CN218952000U - High pier construction platform - Google Patents

High pier construction platform Download PDF

Info

Publication number
CN218952000U
CN218952000U CN202320210480.9U CN202320210480U CN218952000U CN 218952000 U CN218952000 U CN 218952000U CN 202320210480 U CN202320210480 U CN 202320210480U CN 218952000 U CN218952000 U CN 218952000U
Authority
CN
China
Prior art keywords
platform
construction
high pier
fixing
reinforcing rods
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320210480.9U
Other languages
Chinese (zh)
Inventor
聂东周
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Zhongbai Steel Structure Manufacturing Co ltd
Original Assignee
Chongqing Zhongbai Steel Structure Manufacturing Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Zhongbai Steel Structure Manufacturing Co ltd filed Critical Chongqing Zhongbai Steel Structure Manufacturing Co ltd
Priority to CN202320210480.9U priority Critical patent/CN218952000U/en
Application granted granted Critical
Publication of CN218952000U publication Critical patent/CN218952000U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/30Adapting or protecting infrastructure or their operation in transportation, e.g. on roads, waterways or railways

Abstract

The utility model relates to the technical field of construction platforms, in particular to a high pier construction platform which comprises platforms which are wound on the outer side of a high pier and are distributed in a layered manner, wherein the platforms are in a fan shape; the upper surface of the platform is open and is arranged as a standing area, and the upper sides of the end parts of the platform, which are close to each other, are commonly connected with a connecting belt; the inner side of the platform is provided with a connecting seat, a fixing sheet is poured in the connecting seat, reinforcing rods are inserted on the fixing sheet, connecting hoop sheets are jointly installed between the inner sides of the reinforcing rods extending to the lower side of the platform, fixing pins are inserted between the corresponding two reinforcing rods of the connecting hoop sheets, and the fixing pins are used for connecting the connecting hoop sheets with the high pier; the platform is close to each other and all installs the cooperation seat in the tip downside, and the upper end of two cooperation seats is connected with the U-shaped pole jointly. The device reasonable in design, whole construction platform accomplishes the use through quick assembly disassembly's form, is favorable to high mound construction platform's establishment, and has stronger security, and the planar setting of multilayer construction is favorable to promoting the construction progress.

Description

High pier construction platform
Technical Field
The utility model relates to the technical field of construction platforms, in particular to a high pier construction platform.
Background
When the high pier on the highway bridge or the railway bridge is constructed, the hanging type hanging frame is basically adopted, and after constructors make protective measures such as wearing safety belts, construction operation of the surface of the high pier is directly carried out on the hanging frame, so that the safety is poor.
The Chinese patent grant publication No. CN214271708U discloses a high pier turnover formwork construction platform, which comprises a high pier, a formwork and a construction platform, wherein the construction platform comprises an upper annular construction platform and a lower annular construction platform, a hydraulic lifting device and a guide column are arranged between the upper annular construction platform and the lower annular construction platform, the hydraulic lifting device and the guide column can enable the upper annular construction platform and the lower annular construction platform to climb upwards along the formwork, a scaffold is not required to be erected around the high pier, and construction cost is saved.
During construction operation of the high pier in the prior art, the hydraulic lifting device is in an actual use process, cannot guarantee sufficient supply of electric quantity at high altitude, cannot guarantee faults of the hydraulic lifting device, has the advantage of detachable assembly, occupies a large space, and influences smooth construction. For this reason, there is a need to propose an improvement for solving the above-mentioned problems.
Disclosure of Invention
The utility model aims to solve the defects in the prior art, and provides the high pier construction platform, the whole construction platform is used in a form of quick assembly and disassembly, the construction platform is beneficial to the construction of the high pier construction platform, the safety is high, and the arrangement of multiple layers of construction planes is beneficial to the improvement of the construction progress.
In order to achieve the above purpose, the utility model adopts the following technical scheme: the high pier construction platform comprises platforms which are wound on the outer side of a high pier and are distributed in a layered mode, the upper surfaces of the platforms are open and are arranged to be standing areas, and connecting belts are connected to the upper sides of the end parts, close to each other, of the platforms;
the inner side of the platform is provided with a connecting seat, a fixing sheet is poured in the connecting seat, a reinforcing rod is inserted on the fixing sheet, a connecting hoop sheet is jointly installed between the inner sides of the reinforcing rods extending to the lower side of the platform, a fixing pin is inserted between the connecting hoop sheets corresponding to the two reinforcing rods, and the fixing pin is used for connecting the connecting hoop sheet with a high pier;
the platform is close to each other and all installs the cooperation seat in the tip downside, two the upper end of cooperation seat is connected with the U-shaped pole jointly.
Preferably, adjacent platforms in stacked distribution are connected through a mode that reinforcing rods are welded with fixing plates, insertion holes are formed in the fixing plates corresponding to the reinforcing rods, the reinforcing rods extend to the insertion holes and are internally connected with dowel bars, and the dowel bars are connected with the fixing plates.
Preferably, the inner side of the connecting hoop sheet corresponding to the fixing pin is provided with a first mounting groove, the screwing end of the fixing pin is arranged in the first mounting groove, and the fixing pin is an expansion screw with the length larger than the thickness of the connecting hoop sheet.
Preferably, the height of the connecting hoop sheet is twice that of the platform, and the connecting hoop sheet is attached to the inner side of the platform.
Preferably, the connecting belt is composed of a safety construction net with elasticity.
Preferably, the lower end of the outer side of the connecting hoop sheet is provided with a second installation groove which is uniformly distributed, and the connecting hoop sheet is provided with a fixing rod through the second installation groove.
Compared with the prior art, the utility model has the following beneficial effects:
1. according to the construction requirement, the number of layers of the platform is increased, so that the reinforcing rods are connected with the fixing sheets in a welding way, the purpose that the round platform is arranged outside the high pier in a stacking way at the same time, and the purposes that the construction surfaces are layered and are all arranged as construction platforms in the construction process of the high pier are achieved;
2. the number of the platforms can be freely adjusted according to the area of the construction surface, so that the purpose of saving assembly parts of the construction platform is achieved, smooth construction is realized, and construction progress is quickened.
Drawings
FIG. 1 is a schematic diagram of an assembled structure of the present utility model;
FIG. 2 is a schematic view of the bottom view of the structure of the present utility model;
FIG. 3 is a schematic diagram of the main structure of the present utility model;
FIG. 4 is a schematic bottom view of the assembled structure of the present utility model;
FIG. 5 is a schematic diagram of the structural resolution of the monomer structure of the present utility model;
FIG. 6 is a schematic view of a connecting mechanism according to the present utility model;
fig. 7 is a top view of the present utility model.
In the figure: 1. a station; 2. a connecting seat; 3. a standing area; 4. a connecting belt; 5. connecting the hoop sheets; 6. a reinforcing rod; 7. a fixed rod; 8. a fixing pin; 9. a first mounting groove; 10. a second mounting groove; 11. a mating seat; 12. a U-shaped rod; 13. a fixing piece; 14. a jack; 15. and (5) inserting a rib.
Detailed Description
The following description is presented to enable one of ordinary skill in the art to make and use the utility model. The preferred embodiments in the following description are by way of example only and other obvious variations will occur to those skilled in the art.
The high pier construction platform shown in the figures 1-7 comprises platforms 1 which are wound on the outer side of a high pier and are distributed in a layered mode, wherein the platforms 1 are in a fan shape; the upper surface of the platform 1 is opened and is provided with a standing area 3, and the upper sides of the end parts of the platform 1, which are close to each other, are commonly connected with a connecting belt 4; the inner side of the platform 1 is provided with a connecting seat 2, a fixing sheet 13 is poured in the connecting seat 2, a reinforcing rod 6 is inserted on the fixing sheet 13, a connecting hoop sheet 5 is jointly arranged between the inner sides of the reinforcing rods 6 extending to the lower side of the platform 1, a fixing pin 8 is inserted between the connecting hoop sheet 5 corresponding to the two reinforcing rods 6, and the fixing pin 8 is used for connecting the connecting hoop sheet 5 with a high pier; the lower sides of the mutually approaching ends of the platform 1 are respectively provided with a matching seat 11, and the upper ends of the two matching seats 11 are commonly connected with a U-shaped rod 12.
During operation, the connection between the connecting hoop sheet 5 and the high pier outer template is completed through the fixing rod 7, namely, the platform 1 and the connecting hoop sheet 5 can form stable connection with the high pier, further adjacent platforms 1 are respectively clamped on the matching seat 11 through the U-shaped rods 12, single-layer installation of the whole construction platform is achieved, meanwhile, the number of layers of the platforms 1 can be increased according to construction requirements, and the reinforcing rods 6 and the fixing sheets 13 are welded and connected, so that the purposes that the round platforms 1 are simultaneously overlapped and arranged outside the high pier, and the construction surface is layered and set as a construction platform in the construction process of the high pier are achieved; in the actual construction process, the construction direction from bottom to top is generally adopted, after the construction platform at the bottom is constructed, the platform 1 at the bottom is disassembled and assembled in reverse order according to the installation mode, the hanging of each part is completed through the suspension device necessary for high pier construction, the hanging is carried out above the construction platform at the upper side, the reinstallation is completed, the installation process of the construction platform is safe, the cyclic utilization is realized, and the construction progress is promoted.
In this embodiment, adjacent platforms 1 in laminated distribution are connected with a fixing piece 13 by welding the reinforcing rods 6, the fixing piece 13 is provided with insertion holes 14 corresponding to the reinforcing rods 6, the reinforcing rods 6 extend to the insertion holes 14 and are internally connected with dowel bars 15, and the dowel bars 15 are connected with the fixing piece 13.
In this embodiment, the inner side of the connecting band 5 corresponding to the fixing pin 8 is provided with a first mounting groove 9, the screwing end of the fixing pin 8 is disposed in the first mounting groove 9, and the fixing pin 8 is an expansion screw with a length greater than the thickness of the connecting band 5.
In this embodiment, the height of the connecting hoop 5 is twice that of the platform 1, the connecting hoop 5 is attached to the inner side of the platform 1, the connecting belt 4 is composed of a safety construction net with elasticity, and a protection net structure can be formed between the platforms 1, so that the collection of construction falling objects and the safety protection of constructors are facilitated. The lower end of the outer side of the connecting hoop sheet 5 is provided with a second installation groove 10 which is uniformly distributed, and the connecting hoop sheet 5 is provided with a fixing rod 7 through the second installation groove 10.
The working principle of the utility model is as follows:
referring to the description of figures 1-7, in the actual use process of the construction platform, the connection between the connecting hoop sheet 5 and the high pier outer template is completed through the fixing rod 7, namely, the platform 1 and the connecting hoop sheet 5 can form stable connection with the high pier, and further adjacent platforms 1 are respectively clamped on the matching seat 11 through the U-shaped rods 12, so that single-layer installation of the whole construction platform is achieved; according to the construction requirement, the number of layers of the platform 1 is increased, so that the reinforcing rod 6 is welded with the fixing piece 13, the purposes that the round platform 1 is arranged outside the high pier in a stacking mode at the same time, the construction surfaces are layered in the construction process of the high pier and are all arranged as construction platforms are achieved, the number of the platforms 1 can be freely adjusted according to the area of the construction surfaces, and therefore the purpose of saving assembly parts of the construction platforms is achieved;
in the actual construction process, the construction direction from bottom to top is generally adopted, after the construction platform at the bottom is constructed, the platform 1 at the bottom is disassembled and assembled in reverse order according to the installation mode, the hanging of each part is completed through the suspension device necessary for high pier construction, the hanging is carried out above the construction platform at the upper side, the reinstallation is completed, the installation process of the construction platform is safe, the cyclic utilization is realized, and the construction progress is promoted.
To sum up: the whole construction platform is used in a mode of quick assembly disassembly, is beneficial to the construction of the high pier construction platform, has high safety, and is beneficial to the improvement of construction progress due to the arrangement of multiple layers of construction planes.
The foregoing has shown and described the basic principles, principal features and advantages of the utility model. It will be understood by those skilled in the art that the present utility model is not limited to the embodiments described above, and that the above embodiments and descriptions are merely illustrative of the principles of the present utility model, and various changes and modifications may be made therein without departing from the spirit and scope of the utility model, which is defined by the appended claims. The scope of the utility model is defined by the appended claims and equivalents thereof.

Claims (6)

1. High mound construction platform, its characterized in that: the high pier comprises platforms (1) which are wound on the outer side of a high pier and are distributed in a layered mode, wherein the upper surfaces of the platforms (1) are open and are arranged to be standing areas (3), and connecting belts (4) are connected to the upper sides of the end parts, close to each other, of the platforms (1);
the novel high pier connecting device is characterized in that a connecting seat (2) is arranged on the inner side of the platform (1), a fixing sheet (13) is poured in the connecting seat (2), reinforcing rods (6) are inserted into the fixing sheet (13), connecting hoop sheets (5) are jointly arranged between the inner sides of the reinforcing rods (6) extending to the lower side of the platform (1), fixing pins (8) are inserted between the corresponding two reinforcing rods (6) of the connecting hoop sheets (5), and the fixing pins (8) are used for connecting the connecting hoop sheets (5) with the high pier;
the platform (1) is close to each other and is all installed cooperation seat (11) in the tip downside, and two the upper end of cooperation seat (11) is connected with U-shaped pole (12) jointly.
2. The high pier construction platform according to claim 1, wherein adjacent platforms (1) which are distributed in a stacked manner are connected with fixing plates (13) through reinforcing rods (6), insertion holes (14) are formed in the fixing plates (13) corresponding to the reinforcing rods (6), the reinforcing rods (6) extend to the insertion holes (14) and are internally connected with dowel bars (15), and the dowel bars (15) are connected with the fixing plates (13).
3. The high pier construction platform according to claim 1, wherein the inner side of the connecting hoop sheet (5) corresponding to the fixing pin (8) is provided with a first installation groove (9), the screwing end of the fixing pin (8) is arranged in the first installation groove (9), and the fixing pin (8) is an expansion screw with the length larger than the thickness of the connecting hoop sheet (5).
4. The high pier construction platform according to claim 1, characterized in that the height of the connecting hoop sheet (5) is twice as high as that of the platform (1), and the connecting hoop sheet (5) is attached to the inner side of the platform (1).
5. The high pier construction platform according to claim 1, characterized in that the connecting belt (4) is composed of a safety construction net with elasticity.
6. The high pier construction platform according to claim 1, wherein the lower end of the outer side of the connecting hoop sheet (5) is provided with a second installation groove (10) which is uniformly distributed, and the connecting hoop sheet (5) is provided with a fixing rod (7) through the second installation groove (10).
CN202320210480.9U 2023-02-14 2023-02-14 High pier construction platform Active CN218952000U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320210480.9U CN218952000U (en) 2023-02-14 2023-02-14 High pier construction platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320210480.9U CN218952000U (en) 2023-02-14 2023-02-14 High pier construction platform

Publications (1)

Publication Number Publication Date
CN218952000U true CN218952000U (en) 2023-05-02

Family

ID=86102375

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320210480.9U Active CN218952000U (en) 2023-02-14 2023-02-14 High pier construction platform

Country Status (1)

Country Link
CN (1) CN218952000U (en)

Similar Documents

Publication Publication Date Title
CN201116267Y (en) Externally hung supporting device for internally climbing tower crane
CN218952000U (en) High pier construction platform
CN202944998U (en) Attached installation and maintenance platform of calibrated tower crane
CN208748518U (en) A kind of formwork for placing support device
CN212175513U (en) Counter-force supporting and adjusting device for mounting assembled bridge pier cap
CN105971287B (en) Counter force wall vertical prestressing construction method
CN101806153A (en) Knock-down horizontal truss used for resisting lateral bending in lifting sheet large-span steel truss
CN205275070U (en) Wedge type adheres to frame bracing structure
CN210855055U (en) Convenient dismouting of standard festival platform cat ladder is put
CN209685126U (en) A kind of steel vestibule integrally promotes lifting lug device
CN207277870U (en) A kind of elevator protective device with shaped
CN218621750U (en) Steel structure bridge
CN201952736U (en) Auxiliary pier movable bracket for assisting invariable-amplitude beam erecting crane in erecting steel box girder
CN210712577U (en) Temporary support for mounting of arch continuous steel box girder
CN209835356U (en) Aerial conversion platform of construction elevator
CN213563426U (en) A suspension type platform for prefabricating prestressing force stretch-draw of bent cap
CN215716210U (en) Full-bolt buckling-restrained brace
CN219338061U (en) Precast disc buckle type pedestal for concrete arch bridge segment
CN219240305U (en) Assembled pier column construction platform
CN209795779U (en) Efficient and convenient modular shipbuilding auxiliary frame
CN220828093U (en) Coating weather shed
CN219794233U (en) Overlap joint post rigid connection node
CN210066511U (en) Light steel bar framework
CN209353484U (en) A kind of connector of the vertical and oblique lifting of rope
CN212559090U (en) Special lifting appliance for lifting reinforcing cage of bridge deck panel

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant