CN219175489U - Put in inside temporary connecting device of slotting tenon formula construction of steel member that seals - Google Patents

Put in inside temporary connecting device of slotting tenon formula construction of steel member that seals Download PDF

Info

Publication number
CN219175489U
CN219175489U CN202223362588.4U CN202223362588U CN219175489U CN 219175489 U CN219175489 U CN 219175489U CN 202223362588 U CN202223362588 U CN 202223362588U CN 219175489 U CN219175489 U CN 219175489U
Authority
CN
China
Prior art keywords
steel member
tenon
section steel
wall
adjusting screw
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223362588.4U
Other languages
Chinese (zh)
Inventor
王一功
李光星
陈宁旭
陈传荣
潘琴存
区力生
刘杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou City Construction & Development Design Institute Co ltd
Original Assignee
Guangzhou City Construction & Development Design Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou City Construction & Development Design Institute Co ltd filed Critical Guangzhou City Construction & Development Design Institute Co ltd
Priority to CN202223362588.4U priority Critical patent/CN219175489U/en
Application granted granted Critical
Publication of CN219175489U publication Critical patent/CN219175489U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a temporary connecting device for slotted tenon type construction, which is arranged in a closed steel member, and comprises an upper section steel member and a lower section steel member, wherein a tenon matched with the tenon is arranged at the bottom end of the upper section steel member, the tenon is in clearance fit with the tenon, a clamping groove is formed in the outer side of the tenon, and an adjusting screw capable of being inserted into the clamping groove is connected to the outer wall of the lower section steel member in a threaded manner. The utility model relates to a temporary connecting device for slotted tenon type construction, which is arranged in a closed steel member, belongs to the technical field of civil engineering, and is characterized in that a tenon and a mortise which are arranged in the member, so that a welding part is not blocked, the position which needs to be welded during on-site splicing is avoided, continuous welding can be performed, the number of striking and landing arcs is reduced, and the quality of a welding seam is improved; no external connection device is blocked, and the welding device is more suitable for automatic welding equipment.

Description

Put in inside temporary connecting device of slotting tenon formula construction of steel member that seals
Technical Field
The utility model relates to the technical field of civil engineering, in particular to a temporary connecting device for slotted tenon type construction, which is arranged in a closed steel member.
Background
With the development of the economic development and the vigorous development of civil engineering construction in China, particularly the gushing of super high-rise buildings and large-span buildings, the use of steel structural members is becoming more and more common. Due to limitations in processing capacity, allowable transport length, and lifting capacity, steel structural members need to be manufactured and transported in sections, and different sections of steel structural members are connected in the field.
At present, the field connection means of closed steel members such as rectangular steel pipes, round steel pipes, double-steel-plate shear walls and the like mainly comprise the steps of respectively welding lug plates outside upper and lower sections of steel members, and temporarily connecting the lug plates of the upper and lower sections of steel members by using mounting bolts through connecting plates. After the construction of the permanently spliced weld joint is finished, the mounting bolts and the connecting plate are disassembled, and the lug plates are removed. The traditional construction temporary connection mode can be seen from a national standard atlas of "detail of the construction of the steel structure node of the civil construction of multiple and high-rise" 16G519 ".
The traditional temporary connection mode mainly has the problems that the lug plates and the connecting plates prevent continuous welding of the field spliced weld joints of the steel members, and excessive striking and landing arcs influence the quality of the weld joints; the lug plates and the connecting plates block the advancing path of the automatic welding device, so that the on-site automatic welding is difficult to realize.
Because the positions of the lug plates relative to the steel members are fixed, and the positions of the bolt holes on the connecting plates and the lug plates are also determined, the perpendicularity deviation of the upper-section steel members is difficult to adjust on site. The initial defects of the steel member are also increased due to heat input and mechanical damage to the steel member when the temporary connection lugs are cut off in a later stage.
Disclosure of Invention
The utility model aims to solve the technical problems in the prior art and aims to provide a temporary connecting device for open-tenon construction, which is arranged in a closed steel member.
In order to achieve the above purpose, the utility model provides a temporary connecting device for slotted tenon type construction, which is arranged in a closed steel member, and comprises an upper section steel member and a lower section steel member, wherein a tenon is arranged at the top of the inner wall of the lower section steel member, a tenon matched with the tenon is arranged at the bottom end of the upper section steel member, the tenon is in clearance fit with the tenon, a clamping groove is arranged at the outer side of the tenon, and an adjusting screw capable of being inserted into the clamping groove is connected to the outer wall of the lower section steel member in a threaded manner.
Further, a splicing welding seam is arranged at the bottom end of the outer wall of the upper section steel member.
Furthermore, the upper groove wall of the tenon opening is provided with a wedge surface, and the adjusting screw can be abutted against the wedge surface.
Furthermore, the outer wall of the lower section steel member is provided with a screw hole matched with the adjusting screw, and the adjusting screw arranged in the screw hole can be abutted against the inclined wedge surface.
Furthermore, the clamping groove is a transverse groove which is transversely extended on the outer side surface of the bottom of the tenon.
Advantageous effects
Compared with the prior art, the temporary connecting device for the open-slot tenon type construction arranged in the closed steel member has the following advantages: the novel temporary connecting device for slotted tenon type construction arranged in the closed steel member is characterized in that the tenon and the mortise which are arranged in the member, so that the welding part is not blocked, the position which needs to be welded during on-site splicing is avoided, continuous welding can be performed, the number of striking and landing arcs is reduced, and the quality of welding seams is improved; no external connection device is blocked, and the welding device is more suitable for automatic welding equipment.
Drawings
FIG. 1 is a perspective view of the structure of a tongue-and-groove construction temporary connection device of the present utility model placed inside a closed steel member;
FIG. 2 is a front elevational view of the structure of the tongue-and-groove construction temporary connection device of the present utility model disposed within a closed steel member, in place;
FIG. 3 is a front view of the structure of the tongue-and-groove construction temporary connection device of the present utility model placed inside a closed steel member, in place;
FIG. 4 is an enlarged schematic view of the structure of the utility model in which the adjusting screw is engaged with the tenon.
In the figure: 1. an upper section steel member; 2. a lower section steel member; 3. a mortise; 4. a tenon; 5. a clamping groove; 6. an adjusting screw; 7. splicing welding seams; 8. wedge surface; 9. screw holes.
Detailed Description
The following detailed description of embodiments of the utility model is, therefore, to be taken in conjunction with the accompanying drawings, and it is to be understood that the scope of the utility model is not limited to the specific embodiments.
Embodiments of the present utility model are as follows: as shown in figures 1-4, the temporary connecting device for slotted tenon type construction arranged in a closed steel member comprises an upper section steel member 1 and a lower section steel member 2, wherein the upper section steel member 1 and the lower section steel member 2 can be cylindrical steel members or square steel members, a tenon 3 is arranged at the top of the inner wall of the lower section steel member 2, a tenon 4 matched with the tenon 3 is arranged at the bottom end of the upper section steel member 1, the tenon 4 is in clearance fit with the tenon 3, a clamping groove 5 is arranged at the outer side of the tenon 4, and an adjusting screw 6 capable of being inserted into the clamping groove 5 is connected to the outer wall of the lower section steel member 2 in a threaded manner.
In this arrange inside open slot tenon formula construction temporary connection device of steel member of closing in, set up tenon 3 in the inside of hypomere steel member 2, the bottom of upper segment steel member 1 sets up downward convex tenon 4 and tenon 3 block, thereby install upper segment steel member 1 in the top of hypomere steel member 2, in stretching into draw-in groove 5 through adjusting screw 6 spiral, thereby lock upper segment steel member 1 and hypomere steel member 2, finally weld fixing can be carried out in upper segment steel member 1 and hypomere steel member 2 butt joint department, after the welding is accomplished, upper segment steel member 1 does not have unnecessary protruding structure to need demolish with the surface of hypomere steel member 2, need not cut out the otic placode, reduced the influence to the steel member, member bearing capacity and ductility have been improved.
The tenon 4 and the tenon opening 3 are arranged in the member, so that the welding part is not blocked, the position to be welded during on-site splicing is avoided, continuous welding can be performed, the number of landing arcs is reduced, and the quality of welding seams is improved; no external connection device is blocked, and the welding device is more suitable for automatic welding equipment.
In the embodiment, the bottom end of the outer wall of the upper section steel member 1 is provided with the splicing welding line 7, the positions of the upper section steel member 1 and the lower section steel member 2 cannot interfere and block the position of the splicing welding line 7, the position of the on-site splicing welding line 7 is avoided, the splicing welding line 7 can be welded continuously, the number of starting and landing arcs is reduced, and the welding line quality is improved.
In this embodiment, the upper groove wall of the tenon 3 is provided with a wedge surface 8, the outer end of the wedge surface 8 is high, the inner end is low, the adjusting screw 6 can be abutted on the wedge surface 8, a gap is reserved between the tenon 4 and the side wall of the tenon 3, and when the adjusting screw 6 abuts against the wedge surface 8, the tenon 4 can be slightly jacked upwards, so that the upper steel member 1 can slightly deflect to one side, the position of the upper steel member 1 is adjusted, the upper steel member 1 is horizontally positioned on the lower steel member 2, and the situation that the upper steel member 1 is inclined due to uneven connecting end surfaces of the upper steel member 1 and the lower steel member 2 is avoided.
In this embodiment, a screw hole 9 adapted to the adjusting screw 6 is provided on the outer wall of the lower steel member 2, and the adjusting screw 6 mounted in the screw hole 9 can abut against the cam surface 8. A gap is arranged between the side wall of the tenon 4 and the groove wall of the tenon opening 3. The adjusting screw 6 is propped against the inclined wedge surface 8 on the upper surface of the notch of the clamping groove 5 of the slotted tenon 4 through the screw hole 9 on the lower section steel member 2; because the upper surface of the notch is slightly inclined, the upper section steel member 1 can be lifted or lowered by screwing the adjusting screw 6 to advance and retreat, and the inclination of the upper section steel member 1 is adjusted.
The inclination of the upper section steel member 1 can be adjusted at any time through the adjusting screw 6 during construction, the upper section steel member 1 is vertically installed on the lower section steel member 2, and then the upper section steel member 1 and the lower section steel member 2 are fixed through welding at the splicing welding seam 7.
In this embodiment, the tenon 4 has a square structure, and the mortise 3 has a square groove structure.
In this embodiment, the clamping groove 5 is a transverse groove extending transversely on the outer side surface of the bottom of the tenon 4, and the inclined wedge surface 8 has an inclination angle of 3 ° to 15 °.
In the temporary connecting device for the slotted tenon type construction arranged in the closed steel member, the shearing force born by the upper section steel member 1 is transmitted to the wall plate of the lower section steel member 2 and the wall plate of the tenon 3 through the tenon 4. The pressure borne by the upper steel member 1 is transmitted to the lower steel member 2 through the tightly-propped end surfaces of the upper steel member 1 and the lower steel member 2, the tenons 4 and the adjusting screws 6. The bending moment born by the upper section steel member 1 transmits the prying force between the rabbet 4 and the rabbet 3 to the lower section steel member 2. The adjusting screw 6 also ensures that the tenon 4 does not pull out the mortise 3.
The foregoing is merely a preferred embodiment of the present utility model, and it should be noted that modifications and improvements can be made by those skilled in the art without departing from the structure of the present utility model, and these do not affect the effect of the implementation of the present utility model and the utility of the patent.

Claims (5)

1. The utility model provides a arrange inside temporary connecting device of slotted tenon formula construction of steel member in closing, includes upper segment steel member (1) and hypomere steel member (2), its characterized in that, the top of hypomere steel member (2) inner wall is equipped with tenon (3), upper segment steel member (1) bottom be equipped with tenon (4) of tenon (3) looks adaptation, tenon (4) and tenon (3) clearance fit, the outside of tenon (4) is equipped with draw-in groove (5), threaded connection has on the outer wall of hypomere steel member (2) can insert adjusting screw (6) in draw-in groove (5).
2. The temporary connection device for open-tenon construction placed inside a closed steel member according to claim 1, wherein the bottom end of the outer wall of the upper steel member (1) is provided with a splice weld (7).
3. A temporary connection for open-mortised construction placed inside a closed steel element according to claim 1 or 2, characterised in that the upper groove wall of the mortised (3) is provided with a wedge surface (8), on which wedge surface (8) the adjusting screw (6) can abut.
4. A temporary connection device for open-tenon construction placed inside a closed steel member according to claim 3, characterized in that the outer wall of the lower steel member (2) is provided with a screw hole (9) adapted to the adjusting screw (6), and the adjusting screw (6) installed in the screw hole (9) can be abutted against the wedge surface (8).
5. A temporary connection for open-mortised construction placed inside a closed steel element according to claim 4, characterised in that the clamping groove (5) is a transversal groove extending transversely on the outer side of the bottom of the tenon (4).
CN202223362588.4U 2022-12-13 2022-12-13 Put in inside temporary connecting device of slotting tenon formula construction of steel member that seals Active CN219175489U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223362588.4U CN219175489U (en) 2022-12-13 2022-12-13 Put in inside temporary connecting device of slotting tenon formula construction of steel member that seals

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223362588.4U CN219175489U (en) 2022-12-13 2022-12-13 Put in inside temporary connecting device of slotting tenon formula construction of steel member that seals

Publications (1)

Publication Number Publication Date
CN219175489U true CN219175489U (en) 2023-06-13

Family

ID=86663544

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223362588.4U Active CN219175489U (en) 2022-12-13 2022-12-13 Put in inside temporary connecting device of slotting tenon formula construction of steel member that seals

Country Status (1)

Country Link
CN (1) CN219175489U (en)

Similar Documents

Publication Publication Date Title
CN109610641A (en) A kind of quick splicing node and its construction method suitable for all types of steel columns
CN211622592U (en) Template assembly for construction of deformation joint of building structure
CN105804387A (en) Wall connecting piece and assembling and disassembling method thereof
CN219175489U (en) Put in inside temporary connecting device of slotting tenon formula construction of steel member that seals
CN111576916A (en) Large-size hole-opening combined reinforcing structure and reinforcing method for shear wall
CN221609524U (en) Aluminum template and wood template connection structure
CN113107199B (en) Beam wall fast-assembling early-dismantling beam structure convenient for beam bottom adjusting and positioning
CN209723217U (en) A kind of quick splicing node suitable for all types of steel columns
CN110565943B (en) Steel back edge for reinforcing combined type assembled cast-in-situ hidden column template and mounting method
CN112523529A (en) Simple protective door for edge-facing opening and using method thereof
CN211312508U (en) Precast concrete pile connection structure
CN221646170U (en) Reinforcing steel bar side-by-side splicing device and structure
CN115788076B (en) Temporary connecting device for prestressed cable construction arranged in closed steel member
CN113323143A (en) Building steel tube bundle supporting platform structure
CN112982975A (en) Method for reserving and forming accurate pore passages in corner structures of buildings
CN211850203U (en) Detachable heat-insulation connecting assembly for prefabricated external wall and prefabricated superposed component
CN208593935U (en) Elevator steel structure frame quarter bend positions coupling structure
CN219734987U (en) H-shaped steel easy to install
CN218842888U (en) Splicing apparatus of steel construction for bridge construction
CN215252816U (en) Temporary locking device for joint of steel reinforcement cage
CN216380558U (en) Drilling-free template reinforcing structure for shear wall construction
CN216714396U (en) Pipe jacking construction device suitable for small-caliber pipe jacking well
CN114473342B (en) Overhead butt joint tool for steel structure building
CN219808274U (en) Spacing structure
CN215055293U (en) Shear force wall evagination lines template constructional device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant