thereby support the second template through second dwang, second telescopic link and the firm foot of second, strengthen the stability of second template, this mode easy operation need not to erect a large amount of supports in the outside of template, can reduce the construction degree of difficulty, save template engineering time, raise the efficiency.

Description

Building construction pouring template
Technical Field
The utility model belongs to the technical field of templates, and particularly relates to a building construction pouring template.
Background
The building template is a temporary supporting structure, and is manufactured according to the design requirement, so that a concrete structure and a component are formed according to the specified position and geometric dimension, the correct position of the concrete structure and the component is kept, the self weight of the building template and the external load acted on the self weight of the building template are borne, when the concrete is poured, the cavity is formed by assembling the template, the concrete is poured into the cavity for pouring, and the template is removed after the concrete is shaped.
When the template is installed, in order to guarantee the stability of template, can install a large amount of supports in the outside of template, this kind of mode can influence the efficiency of construction to a certain extent, and the connection between template and the template is mostly all butt joint, and the template is in the in-process of using if deformation appears in edge, and the gap just easily appears in the position of that butt joint for when pouring concrete, mud can flow away from the gap, causes the phenomenon of leakage.
For the problems in the related art, no effective solution has been proposed at present.
Therefore, in order to solve the problems, the utility model provides a building construction pouring template.
Disclosure of Invention
In order to overcome the technical problems, the utility model aims to provide a building construction pouring template, which is characterized in that a clamping block is clamped into a clamping groove, so that the connection between a first template and a second template can be completed, the operation is simple, the first template is supported through a first rotating rod, a first telescopic rod and a first stabilizing leg, the stability of the first template is enhanced, the second template is supported through a second rotating rod, a second telescopic rod and a second stabilizing leg, the stability of the second template is enhanced, the operation is simple in the mode, a large number of brackets are not required to be erected on the outer side of the template, the construction difficulty can be reduced, the construction time of the template is saved, the efficiency is improved, the first blade and the second blade can be lowered through an electric telescopic rod, the inner part of the clamping groove and the outer side of the clamping block can be cleaned, and some mud is prevented from flowing into the inner hardening of the clamping groove.
The aim of the utility model can be achieved by the following technical scheme:
the utility model provides a building construction pouring template, includes first template, second template and locating lever, the draw-in groove has been seted up to first template with one side that the second template is adjacent, the second template with one side fixed mounting that the first template is adjacent has the fixture block, the fixture block with the draw-in groove male connection, first side slot has been seted up to one side of first template, the internally mounted in first side slot has first dwang, the internally sliding connection of first dwang has first telescopic link, the one end fixed mounting of first telescopic link has first firm foot, the roof groove has been seted up on the top of first template, the inside sliding connection of roof groove has the slider, the top fixed mounting of slider has branch, the top fixed mounting of branch has the mounting bracket, the bottom fixed mounting of mounting bracket has electric telescopic link, the bottom fixed mounting of electric telescopic link has the mounting panel, the first blade of one side both ends equal fixed mounting of opposite side of mounting panel has the second blade, the internally mounted of second side blade, the inside sliding connection of second side lever has first telescopic link, second side template has the second firm foot, the second template is connected to first firm foot, the first template is accomplished through the second firm foot, the first template is connected to the first firm foot, the first template, the first firm foot rotates, the first template is convenient for the first firm, the first template is connected to the first firm, the first firm foot, the first template is easy to rotate, need not to erect a large amount of supports in the outside of template, can reduce the construction degree of difficulty, save template engineering time, raise the efficiency makes first blade and second blade descend through electric telescopic handle, can clear up the inside of draw-in groove and the outside of fixture block, avoids some mud to flow into the inside hardening of draw-in groove.
Further, a plurality of groups of first positioning holes are formed in the clamping groove, a plurality of groups of second positioning holes are formed in the clamping block, the first positioning holes are matched with the second positioning holes and correspond to the second positioning holes one by one, and the positioning rods are connected with the first positioning holes and the second positioning holes in an inserted mode.
Further, the inside fixed mounting of first side groove has first bull stick, rotate on the first bull stick and be connected with first rotation seat, one side fixed mounting of first rotation seat has first dwang, threaded connection has first positioning bolt on the first dwang.
Further, the distance between the two groups of first blades is matched with the width of the clamping groove.
Further, the distance between the two groups of second blades is matched with the width of the clamping block.
The novel rotary table is characterized in that a second rotary rod is fixedly arranged in the second side groove, a second rotary seat is connected to the second rotary rod in a rotary mode, a second rotary rod is fixedly arranged on one side of the second rotary seat, and a second positioning bolt is connected to the second rotary rod in a threaded mode.
The electric telescopic device is characterized in that an external power supply and a control switch are arranged on the first template, the external power supply is electrically connected with the control switch, and the control switch is electrically connected with the electric telescopic rod.
Compared with the prior art, the utility model has the following beneficial effects:
1. according to the utility model, the clamping block is clamped into the clamping groove, so that the connection of the first template and the second template can be completed, and the operation is simple, convenient and quick.
2. According to the utility model, the first rotating rod is rotated out of the first side groove, and then the first telescopic rod is pulled, so that the first stabilizing leg can be in contact with the ground, the first template is supported through the first rotating rod, the first telescopic rod and the first stabilizing leg, the stability of the first template is enhanced, the second rotating rod is rotated out of the second side groove, and then the second telescopic rod is pulled, so that the second stabilizing leg can be in contact with the ground, and the second template is supported through the second rotating rod, the second telescopic rod and the second stabilizing leg, so that the stability of the second template is enhanced.
3. According to the utility model, the first blade and the second blade are lowered by the electric telescopic rod, and the inside of the clamping groove and the outside of the clamping block can be cleaned along with the lowering of the first blade and the second blade, so that some slurry is prevented from flowing into the inside of the clamping groove to harden.
Drawings
In order to more clearly illustrate the embodiments of the present utility model or the technical solutions in the prior art, the drawings that are needed in the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present utility model, and other drawings may be obtained according to these drawings without inventive effort for a person skilled in the art.
FIG. 1 is a schematic perspective view of the present utility model;
FIG. 2 is a schematic diagram of a first template and a second template according to the present utility model;
fig. 3 is a front view of the present utility model.
Reference numerals:
1. a first template; 101. a clamping groove; 102. a first positioning hole; 103. a first side groove; 104. a first rotating lever; 105. a first rotating seat; 106. a first rotating lever; 107. a first telescopic rod; 108. a first stabilizing leg; 109. a first positioning bolt; 110. a top groove; 111. a slide block; 112. a support rod; 113. a mounting frame; 114. an electric telescopic rod; 115. a mounting plate; 116. a first blade; 117. a second blade; 2. a second template; 201. a clamping block; 202. a second positioning hole; 203. a second side groove; 204. a second rotating rod; 205. a second rotating seat; 206. a second rotating lever; 207. a second telescopic rod; 208. a second stabilizing leg; 209. a second positioning bolt; 3. and a positioning rod.
Detailed Description
The utility model is further described below with reference to the accompanying drawings and detailed description:
referring to fig. 1-3, a construction pouring formwork according to an embodiment of the present utility model includes a first formwork 1, a second formwork 2 and a positioning rod 3, wherein a clamping groove 101 is formed on one side of the first formwork 1 adjacent to the second formwork 2, a clamping block 201 is fixedly mounted on one side of the second formwork 2 adjacent to the first formwork 1, the clamping block 201 is connected with the clamping groove 101 in an inserted manner, a first side groove 103 is formed on one side of the first formwork 1, a first rotating rod 106 is mounted in the first side groove 103, a first telescopic rod 107 is slidingly connected in the first rotating rod 106, a first stabilizing leg 108 is fixedly mounted at one end of the first telescopic rod 107, a top groove 110 is formed at the top end of the first formwork 1, a sliding block 111 is slidingly connected in the top groove 110, a supporting rod 112 is fixedly mounted at the top end of the sliding block 111, a mounting frame 113 is fixedly mounted at the top end of the supporting rod 112, the bottom fixed mounting of mounting bracket 113 has electric telescopic handle 114, electric telescopic handle 114's bottom fixed mounting has mounting panel 115, the one side both ends of mounting panel 115 are all fixed mounting has first blade 116, the opposite side both ends of mounting panel 115 are all fixed mounting has second blade 117, second side slot 203 has been seted up to one side of second template 2, the internally mounted of second side slot 203 has second dwang 206, the inside sliding connection of second dwang 206 has second telescopic handle 207, the one end fixed of second telescopic handle 207 has second firm foot 208, with fixture block 201 block into draw-in groove 101, can accomplish the connection of first template 1 and second template 2, easy operation, and is convenient and fast, through rotating out first dwang 106 from first side slot 103, then pulling first telescopic handle 107, make first firm foot 108 can contact with ground, thereby through first dwang 106, the one end fixed of second telescopic handle 207 has second firm foot 208, with fixture block 201 block into draw-in groove 101, can accomplish the connection of first template 1 and second template 2, easy operation, through rotating first dwang 107, and pulling first firm foot 108 can contact with ground The first telescopic rod 107 and the first stable foot 108 support the first template 1, stability of the first template 1 is enhanced, through rotating the second rotary rod 206 out of the second side groove 203, then the second telescopic rod 207 is pulled, the second stable foot 208 can be in contact with the ground, and accordingly the second template 2 is supported through the second rotary rod 206, the second telescopic rod 207 and the second stable foot 208, stability of the second template 2 is enhanced, the mode is easy to operate, a large number of supports are not required to be erected on the outer side of the template, construction difficulty can be reduced, template construction time is saved, efficiency is improved, the first blade 116 and the second blade 117 are enabled to descend through the electric telescopic rod 114, the inside of the clamping groove 101 and the outer side of the clamping block 201 can be cleaned along with descending of the first blade 116 and the second blade 117, and certain slurry is prevented from flowing into the inside of the clamping groove 101 to be hardened.
The clamping groove 101 is provided with a plurality of groups of first positioning holes 102, the clamping block 201 is provided with a plurality of groups of second positioning holes 202, the first positioning holes 102 are matched with the second positioning holes 202, the positioning rods 3 are in one-to-one correspondence with the first positioning holes 102 and the second positioning holes 202 in an inserted mode.
The first rotating rod 104 is fixedly arranged in the first side groove 103, the first rotating rod 104 is rotatably connected with the first rotating seat 105, the first rotating rod 106 is fixedly arranged on one side of the first rotating seat 105, and the first positioning bolt 109 is in threaded connection with the first rotating rod 106.
The spacing of the two sets of first blades 116 matches the width of the card slot 101.
The spacing between the two sets of second blades 117 matches the width of the latch 201.
The second rotating rod 204 is fixedly arranged in the second side groove 203, a second rotating seat 205 is rotatably connected to the second rotating rod 204, a second rotating rod 206 is fixedly arranged on one side of the second rotating seat 205, and a second positioning bolt 209 is connected to the second rotating rod 206 in a threaded mode.
The first template 1 is provided with an external power supply and a control switch, the external power supply is electrically connected with the control switch, and the control switch is electrically connected with the electric telescopic rod 114.
The utility model relates to a working principle of a building construction pouring template, which comprises the following steps: through with the fixture block 201 block to the draw-in groove 101 in, can accomplish the connection of first template 1 and second template 2, easy operation, and the mode can play the effect of placing the thick liquid that leaks, through rotating out first dwang 106 from first side tank 103 in, then pull first telescopic link 107, make first firm foot 108 can contact with ground, thereby support first template 1 through first dwang 106, first telescopic link 107 and first firm foot 108, strengthen the stability of first template 1, through rotating out second dwang 206 from second side tank 203 in, then pull second telescopic link 207, make second firm foot 208 can contact with ground, thereby support second template 2 through second dwang 206, second telescopic link 207 and second firm foot 208, the stability of reinforcing second template 2, this mode easy operation need not in the outside of template at a large amount of supports, can reduce the construction degree of difficulty, save template construction time, raise the efficiency, make first blade 114 and second blade 117 and the inside of blade 117 can be avoided descending the inside of first template 116 and second blade 116, and the inside of the clearance groove 101 can be avoided to some of the inside of blade 116, and the inside of blade 116 is down-set up.
What is not described in detail in this specification is prior art known to those skilled in the art.
Finally, it should be noted that: the foregoing description is only a preferred embodiment of the present utility model, and the present utility model is not limited to the above-described embodiment, but may be modified or substituted for some of the technical features described in the above-described embodiments by those skilled in the art. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present utility model should be included in the protection scope of the present utility model.

Claims (7)

1. The utility model provides a building construction pouring template, its characterized in that includes first template (1), second template (2) and locating lever (3), draw-in groove (101) have been seted up to one side that first template (1) with second template (2) are adjacent, second template (2) with one side fixed mounting that first template (1) is adjacent has fixture block (201), fixture block (201) with draw-in groove (101) are inserted and are connected, first side groove (103) have been seted up to one side of first template (1), the internally mounted in first side groove (103) has first dwang (106), the inside sliding connection of first dwang (106) has first telescopic link (107), the one end fixed mounting bracket of first telescopic link (107) has first foot (108), roof groove (110) have been seted up on the top of first template (1), the inside sliding connection of roof groove (110) has slider (111), the top fixed mounting of slider (111) branch has branch, the internally mounted in first side groove (103) has first telescopic link (116), the bottom of first telescopic link (107) has electric knife blade (112), the bottom (114) has fixed mounting panel (114), the utility model discloses a fixed mounting structure of a die plate, including mounting panel (115) and second template, second blade (117) are all fixed mounting at opposite side both ends of mounting panel (115), second side groove (203) have been seted up to one side of second template (2), internally mounted in second side groove (203) has second dwang (206), the inside sliding connection of second dwang (206) has second telescopic link (207), the one end fixed mounting of second telescopic link (207) has second firm foot (208).
2. The building construction pouring template according to claim 1, wherein a plurality of groups of first positioning holes (102) are formed in the clamping groove (101), a plurality of groups of second positioning holes (202) are formed in the clamping block (201), the first positioning holes (102) are matched with the second positioning holes (202) and correspond to each other one by one, and the positioning rods (3) are connected with the first positioning holes (102) and the second positioning holes (202) in an inserted mode.
3. The building construction pouring formwork according to claim 1, wherein a first rotating rod (104) is fixedly installed in the first side groove (103), a first rotating seat (105) is rotatably connected to the first rotating rod (104), a first rotating rod (106) is fixedly installed on one side of the first rotating seat (105), and a first positioning bolt (109) is connected to the first rotating rod (106) in a threaded mode.
4. A construction pouring formwork according to claim 1, wherein the spacing of the two sets of first blades (116) matches the width of the clamping groove (101).
5. A construction pouring formwork according to claim 1, wherein the spacing of the two sets of second blades (117) matches the width of the clips (201).
6. The building construction pouring formwork according to claim 1, wherein a second rotating rod (204) is fixedly installed in the second side groove (203), a second rotating seat (205) is rotatably connected to the second rotating rod (204), a second rotating rod (206) is fixedly installed on one side of the second rotating seat (205), and a second positioning bolt (209) is connected to the second rotating rod (206) in a threaded mode.
7. The building construction pouring formwork according to claim 1, wherein an external power supply and a control switch are arranged on the first formwork (1), the external power supply is electrically connected with the control switch, and the control switch is electrically connected with the electric telescopic rod (114).
CN202320172462.6U 2023-02-10 2023-02-10 Building construction pouring template Active CN219298779U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320172462.6U CN219298779U (en) 2023-02-10 2023-02-10 Building construction pouring template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320172462.6U CN219298779U (en) 2023-02-10 2023-02-10 Building construction pouring template

Publications (1)

Publication Number Publication Date
CN219298779U true CN219298779U (en) 2023-07-04

Family

ID=86985569

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320172462.6U Active CN219298779U (en) 2023-02-10 2023-02-10 Building construction pouring template

Country Status (1)

Country Link
CN (1) CN219298779U (en)

Similar Documents

Publication Publication Date Title
CN219298779U (en) Building construction pouring template
CN209723602U (en) A kind of architectural engineering reinforced support device
CN204886812U (en) Photovoltaic board mounting bracket
CN217679137U (en) Deep foundation pit supporting structure
CN215164433U (en) Integral road surface basic unit resin template support frame
CN113513142B (en) Prefabricated convex window correction device and correction method adopting same
CN210976625U (en) Stupefied bracing system of super high-rise building template back of body
CN211899829U (en) Combined top support device convenient for building
CN220619807U (en) Construction platform for turning over mould of variable-camber bridge pier
CN219298784U (en) Quick detach formula building engineering template bearing structure
CN220847129U (en) Folding reinforcing tool for bridge deck pavement side mold of steel-concrete composite beam
CN218492332U (en) Safety warning device for electric power construction
CN218952116U (en) Bottom shaft supporting and positioning device
CN211714594U (en) Building external wall insulation integration template bearing structure
CN214819409U (en) Assembly type concrete structure based on SEM
CN221095807U (en) Movable scaffold support assembly
CN215859090U (en) Template fixing device for building engineering construction
CN218061459U (en) A template supporting device for building engineering
CN216840764U (en) Construction engineering is with consolidating bearing structure
CN219060548U (en) Assembled roof node structure
CN214739250U (en) Green's bearing precast beam
CN218205725U (en) Portable supporting building template device
CN217399714U (en) Garage mattress layer internal frame column pier external diameter adjustable mould
CN217896292U (en) Culvert gate support frame for hydraulic engineering construction
CN219809091U (en) Wind tower steel frame convenient to assembly

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant