CN219100666U - Climbing form lower hanging platform stabilizing mechanism - Google Patents

Climbing form lower hanging platform stabilizing mechanism Download PDF

Info

Publication number
CN219100666U
CN219100666U CN202223006531.0U CN202223006531U CN219100666U CN 219100666 U CN219100666 U CN 219100666U CN 202223006531 U CN202223006531 U CN 202223006531U CN 219100666 U CN219100666 U CN 219100666U
Authority
CN
China
Prior art keywords
platform
wall
fixedly connected
hanging platform
lower hanging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223006531.0U
Other languages
Chinese (zh)
Inventor
余大海
姚志刚
贾建祥
杨正茂
王伟
杨磊
吕明
叶建平
杨仁飞
王斌
肖福鑫
刘杰武
李城茂
孙凯
徐国杰
杨铠铨
范双
彭诗苡
陆灿
舒宁
吴远进
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No 4 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group
Original Assignee
No 4 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No 4 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group filed Critical No 4 Construction Engineering Co Ltd of Guizhou Construction and Engineering Group
Priority to CN202223006531.0U priority Critical patent/CN219100666U/en
Application granted granted Critical
Publication of CN219100666U publication Critical patent/CN219100666U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00—Energy generation through renewable energy sources
    • Y02E10/20—Hydro energy

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

本实用新型公开了一种爬模下挂平台稳定机构,包括剪力墙和爬模下挂平台,所述爬模下挂平台侧壁开设有滑槽,所述滑槽内壁滑动连接有延伸平台,所述爬模下挂平台下端固定连接有加强杆,所述加强杆另一端通过第一螺栓与剪力墙固定连接,所述加强杆侧壁固定连接有固定筒,所述固定筒内壁滑动连接有稳定杆,所述稳定杆另一端与延伸平台下端固定连接,所述滑槽内安装有驱动机构,所述驱动机构包括转动连接在滑槽内壁的丝杠,所述丝杠侧壁与延伸平台螺纹连接,所述驱动机构还包括开设在爬模下挂平台内的凹槽。本实用新型能够对爬模下挂平台和延伸平台起到支撑作用,使得爬模下挂平台和延伸平台的稳定性更好,更好安全。

Figure 202223006531

The utility model discloses a stabilizing mechanism for a climbing formwork hanging platform, which comprises a shear wall and a climbing formwork hanging platform. The side wall of the climbing formwork hanging platform is provided with a chute, and the inner wall of the chute is slidably connected with an extension platform. , the lower end of the hanging platform of the climbing formwork is fixedly connected with a reinforcement rod, the other end of the reinforcement rod is fixedly connected with the shear wall through the first bolt, the side wall of the reinforcement rod is fixedly connected with a fixed cylinder, and the inner wall of the fixed cylinder slides A stabilizer bar is connected, the other end of the stabilizer bar is fixedly connected to the lower end of the extension platform, a drive mechanism is installed in the chute, and the drive mechanism includes a lead screw that is rotatably connected to the inner wall of the chute, and the side wall of the lead screw is connected to the The extension platform is screwed, and the drive mechanism also includes a groove provided in the hanging platform of the climbing formwork. The utility model can support the lower hanging platform and the extension platform of the climbing formwork, so that the stability and safety of the lower hanging platform and the extension platform of the climbing formwork are better.

Figure 202223006531

Description

一种爬模下挂平台稳定机构A Stabilizing Mechanism for Hanging Platform Under Climbing Formwork

技术领域technical field

本实用新型涉及建筑施工技术领域,尤其涉及一种爬模下挂平台稳定机构。The utility model relates to the technical field of building construction, in particular to a climbing formwork hanging platform stabilization mechanism.

背景技术Background technique

爬模下挂平台在建筑施工过程中起着十分重要的作用,工人通过站在爬模下挂平台上对建筑物进行施工,因此其稳定性是十分重要的,它保障这建筑施工人员的生命安全。The hanging platform under the climbing formwork plays a very important role in the construction process. Workers construct the building by standing on the hanging platform under the climbing formwork. Therefore, its stability is very important, and it guarantees the life of the construction workers. Safety.

现有的爬模下挂平台通过螺栓安装在剪力墙侧壁,而由于爬模下挂平台的结构固定,无法根据使用情况对爬模下挂平台的宽度进行调节,因此现有的爬模下挂平台在使用过程中存在很大的局限性,使用起来十分的不方便,并且稳定性能也不好,基于此,我们提出一种爬模下挂平台稳定机构。The existing climbing formwork hanging platform is installed on the side wall of the shear wall through bolts, but because the structure of the climbing formwork hanging platform is fixed, the width of the climbing formwork hanging platform cannot be adjusted according to the use situation, so the existing climbing formwork There are great limitations in the use of the hanging platform, which is very inconvenient to use, and the stability performance is not good. Based on this, we propose a stabilizing mechanism for the climbing formwork hanging platform.

实用新型内容Utility model content

本实用新型的目的是为了解决现有技术中存在的缺点,而提出的一种爬模下挂平台稳定机构。The purpose of the utility model is to solve the shortcomings in the prior art, and propose a climbing formwork hanging platform stabilization mechanism.

为了实现上述目的,本实用新型采用了如下技术方案:In order to achieve the above object, the utility model adopts the following technical solutions:

一种爬模下挂平台稳定机构,包括剪力墙和爬模下挂平台,所述爬模下挂平台侧壁开设有滑槽,所述滑槽内壁滑动连接有延伸平台,所述爬模下挂平台下端固定连接有加强杆,所述加强杆另一端通过第一螺栓与剪力墙固定连接,所述加强杆侧壁固定连接有固定筒,所述固定筒内壁滑动连接有稳定杆,所述稳定杆另一端与延伸平台下端固定连接,所述滑槽内安装有驱动机构。A climbing formwork hanging platform stabilization mechanism, comprising a shear wall and a climbing formwork hanging platform, the side wall of the climbing formwork hanging platform is provided with a chute, the inner wall of the chute is slidably connected with an extension platform, and the climbing formwork The lower end of the hanging platform is fixedly connected with a reinforcing rod, the other end of the reinforcing rod is fixedly connected with the shear wall through the first bolt, the side wall of the reinforcing rod is fixedly connected with a fixing tube, and the inner wall of the fixing tube is slidably connected with a stabilizing rod, The other end of the stabilizer bar is fixedly connected to the lower end of the extension platform, and a driving mechanism is installed in the chute.

优选地,所述驱动机构包括转动连接在滑槽内壁的丝杠,所述丝杠侧壁与延伸平台螺纹连接。Preferably, the driving mechanism includes a lead screw rotatably connected to the inner wall of the chute, and the side wall of the lead screw is screwed to the extension platform.

优选地,所述驱动机构还包括开设在爬模下挂平台内的凹槽,所述凹槽内壁转动连接有转轴,所述转轴侧壁固定连接有第一锥齿轮,所述丝杠一端延伸至凹槽内并固定连接有第二锥齿轮,所述第一锥齿轮与第二锥齿轮啮合连接,所述爬模下挂平台侧壁固定连接有电机,所述电机输出端贯穿爬模下挂平台侧壁并与转轴固定连接。Preferably, the driving mechanism further includes a groove provided in the lower hanging platform of the climbing form, the inner wall of the groove is rotatably connected with a rotating shaft, the side wall of the rotating shaft is fixedly connected with a first bevel gear, and one end of the lead screw extends Into the groove and fixedly connected with the second bevel gear, the first bevel gear is meshed with the second bevel gear, the side wall of the hanging platform under the climbing formwork is fixedly connected with a motor, and the output end of the motor runs through the bottom of the climbing formwork Hang the side wall of the platform and be fixedly connected with the rotating shaft.

优选地,所述延伸平台上端固定连接有栏杆。Preferably, railings are fixedly connected to the upper end of the extension platform.

优选地,所述滑槽内壁转动连接有多个滚珠。Preferably, a plurality of balls are rotatably connected to the inner wall of the chute.

优选地,所述爬模下挂平台侧壁通过多个第二螺栓与剪力墙固定连接。Preferably, the side wall of the lower hanging platform of the climbing formwork is fixedly connected to the shear wall through a plurality of second bolts.

本实用新型具有以下有益效果:The utility model has the following beneficial effects:

1、通过设置滑槽、延伸平台和驱动机构,通过驱动电机转动,可以带动延伸平台水平移动,从而对整个平台的宽度进行自由调节,适用范围更广,使用起来更加方便。1. By setting the chute, the extension platform and the driving mechanism, the extension platform can be driven to move horizontally by driving the motor to rotate, so that the width of the entire platform can be adjusted freely, the application range is wider, and it is more convenient to use.

2、通过设置加强杆、固定筒和稳定杆,能够对爬模下挂平台和延伸平台起到支撑作用,使得爬模下挂平台和延伸平台的稳定性更好,更好安全。2. By setting the reinforcing bar, the fixing tube and the stabilizing bar, it can play a supporting role for the hanging platform and the extension platform of the climbing formwork, so that the stability and safety of the hanging platform and the extension platform of the climbing formwork are better.

附图说明Description of drawings

图1为本实用新型提出的一种爬模下挂平台稳定机构的结构示意图;Fig. 1 is the structural representation of a kind of climbing formwork lower hanging platform stabilizing mechanism that the utility model proposes;

图2为图1中结构的后视示意图;Fig. 2 is a rear view schematic diagram of the structure in Fig. 1;

图3为图1中A处结构的放大示意图。FIG. 3 is an enlarged schematic view of the structure at A in FIG. 1 .

图中:1剪力墙、2爬模下挂平台、3滑槽、4延伸平台、5加强杆、6第一螺栓、7固定筒、8稳定杆、9丝杠、10凹槽、11转轴、12第一锥齿轮、13第二锥齿轮、14电机、15栏杆、16滚珠、17第二螺栓。In the figure: 1 shear wall, 2 hanging platform of climbing formwork, 3 chute, 4 extension platform, 5 reinforcing rod, 6 first bolt, 7 fixing cylinder, 8 stabilizing rod, 9 lead screw, 10 groove, 11 rotating shaft , 12 first bevel gears, 13 second bevel gears, 14 motors, 15 railings, 16 balls, 17 second bolts.

具体实施方式Detailed ways

下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. example.

在本实用新型的描述中,需要理解的是,术语“上”、“下”、“前”、“后”、“左”、“右”、“顶”、“底”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本实用新型和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本实用新型的限制。In describing the present utility model, it should be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", The orientation or positional relationship indicated by "outside" is based on the orientation or positional relationship shown in the drawings, which is only for the convenience of describing the utility model and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation , are constructed and operated in a specific orientation and therefore cannot be construed as limiting the invention.

参照图1-3,一种爬模下挂平台稳定机构,包括剪力墙1和爬模下挂平台2,爬模下挂平台2侧壁开设有滑槽3,滑槽3内壁滑动连接有延伸平台4,爬模下挂平台2下端固定连接有加强杆5,加强杆5另一端通过第一螺栓6与剪力墙1固定连接,加强杆5侧壁固定连接有固定筒7,固定筒7内壁滑动连接有稳定杆8,稳定杆8另一端与延伸平台4下端固定连接,稳定杆8呈L形状,滑槽3内安装有驱动机构。Referring to Figure 1-3, a climbing formwork hanging platform stabilization mechanism includes a shear wall 1 and a climbing formwork hanging platform 2, a chute 3 is opened on the side wall of the climbing formwork hanging platform 2, and the inner wall of the chute 3 is slidingly connected with The extension platform 4, the lower end of the hanging platform 2 of the climbing formwork is fixedly connected with a reinforcing rod 5, the other end of the reinforcing rod 5 is fixedly connected with the shear wall 1 through the first bolt 6, and the side wall of the reinforcing rod 5 is fixedly connected with a fixed cylinder 7, and the fixed cylinder The 7 inner walls are slidingly connected with a stabilizing rod 8, the other end of the stabilizing rod 8 is fixedly connected with the lower end of the extension platform 4, the stabilizing rod 8 is L-shaped, and a drive mechanism is installed in the chute 3.

驱动机构包括转动连接在滑槽3内壁的丝杠9,丝杠9侧壁与延伸平台4螺纹连接,需要说明的是,延伸平台4侧壁与滑槽3内壁相抵,使得延伸平台4不会随着丝杠9一起转动,驱动机构还包括开设在爬模下挂平台2内的凹槽10,凹槽10内壁转动连接有转轴11,转轴11侧壁固定连接有第一锥齿轮12,丝杠9一端延伸至凹槽10内并固定连接有第二锥齿轮13,第一锥齿轮12与第二锥齿轮13啮合连接,爬模下挂平台2侧壁固定连接有电机14,电机14输出端贯穿爬模下挂平台2侧壁并与转轴11固定连接。The drive mechanism includes a lead screw 9 that is rotatably connected to the inner wall of the chute 3, and the side wall of the lead screw 9 is threadedly connected with the extension platform 4. It should be noted that the side wall of the extension platform 4 is against the inner wall of the chute 3, so that the extension platform 4 will not Along with the lead screw 9 rotates together, the driving mechanism also includes a groove 10 provided in the hanging platform 2 of the climbing formwork. One end of the bar 9 extends into the groove 10 and is fixedly connected with the second bevel gear 13, the first bevel gear 12 is meshed with the second bevel gear 13, and the side wall of the hanging platform 2 under the climbing form is fixedly connected with the motor 14, and the motor 14 outputs The end passes through the side wall of the hanging platform 2 of the climbing formwork and is fixedly connected with the rotating shaft 11.

延伸平台4上端固定连接有栏杆15,栏杆15可以对爬模下挂平台2上的施工人员进行保护,避免其从爬模下挂平台2上摔落。The extension platform 4 upper end is fixedly connected with railing 15, and railing 15 can protect the construction personnel on the hanging platform 2 under the climbing formwork, and prevents it from falling down from the hanging platform 2 under the climbing formwork.

滑槽3内壁转动连接有多个滚珠16,延伸平台4在滑槽3内壁滑动时,滚珠16会转动,将延伸平台4与滑槽3内壁之间的滑动摩擦转变为滚动摩擦,减小摩擦力,便于延伸平台4滑动,同时也可以降低电机14的负荷,提高电机14的使用寿命。The inner wall of the chute 3 is rotatably connected with a plurality of balls 16. When the extension platform 4 slides on the inner wall of the chute 3, the balls 16 will rotate to convert the sliding friction between the extension platform 4 and the inner wall of the chute 3 into rolling friction, reducing the friction Force, easy to extend the platform 4 to slide, also can reduce the load of motor 14 simultaneously, improve the service life of motor 14.

爬模下挂平台2侧壁通过多个第二螺栓17与剪力墙1固定连接。The side wall of the climbing formwork hanging platform 2 is fixedly connected with the shear wall 1 through a plurality of second bolts 17 .

本实用新型中,首先通过第二螺栓17将爬模下挂平台2与剪力墙1固定连接,然后在通过第一螺栓6将加强杆5与剪力墙1固定,爬模下挂平台2、剪力墙1与加强杆5之间形成三角形结构,使得爬模下挂平台2会更加稳定,而固定筒7、稳定杆8和延伸平台4之间也形成三角形结构,使得延伸平台4也更为稳定。In the utility model, firstly, the platform 2 under the climbing formwork is fixedly connected with the shear wall 1 through the second bolt 17, and then the reinforcement rod 5 is fixed with the shear wall 1 through the first bolt 6, and the platform 2 under the climbing formwork is fixed. , A triangular structure is formed between the shear wall 1 and the reinforcing rod 5, so that the hanging platform 2 under the climbing formwork will be more stable, and a triangular structure is also formed between the fixed tube 7, the stabilizing bar 8 and the extension platform 4, so that the extension platform 4 is also more stable.

通过驱动电机14转动,带动转轴11转动,带动第一锥齿轮12转动,带动第二锥齿轮13转动,进而带动丝杠9转动,带动延伸平台4水平移动,此时稳定杆8也会随着延伸平台4一起移动,可以对延伸平台4的位置进行调节,从而可以根据实际使用情况对整个平台的宽度进行调节,适用范围更广。By driving the motor 14 to rotate, the rotating shaft 11 is driven to rotate, the first bevel gear 12 is driven to rotate, the second bevel gear 13 is driven to rotate, and then the lead screw 9 is driven to rotate to drive the extension platform 4 to move horizontally. The extension platform 4 moves together, and the position of the extension platform 4 can be adjusted, so that the width of the entire platform can be adjusted according to the actual use situation, and the applicable range is wider.

以上所述,仅为本实用新型较佳的具体实施方式,但本实用新型的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本实用新型揭露的技术范围内,根据本实用新型的技术方案及其实用新型构思加以等同替换或改变,都应涵盖在本实用新型的保护范围之内。The above is only a preferred embodiment of the utility model, but the scope of protection of the utility model is not limited thereto. The equivalent replacement or change of the new technical solution and the concept of the utility model shall be covered by the protection scope of the utility model.

Claims (6)

1. The utility model provides a hang platform stabilizing mean under creeping formwork, includes shear force wall (1) and creeping formwork, its characterized in that, creeping formwork hangs platform (2) lateral wall down and has seted up spout (3), spout (3) inner wall sliding connection has extension platform (4), creeping formwork hangs platform (2) lower extreme fixedly connected with stiffener (5) down, stiffener (5) other end is through first bolt (6) and shear force wall (1) fixed connection, stiffener (5) lateral wall fixedly connected with fixed cylinder (7), fixed cylinder (7) inner wall sliding connection has stabilizer bar (8), stabilizer bar (8) other end and extension platform (4) lower extreme fixed connection, install actuating mechanism in spout (3).
2. The climbing form lower hanging platform stabilizing mechanism according to claim 1, wherein the driving mechanism comprises a screw rod (9) rotatably connected to the inner wall of the chute (3), and the side wall of the screw rod (9) is in threaded connection with the extension platform (4).
3. The climbing form lower hanging platform stabilizing mechanism according to claim 2, wherein the driving mechanism further comprises a groove (10) formed in the climbing form lower hanging platform (2), a rotating shaft (11) is rotatably connected to the inner wall of the groove (10), a first bevel gear (12) is fixedly connected to the side wall of the rotating shaft (11), one end of the screw rod (9) extends into the groove (10) and is fixedly connected with a second bevel gear (13), the first bevel gear (12) is meshed with the second bevel gear (13), a motor (14) is fixedly connected to the side wall of the climbing form lower hanging platform (2), and the output end of the motor (14) penetrates through the side wall of the climbing form lower hanging platform (2) and is fixedly connected with the rotating shaft (11).
4. A lower hanging platform stabilizing mechanism for a climbing form according to claim 3, wherein the upper end of the extension platform (4) is fixedly connected with a railing (15).
5. The climbing form lower hanging platform stabilizing mechanism according to claim 4, wherein a plurality of balls (16) are rotatably connected to the inner wall of the chute (3).
6. The climbing form lower hanging platform stabilizing mechanism according to claim 1, wherein the side wall of the climbing form lower hanging platform (2) is fixedly connected with the shear wall (1) through a plurality of second bolts (17).
CN202223006531.0U 2022-11-11 2022-11-11 Climbing form lower hanging platform stabilizing mechanism Active CN219100666U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223006531.0U CN219100666U (en) 2022-11-11 2022-11-11 Climbing form lower hanging platform stabilizing mechanism

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223006531.0U CN219100666U (en) 2022-11-11 2022-11-11 Climbing form lower hanging platform stabilizing mechanism

Publications (1)

Publication Number Publication Date
CN219100666U true CN219100666U (en) 2023-05-30

Family

ID=86463302

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223006531.0U Active CN219100666U (en) 2022-11-11 2022-11-11 Climbing form lower hanging platform stabilizing mechanism

Country Status (1)

Country Link
CN (1) CN219100666U (en)

Similar Documents

Publication Publication Date Title
CN201679222U (en) Double mast climbing work platform
CN206408952U (en) A kind of construction adhesion type lifts discharging platform
CN212249184U (en) Electric creeping formwork device for building construction
CN105016223A (en) Cross beam supporting system used for tower crane
CN218563001U (en) Assembly type structure safety construction platform
CN201286668Y (en) Special-shaped suspension platform
CN211114733U (en) Telescopic shaft platform support
CN209163846U (en) A kind of drawing and pulling type Anchor Agent tamponade device
CN210369893U (en) Light-duty creeping formwork system of lead screw promotion
CN211647291U (en) Electric control rotary lifting type steel platform integral lifting device
CN210798103U (en) A prefabricated steel-concrete structure staircase
CN108277970A (en) Elevator civil construction mobile platform
CN210152203U (en) Installation operation platform for housing construction
CN215858940U (en) Novel detachable combined type steel structure aerial work moving operation platform
CN204999580U (en) A guide frame climbing type work platform overload detection device
CN215716381U (en) Curtain wall system
CN211341824U (en) An assembled steel structure sliding frame
CN211447761U (en) An electric climbing formwork device for building construction
CN209397896U (en) A tunnel construction scaffold
CN208235973U (en) A kind of construction discharging platform
CN111719445B (en) Crack repairing and reinforcing device for small bridge maintenance
CN221759465U (en) Building engineering elevating gear
CN206928661U (en) Concreting workbench is built in a kind of room
CN106348186A (en) Tower type multifunctional truck crane
CN207452729U (en) A kind of bridge rib hoisting and supporting rack integral constructing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PP01 Preservation of patent right

Effective date of registration: 20250822

Granted publication date: 20230530

PP01 Preservation of patent right