CN218758655U - Engineering scaffold puts up top and holds in palm quick assembly device - Google Patents

Engineering scaffold puts up top and holds in palm quick assembly device Download PDF

Info

Publication number
CN218758655U
CN218758655U CN202222796373.7U CN202222796373U CN218758655U CN 218758655 U CN218758655 U CN 218758655U CN 202222796373 U CN202222796373 U CN 202222796373U CN 218758655 U CN218758655 U CN 218758655U
Authority
CN
China
Prior art keywords
jacking
power
tray
main shaft
sides
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222796373.7U
Other languages
Chinese (zh)
Inventor
马曼云
胡晓光
卓越
李晓磊
李思伟
王丹妮
谢术数
陈春吉
莫成城
杨杰
张洋
王成
冉立
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 8 Engineering Group Co Ltd
Construction Co of China Railway No 8 Engineering Group Co Ltd
Original Assignee
China Railway No 8 Engineering Group Co Ltd
Construction Co of China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 8 Engineering Group Co Ltd, Construction Co of China Railway No 8 Engineering Group Co Ltd filed Critical China Railway No 8 Engineering Group Co Ltd
Priority to CN202222796373.7U priority Critical patent/CN218758655U/en
Application granted granted Critical
Publication of CN218758655U publication Critical patent/CN218758655U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Transmission Devices (AREA)

Abstract

The utility model provides a quick assembly device for the jacking of an engineering scaffold, which comprises a jacking device and a jacking assembly, wherein the jacking device is in an inverted state and is arranged on a horizontal plane, the quick assembly device comprises a power main shaft and a power driven shaft, the power main shaft and the power driven shaft are connected into an integrated structure, and a fastener nut is arranged at the top of the power main shaft; the tray is screwed into a screw of the top support and comprises flanges on two sides; the power main shaft inserts in the top support, and the power is handed over from the edge of a wing of axle and tray both sides, including electric spanner, electric spanner is connected with the fastener nut, the electric spanner operation drives power main shaft and power from the rotation of axle through the fastener nut, the power from the axle passes through the edge of a wing of tray both sides, promotes the tray and rotates, and the screw in top holds in the palm fast assembly. The utility model discloses an assembly device replaces traditional manual assembly, combines electric wrench to show the equipment speed that has improved the top and hold in the palm.

Description

Engineering scaffold puts up top and holds in palm quick assembly device
Technical Field
The utility model discloses technical field of building engineering scaffold frame installation, concretely relates to engineering scaffold frame top holds in palm fast assembly device.
Background
At present, in engineering scaffold frame work progress, often need carry out artifical the equipment to the top support, need rotate the tray earlier to the top support top, insert the pole setting top with the top support again and carry out the secondary and adjust, in the assembling process that scaffold frame top held in the palm, whole process is artifical the completion, and artifical assembling process is long consuming time and repetition degree is high, and is inefficient, can increase the time limit for a project of whole engineering among the intangible.
The utility model patent application with the application number of CN202220682054.0 discloses a scaffold top support, which comprises a threaded pipe, a supporting plate and a threaded sleeve, wherein the supporting plate is arranged at the top of the threaded pipe, the outer side of the threaded pipe is connected with the threaded sleeve, handles are fixed on two sides of the threaded sleeve, and an inserting groove is formed in the threaded sleeve; the outer edge of the threaded sleeve is provided with a connecting seat, the inner side of the connecting seat is connected with a rotating block, and the outer portion of the threaded sleeve is sleeved with an anti-loosening sleeve. This scaffold puts up support, butt joint the welding seam groove of the inboard lower limb of arch and the plug bush in the screwed pipe outside, use welding equipment to weld along annular welding seam groove, conveniently fix a position welding equipment position, can lock with the assigned position through the spacing frame of layer board cooperation, avoid this top support to appear the butt joint skew, shift up and extrude the turning block and carry out the centre gripping to scaffold steel pipe outer wall along the screwed sleeve through rotatory locking collar, the convenience plays the effect that high-efficient support prevented rocking to scaffold steel pipe's top. The scaffold jacking structure disclosed by the application aims to enhance the stability of the connected scaffold and ensure the use safety, and particularly discloses a specific structure of the scaffold jacking; this application is concrete scaffold frame structure combination, and aim at how accelerates scaffold frame top tray's installation time, and can be more accurate through the quick assembly device find the center pin that holds in the palm on the top for the faster screw in top of tray in the installation holds in the palm and accomplishes the equipment operation.
SUMMERY OF THE UTILITY MODEL
The object of the present invention is to provide a quick assembling device for supporting scaffold of engineering, including a supporting device, the supporting device is placed on a horizontal plane in an inverted state, the quick assembling device includes a power main shaft and a power driven shaft, the power main shaft and the power driven shaft are connected into an integrated structure, and a fastener nut is disposed on the top of the power main shaft; the tray is screwed into a screw of the top support and comprises flanges on two sides; the power main shaft inserts in the top support, and the power is handed over from the edge of a wing of axle and tray both sides, including electric spanner, electric spanner is connected with the fastener nut, the electric spanner operation drives power main shaft and power from the rotation of axle through the fastener nut, the power from the axle passes through the edge of a wing of tray both sides, promotes the tray and rotates, and the screw in top holds in the palm fast assembly. The utility model discloses an assembly device replaces traditional manual assembly, combines electric wrench to show the equipment speed that has improved the top and held in the palm.
The utility model adopts the technical scheme as follows:
the utility model discloses a quick assembly device for the jacking of an engineering scaffold, which comprises a jacking device and a jacking assembly, wherein the jacking device is in an inverted state and is arranged on a horizontal plane, the quick assembly device comprises a power main shaft and a power driven shaft, the power main shaft and the power driven shaft are connected into an integrated structure, and a fastener nut is arranged at the top of the power main shaft;
the tray is screwed into a screw of the top support and comprises flanges on two sides; the power main shaft inserts in the top support, and the power is handed over from the edge of a wing of axle and tray both sides, including electric spanner, electric spanner is connected with the fastener nut, the electric spanner operation drives power main shaft and power from the rotation of axle through the fastener nut, the power from the axle passes through the edge of a wing of tray both sides, promotes the tray and rotates, and the screw in top holds in the palm fast assembly.
Furthermore, the power driven shaft is of a door-shaped frame structure, the door-shaped frame structure comprises two side rods, the side rods are connected with flanges on two sides of the tray to transmit the rotating power of the tray, the power main shaft is arranged in the middle of the door-shaped frame structure, and the separated power driven shaft is of a symmetrical structure.
Further, the top support comprises a top support screw rod, a top support and a top support, the top support screw rod is connected with the top support, the top support screw rod is supported through the top support to be stable in position, the top support screw rod is of a hollow rod structure, a power main shaft of the rapid assembly device is inserted into the top support screw rod, and a rotation center shaft of the rapid assembly device is formed.
Furthermore, the tray comprises flanges at two sides, the flanges at two sides of the tray are connected with side rods of the power driven shaft, and the flanges at two sides of the tray and the side rods of the power driven shaft are arranged in a front-back staggered connection mode; the outer surface of the jacking screw rod is provided with threads, the threads are matched with the inner threads of the tray, the electric wrench drives the quick assembly device to rotate, the side rods and the flanges on the two sides of the tray form the rotating torque of the tray, and the tray is screwed into the jacking screw rod through the matched threads.
Further, the fastener nut is the hexagon structure, and the fastener nut matches in electric spanner's connector setting, the fastener nut is connected with electric spanner's connector, and electric spanner passes through fastener nut drive fast assembly device unidirectional rotation.
Further, the power driven shaft comprises side bars on two sides, the length of the side bars on the two sides is the same, and the length of the side bars is larger than that of the power main shaft; setting a power main shaft as a steel bar with the diameter of 18-20mm and a power driven shaft as a steel bar with the diameter of 16-18 mm.
The technical effects of the utility model are as follows:
the utility model discloses an engineering scaffold puts up support fast assembly device, the effectual manual assembly process time-consuming is long and the repeatability is high among the prior art of having solved, lead to the problem of inefficiency. The utility model provides a device that combines electric spanner fast revolution equipment tray, and adopt welding such as the common material reinforcing bar of job site, fastener nut to constitute, have low in manufacturing cost, simple, the fast a bit of equipment of preparation technique. The utility model discloses an assembly device has replaced traditional manual equipment, combines electric wrench to show the equipment speed that has improved the top and hold in the palm.
Drawings
Fig. 1 is a schematic view of the installation structure of the present invention;
FIG. 2 is a front view of the quick assembly device of the present invention;
FIG. 3 is a top view of the quick assembly device of the present invention;
the labels in the figure are: 1-top support, 101-top support screw rod, 102-top support base, 103-top support, 2-quick assembly device, 201-power main shaft, 202-power driven shaft, 203-fastener nut, 3-pallet and 4-electric wrench.
Detailed Description
The present invention will be described in detail with reference to the accompanying drawings.
In order to make the objects, technical solutions and advantages of the present invention more clearly understood, the present invention will be further described in detail with reference to the accompanying drawings and embodiments.
In this embodiment, the adopted data is a preferred solution, but is not used to limit the present invention;
example 1
As shown in fig. 1-3, the embodiment provides a quick assembly device for a jacking of an engineering scaffold, which comprises a jacking, wherein the jacking is placed on a horizontal plane in an inverted state and comprises a quick assembly device and a jacking combination, the quick assembly device comprises a power main shaft and a power driven shaft, the power main shaft and the power driven shaft are connected into an integrated structure, and a fastener nut is arranged at the top of the power main shaft;
the tray is screwed into a screw of the top support and comprises flanges on two sides; the power main shaft inserts in the top support, and the power is handed over from the edge of a wing of axle and tray both sides, including electric spanner, electric spanner is connected with the fastener nut, the electric spanner operation drives power main shaft and power from the rotation of axle through the fastener nut, the power from the axle passes through the edge of a wing of tray both sides, promotes the tray and rotates, and the screw in top holds in the palm fast assembly.
In this embodiment, power from the axle is door shape frame construction, and door shape frame construction includes two side levers, and the side lever hands over with the both sides edge of a wing of tray, the rotation power of transmission tray, and in the rotatory in-process of device, rotation power passes through power main shaft and transmits to the power from the axle, provides tray rotation power through two side levers, power main shaft sets up in the middle part position of door shape frame construction, and it is symmetrical structure to separate the power from the axle.
In this embodiment, the power main shaft is a connecting piece arranged in the middle of the power driven shaft, the power main shaft penetrates through the power driven shaft, and the lower edge surface of the door-shaped frame structure is in contact with the top of the jacking screw rod to limit the displacement of the power main shaft.
Further, the top support comprises a top support screw rod, a top support and a top support, the top support screw rod is connected with the top support, the top support screw rod is supported through the top support to be stable in position, the top support screw rod is of a hollow rod structure, a power main shaft of the rapid assembly device is inserted into the top support screw rod, and a rotation center shaft of the rapid assembly device is formed. As shown in fig. 1, the power spindle is vertically inserted downwards into the jacking screw, that is, in the manual operation process, besides the slow speed of manually rotating the tray, the problem of low manual operation correction rate exists, and the rotation angle of the tray is inclined, so that the assembly of the tray is not standard. This embodiment inserts the top support as the center pin through power main shaft for the device rotates and uses power main shaft as the rotation of center, has reduced the device and has produced eccentric rotation.
In the embodiment, the tray comprises flanges at two sides, the flanges at two sides of the tray are connected with the side rods of the power driven shaft, and the flanges at two sides of the tray are connected with the side rods of the power driven shaft in a front-back staggered manner; the outer surface of the jacking screw rod is provided with threads, the threads are matched with the inner threads of the tray, the electric wrench drives the quick assembly device to rotate, the side rods and the flanges on the two sides of the tray form the rotating torque of the tray, and the tray is screwed into the jacking screw rod through the matched threads.
In this embodiment, as shown in fig. 1, the tray and the side rods are connected in a front-back connection manner, and under the action of the side rods, the whole tray is stressed in a rod state, and rotates around a jacking screw rod serving as a central shaft.
In the embodiment, when the device is used, the jacking is inverted, the tray is screwed into the jacking screw rod by about 1cm, the power main shaft in the middle of the assembling device is inserted into the jacking to achieve the fixing effect, and the electric wrench can be started to rotate the device to drive the tray to rotate so as to achieve the effect of quick assembly; after the assembly is completed, the device is directly pulled out to be used for the assembly operation of the next jacking.
Example 2
As shown in fig. 1-3, the embodiment provides a quick assembly device for a jacking of an engineering scaffold, which comprises a jacking, wherein the jacking is placed on a horizontal plane in an inverted state and comprises a quick assembly device and a jacking combination, the quick assembly device comprises a power main shaft and a power driven shaft, the power main shaft and the power driven shaft are connected into an integrated structure, and a fastener nut is arranged at the top of the power main shaft;
the tray is screwed into a screw of the top support and comprises flanges on two sides; the power main shaft inserts in the top support, and the power is handed over from the edge of a wing of axle and tray both sides, including electric spanner, electric spanner is connected with the fastener nut, the electric spanner operation drives power main shaft and power from the rotation of axle through the fastener nut, the power from the axle passes through the edge of a wing of tray both sides, promotes the tray and rotates, and the screw in top holds in the palm fast assembly.
In the embodiment, the power driven shaft comprises a power main shaft and a power driven shaft, wherein the power driven shaft comprises side bars on two sides, the length of the side bars on the two sides is the same, and the length of the side bars is larger than that of the power main shaft; the power main shaft is set to be a steel bar with the diameter of 20mm, and the power main shaft is set to be a steel bar with the diameter of 18 mm.
In this embodiment, adopt job site material welded forming assembly device, including reinforcing bar and fastener nut, carry out bending process and welded forming to the reinforcing bar, with a fastener nut of top welding again.
In this embodiment, the fastener nut is the hexagon structure, and the fastener nut matches in electric spanner's connector setting, the fastener nut is connected with electric spanner's connector, and electric spanner passes through fastener nut drive fast assembly device unidirectional rotation.
The above description is only a preferred embodiment of the present invention and should not be taken as limiting the invention, and any modifications, equivalent replacements, and improvements made within the spirit and principle of the present invention should be included within the protection scope of the present invention.

Claims (6)

1. A quick assembly device for a jacking of an engineering scaffold comprises a jacking (1), wherein the jacking (1) is arranged on a horizontal plane in an inverted state, and is characterized by comprising a quick assembly device (2) and the jacking (1) which are combined, wherein the quick assembly device (2) comprises a power main shaft (201) and a power driven shaft (202), the power main shaft (201) and the power driven shaft (202) are connected into an integral structure, and a fastener nut (203) is arranged at the top of the power main shaft (201);
the tray (3) is screwed into a jacking screw (101), and the tray (3) comprises flanges at two sides; power main shaft (201) insert in top support (1), and power connects from the flange handing-over of axle (202) and tray (3) both sides, including electric spanner (4), and electric spanner (4) are connected with fastener nut (203), electric spanner (4) operation drives power main shaft (201) and power from the axle (202) rotation through fastener nut (203), power pushes away tray (3) and rotates from the flange of axle (202) through tray (3) both sides, and screw in top support (1) fast assembly.
2. The quick assembling device for the jacking of the engineering scaffold as claimed in claim 1, wherein the power driven shaft (202) is a door-shaped frame structure, the door-shaped frame structure comprises two side bars, the side bars are connected with flanges at two sides of the tray (3) to transmit the rotation power of the tray (3), the power main shaft (201) is arranged at the middle position of the door-shaped frame structure, and the separation power driven shaft (202) is a symmetrical structure.
3. The quick assembling device for the jacking of the engineering scaffold according to claim 2, wherein the jacking (1) comprises a jacking screw (101), a jacking support (102) and a jacking support (103), the jacking screw (101) is connected with the jacking support (102), the position of the jacking screw (101) is stabilized by the jacking support (103), the jacking screw (101) is of a hollow rod structure, and a power spindle (201) of the quick assembling device (2) is inserted into the jacking screw (101) to form a rotating central shaft of the quick assembling device (2).
4. The quick assembling device for the jacking of the engineering scaffold as claimed in claim 3, wherein the tray (3) comprises flanges at two sides, the flanges at two sides of the tray (3) are connected with side bars of the power driven shaft (202), and the flanges at two sides of the tray (3) are connected with the side bars of the power driven shaft (202) in a front-back staggered manner; the outer surface of the jacking screw rod (101) is provided with threads, the threads are matched with internal threads of the tray (3), the electric wrench (4) drives the quick assembly device (2) to rotate, the side rods and flanges on two sides of the tray (3) form the rotating torque of the tray (3), and the tray (3) is screwed in through the matched threads to jack the jacking screw rod (101).
5. The quick assembly device for the jacking of the engineering scaffold as claimed in claim 1 or 4, wherein the fastening nut (203) is a hexagonal structure, the fastening nut (203) is matched with the connector of the electric wrench (4), the fastening nut (203) is connected with the connector of the electric wrench (4), and the electric wrench (4) drives the quick assembly device (2) to rotate in one direction through the fastening nut (203).
6. The quick assembling device for the jacking of the engineering scaffold as claimed in claim 5, which comprises a power main shaft (201) and a power driven shaft (202), wherein the power driven shaft (202) comprises side bars on two sides, and the length of each side bar is larger than that of the power main shaft (201); the power main shaft (201) is set to be a steel bar with the diameter of 18-20mm, and the power driven shaft (202) is set to be a steel bar with the diameter of 16-18 mm.
CN202222796373.7U 2022-10-24 2022-10-24 Engineering scaffold puts up top and holds in palm quick assembly device Active CN218758655U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222796373.7U CN218758655U (en) 2022-10-24 2022-10-24 Engineering scaffold puts up top and holds in palm quick assembly device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222796373.7U CN218758655U (en) 2022-10-24 2022-10-24 Engineering scaffold puts up top and holds in palm quick assembly device

Publications (1)

Publication Number Publication Date
CN218758655U true CN218758655U (en) 2023-03-28

Family

ID=85700385

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222796373.7U Active CN218758655U (en) 2022-10-24 2022-10-24 Engineering scaffold puts up top and holds in palm quick assembly device

Country Status (1)

Country Link
CN (1) CN218758655U (en)

Similar Documents

Publication Publication Date Title
CN219158181U (en) U-sleeve steel bar threaded connecting piece
CN218758655U (en) Engineering scaffold puts up top and holds in palm quick assembly device
CN107700736B (en) A kind of steel-structure roof and its installation method
CN206722449U (en) A kind of building iron support frame
CN213793997U (en) Welding and positioning device for main reinforcement of steel reinforcement cage
CN214362660U (en) Road and bridge crack reinforcing structure
CN107419853B (en) A kind of reinforced steel bar straight thread coupling sleeve with realizing middle limiting
CN219327335U (en) Manual steel bar deviation adjusting device
CN208960871U (en) A kind of portable screw-thread steel Quick mechanical attachment device
CN219887190U (en) Reinforcing apparatus of assembled wall body
CN112427692A (en) Bailey pin pulling-out device and pulling-out method
CN220539190U (en) Mounting tool for socket type disc buckle scaffold adjusting nut
CN214272406U (en) Energy-saving steel structure unit
CN214162845U (en) Dismounting device for water stop screw
CN218264895U (en) Building engineering outrigger is wall spare even convenient to installation
CN212497481U (en) Special tool for assembling and disassembling tower crane
CN220954225U (en) Joint converter for connection between steel bars
CN221186253U (en) Screw-thread steel fastener
CN219993080U (en) Scaffold and wall connection structure
CN215433491U (en) Special tool for bearing disassembly
CN221088699U (en) Constant force clamp
CN220783580U (en) Drilling fixture for steel structure connecting plate
CN221001920U (en) Pre-buried steel pipe fastener formula even wall spare
CN220239688U (en) Pipe out-of-roundness correction tool
CN214942445U (en) Adjustable jacking quick adjustment instrument

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant