CN218843171U - Novel pipe gallery connection structure - Google Patents

Novel pipe gallery connection structure Download PDF

Info

Publication number
CN218843171U
CN218843171U CN202222926533.5U CN202222926533U CN218843171U CN 218843171 U CN218843171 U CN 218843171U CN 202222926533 U CN202222926533 U CN 202222926533U CN 218843171 U CN218843171 U CN 218843171U
Authority
CN
China
Prior art keywords
main part
piping lane
pipe gallery
part module
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222926533.5U
Other languages
Chinese (zh)
Inventor
徐鹏升
陈城伟
杨榕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yuehong Construction Development Co ltd
Original Assignee
Yuehong Construction Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yuehong Construction Development Co ltd filed Critical Yuehong Construction Development Co ltd
Priority to CN202222926533.5U priority Critical patent/CN218843171U/en
Application granted granted Critical
Publication of CN218843171U publication Critical patent/CN218843171U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Branch Pipes, Bends, And The Like (AREA)

Abstract

The utility model relates to a piping lane technical field just discloses a novel piping lane connection structure, including piping lane main part module, both ends run through around the piping lane main part module and seted up the channel hole, and the butt joint coupling head with the inside cross section looks adaptation of channel hole is installed to the front end of piping lane main part module, and the top all is provided with the subassembly of consolidating forever between two adjacent piping lane main part modules, the utility model discloses in, novel piping lane connection structure in this scheme adopts the mode of sectional type module butt joint to design, conveniently transports piping lane main part module, through being provided with the subassembly of consolidating forever, strengthens the fixed effect between two adjacent piping lane main part modules, avoids appearing playing between two adjacent piping lane main part modules threaded rod and the screw hole of key connection and takes place to corrode and rust, leads to the condition that takes place the seepage between two piping lane main part modules to appear.

Description

Novel pipe gallery connection structure
Technical Field
The utility model relates to a piping lane technical field especially relates to a novel piping lane connection structure.
Background
At present, transformation conditions such as underground pipe gallery and tunnel movable pipe joints are common, and a common construction method is to open holes in the side wall of an original old pipe gallery, reserve original steel bars, connect the original steel bars with the side wall steel bars of a newly-built pipe gallery, integrally pour concrete, and arrange a water-swelling water stop strip at a joint.
The existing gallery house mechanism is integrally cast and cannot be transported by a truck; simultaneously current open (announce) number is the assembled utility tunnel of municipal administration usefulness disclosed in CN216689483U, including the piping lane unit, the one end of piping lane unit is seted up flutedly, and the other end of piping lane unit is provided with the lug, recess and lug looks adaptation, and the piping lane unit includes lower piping lane and upper piping lane, and lower piping lane and upper piping lane are trapezoidal, and lower piping lane is connected with the upper piping lane and forms the hexagon, and the both ends of lower piping lane all are provided with first connecting block. This assembled utility tunnel of municipal administration usefulness at hexagonal pipe gallery unit, makes the vertical atress of part that it bore decompose to both sides to the stress stability of pipe gallery unit has been strengthened.
Although adopt the modularized design among the above-mentioned technical scheme, convenient transportation, but the bolt and nut who plays the most important fixed connection between two adjacent piping lane units buries in soil, directly receives the influence of underground humid environment, in the long run, plays fasteners such as fixed bolt and can take place rusty condition to appear, influences to connect fixedly between the adjacent modularization piping lane unit, can lead to the junction to produce the gap, leads to sewer water to spill over from the gap and outflows.
To this end, we propose a new pipe gallery connection structure.
SUMMERY OF THE UTILITY MODEL
The utility model discloses solve above-mentioned current technical problem, provide a novel piping lane connection structure.
In order to realize the above-mentioned purpose, the utility model discloses a following technical scheme, a novel piping lane connection structure, including piping lane main part module, piping lane main part module is transversal hexagon pipeline of personally submitting, and both ends run through around the piping lane main part module and seted up the access hole, the butt joint connector with access hole inside cross section looks adaptation is installed to the front end of piping lane main part module, and the front end of every piping lane main part module is the circular connection with access hole inside center pin and has a butt joint slabstone, and the rear end edge department of every piping lane main part module is the circular connection and sets up the butt joint groove with butt joint slabstone looks adaptation, and the top all is provided with the forever solid subassembly between two adjacent piping lane main part modules, forever solid subassembly include with the reinforcement piece two on the preceding piping lane main part module and the reinforcement piece one at back piping lane main part module top, the front end fixedly connected with the outer cylinder of seting up the external screw thread on the reinforcement piece one, the rear side of reinforcement piece two runs through and sets up the screw hole continuous screw hole, and screw hole internal channel is the T type, the inside front end of screw hole is provided with the nut spare of threaded rod fixed with the threaded rod, the screw hole of every screw hole of screw hole is all installed and the leading-in the inside connection screw hole top of the leading-in the screw hole of the connection of pouring.
Preferably, every the inside center pin that uses pipe gallery main part module of pipe gallery main part module is the centre of a circle, and the inside annular through connection of pipe gallery main part module has first strengthening steel bar, and all twines between the inside first strengthening steel bar of every pipe gallery main part module has the second strengthening steel bar.
Preferably, piping lane main part module and butt joint pipe head are cement and pour integrated into one piece.
Preferably, every all be provided with the inside maintenance subassembly of intercommunication passway on the piping lane main part module, and every the top of piping lane main part module all runs through the detection mouth of seting up intercommunication passway downthehole portion, and detection subassembly is including examining modification and handle, overhauls to change to seal down inside the detection mouth, and the handle is fixed at the top of examining the modification.
Preferably, overhaul and change the threaded rod that is the T type and overhaul and change and insert and detect the mouthful inside between cup joint the sealing washer.
Advantageous effects
The utility model provides a novel piping lane connection structure. The method has the following beneficial effects:
(1) The novel pipe rack connecting structure is designed in a sectional type module butt joint mode, pipe rack main body modules can be conveniently transported, two adjacent pipe rack main body modules in the front and back are communicated with each other by inserting butt joints into channel holes, the front ends and the back ends of the adjacent pipe rack main body modules are respectively inserted into corresponding butt joint grooves through corresponding butt joint stone plates, each pipe rack main body module is subjected to calibration butt joint, rapid butt joint between the two adjacent pipe rack main body modules is facilitated, laying is accelerated between the pipe rack main body modules, and when the two pipe rack main body modules are in butt joint, the upper ends of the adjacent pipe rack main body modules reinforce the fixing effect between the two adjacent pipe rack main body modules through permanent fixing components;
after the threaded rod inserts threaded hole inside, carry out the thread tightening through the nut spare that the threaded hole is inside to be reserved, with the tight intercommunication that agrees with between piping lane main part module and the passageway hole, connecting pipe orifice cooperation on two through every reinforcing block, pour into threaded hole inside with concrete from connecting pipe orifice, pour the sealing at threaded hole inside fixing the connecting pipe orifice on the threaded rod, carry out permanent reinforcement between adjacent piping lane main part module, prevent between the adjacent piping lane main part module from receiving the water corrosion in the place, the threaded rod that leads to playing the key joint between two adjacent piping lane main part modules and the screw hole emergence of the rusty condition of corroding, avoid the kneck connection between two adjacent piping lane main part modules to appear the condition emergence in gap.
(2) This novel pipe gallery connection structure is provided with first reinforcing bar and second reinforcing bar through the inside at pipe gallery main part module, strengthens pipe gallery main part module overall structure, improves the whole hardness of pipe gallery main part module.
(3) This novel piping lane connection structure, through reserve the maintenance subassembly that has intercommunication access hole inside on every piping lane main part module, the permanent fixed condition of pinning of installation takes place between adjacent piping lane main part module, through the maintenance subassembly that corresponds on the piping lane main part module, conveniently gets into the access hole inside, overhauls the access hole inside.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below. It should be apparent that the drawings in the following description are merely exemplary, and that other embodiments can be derived from the drawings provided by those of ordinary skill in the art without inventive effort.
The structure, ratio, size and the like shown in the present specification are only used for matching with the content disclosed in the specification, so as to be known and read by people familiar with the technology, and are not used for limiting the limit conditions which can be implemented by the present invention, so that the present invention has no technical essential significance, and any structure modification, ratio relationship change or size adjustment should still fall within the scope which can be covered by the technical content disclosed by the present invention without affecting the efficacy and the achievable purpose of the present invention.
Fig. 1 is a perspective view of a connection according to a first embodiment of the present invention;
fig. 2 is a side sectional view of a main body module of a middle pipe gallery according to an embodiment of the present invention;
fig. 3 is a rear side split view of a main body module of a middle pipe gallery according to an embodiment of the present invention;
fig. 4 is a connection perspective view in the second embodiment of the present invention.
Illustration of the drawings:
1. a pipe gallery body module; 2. a passage hole; 3. a butt joint head; 4. a first reinforcing bar; 5. a second reinforcing bar; 6. butt joint of stone slabs; 7. a butt joint groove; 8. a first reinforcing block; 9. a threaded rod; 10. a second reinforcing block; 11. a threaded hole; 12. connecting the pipe orifices; 13. a nut member; 14. a detection port; 15. checking and modifying; 16. a handle.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The first embodiment is as follows: the utility model provides a novel piping lane connection structure, like fig. 1-fig. 3 show, including piping lane main part module 1, piping lane main part module 1 is transversal hexagon of personally submitting's pipeline, and both ends run through around piping lane main part module 1 and seted up access hole 2, and the butt joint coupling 3 with the inside cross section looks adaptation of access hole 2 is installed to the front end of piping lane main part module 1, and piping lane main part module 1 is cement pouring integrated into one piece to butt joint coupling 3.
Further, the front end of every pipe gallery main part module 1 is the circular connection with butt joint slabstone 6 with the inside center pin of passageway hole 2, the rear end edge department of every pipe gallery main part module 1 is the annular and offers the butt joint groove 7 with butt joint slabstone 6 looks adaptation, the top all is provided with the subassembly forever between two adjacent pipe gallery main part modules 1, the subassembly forever includes with the reinforcement piece two 10 on the preceding pipe gallery main part module 1 and the reinforcement piece one 8 at the top of the next pipe gallery main part module 1, the threaded rod 9 of seting up the external screw thread on the front end fixedly connected with of reinforcement piece one 8, the rear side of reinforcement piece two 10 runs through and sets up the screw hole 11 that links to each other with threaded rod 9 screw thread, and screw hole 11 inside channel is the T type, the inside front end of screw hole 11 is provided with nut spare 13 with threaded rod 9 thread tightening, the inside connection mouth 12 that the intercommunication corresponds screw hole 11 inside is all installed at the top of every reinforcement piece two 10, the leading-in of the top of connection mouth 12 pours the inside concrete of screw hole 11.
Every piping lane main part module 1 is inside to use the center pin of piping lane main part module 1 as the centre of a circle, the inside annular through connection of piping lane main part module 1 has first reinforcing bar 4, and all twine between the inside first reinforcing bar 4 of every piping lane main part module 1 has second reinforcing bar 5, be provided with first reinforcing bar 4 and second reinforcing bar 5 through the inside at piping lane main part module 1, strengthen 1 overall structure of piping lane main part module, improve the whole hardness of piping lane main part module.
The utility model discloses a theory of operation: novel piping lane connection structure in this scheme adopts the mode of sectional type module butt joint to design, connect through inserting passageway hole 2 inside to connect through butt joint pipe head 3 between two adjacent piping lane main part modules 1 around, simultaneously around between adjacent piping lane main part module 1 both ends insert corresponding butt joint 7 inside through corresponding butt joint slabstone 6 respectively, calibrate the butt joint between every piping lane main part module 1, make things convenient for and carry out quick butt joint between two adjacent piping lane main part modules 1, lay between the acceleration piping lane main part module 1, when butt joint agrees with between two piping lane main part modules 1 simultaneously, 1 upper end of adjacent piping lane main part module strengthens the fixed effect between two adjacent piping lane main part modules 1 through the permanent solid subassembly this moment, after threaded rod 9 inserts threaded hole 11 inside, carry out the thread tightening through the nut spare 13 of the inside reservation of threaded hole 11, with tight close intercommunication between piping lane main part module 1 and passageway hole 2, connect mouth of pipe 12 cooperation on through every back up piece two 10, pour into threaded hole 12 from the mouth of pipe and connect inside, fix the mouth of pipe 12 of pipe on threaded rod 9, seal up the sealed up the adjacent piping lane main part module and prevent that adjacent piping lane main part module 1 and take place the adjacent corrosion of adjacent piping lane main part module and take place the emergence seam of taking place to take place the adjacent corrosion of adjacent threaded rod and take place the adjacent main part module and take place the adjacent water connection module and take place the adjacent threaded rod and take place the seam of the adjacent threaded rod and take place the adjacent main part module and take place the adjacent threaded hole 1 and take place the adjacent connection module and take place the seam of taking place the adjacent threaded rod and take place the adjacent threaded hole 1.
Example two: on the basis of embodiment one, as shown in fig. 4, all be provided with the inside maintenance subassembly of intercommunication access hole 2 on every piping lane main part module 1, and the top of every piping lane main part module 1 all runs through and sets up the inside detection mouth 14 of intercommunication access hole 2, and detection subassembly is including examining and revising 15 and handle 16, overhauls and revises 15 downward seals inside detection mouth 14, and handle 16 fixes and examines the top of revising 15.
Further, overhaul and change 15 threaded rods that are the T type and overhaul and change 15 and insert and detect the mouth 14 inside between cup joint the sealing washer.
The utility model discloses a theory of operation: through reserve the maintenance subassembly that has the inside of intercommunication access hole 2 on every piping lane main part module 1, the permanent fixed condition of pinning of installation takes place between adjacent piping lane main part module 1, through the maintenance subassembly that corresponds on the piping lane main part module 1, conveniently gets into inside access hole 2, overhauls access hole 2 inside.
The basic principles and the main features of the invention and the advantages of the invention have been shown and described above. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments, and the above embodiments and descriptions are only illustrative of the principles of the present invention, and that various changes and modifications may be made without departing from the spirit and scope of the present invention, and all such changes and modifications fall within the scope of the present invention as claimed. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (5)

1. The utility model provides a novel pipe gallery connection structure, includes pipe gallery main part module (1), pipe gallery main part module (1) is transversal pipeline of personally submitting the hexagon, and both ends run through and seted up access hole (2), its characterized in that around pipe gallery main part module (1): the utility model discloses a concrete pouring system, including pipe gallery main body module (1), the front end of pipe gallery main body module (1) is installed and is connected to butt joint union coupling (3) with the inside cross section looks adaptation of access hole (2), the front end of every pipe gallery main body module (1) is the ring junction with butt joint slabstone (6) with access hole (2) inside center pin, the rear end edge of every pipe gallery main body module (1) is the annular and offers butt joint groove (7) with butt joint slabstone (6) looks adaptation, the top all is provided with the solid subassembly forever between two adjacent pipe gallery main body modules (1), the solid subassembly forever includes with reinforcing block two (10) on the preceding pipe gallery main body module (1) and reinforcing block one (8) at back pipe gallery main body module (1) top, set up threaded rod (9) of external screw thread on the front end fixedly connected with of reinforcing block one (8), the rear side of reinforcing block two (10) runs through sets up screw hole (11) that link to each other with threaded rod (9) screw thread, and screw hole (11) internal channel of screw hole (11) is the T type, the inside front end of screw hole (11) is provided with threaded rod (9) screw rod (13), the nut piece (11) screw hole (12) that the inside connection of pouring is connected with the screw hole (11) top that all installed and is connected to be connected with the concrete hole (12), the screw hole (11), the leading-in the concrete hole (11).
2. The novel pipe gallery connecting structure of claim 1, wherein: every inside center pin that uses piping lane main part module (1) of piping lane main part module (1) is the centre of a circle, and the inside annular through connection of piping lane main part module (1) has first reinforcing bar (4), and all twines between every inside first reinforcing bar (4) of piping lane main part module (1) has second reinforcing bar (5).
3. The novel pipe gallery connecting structure of claim 1, wherein: piping lane main part module (1) and butt joint pipe head (3) are cement and pour integrated into one piece.
4. The novel pipe gallery connecting structure of claim 1, wherein: every all be provided with the inside maintenance subassembly of intercommunication access hole (2) on piping lane main part module (1), and every the top of piping lane main part module (1) all runs through and sets up inside detection mouth (14) of intercommunication access hole (2), and detection subassembly is including examining and revising (15) and handle (16), overhauls and changes (15) and seal down inside detection mouth (14), and handle (16) are fixed and are examined the top of revising (15).
5. The novel pipe gallery connecting structure of claim 4, wherein: examine and modify (15) threaded rod that is the T type and examine and repair and change (15) and insert and detect mouthful (14) inside between cup joint the sealing washer.
CN202222926533.5U 2022-11-03 2022-11-03 Novel pipe gallery connection structure Active CN218843171U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222926533.5U CN218843171U (en) 2022-11-03 2022-11-03 Novel pipe gallery connection structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222926533.5U CN218843171U (en) 2022-11-03 2022-11-03 Novel pipe gallery connection structure

Publications (1)

Publication Number Publication Date
CN218843171U true CN218843171U (en) 2023-04-11

Family

ID=87292653

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222926533.5U Active CN218843171U (en) 2022-11-03 2022-11-03 Novel pipe gallery connection structure

Country Status (1)

Country Link
CN (1) CN218843171U (en)

Similar Documents

Publication Publication Date Title
CN218843171U (en) Novel pipe gallery connection structure
CN107165271A (en) A kind of assembled Special-Shaped Column concrete frame structure
CN205617661U (en) Short sleeve grout steel bar connection connects and connecting sleeve and pressure -bearing ring that have thereof
CN212078628U (en) Overhanging type scaffold
CN212896870U (en) Reinforced connecting piece for fabricated building
CN205875418U (en) Assembled concrete wall and floor dry -type connection structure
CN216239723U (en) Exempt from to drawing structure template reinforcement
CN110238963A (en) Double-tube type steel bar connecting structure and its construction method between precast concrete
CN106592865B (en) Prefabricated concrete lintel
CN108729350B (en) Prefabricated UHPC side anti-collision guardrail grouting connection structure
CN210500792U (en) Double-tube type steel bar connecting structure between precast concrete components
CN211873553U (en) Assembled construction grout sleeve
CN110439120A (en) A kind of construction method of the connection structure and shear wall of reinforcing bar and steel core concrete column
CN207121992U (en) A kind of assembled Special-Shaped Column concrete frame structure
CN207619953U (en) A kind of U-frame for gate installation
CN206752851U (en) Precast concrete bar connecting box
CN216813295U (en) Novel composite pipeline connecting structure
CN219221637U (en) Faucet steel mould for repairing cement pipeline
CN216046006U (en) Municipal administration water supply and drainage pipeline connection structure
CN210621510U (en) Large-span corrugated steel arch culvert structure
CN219304387U (en) Wire sleeve suitable for pile foundation self-balancing test
CN211614147U (en) Steel bar connector for building engineering
CN220953682U (en) Prefabricated part for cleaning opening
CN208718688U (en) A kind of inverted arch arch and abutment wall arch connection structure
CN210177373U (en) Vertical prestressed duct grouting communicating unit

Legal Events

Date Code Title Description
GR01 Patent grant