CN218911491U - Combined temporary building fast-assembling foundation - Google Patents

Combined temporary building fast-assembling foundation Download PDF

Info

Publication number
CN218911491U
CN218911491U CN202223254640.4U CN202223254640U CN218911491U CN 218911491 U CN218911491 U CN 218911491U CN 202223254640 U CN202223254640 U CN 202223254640U CN 218911491 U CN218911491 U CN 218911491U
Authority
CN
China
Prior art keywords
sleeve
pile
foundation
annular plate
temporary building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223254640.4U
Other languages
Chinese (zh)
Inventor
周龙壮
杨帅
赵帅普
时亮
陈臻泽
焦宗骞
江坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Shandong Construction Engineering Co ltd
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Shandong Construction Engineering Co ltd
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Shandong Construction Engineering Co ltd, China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Shandong Construction Engineering Co ltd
Priority to CN202223254640.4U priority Critical patent/CN218911491U/en
Application granted granted Critical
Publication of CN218911491U publication Critical patent/CN218911491U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a combined temporary building quick-mounting foundation, which belongs to the technical field of temporary building foundation construction and comprises a screw pile, a flange, a limiting part, section steel and a connecting part; the spiral pile is buried underground; the flange is fixedly arranged on the top surface of the spiral pile; the section steel is fixedly connected with the flange; the connecting piece is connected with two adjacent section steel; the limiting piece comprises a sleeve, a ring plate, a connecting rod and a fixing bolt; the sleeve is sleeved at the top of the spiral pile; the annular plate is horizontally arranged around the surface of the sleeve, the bottom surface of the annular plate is contacted with the ground, the sleeve below the annular plate is buried underground, and the sleeve above the annular plate is exposed out of the ground; the connecting rod is transversely inserted into the sleeve and the fixed pile; the fixing bolt is buried underground and connected with the annular plate. The components are connected through bolts, so that the installation and the disassembly are convenient; through setting up the locating part, guarantee that the fixed pile exposes the high same on ground, the annular plate contacts with ground, avoids the fixed pile to appear sinking the phenomenon, guarantees the level setting of foundation beam.

Description

Combined temporary building fast-assembling foundation
Technical Field
The utility model belongs to the technical field of temporary construction foundations, and particularly relates to a combined temporary building quick-mounting foundation.
Background
Most of the temporary building board house foundations adopt concrete pile foundations, enough maintenance time is needed after the traditional concrete piles are poured, and the construction period is long; the mud protection wall needs a mud pit, so that certain environmental pollution is caused; the construction of the concrete filling pile requires a larger working surface, and the large-area earth and stone excavation can damage the vegetation on the ground surface and can have a certain influence on ecological balance and water and soil conservation; when the temporary construction is dismantled, the concrete pile foundation is dismantled for a long time.
And then, the spiral pile is used as a temporary building board house foundation in part of construction sites, the application of the spiral pile can make up for the defects of the concrete pile foundation to a certain extent, but in actual construction, the spiral pile foundation still has the following problems: the screw pile may sink in soft soil, and in pile driving process, the screw pile needs to be repeatedly measured and positioned to maintain the consistent height of the exposed ground, which affects the construction progress and greatly limits the application range.
Disclosure of Invention
The utility model aims to provide a combined temporary building quick-mounting foundation, which solves the problems that a spiral pile in the background technology can sink, repeated measurement and positioning are needed in the piling process, and the construction progress is affected.
In order to achieve the above purpose, the present utility model provides the following technical solutions: a combined temporary building quick-assembly foundation comprises a screw pile, a flange, a limiting piece, profile steel and a connecting piece; the spiral pile is buried underground; the flange is fixedly arranged on the top surface of the spiral pile; the section steel is fixedly connected with the flange; the connecting piece is connected with two adjacent section steel;
the limiting piece comprises a sleeve, a ring plate, a connecting rod and a fixing bolt; the sleeve is sleeved at the top of the spiral pile; the annular plate is horizontally arranged around the surface of the sleeve, the bottom surface of the annular plate is in contact with the ground, the sleeve below the annular plate is buried underground, and the sleeve above the annular plate is exposed out of the ground; the connecting rod is transversely inserted into the sleeve and the fixed pile; the fixing bolts are buried underground and connected with the annular plate.
Further, the screw pile is a steel screw pile and is arranged at intervals and comprises a central steel shaft and screw blades.
Further, the section steel is H-shaped steel and comprises a lower wing plate, a web plate and an upper wing plate, and the lower wing plate is connected with a flange through bolts.
Further, the connecting piece comprises two connecting plates which are respectively arranged on the inner side and the outer side of the section steel.
Further, the cross section of the connecting plate is L-shaped, and the connecting plate comprises two side plates which are connected with each other, and the two side plates are respectively connected with webs of the two sections by bolts.
Further, the points of the spiral piles are distributed in a rectangular shape in space; the section steel integrally encloses to form a rectangular foundation.
Further, the part of the screw pile corresponding to the limiting piece is not provided with screw blades, and the inner diameter of the sleeve is matched with the outer diameter of the central steel shaft.
The utility model has the following beneficial effects:
1. according to the combined temporary building quick-mounting foundation, the steel screw piles are tightly connected with the H-shaped steel to bear the structural gravity of the temporary building, and the components are connected through the bolts, so that the combined temporary building quick-mounting foundation is convenient to mount and dismount, can be recycled after the screw piles are pulled out after project construction is completed, reduces material cost, and accords with the green building concept.
2. According to the combined temporary building quick-mounting foundation, the positions of the fixed piles are limited by arranging the limiting parts, so that the exposed heights of the fixed piles on the ground are guaranteed to be the same, repeated measurement is avoided, construction efficiency is improved, the ring plates are in contact with the ground, sinking of individual fixed piles is avoided, and further horizontal arrangement of the foundation beam is guaranteed.
3. The combined temporary building quick-mounting foundation provided by the utility model has the advantages of simple structure, convenience in construction, small space required by construction, low requirement on construction sites, capability of reducing the site occupation period caused by construction, no noise in installation, no need of protection and drainage equipment, and capability of reducing noise and environmental pollution caused by construction.
Drawings
FIG. 1 is a schematic diagram of the connection layout of a fixed pile and a foundation beam according to the present utility model;
FIG. 2 is a schematic view of a fixing pile according to the present utility model;
FIG. 3 is a schematic view of a limiting member according to the present utility model;
FIG. 4 is a top view of FIG. 3 in accordance with the present utility model;
fig. 5 is a schematic structural view of a connection board according to the present utility model.
In the figure: 1-screw pile, 2-flange, 3-limiting piece, 4-shaped steel and 5-connecting piece.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
As shown in FIG 1, the combined temporary building quick-assembly foundation provided by the utility model comprises a screw pile 1, a flange 2, a limiting piece 3, a section steel 4 and a connecting piece 5; the spiral pile 1 is buried underground; the flange 2 is fixedly arranged on the top surface of the spiral pile 1; the limiting piece 3 is sleeved on the screw pile 1 and is contacted with the ground, so as to limit the vertical direction of the screw pile 1 and prevent the screw pile 1 from sinking after the construction is completed; the section steel 4 is fixedly connected with the spiral pile 1 through the flange 2; the connecting piece 5 is arranged at the connecting position of the section steel 4 and is used for connecting the section steel 4.
As shown in fig. 2, the screw pile 1 is a steel screw pile, and is formed by connecting a central steel shaft and screw blades, preferably, the points of the screw pile are distributed in a rectangular shape in space, that is, the connecting lines between adjacent screw shapes jointly enclose a rectangle, and the screw pile is arranged on four vertexes of the rectangle.
The flanges 2 are arranged in one-to-one correspondence with the spiral piles 1, bolt holes are arranged on the flanges at intervals, and the top ends of central steel shafts of the spiral piles 1 are welded with the flanges 2.
As shown in fig. 3 and 4, the limiting piece 3 comprises a sleeve, a ring plate, a connecting rod and a fixing bolt; the sleeve is sleeved on the top of the screw pile 1, the part of the screw pile 1 corresponding to the limiting piece 3 is not provided with screw blades, and the inner diameter of the sleeve is matched with the outer diameter of the central steel shaft; the annular plate is horizontally arranged around the surface of the sleeve, the bottom surface of the annular plate is contacted with the ground, the sleeve below the annular plate is buried underground, and the sleeve above the annular plate is exposed out of the ground surface; the connecting rod is inserted in the sleeve along the horizontal direction, two ends of the connecting rod extend out of the sleeve, the screw pile 1 is provided with a through hole corresponding to the position of the connecting rod, and the connecting rod is inserted in the through hole of the screw pile 1 to realize the connection between the screw pile 1 and the limiting piece 3; the bolt holes are arranged on the annular plate at intervals, after the fixing bolts penetrate through the bolt holes, the fixing bolts are buried underground, further fixation of the limiting piece 3 and the ground is achieved, and the fixing bolts are anchor bolts. Through setting up locating part 3, can avoid later stage screw pile 1 to take place to sink, influence building quality, be connected with screw pile 1 with the connecting rod simultaneously, can guarantee that screw pile 1 exposes the height on ground the same, and then guarantee follow-up shaped steel 4's level, avoid measuring repeatedly in the work progress, improve the efficiency of construction.
The section steel 4 is H-shaped steel and comprises a lower wing plate, a web plate and an upper wing plate, and the lower wing plate is connected with the flange 2 through bolts. The section steel 4 is integrally enclosed to form a rectangular foundation.
As shown in fig. 5, the connecting piece 5 is disposed at a corner of the rectangular foundation and is connected with two adjacent section steels 4, the connecting piece 5 includes two connecting plates, the two connecting plates are disposed at an inner side and an outer side of a connecting position of the section steels 4 respectively, a section of the connecting plates is L-shaped, the connecting plates include two side plates connected with each other, the two side plates are connected with web bolts of the two section steels 4 respectively, and further the fixation between the section steels 4 is realized.
A construction method of a combined temporary building fast-assembling foundation comprises the following steps:
step one: firstly, designing the height setting number of the steel spiral piles, the size and setting spacing of H-shaped steel according to design requirements, and then transporting to a construction site;
step two: the method comprises the steps of placing points in advance according to the construction requirements of temporary construction, and piling a spiral pile according to the points;
step three: installing a limiting piece 3, sleeving the limiting piece 3 on the top of the spiral pile 1, connecting the spiral pile 1 with the limiting piece 3 by using a pull rod, and positioning by using a fixing bolt;
step four: a flange 2 is arranged at the top of the screw pile 1;
step five: installing a first section steel 4, fixing the section steel 4 with a flange 2 through bolts, then installing other section steels 4 in sequence, and connecting adjacent section steels 4 through a connecting piece 5;
step six: checking bolts among all connection points, and performing construction of the temporary building board house after checking.
Finally, it should be noted that: the foregoing description is only illustrative of the preferred embodiments of the present utility model, and although the present utility model has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described, or equivalents may be substituted for elements thereof, and any modifications, equivalents, improvements or changes may be made without departing from the spirit and principles of the present utility model.

Claims (7)

1. A combined temporary building fast-assembling foundation which is characterized in that: comprises a screw pile (1), a flange (2), a limiting piece (3), a section steel (4) and a connecting piece (5); the spiral pile (1) is buried underground; the flange (2) is fixedly arranged on the top surface of the spiral pile (1); the section steel (4) is fixedly connected with the flange (2); the connecting piece (5) is connected with two adjacent section steel (4);
the limiting piece (3) comprises a sleeve, a ring plate, a connecting rod and a fixing bolt; the sleeve is sleeved on the top of the spiral pile (1); the annular plate is horizontally arranged around the surface of the sleeve, the bottom surface of the annular plate is in contact with the ground, the sleeve below the annular plate is buried underground, and the sleeve above the annular plate is exposed out of the ground; the connecting rod is transversely inserted into the sleeve and the fixed pile; the fixing bolts are buried underground and connected with the annular plate.
2. The modular temporary building quick-fit foundation of claim 1, wherein: the screw pile (1) is a steel screw pile and is arranged at intervals and comprises a central steel shaft and screw blades.
3. The modular temporary building quick-fit foundation of claim 1, wherein: the section steel (4) is H-shaped steel and comprises a lower wing plate, a web plate and an upper wing plate, and the lower wing plate is connected with the flange (2) through bolts.
4. A modular temporary building quick-fit foundation according to claim 3, wherein: the connecting piece (5) comprises two connecting plates which are respectively arranged on the inner side and the outer side of the section steel (4).
5. The modular temporary building quick-fit foundation of claim 4, wherein: the section of the connecting plate is L-shaped and comprises two side plates which are connected with each other, and the two side plates are respectively connected with webs of the two sections (4) through bolts.
6. The modular temporary building quick-fit foundation of claim 1, wherein: the point positions of the spiral piles (1) are distributed in a rectangular shape in space; the section steel (4) is integrally enclosed to form a rectangular foundation.
7. A modular temporary building quick-fit foundation according to claim 2, wherein: the screw pile (1) is provided with no screw blade at the part corresponding to the limiting piece (3), and the inner diameter of the sleeve is matched with the outer diameter of the central steel shaft.
CN202223254640.4U 2022-12-06 2022-12-06 Combined temporary building fast-assembling foundation Active CN218911491U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223254640.4U CN218911491U (en) 2022-12-06 2022-12-06 Combined temporary building fast-assembling foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223254640.4U CN218911491U (en) 2022-12-06 2022-12-06 Combined temporary building fast-assembling foundation

Publications (1)

Publication Number Publication Date
CN218911491U true CN218911491U (en) 2023-04-25

Family

ID=86040181

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223254640.4U Active CN218911491U (en) 2022-12-06 2022-12-06 Combined temporary building fast-assembling foundation

Country Status (1)

Country Link
CN (1) CN218911491U (en)

Similar Documents

Publication Publication Date Title
CN210031842U (en) Combined supporting system for adjacent deep foundation pit based on row piles, connecting beams and counter-pulling anchor cables
CN111236952A (en) Full-recovery assembly type rectangular pipe-jacking working well steel structure supporting device and construction method of working well
CN110878555A (en) Large-span underground space deep foundation pit supporting system and construction method
CN218911491U (en) Combined temporary building fast-assembling foundation
CN112575789A (en) Diagonal space truss foundation pit inner support system
CN212175797U (en) Large-span underground space deep foundation pit supporting system
CN208009473U (en) The integrated concrete pipe gallery in braced wall corridor
CN116254870A (en) Integrated beach photovoltaic power station support foundation structure and construction method thereof
CN110578336A (en) Anchor bolt assembly type column plate type greening retaining wall
CN110685283A (en) Sandbar combined tile type foundation pit supporting structure and construction method thereof
CN216275712U (en) Corner bracing construction structures
CN212896435U (en) Combined prefabricated bearing platform pile foundation
CN115977135A (en) Assembly type temporary construction foundation system capable of being circulated
CN113090066A (en) Construction method for newly added entrances and exits of existing buildings and elevator shaft
CN210887229U (en) Irregular foundation pit assembled steel strutting arrangement
CN220686117U (en) Assembled open caisson adopting duct piece type prefabricated component
CN112160325A (en) Composite supporting structure for enhancing rigidity of prestressed pipe pile
CN112049251A (en) Civil engineering is with assembled steel construction concreting building structure exempts from
CN115404901B (en) Assembled slurry stirring station foundation and construction method
CN111119222A (en) Assembling device for ultra-high voltage direct current transmission line iron tower in alpine region
CN218990205U (en) Deep foundation pit row pile supporting structure
CN218933194U (en) Group anchor type screw anchor foundation adopting flange connection
CN113684834B (en) Construction method of complex environment supporting system
CN216615932U (en) Assembled cross beam slab spiral pile foundation for power transmission line
CN219343296U (en) Tower crane foundation based on basement cast-in-situ structural column and steel bearing platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant