CN218814759U - Roof structure - Google Patents

Roof structure Download PDF

Info

Publication number
CN218814759U
CN218814759U CN202223286922.2U CN202223286922U CN218814759U CN 218814759 U CN218814759 U CN 218814759U CN 202223286922 U CN202223286922 U CN 202223286922U CN 218814759 U CN218814759 U CN 218814759U
Authority
CN
China
Prior art keywords
roof boarding
length direction
water
roof
steel sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223286922.2U
Other languages
Chinese (zh)
Inventor
傅志忠
傅志哲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Zhongwei Construction Development Co ltd
Original Assignee
Fujian Zhongwei Construction Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Zhongwei Construction Development Co ltd filed Critical Fujian Zhongwei Construction Development Co ltd
Priority to CN202223286922.2U priority Critical patent/CN218814759U/en
Application granted granted Critical
Publication of CN218814759U publication Critical patent/CN218814759U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Abstract

The application discloses roofing structure, including a plurality of roof boarding, splice in order through the gap filler between a plurality of roof boarding, the concatenation direction is the width direction of roof boarding, the concatenation department of adjacent roof boarding is equipped with the stagnant water steel sheet, the length direction of stagnant water steel sheet is the length direction of roof boarding, the concatenation department of stagnant water steel sheet expert closed adjacent roof boarding, one side that the roof boarding is close to adjacent roof boarding is equipped with the breakwater, the length direction of breakwater is the length direction of roof boarding, the inboard of stagnant water steel sheet is located to two adjacent breakwater. This application has the effect that the rainwater appears and permeates the inside condition in house through the gap in the reduction.

Description

Roof structure
Technical Field
The application relates to the field of building waterproofing, in particular to a roof structure.
Background
When some houses are built, the roof structure is made of double T-shaped plates, two double T-shaped plates are directly spliced together, and then a gap between two adjacent double T-shaped plates is filled with a gap filling agent.
However, the gap filler is difficult to avoid aging phenomenon after long-time use, so that gaps exist between the adjacent double T plates, and when the rainwater weather exists, the rainwater permeates through the gaps between the adjacent double T plates, so that the water seepage phenomenon of a house is caused.
SUMMERY OF THE UTILITY MODEL
In order to reduce the condition that appears the rainwater and permeate to house inside through the gap, this application provides a roofing structure.
The application provides a roofing structure adopts following technical scheme:
the utility model provides a roofing structure, includes a plurality of roof boarding, it is a plurality of splice in order through the gap filler between the roof boarding, the concatenation direction does the width direction of roof boarding is adjacent the concatenation department of roof boarding is equipped with the stagnant water steel sheet, the length direction of stagnant water steel sheet does the length direction of roof boarding, the stagnant water steel sheet leads to close adjacently the concatenation department of roof boarding, the roof boarding is close to adjacently one side of roof boarding is equipped with the breakwater, the length direction of breakwater does the length direction of roof boarding, two are adjacent the breakwater is located the inboard of stagnant water steel sheet.
By adopting the technical scheme, when raining, the splicing parts of the adjacent roof panels are shielded by the water stop steel plates, so that the water stop steel plates block paths between rainwater and the splicing parts of the adjacent roof panels, and the phenomenon that the rainwater permeates into gaps between the adjacent roof panels is favorably reduced. Meanwhile, the water retaining strip is arranged on the outer side of the joint of the adjacent roof panels, and when part of rainwater enters the gap between the water stopping steel plate and the roof panels, the water retaining strip can prevent the rainwater from being close to the joint of the adjacent roof panels, so that the condition that the rainwater penetrates into the gap between the adjacent roof panels is further reduced.
Optionally, the water stop steel plate includes a horizontal portion and an inclined portion, the horizontal portion and the inclined portion are integrally disposed, a tangent plane is disposed on one side of the water stop strip close to the inclined portion, and the tangent plane abuts against the inclined portion.
Through adopting above-mentioned technical scheme, in the installation, the tangent plane can laminate with the rake, makes the stagnant water steel sheet can place on two adjacent water bars to follow-up workman is fixed the stagnant water steel sheet.
Optionally, the upper surface of the water bar is a wide surface.
By adopting the technical scheme, a long and narrow blocking path is formed between the water retaining strip and the roof panel, so that rainwater is difficult to pass through a gap between the water retaining strip and the roof panel, and the phenomenon that the rainwater permeates into the gap between the adjacent roof panels is favorably reduced.
Optionally, a groove is formed in the upper surface of the roof panel, the length direction of the groove is the length direction of the roof panel, and the groove is formed between the water bar and the edge of the roof panel.
Through adopting above-mentioned technical scheme, if have partial rainwater when passing through the clearance between water bar and the roof boarding, the rainwater can enter into the recess inside, is favorable to reducing the condition that the rainwater infiltrates gap between the adjacent roof boarding.
Optionally, the bottom of the groove is provided with a sponge strip, the length direction of the sponge strip is the length direction of the groove, and the sponge strip is connected with the bottom of the groove through a magic tape.
Through adopting above-mentioned technical scheme, the sponge strip leaves the water stain of rainwater, soaks the position at the sponge strip through water to fill the gap between water bar and the roof boarding.
Optionally, the inclined portion is provided with a plurality of locking pieces, the plurality of locking pieces are arranged along the length direction of the inclined portion, each locking piece comprises a screw rod and a nut, the nut is in threaded connection with the screw rod, the screw rod penetrates through the inclined portion and is in threaded connection with the water bar, and the nut is abutted to the surface of the inclined portion.
Through adopting above-mentioned technical scheme, through bolt and nut, make can dismantle between stagnant water steel sheet and the breakwater and be connected, be favorable to the workman to the regular concatenation department inspection to adjacent roof boarding.
Optionally, a connecting assembly is arranged between the two inclined parts.
Through adopting above-mentioned technical scheme, through setting up coupling assembling, reduce the trend that two inclinations can keep away from each other, be favorable to improving the structural strength of stagnant water steel sheet.
Optionally, coupling assembling includes first spring, second spring, swivel nut and double-screw bolt, the one end and one of them rake are connected of first spring, the other end of first spring with the swivel nut is connected, the one end and another of second spring the rake is connected, the other end of second spring with the double-screw bolt is connected, the double-screw bolt with swivel nut threaded connection.
Through adopting above-mentioned technical scheme, through the position relation of adjusting swivel nut and double-screw bolt, make the elastic potential energy that has of first spring and second spring, the rake supports the surface of tight water bar, is favorable to strengthening the fixed effect between stagnant water steel sheet and the water bar.
In summary, the present application includes at least one of the following beneficial technical effects:
1. by arranging the water stop steel plate and the water retaining strip, when raining, the water stop steel plate shields the splicing position of the adjacent roof boards, and the water retaining strip prevents rainwater from being close to the splicing position of the adjacent roof boards, so that the condition that the rainwater penetrates into gaps between the adjacent roof boards is favorably reduced;
2. through setting up the recess, if when having partial rainwater to pass through the clearance between water bar and the roof boarding, the rainwater can enter into the recess inside, is favorable to reducing the condition that the rainwater permeates the gap between the adjacent roof boarding.
3. Through setting up the sponge strip, the sponge strip leaves the water stain of rainwater, according to the position of water stain at the sponge strip to fill the gap between water bar and the roof boarding.
Drawings
Fig. 1 is a schematic view of the overall structure of an embodiment of the present application.
Fig. 2 is an enlarged view of fig. 1 at a.
Description of reference numerals:
1. a roof panel; 11. a groove; 12. a sponge strip; 13. magic tape; 2. a caulking agent; 3. a water stop steel plate; 31. a horizontal portion; 32. an inclined portion; 33. a locking member; 331. a screw; 332. a nut; 4. a water bar; 5. an adhesive; 6. a connecting assembly; 61. a first spring; 62. a second spring; 63. a threaded sleeve; 64. a stud.
Detailed Description
The present application is described in further detail below with reference to figures 1-2.
The embodiment of the application discloses roofing structure. Referring to fig. 1 and 2, the roofing structure includes a plurality of roof boarding 1, roof boarding 1 is two T boards, splice in order through gap filler 2 between a plurality of roof boarding 1, the concatenation direction is roof boarding 1's width direction, the concatenation department of adjacent roof boarding 1 is equipped with stagnant water steel sheet 3, stagnant water steel sheet 3's length direction is roof boarding 1's length direction, stagnant water steel sheet 3 leads to the concatenation department of closing adjacent roof boarding 1, stagnant water steel sheet 3 includes horizontal part 31 and rake 32, horizontal part 31 sets up with rake 32 is integrative.
One side that roof boarding 1 is close to adjacent roof boarding 1 is equipped with breakwater 4, it is fixed through adhesive 5 between breakwater 4 and the roofing, the upper surface of breakwater 4 is wide face, one side that breakwater 4 is close to rake 32 is equipped with the tangent plane, tangent plane and rake 32 butt, the length direction of breakwater 4 is the length direction of roof boarding 1, two adjacent breakwaters 4 are located stagnant water steel sheet 3's inboard, through setting up breakwater 4, be favorable to hindering the rainwater to pass through the clearance between stagnant water steel sheet 3 and the roof boarding 1 and be close to in the position of concatenation department between adjacent roof boarding 1.
Be connected through locking piece 33 between water bar 4 and the rake 32, locking piece 33 is equipped with a plurality ofly, a plurality of locking pieces 33 set up along rake 32 length direction, locking piece 33 includes screw rod 331 and nut 332, nut 332 and screw rod 331 threaded connection, screw rod 331 passes rake 32 and water bar 4 threaded connection, nut 332 and rake 32's surface butt, can dismantle between stagnant water steel sheet 3 and the water bar 4 and be connected promptly to be convenient for the workman can dismantle stagnant water steel sheet 3.
Be equipped with coupling assembling 6 between two rake 32, coupling assembling 6 includes first spring 61, second spring 62, swivel nut 63 and double-screw bolt 64, first spring 61, second spring 62, swivel nut 63 and double-screw bolt 64 are the steelwork, the one end of first spring 61 is connected with one of them rake 32, the other end and the swivel nut 63 of first spring 61 are connected, the one end and another rake 32 of second spring 62 are connected, the other end and the double-screw bolt 64 of second spring 62 are connected, double-screw bolt 64 and swivel nut 63 threaded connection, through adjusting the position relation between swivel nut 63 and the double-screw bolt 64, make rake 32 can support the surface of tight water bar 4, be favorable to strengthening the fixed effect of stagnant water steel sheet 3 and baffle.
The upper surface of roof boarding 1 is equipped with recess 11, and the length direction of recess 11 is roof boarding 1's length direction, and recess 11 is located between the edge of water bar 4 and roof boarding 1, and recess 11 bottom is equipped with sponge strip 12, and the length direction of sponge strip 12 is recess 11's length direction, connects through magic subsides 13 between the bottom of sponge strip 12 and recess 11.
After the adhesive 5 between the water bar 4 and the roof panel 1 is aged, cracks can appear between the water bar 4 and the roof panel 1, and rainwater is collected through the groove 11, so that the rainwater cannot be close to the splicing position between the adjacent roof panels 1. Meanwhile, the position of the crack is found in time and the adhesive 5 is used for filling the crack again through water stain on the sponge strip 12.
The embodiment of the application relates to a roof structure implementation principle: when raining, the water stop steel plate 3 shields the splicing part of the adjacent roof boards 1, so that a channel between rainwater and the splicing part of the adjacent roof boards 1 is isolated, and meanwhile, the water retaining strip 4 blocks the rainwater from passing through the gap between the water stop steel plate 3 and the roof boards 1, thereby being beneficial to reducing the condition that the rainwater permeates into the gap between the adjacent roof boards 1.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. A roofing structure characterized by: including a plurality of roof boarding (1), it is a plurality of splice in order through gap filler (2) between roof boarding (1), the concatenation direction does the width direction of roof boarding (1), it is adjacent the concatenation department of roof boarding (1) is equipped with stagnant water steel sheet (3), the length direction of stagnant water steel sheet (3) does the length direction of roof boarding (1), stagnant water steel sheet (3) lead to close adjacently the concatenation department of roof boarding (1), roof boarding (1) is close to adjacently one side of roof boarding (1) is equipped with breakwater (4), the length direction of breakwater (4) does the length direction of roof boarding (1), two are adjacent breakwater (4) are located the inboard of stagnant water steel sheet (3).
2. A roofing structure according to claim 1 wherein: the water stop steel plate (3) comprises a horizontal part (31) and an inclined part (32), the horizontal part (31) and the inclined part (32) are integrally arranged, one side, close to the inclined part (32), of the water stop strip (4) is provided with a tangent plane, and the tangent plane is abutted to the inclined part (32).
3. A roofing structure according to claim 2 wherein: the upper surface of the water retaining strip (4) is a wide surface.
4. A roofing structure according to claim 2 wherein: the water-retaining strip is characterized in that a groove (11) is formed in the upper surface of the roof board (1), the length direction of the groove (11) is the length direction of the roof board (1), and the groove (11) is formed between the water-retaining strip (4) and the edge of the roof board (1).
5. A roofing structure according to claim 4 wherein: recess (11) bottom is equipped with sponge strip (12), the length direction of sponge strip (12) does the length direction of recess (11), sponge strip (12) with connect through magic subsides (13) between the bottom of recess (11).
6. A roofing structure according to claim 2 wherein: slope portion (32) are equipped with locking piece (33), locking piece (33) are equipped with a plurality ofly, and are a plurality of locking piece (33) are followed slope portion (32) length direction sets up, locking piece (33) include screw rod (331) and nut (332), nut (332) with screw rod (331) threaded connection, screw rod (331) pass slope portion (32) with water bar (4) threaded connection, nut (332) with the surface butt of slope portion (32).
7. A roofing structure according to claim 6 wherein: and a connecting component (6) is arranged between the two inclined parts (32).
8. A roofing structure according to claim 7 wherein: coupling assembling (6) include first spring (61), second spring (62), swivel nut (63) and double-screw bolt (64), the one end and one of them rake (32) of first spring (61) are connected, the other end of first spring (61) with swivel nut (63) are connected, the one end and another of second spring (62) rake (32) are connected, the other end of second spring (62) with double-screw bolt (64) are connected, double-screw bolt (64) with swivel nut (63) threaded connection.
CN202223286922.2U 2022-12-08 2022-12-08 Roof structure Active CN218814759U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223286922.2U CN218814759U (en) 2022-12-08 2022-12-08 Roof structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223286922.2U CN218814759U (en) 2022-12-08 2022-12-08 Roof structure

Publications (1)

Publication Number Publication Date
CN218814759U true CN218814759U (en) 2023-04-07

Family

ID=87248127

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223286922.2U Active CN218814759U (en) 2022-12-08 2022-12-08 Roof structure

Country Status (1)

Country Link
CN (1) CN218814759U (en)

Similar Documents

Publication Publication Date Title
DE4014200A1 (en) Frameless solar generator - with solar cell laminate resting on profiles with silicone adhesive pads
CN215290700U (en) Assembly type building sealing waterproof structure
CN218814759U (en) Roof structure
EP0419775A2 (en) Photovoltaic frameless solar generator
CN210067162U (en) Waterproof stone curtain wall
CN210780636U (en) Full-structure waterproof photovoltaic support
CN211665968U (en) Novel building waterproof structure
AT17586U1 (en) Pre-assembled insulated window sill system
CN110778031A (en) BIPV waterproof system
CN213741617U (en) Assembly type building connecting structure
CN211973085U (en) Bridge expansion joint waterproof construction
CN216156977U (en) Aluminum alloy layering type smooth glass daylighting roof structure
CN216616527U (en) Fire-resistant anticorrosive type nonmetal honeycomb fills foam composite sheet
CN211341455U (en) BIPV waterproof system
CN219773380U (en) Composite profiled steel sheet
CN220953938U (en) Wall deformation joint plugging device
CN221031015U (en) Ceramic tile roof and glass shutter daylighting roof node structure
CN210780664U (en) Photovoltaic module for waterproofing
CN214329610U (en) Roof waterproof structure
CN210530090U (en) Durable roof with steel frame structure
CN218437819U (en) Novel sunshine roof section bar structure
CN215442577U (en) Curtain corner waterproof construction
CN219158188U (en) Water seepage prevention structure for building roof board
CN219365064U (en) Mounting structure of building curtain wall
CN212506940U (en) Waterproof heat-preserving energy-saving building curtain wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant