CN218915871U - Novel energy recovery tunnel furnace - Google Patents

Novel energy recovery tunnel furnace Download PDF

Info

Publication number
CN218915871U
CN218915871U CN202223185482.1U CN202223185482U CN218915871U CN 218915871 U CN218915871 U CN 218915871U CN 202223185482 U CN202223185482 U CN 202223185482U CN 218915871 U CN218915871 U CN 218915871U
Authority
CN
China
Prior art keywords
cavity
tunnel furnace
pipe
novel energy
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223185482.1U
Other languages
Chinese (zh)
Inventor
张伟
孙鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Fenglu Food Technology Co ltd
Original Assignee
Shenyang Fenglu Food Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenyang Fenglu Food Technology Co ltd filed Critical Shenyang Fenglu Food Technology Co ltd
Priority to CN202223185482.1U priority Critical patent/CN218915871U/en
Application granted granted Critical
Publication of CN218915871U publication Critical patent/CN218915871U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P10/00Technologies related to metal processing
    • Y02P10/25Process efficiency

Landscapes

  • Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)

Abstract

The utility model discloses a novel energy recovery tunnel furnace, which comprises a tunnel furnace, wherein a shell, a turbine generator and a storage battery are respectively arranged at the front side of the tunnel furnace from left to right, a first cavity and a second cavity are respectively arranged at the upper end and the lower end of an inner cavity of the shell, one end of a heat conduction pipe is arranged at the bottom end of the inner cavity of the first cavity from left to right, the other end of the heat conduction pipe extends into the inner cavity of the second cavity, and a filter bag and an active carbon filter screen are respectively arranged at the upper end and the lower end of the inner cavity of the first cavity. This novel energy recovery tunnel furnace can recycle tail gas to produce new resource, not only can heat water and discharge, and the water that discharges after the heating can be used to people's daily life water, but also can utilize the vapor that heats water and form to generate electricity, for people provides daily required electric energy, also can purify tail gas simultaneously, is favorable to sustainable development, uses in a flexible way, and the practicality is strong, satisfies the user demand on the current market.

Description

Novel energy recovery tunnel furnace
Technical Field
The utility model relates to the technical field of tunnel furnaces, in particular to a novel energy recovery tunnel furnace.
Background
Tunnel ovens (food processing) are tunnel-type mechanical devices that perform baking of food by conduction, convection, radiation of heat.
At present, in the working process of the existing tunnel furnace, tail gas generated after combustion and baking is directly discharged into air in the form of waste gas, heat in the tail gas is lost, resources are lost, heat cannot be utilized to the maximum extent, a large amount of heat resources are wasted, sustainable development is not facilitated, a lot of trouble is brought to workers, and therefore, based on the defects, the novel energy recovery tunnel furnace is provided for improving the heat.
Disclosure of Invention
The utility model aims to provide a novel energy recovery tunnel furnace so as to solve the problems in the background technology.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides a novel energy recovery tunnel furnace, includes the tunnel furnace, casing, turbo generator and battery are installed respectively from a left side to the right side to the front side of tunnel furnace, first cavity and second cavity have been seted up respectively to both ends about the inner chamber of casing, the one end of heat pipe is all installed from a left side to the right side to the inner chamber bottom of first cavity, and the other end of heat pipe extends into the inner chamber of second cavity, filter bag and active carbon filter screen are installed respectively to both ends about the inner chamber of first cavity, the inlet tube is installed in the left side of casing, the outlet pipe is installed to the front side of casing, the top of tunnel furnace is provided with the one end of blast pipe, and the other end of blast pipe is installed on the top of casing, the one end of connecting pipe is installed to the front side of turbo generator, the valve is all installed to the outer wall of inlet tube, blast pipe and connecting pipe, the power transmission line is installed to the front side of turbo generator.
Preferably, the steam turbine generator and the storage battery are electrically connected through a wire.
Preferably, the distance between the bottom end of the heat conduction pipe and the lower surface of the inner cavity of the second cavity is 5cm.
Preferably, the filter bag is arranged above the active carbon filter screen.
Preferably, a viewing window is provided on the front side of the housing.
Compared with the prior art, the utility model has the beneficial effects that: according to the novel energy recovery tunnel furnace, water can be stored through the cooperation between the second cavity, the water inlet pipe and the water outlet pipe, tail gas generated by baking of the tunnel furnace enters the shell through the exhaust pipe and is filtered by the filter bag and the active carbon filter screen in sequence, the heat in the tail gas can be used for heating the heat conducting pipe, meanwhile, the tail gas can also enter the steam turbine generator through the connecting pipe, the heat conducting pipe can be used for heating stored water in the process of continuously heating the heat conducting pipe, so that the heat conducting pipe is boiled, hot water can be discharged through the water outlet pipe, domestic water is provided for people, after the water is heated and boiled to a certain degree, water can form water vapor, the water vapor can enter the steam turbine generator through the connecting pipe, electric energy can be generated through the treatment of the steam turbine generator due to the tail gas after filtration, part of electric power can be stored in the storage battery for standby, and the other part of electric power can be discharged through the power transmission line, and thus the electric energy is provided for people. The device can recycle tail gas to produce new resources, not only can heat water and discharge, the water that discharges after the heating can be used to people's daily life water, but also can utilize the vapor that heats water and form to generate electricity, for people provides daily required electric energy, also can purify tail gas simultaneously, is favorable to sustainable development, uses in a flexible way, and the practicality is strong, satisfies the user demand on the current market.
Drawings
FIG. 1 is a schematic diagram of the structure of the present utility model;
fig. 2 is a schematic view of a heat conducting pipe structure according to the present utility model.
In the figure: 1. a tunnel furnace, 2, a shell, 3, a turbo generator, 4, a storage battery, 5, a first cavity, 6, a second cavity, 7, a heat conduction pipe, 8, a filter bag, 9, an active carbon filter screen, 10, a water inlet pipe, 11, a water outlet pipe, 12, an exhaust pipe, 13, a connecting pipe, 14, a valve, 15 and a power transmission line.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1-2, the present utility model provides a technical solution: the utility model provides a novel energy recovery tunnel furnace, including tunnel furnace 1, casing 2 is installed respectively from a left side to the right side in tunnel furnace 1, turbo generator 3 and battery 4, first cavity 5 and second cavity 6 have been seted up respectively to both ends about the inner chamber of casing 2, the one end of heat pipe 7 is all installed from a left side to the right to the inner chamber bottom of first cavity 5, and the other end of heat pipe 7 extends into the inner chamber of second cavity 6, filter bag 8 and active carbon filter screen 9 are installed respectively to both ends about the inner chamber of first cavity 5, can purify the filtration to the tail gas through filter bag 8 and active carbon filter screen 9, inlet tube 10 is installed in the left side of casing 2, outlet pipe 11 is installed to the front side of casing 2, the top of tunnel furnace 1 is provided with the one end of blast pipe 12, and the other end of blast pipe 12 is installed on the top of casing 2, the one end of connecting pipe 13 is installed to the front side of casing 2, and the other end of connecting pipe 13 is installed in the front side of turbo generator 3, valve 14 is all installed to the outer wall of inlet tube 10, 11, outlet pipe 12 and connecting pipe 13, power transmission line 15 is installed to the front side of turbo generator 3.
Preferably, the steam turbine generator 3 and the storage battery 4 are electrically connected with each other through wires.
Preferably, the distance between the bottom end of the heat conducting pipe 7 and the lower surface of the inner cavity of the second cavity 6 is 5cm.
As a preferred scheme, the filter bag 8 is arranged above the activated carbon filter screen 9.
As a preferred solution, the front side of the housing 2 is provided with an observation window through which the working conditions inside the housing 2 can be understood.
The electrical components mentioned in the scheme are all the prior art, and the model is only one of the prior art, so long as the electrical components can be used for achieving the purpose in the scheme.
All electric components in the scheme are connected with an adaptive power supply through wires by a person skilled in the art, and an appropriate controller is selected according to actual conditions so as to meet control requirements, specific connection and control sequences, and the electric connection is completed by referring to the working sequence among the electric components in the following working principles, wherein the detailed connection means are known in the art, the working principles and the processes are mainly introduced below, and the electric control is not described any more, and the specific work is as follows.
When the boiler is used, water is injected into the second cavity 6 through the water inlet pipe 10, the tunnel furnace 1 is started, tail gas generated in the working process of the tunnel furnace 1 enters the shell 2 through the exhaust pipe 12, the tail gas sequentially passes through the filter bag 8 and the activated carbon filter screen 9 and contacts with the heat conducting pipe 7, the heat in the tail gas can be used for heating the heat conducting pipe 7, meanwhile, the tail gas also enters the steam turbine generator 3 through the connecting pipe 13, in the process of continuously heating the heat conducting pipe 7, the heat conducting pipe 7 can be used for heating water injected into the second cavity 6 so as to boil the water, the hot water can be discharged from the water outlet pipe 11, so that domestic water is provided for people, after the water is heated and boiled to a certain extent, the water vapor can be formed into the steam turbine generator 3 through the connecting pipe 13, electric energy can be generated through the treatment of the steam turbine generator 3 due to the filtered tail gas and the entering of the water vapor, wherein part of the electric energy can be stored in the storage battery 4 for standby power transmission line, and the other part of the electric energy can be discharged through 15, and thus the electric energy is provided for people; the device can recycle tail gas to produce new resources, not only can heat water and discharge, the water discharged after the heating can be used for daily life water of people, but also can utilize the vapor formed by heating water to generate electricity, provide daily required electric energy for people, simultaneously can purify tail gas, is favorable to sustainable development, uses in a flexible way, and the practicality is strong, is fit for promoting.
In the description of the present utility model, it should be understood that the terms "coaxial," "bottom," "one end," "top," "center location," "other end," "upper," "one side," "top," "inner," "front," "center," "two ends," etc. indicate orientations or positional relationships based on the orientation or positional relationships shown in the drawings, merely to facilitate describing the present utility model and simplify the description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be configured and operate in a particular orientation; meanwhile, unless explicitly specified and limited otherwise, the terms "snap-in," "socket," "weld," "mount," "set," "interference fit," "screw connection," "pin connection," and the like are to be construed broadly, and may be, for example, a fixed connection, a removable connection, or an integral body; can be mechanically or electrically connected; either directly or indirectly through intermediaries, or in communication with each other or in interaction with each other, unless explicitly defined otherwise, the meaning of the terms described above in this application will be understood by those of ordinary skill in the art in view of the specific circumstances.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides a novel energy recuperation tunnel furnace, includes tunnel furnace (1), its characterized in that: the utility model discloses a steam turbine generator, including casing (2), turbo generator (3) and battery (4) are installed respectively to the front side of tunnel furnace (1) from a left side to the right side, first cavity (5) and second cavity (6) have been seted up respectively to both ends about the inner chamber of casing (2), the one end of heat pipe (7) is all installed from a left side to the right side to the inner chamber bottom of first cavity (5), and the other end of heat pipe (7) extends into the inner chamber of second cavity (6), filter bag (8) and active carbon filter screen (9) are installed respectively to both ends about the inner chamber of first cavity (5), inlet tube (10) are installed in the left side of casing (2), outlet pipe (11) are installed to the front side of casing (2), the top of tunnel furnace (1) is provided with the one end of blast pipe (12), and the other end of blast pipe (12) is installed on the top of casing (2), the one end of connecting pipe (13) is installed to the front side of heat pipe (13), and the other end of connecting pipe (13) is installed in the front side of generator (3), turbo generator (14) are installed in front of the connecting pipe (13), and the outer wall (15) are installed in front of the connecting pipe (14).
2. The novel energy recovery tunnel furnace according to claim 1, wherein: the steam turbine generator (3) and the storage battery (4) are electrically connected through a wire.
3. The novel energy recovery tunnel furnace according to claim 1, wherein: the space between the bottom end of the heat conduction pipe (7) and the lower surface of the inner cavity of the second cavity (6) is 5cm.
4. The novel energy recovery tunnel furnace according to claim 1, wherein: the filter bag (8) is arranged above the active carbon filter screen (9).
5. The novel energy recovery tunnel furnace according to claim 1, wherein: the front side of the shell (2) is provided with an observation window.
CN202223185482.1U 2022-11-30 2022-11-30 Novel energy recovery tunnel furnace Active CN218915871U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223185482.1U CN218915871U (en) 2022-11-30 2022-11-30 Novel energy recovery tunnel furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223185482.1U CN218915871U (en) 2022-11-30 2022-11-30 Novel energy recovery tunnel furnace

Publications (1)

Publication Number Publication Date
CN218915871U true CN218915871U (en) 2023-04-25

Family

ID=86041042

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223185482.1U Active CN218915871U (en) 2022-11-30 2022-11-30 Novel energy recovery tunnel furnace

Country Status (1)

Country Link
CN (1) CN218915871U (en)

Similar Documents

Publication Publication Date Title
CN204361942U (en) For Blast Furnace Top Gas Recovery Turbine Unit (TRT) and the domestic boiler system of domestic boiler
CN212132384U (en) Vertical electrode hot water boiler
CN105819398A (en) Arc plasma hydrogen-energy steam generator
CN106287634A (en) A kind of injecting type high-voltage electrode boiler
CN218915871U (en) Novel energy recovery tunnel furnace
CN205351366U (en) Flue gas reutilization biomass boiler
CN204757331U (en) Dual -purpose vacuum furnace of gas and electrical heating
CN210833113U (en) Metal smelting furnace with recyclable waste heat
CN211025691U (en) Thermal regeneration system of adsorbent
CN209386825U (en) A kind of waste heat recycling device for ferro-boron smelting furnace
CN106185802A (en) Hydrolysis Hydrogen Energy combustion method and device
CN209840408U (en) Efficient environment-friendly energy-saving boiler
CN213021094U (en) Boiler waste heat recycling device
CN220583093U (en) Energy-saving and environment-friendly graphitizing furnace
CN201416111Y (en) Heating pipe type garment steamer
CN104913483A (en) Fuel gas and electric heating dual-use vacuum furnace
CN212609595U (en) Fluorination furnace temperature rising and heat preservation device
EP2827435A1 (en) Energy converter
CN217978984U (en) New forms of energy air can heating equipment
CN221238186U (en) Special waste heat recovery system for ITO target sintering furnace
CN213089788U (en) Steam and hot air dual-purpose boiler
CN219243558U (en) Modularized low-hydrogen high-efficiency gas steam generator
CN212777906U (en) Quick water heater
CN216107681U (en) Crumpling machine with heat recovery structure
CN219415255U (en) Miniaturized hydrogen energy wall-mounted furnace

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant