CN218779315U - Pier shaft tye crack control device - Google Patents

Pier shaft tye crack control device Download PDF

Info

Publication number
CN218779315U
CN218779315U CN202223328458.9U CN202223328458U CN218779315U CN 218779315 U CN218779315 U CN 218779315U CN 202223328458 U CN202223328458 U CN 202223328458U CN 218779315 U CN218779315 U CN 218779315U
Authority
CN
China
Prior art keywords
pier shaft
reinforcing bar
tye
cracking
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223328458.9U
Other languages
Chinese (zh)
Inventor
许明迎
段江涛
许龙飞
顾军海
赵洪萍
黄晓勤
国鸿飞
赵扩
刘啸
贾晓凡
孙东阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 3 Engineering Group Co Ltd
Fourth Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Original Assignee
China Railway No 3 Engineering Group Co Ltd
Fourth Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 3 Engineering Group Co Ltd, Fourth Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd filed Critical China Railway No 3 Engineering Group Co Ltd
Priority to CN202223328458.9U priority Critical patent/CN218779315U/en
Application granted granted Critical
Publication of CN218779315U publication Critical patent/CN218779315U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a pier shaft construction tye technical field, the utility model provides a pier shaft tye crack control device, including pier shaft (1), pier shaft (1) surface depression forms tye (11), pier shaft (1) surface laminating sets up vertical reinforcing bar (2), pier shaft (1) one side rigid coupling is kept away from in vertical reinforcing bar (2) has horizontal reinforcing bar (3), pier shaft (2) one side rigid coupling is kept away from in horizontal reinforcing bar (3) has fixed block (4), be connected with anti cracking net (5) on fixed block (4), anti cracking net (5) are the galvanized steel wire net, anti cracking net (5) interval sets up, can make it laminate tye (11) better, the diameter of vertical reinforcing bar (2) and horizontal reinforcing bar (3) is less, can improve the thickness of concrete protective layer, fixed block (4) are the short reinforcing bar, the diameter of short reinforcing bar is little, do not encroach on the thickness of protective layer, the utility model discloses can prevent that pier shaft tye pier shaft department from influencing the whole quality of fracture, and save material, and cost is reduced.

Description

Pier shaft tye crack control device
Technical Field
The utility model relates to a pier shaft construction tye technical field, more specifically say, in particular to pier shaft tye anti cracking device.
Background
The bridge pier is located in the middle of a bridge and supports a building with two adjacent spans of superstructure, and mainly has the function of reliably and effectively transferring load transferred from the superstructure to a foundation, and is divided into a gravity type bridge pier and a light bridge pier. The conventional pier is damaged to a certain extent after being impacted by a vehicle or a ship and the like, flowing water flowing down from a bridge can erode the pier to different extents, the weak link of the high-speed rail round end solid pier is the flume at the front and the back of the pier, and the pier is arc-shaped, so that the design of reinforcing steel bars is dense, and the construction operation is inconvenient.
In the traditional pier body flume construction process method in the prior art, cracks generally exist at the finished pier body flume, the appearance quality of concrete is influenced by the appearance of the cracks, and the integrity of the concrete is also influenced by local cracks; the size of the water flowing groove is small, the steel bars are dense, the operation of increasing the steel bars is difficult, the plasticity of the steel bars is poor, the steel bars cannot be completely attached to the water flowing groove, and the increased steel bars can increase the cost of the pier body.
SUMMERY OF THE UTILITY MODEL
The utility model discloses an it is not enough to overcome above-mentioned condition, aims at providing a pier shaft tye anti cracking device, can prevent that pier shaft tye department fracture from influencing whole quality to save material, reduce cost.
The utility model provides a pier shaft tye anti cracking device, includes the pier shaft, pier shaft surface depression forms the tye that is used for the drainage, the laminating of pier shaft surface sets up vertical reinforcing bar, vertical reinforcing bar is kept away from pier shaft one side rigid coupling has horizontal reinforcement, horizontal reinforcement is kept away from pier shaft one side rigid coupling has the fixed block that is used for connecting the anti cracking net.
Furthermore, the distance between the anti-cracking net and the concrete surface layer is 25-30 mm.
Furthermore, the anti-cracking nets are arranged at intervals, and the distance between every two adjacent anti-cracking nets is 35-50 mm.
Further, the anti-cracking net is a galvanized steel wire net.
Further, the diameter of the vertical reinforcing steel bars and the diameter of the horizontal reinforcing steel bars are 6mm.
Further, the fixed block is a short steel bar.
Compared with the prior art, the beneficial effects of the utility model are that:
(1) the utility model discloses in, the diameter of vertical reinforcing bar and horizontal reinforcement that sets up on pier shaft and tye surface is 6mm, can improve the thickness of concrete protection layer to promoted the elastic modulus of concrete, and added the fixed block on the horizontal reinforcement, and connect the crack control net on the fixed block, crack control net interval sets up, can effectual laminating tye, finally prevent pier shaft tye concrete fracture, avoid influencing the wholeness of concrete.
(2) In the utility model, the anti-cracking net is arranged at the running water tank in a laminating way, and the anti-cracking net is a galvanized steel wire net, so the material cost is low; in the construction process, only the anti-cracking net needs to be additionally arranged, the fixing block is made of short steel bars, and the fixing block can be obtained from the existing steel bar materials without increasing the cost; the anti-cracking nets are arranged at intervals, and the distance between every two anti-cracking nets is 35-50 mm, so that the material is saved, and the cost is reduced.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention. In the drawings:
fig. 1 is a schematic cross-sectional view of an anti-cracking device for a pier body gutter channel;
fig. 2 is a schematic cross section view of a gutter channel of an anti-cracking device for a pier gutter channel;
fig. 3 is a front view of an anti-cracking device for a pier body gutter.
In the figure: 1-pier body, 11-flume, 2-vertical steel bar, 3-horizontal steel bar, 4-fixing block, 5-anti-cracking net and 6-concrete surface layer.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
The specific embodiment is as follows:
as shown in fig. 1, a pier shaft tye crack control device, including pier shaft 1, the sunken tye 11 that forms of pier shaft 1 lateral wall, the laminating of pier shaft 1 surface sets up the vertical reinforcing bar 2 of suitable quantity, one side fixed connection that pier shaft 1 was kept away from to vertical reinforcing bar 2 has horizontal reinforcing bar 3, horizontal reinforcing bar 3 bending shape and pier shaft 1 and tye 11 looks adaptation, the diameter of vertical reinforcing bar 2 and horizontal reinforcing bar 3 is 6mm, reduce the thickness of protective layer, promote concrete elastic modulus, the support body is constituteed to vertical reinforcing bar 2 and horizontal reinforcing bar 3, a protective layer for supporting whole pier shaft 1 and tye 11.
Further, one side fixedly connected with fixed block 4 that pier shaft 1 was kept away from to horizontal reinforcement 3, 4 intervals of fixed block set up, and the preferred short reinforcement of fixed block 4, short reinforcement diameter is less, does not invade the thickness that occupies the protective layer, and the short reinforcement does not have the incremental cost. One side that pier shaft 1 was kept away from to fixed block 4 is connected with anti cracking net 5, and anti cracking net 5 is 25 ~ 30mm apart from concrete surface layer 6, and anti cracking net 5 is preferred galvanized steel wire net, and galvanized steel wire net's bearing capacity is higher, and deformability is better, easily construction to the anticorrosive rust-resistant ability reinforcing of steel wire after the galvanization, life increases, is difficult for being damaged by the concrete. The grids of the anti-cracking net 5 can be made of concrete, are small in diameter and high in plasticity, and can ensure that the anti-cracking net 5 is attached to the steel bars at the position of the flume 11; and the anti-cracking nets 5 are arranged at intervals, and the distance between every two anti-cracking nets 5 is 35-50 mm, so that the anti-cracking nets 5 can be better attached to the launders 11.
The operating principle of a pier body tye crack control device in this embodiment is: the reason why the cracks are generated at the flume 11 is that after the protective layer passes, the semicircular arc-shaped stress is concentrated, so the thickness of the protective layer can be improved by adopting a reinforcing mesh consisting of vertical reinforcing steel bars 2 and horizontal reinforcing steel bars 3 with the thickness of 6 mm; the steel bars at the launder 11 are dense, so that the operation difficulty of the steel bars is increased, the plasticity of the steel bars is poor, and the steel bars cannot be completely attached to the launder 11, so that the anti-cracking net 5 is made of a steel wire net with strong plasticity, and the cost of the galvanized steel wire net is low; the fixing block 4 is a short steel bar, the diameter of the short steel bar is small, the short steel bar does not occupy the thickness of the protective layer, the anti-cracking net 5 can be fixed, and the cost of the short steel bar is not increased; the anti-cracking nets 5 are laid at intervals, the anti-cracking nets 5 are reduced, the anti-cracking nets are attached to the launder 11 better, and finally the concrete at the launder 11 can be prevented from cracking, so that the integrity of the concrete is guaranteed, the cost is low, and materials are saved.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (6)

1. The utility model provides a pier shaft tye crack control device which characterized in that: including pier shaft (1), pier shaft (1) surface depression forms tye (11) that are used for the drainage, pier shaft (1) surface laminating sets up vertical reinforcing bar (2), keep away from vertical reinforcing bar (2) pier shaft (1) one side rigid coupling has horizontal reinforcement (3), horizontal reinforcement (3) are kept away from pier shaft (1) one side rigid coupling has fixed block (4) that are used for connecting anti-cracking net (5).
2. The pier body gutter channel anti-cracking device according to claim 1, characterized in that: the distance between the anti-cracking net (5) and the concrete surface layer (6) is 25-30 mm.
3. The pier body launder anti-cracking device according to claim 1, characterized in that: the anti-cracking nets (5) are arranged at intervals, and the distance between every two adjacent anti-cracking nets (5) is 35-50 mm.
4. The pier body gutter channel anti-cracking device according to claim 1, characterized in that: the anti-cracking net (5) is a galvanized steel wire net.
5. The pier body launder anti-cracking device according to claim 1, characterized in that: the diameters of the vertical reinforcing steel bars (2) and the horizontal reinforcing steel bars (3) are 6mm.
6. The pier body launder anti-cracking device according to claim 1, characterized in that: the fixing block (4) is a short steel bar.
CN202223328458.9U 2022-12-13 2022-12-13 Pier shaft tye crack control device Active CN218779315U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223328458.9U CN218779315U (en) 2022-12-13 2022-12-13 Pier shaft tye crack control device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223328458.9U CN218779315U (en) 2022-12-13 2022-12-13 Pier shaft tye crack control device

Publications (1)

Publication Number Publication Date
CN218779315U true CN218779315U (en) 2023-03-31

Family

ID=85712951

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223328458.9U Active CN218779315U (en) 2022-12-13 2022-12-13 Pier shaft tye crack control device

Country Status (1)

Country Link
CN (1) CN218779315U (en)

Similar Documents

Publication Publication Date Title
CN109680605B (en) Comb-tooth type bridge expansion device
CN207862762U (en) Steel box-girder drainage-free tube built-in drainage system
CN218779315U (en) Pier shaft tye crack control device
CN212294295U (en) U-shaped beam adopting large-diameter steel strand
CN214034551U (en) Building concrete floor with crack control is consolidated with steel fibre
CN212561398U (en) Ultra-high performance concrete light U-shaped aqueduct body
CN210421137U (en) A bearing foundation structure for civil engineering structure uses
CN209759937U (en) Bridge deck pavement structure and bridge structure
CN210104546U (en) Prefabricated pier with lightning protection function
CN215051725U (en) Anti-pavement sinking type permeable pavement
CN215925728U (en) External prestress bearing device for reinforcing old bridge
CN220746576U (en) Rain canal for collecting bridge floor rainwater
CN219671218U (en) Diffuse dam reinforced structure
CN217026908U (en) Multilayer ecological protection structure for rural river
CN205557291U (en) Horizontal stretch -draw enhancement hinge joint 's wide bridge of empty core plate is constructed in turn
CN220166572U (en) Durable anti-leakage pavement structure
CN216740348U (en) Prestressed concrete single-slope double-T plate
CN216949052U (en) Cement building block with prevent structure that ftractures
CN217711098U (en) Multifunctional bracket column
CN213742453U (en) High-drainage cultural relic protection shell structure
CN216839321U (en) Concrete sea-mansion structure with over-joint reinforcing steel bars free of bonding and block stone roughening
CN219385860U (en) Ultra-high performance concrete combination bridge deck pavement layer structure
CN210529756U (en) Assembled integral type underground space top plate settlement joint component
CN214784600U (en) Garage silence ditch cover plate mounting structure
CN221001306U (en) Assembled UHPC drainage structures for underground garage

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant