CN219242835U - Pre-buried pump line fixed bolster - Google Patents

Pre-buried pump line fixed bolster Download PDF

Info

Publication number
CN219242835U
CN219242835U CN202320821216.9U CN202320821216U CN219242835U CN 219242835 U CN219242835 U CN 219242835U CN 202320821216 U CN202320821216 U CN 202320821216U CN 219242835 U CN219242835 U CN 219242835U
Authority
CN
China
Prior art keywords
clamp
threaded rod
buried
pump line
lower clamp
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320821216.9U
Other languages
Chinese (zh)
Inventor
闫旭
陈洪哲
冯浩
张创业
寇宏亮
白喜涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fourth Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltc
Original Assignee
Fourth Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltc filed Critical Fourth Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltc
Priority to CN202320821216.9U priority Critical patent/CN219242835U/en
Application granted granted Critical
Publication of CN219242835U publication Critical patent/CN219242835U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model relates to the technical field of building construction, in particular to a pre-buried pump pipe fixing support. Including fixing the embedded plate on pouring the template, offered two screw holes on the embedded plate, the spiro union has the threaded rod respectively in the screw hole, and the PVC sleeve pipe is equipped with to the cover of one side that just is close to the embedded plate on the threaded rod, swing joint has clamp and lower clamp between two threaded rods, and the pump line is tight fixed through last clamp and lower clamp. The pump pipe is clamped and fixed through the upper clamp and the lower clamp, the whole support is kept stable through the pre-buried plate pre-buried in advance, after the pump pipe is used, the upper clamp and the lower clamp are removed and the pump pipe is taken away, the threaded rod is rotated to enable the threaded rod to be separated from the pre-buried plate, the PVC pipe is left in concrete, the PVC pipe is repaired and filled, the fixing support is kept stable through the pre-buried plate and the threaded rod, the height is adjusted through the movable upper clamp and the lower clamp, the repeated use function is kept through the detachable threaded rod, and the disassembling process is time-saving and labor-saving.

Description

Pre-buried pump line fixed bolster
Technical Field
The utility model relates to the technical field of building construction, in particular to a pre-buried pump pipe fixing support.
Background
The pump pipe is a concrete conveying pump pipe for short, is a novel building engineering accessory product, is generally divided into a vehicle pump pipe and a ground pump pipe, is often called a concrete pump pipe because concrete is short for concrete, is an accessory product which appears simultaneously with the appearance of the concrete conveying pump, can quickly convey concrete to a place where pouring is needed, needs to use a fixing frame when the pump pipe is erected for use, fixes the pump pipe, prevents the pump pipe from falling off when conveying concrete in the pump pipe, and is a supporting device for providing support and fixing for the operation of the pump pipe.
To the problem of how the pump line is fixed, current patent 201710402221.5 discloses a detachable concrete delivery pump line shaped steel fixing device, including steel support, support bottom plate, location clamp, rubber bradyseism gasket, the support bottom plate weld in steel support bottom, location clamp lower extreme weld in steel support top, rubber bradyseism gasket place between pump line and location clamp, support bottom plate four corners respectively be provided with a bolt hole, be fixed in the ground with the support bottom plate through expansion bolts, but the size after the steel support preparation in the comparison document has been fixed, can't have enough to meet the need the use in the place of pump line difference in height, and after using, expansion bolts's demolish difficultly, need use the hammer to beat expansion bolts into the concrete in whole or cut out the position of concrete top, not only construction is loaded down with trivial details and hard and unable used repeatedly.
Disclosure of Invention
The utility model aims to solve the problems, thereby providing a reusable pre-buried pump pipe fixing bracket.
The utility model solves the problems, and adopts the following technical scheme:
the utility model provides an embedded pump line fixed bolster, includes the embedded plate of fixing on pouring the template, has seted up two screw holes on the embedded plate, has the threaded rod in the screw hole spiro union respectively, and one side cover that just is close to the embedded plate on the threaded rod is equipped with the PVC sleeve pipe, swing joint has clamp and lower clamp between two threaded rods, and the pump line is tight fixed through last clamp and lower clamp.
Compared with the prior art, the utility model adopting the technical scheme has the outstanding characteristics that:
during the use, according to the position of clamp and lower clamp down in the high regulation of pump line, clamp down the clamp through last clamp and lower clamp and press from both sides tightly fixedly, make the whole maintenance of support steady through pre-buried embedded plate in advance, after the pump line finishes using, demolish last clamp and lower clamp and take away the pump line, rotate the threaded rod and make the threaded rod break away from the embedded plate, the PVC sleeve pipe stays in the concrete, repair in the PVC sleeve pipe and fill, this fixed bolster keeps stable through embedded plate and threaded rod, go up clamp and lower clamp height-adjusting through the activity, keep repeatedly used's function through detachable threaded rod, and dismantle process labour saving and time saving.
Preferably, the utility model further adopts the technical scheme that:
the two ends of the upper clamp and the lower clamp are provided with lug plates relatively, movable holes are formed in the lug plates and sleeved on the threaded rods, and adjusting nuts are sleeved on the threaded rods and located on one sides, deviating from the adjacent lug plates, of the threaded rods respectively.
A gasket is arranged between the adjusting nut and the lug plate.
And a locking nut is sleeved on the threaded rod and positioned at one end of the PVC sleeve, which is far away from the embedded plate.
The length of the PVC sleeve is equal to the thickness of the concrete casting.
Drawings
FIG. 1 is a schematic diagram of an embodiment of the present utility model;
marked in the figure as: the embedded plate 1, the threaded rod 2, the PVC sleeve 3, the upper clamp 4, the lower clamp 5, the adjusting nut 6, the locking nut 7 and the pump pipe 8.
Detailed Description
The utility model is further described below in connection with the following examples which are provided for the purpose of better understanding of the present utility model and are, therefore, not to be construed as limiting the scope of the utility model.
The utility model provides an embedded pump line fixed bolster, including fixing the embedded plate 1 on pouring the template, embedded plate 1 both can fix on the bottom plate template also can be fixed in on the wallboard template, two screw holes have been seted up on the embedded plate 1, threaded rod 2 has been threaded respectively in the screw hole, make threaded rod 2 removable used repeatedly through the cooperation of threaded rod 2 and screw hole, one side cover that just is close to embedded plate 1 on the threaded rod 2 is equipped with PVC sleeve pipe 3, protect the position of threaded rod 2 in the concrete through PVC sleeve pipe 3, swing joint has clamp 4 and clamp 5 down between two threaded rods 2, pump line 8 is tight fixed through clamp and clamp down.
The two end parts of the upper clamp 4 and the lower clamp 5 are relatively provided with the lug plates, the lug plates are provided with movable holes and sleeved on the threaded rod 2, one sides of the threaded rod 2, which are located on the adjacent lug plates and away from each other, are respectively sleeved with an adjusting nut 6, the upper clamp 4 and the lower clamp 5 can move up and down along the threaded rod 2 through the adjusting nuts 6, and the height of the upper clamp can be adjusted according to the 8 height of a pump pipe.
A gasket is arranged between the adjusting nut 6 and the lug plate.
One end cover that just is located PVC sleeve pipe 3 on the threaded rod 2 and keeps away from embedded plate 1 is equipped with lock nut 7, prevents through lock nut 7 anticreep that PVC sleeve pipe 3 from removing, and the one end and the embedded plate 1 of PVC sleeve pipe 3 are hugged closely.
The length of the PVC sleeve 3 is equal to the thickness of the concrete pouring, the threaded rod 2 is protected through the PVC sleeve 3, and the outer end of the PVC sleeve 3 can serve as an elevation point of the concrete pouring.
During the use, according to the position of clamp and lower clamp down in the high regulation of pump line, clamp down the clamp through last clamp and lower clamp and press from both sides tightly fixedly, make the whole maintenance of support steady through pre-buried embedded plate in advance, after the pump line finishes using, demolish last clamp and lower clamp and take away the pump line, rotate the threaded rod and make the threaded rod break away from the embedded plate, the PVC pipe stays in the concrete, repair in the PVC pipe and fill, this fixed bolster keeps stable through embedded plate and threaded rod, go up clamp and lower clamp height-adjusting through the activity, keep repeatedly used's function through detachable threaded rod, and dismantle process labour saving and time saving.
The foregoing description of the preferred embodiments of the utility model is not intended to limit the scope of the claims, but rather to cover all equivalent modifications within the scope of the present utility model as defined by the appended claims.

Claims (5)

1. A pre-buried pump line fixed bolster, its characterized in that: including fixing the embedded plate on pouring the template, offered two screw holes on the embedded plate, the spiro union has the threaded rod respectively in the screw hole, and the PVC sleeve pipe is equipped with to the cover of one side that just is close to the embedded plate on the threaded rod, swing joint has clamp and lower clamp between two threaded rods, and the pump line is tight fixed through last clamp and lower clamp.
2. The pre-buried pump line fixing bracket according to claim 1, characterized in that: the two ends of the upper clamp and the lower clamp are provided with lug plates relatively, movable holes are formed in the lug plates and sleeved on the threaded rods, and adjusting nuts are sleeved on the threaded rods and located on one sides, deviating from the adjacent lug plates, of the threaded rods respectively.
3. The pre-buried pump line fixing bracket according to claim 2, characterized in that: a gasket is arranged between the adjusting nut and the lug plate.
4. The pre-buried pump line fixing bracket according to claim 1, characterized in that: and a locking nut is sleeved on the threaded rod and positioned at one end of the PVC sleeve, which is far away from the embedded plate.
5. The pre-buried pump line fixing bracket according to claim 1, characterized in that: the length of the PVC sleeve is equal to the thickness of the concrete casting.
CN202320821216.9U 2023-04-14 2023-04-14 Pre-buried pump line fixed bolster Active CN219242835U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320821216.9U CN219242835U (en) 2023-04-14 2023-04-14 Pre-buried pump line fixed bolster

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320821216.9U CN219242835U (en) 2023-04-14 2023-04-14 Pre-buried pump line fixed bolster

Publications (1)

Publication Number Publication Date
CN219242835U true CN219242835U (en) 2023-06-23

Family

ID=86810189

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320821216.9U Active CN219242835U (en) 2023-04-14 2023-04-14 Pre-buried pump line fixed bolster

Country Status (1)

Country Link
CN (1) CN219242835U (en)

Similar Documents

Publication Publication Date Title
CN204645623U (en) Aluminium alloys wafts window template system
CN105971272B (en) Assembled aluminum template masonry shearwalls reinforced concrete structural column and construction method
CN108590177A (en) K plates bracing means and its reinforcement means
CN209457425U (en) A kind of ancient architecture wall recovery support
CN219242835U (en) Pre-buried pump line fixed bolster
CN102720159B (en) Adjusting device specially for steel hoop two-way suspension supporting system
CN210563399U (en) Concrete structure beam template fixing device
CN206397136U (en) Assembled aluminum template masonry shearwalls reinforced concrete structural column
CN113931444B (en) Post-cast edge beam integral type template structure and construction method thereof
CN110499914A (en) Anti- bank formwork reinforcement built-in fitting, anti-bank formwork reinforcement structure and its construction method
CN215848853U (en) Auxiliary installation device for exposed embedded part in prefabricated part
CN209837682U (en) Suspended concrete arc-shaped formwork
CN113215990A (en) Construction device and method for quickly dismantling prefabricated bent cap bottom formwork
CN207295716U (en) A kind of cantilever combined steel template
CN206903186U (en) Adjustable detachable wall-connecting device of scaffold
CN216422938U (en) Clamp device for adjusting support protection distance of template
CN106939698B (en) L-shaped stepping die
CN214939347U (en) Construction equipment that prefabricated bent cap die block board demolishd fast
CN221095826U (en) Mounting structure of shaping post-pouring belt mould hanging tool
CN105569070B (en) The method for pouring large-size concrete beam column
CN211736391U (en) Exempt from formula flitch fixed bolster that punches
CN113216631B (en) Construction structure and process of cabin-jumping method
CN219431383U (en) Simple side-die diagonal bracing base device
CN212175514U (en) Mounting and dismounting device for adjusting bent cap bracket
CN210507073U (en) Auxiliary assembly is repaired on municipal administration road surface

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant