CN218758612U - Civil engineering construction support - Google Patents
Civil engineering construction support Download PDFInfo
- Publication number
- CN218758612U CN218758612U CN202222031518.4U CN202222031518U CN218758612U CN 218758612 U CN218758612 U CN 218758612U CN 202222031518 U CN202222031518 U CN 202222031518U CN 218758612 U CN218758612 U CN 218758612U
- Authority
- CN
- China
- Prior art keywords
- construction support
- civil engineering
- steel pipe
- support
- engineering construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model belongs to the technical field of civil engineering, in particular to a civil engineering construction support, which comprises a construction support, wherein the construction support comprises a support base, a hydraulic cylinder, a telescopic column, an operation platform and a connecting fixing plate, the hydraulic cylinder is arranged at the central position of the support base, and a notch is arranged on the plate; still include guiding mechanism, guiding mechanism and construction support fixed connection, guiding mechanism includes direction steel pipe and buffering subassembly, the direction steel pipe passes breach and support base fixed connection, the direction steel pipe is equipped with ball hole and square hole, the buffering unit mount is in ball hole and square hole, the utility model provides a current civil engineering construction support because lack guiding mechanism at the lift in-process for operation platform ascending process exists rocks, and is not stable enough, and construction support safety in utilization does not have guaranteed problem.
Description
Technical Field
The utility model belongs to the technical field of civil engineering, concretely relates to civil engineering building construction support.
Background
The civil engineering construction is a production activity in the engineering construction implementation stage, is a construction process of various buildings, can be said to be a process of changing various lines on a design drawing into a real object at a designated place, and comprises basic engineering construction, main structure construction, roofing engineering construction, decoration engineering construction and the like, the place of construction operation is called a construction site or a construction site, the civil engineering construction support is an auxiliary support frame for civil engineering construction, is one of building equipment commonly used in the construction process, is usually used for supporting an operator or a material by using the civil engineering construction support frame, and the operator stands on the support frame to carry out high-altitude operation so as to facilitate construction work.
Chinese patent with application number CN202022622191.9 discloses a civil engineering construction support, the on-line screen storage device comprises a base, base bottom symmetry rotates and installs four gyro wheels, the both ends that the base kept away from mutually and being close to a side symmetry of four gyro wheels and installing four fixed establishment, the base is kept away from the one end symmetry embedding of four gyro wheels and is installed four steel pipe spacing rings, all insert between four steel pipe spacing ring inner walls and install a steel pipe, the one end of just keeping away from the base on the outer wall of four steel pipes all fixed the cup joints a support piece, all fixed the cup joint a lantern ring on the outer wall of four steel pipes, equal fixed mounting has a connecting rod between the adjacent inner wall of four lantern rings, the utility model provides a civil engineering construction support, this support adopts movable base, and be provided with fixed establishment, guarantee the stability after the support mounting and effectively improve the convenience that it removed, the steel pipe is convenient for install on the base simultaneously, and connect stably between the steel pipe, the convenience of support installation is greatly improved.
However, the civil engineering and building construction support in the prior art is lack of a guide mechanism in the lifting process, so that the operation platform is shaken in the lifting process and is not stable enough, and the use safety of the construction support is not guaranteed.
SUMMERY OF THE UTILITY MODEL
To the above-mentioned weak point that exists among the prior art, the utility model provides a civil engineering construction support for solve current civil engineering construction support because lack guiding mechanism at the lift in-process for operation platform rises the process and exists and rock, and is unstable inadequately, and construction support safety in utilization does not have the problem of assurance.
In order to solve the technical problem, the utility model discloses a following technical scheme:
the civil engineering building construction support comprises a construction support, wherein the construction support comprises a support base, a hydraulic cylinder, a telescopic column, an operation platform and a connecting and fixing plate, the hydraulic cylinder is arranged at the central position of the support base and is connected with the telescopic column, the telescopic column is fixedly connected with the operation platform through the connecting and fixing plate, the operation platform comprises a bearing plate and a guardrail, the guardrail is arranged on the bearing plate, and a notch is formed in the bearing plate;
still include guiding mechanism, guiding mechanism and construction support fixed connection, guiding mechanism includes direction steel pipe and buffering subassembly, the direction steel pipe passes breach and support base fixed connection, the direction steel pipe is equipped with ball hole and square hole, the buffering subassembly is installed in ball hole and square hole.
When the civil engineering construction support is used specifically, due to the lack of the guide mechanism in the lifting process, the operation platform is shaken and is not stable enough in the lifting process, and the use safety of the construction support is not guaranteed; the operation platform is firstly contacted with a bump when the operation platform rises, the bump is extruded to move in the guide steel pipe, after the operation platform is separated from the bump, the operation platform rebounds and resets under the action of a spring, the buffering effect is achieved, the operation platform is contacted with steel balls and extruded after continuing to rise, the steel balls drive the whole buffering assembly to move in the guide steel pipe, when the operation platform falls in an accident, the operation platform is contacted with the top of the bump, the bump cannot be extruded inwards due to the fact that the top of the bump is horizontal, the operation platform is limited from continuing to fall, workers can continue to fall after pressing the steel balls, the accident falling is prevented, and the safety of the civil engineering construction support is improved.
Furthermore, the buffering component comprises a steel ball, a connecting rod, an elastic sheet, a connecting plate and a clamping mechanism, wherein the steel ball is installed in the ball hole, the connecting rod is installed inside the guide steel pipe, the steel ball is connected with the middle of the connecting plate through the connecting rod, the upper end of the connecting plate is hinged to the inner wall of the guide steel pipe, one end of the elastic sheet is fixedly connected with the inner wall of the guide steel pipe, the other end of the elastic sheet is fixedly connected with the middle of the connecting plate, the clamping mechanism is movably connected with the connecting plate, and the clamping mechanism is installed in the square hole.
Further, screens mechanism includes movable rod, spring, lug and stopper, the round hole and the lug connection of connecting plate bottom are passed to movable rod one end, the other end and the stopper of movable rod are connected, be equipped with positioning groove on the lug, the periphery at the movable rod is established to the spring housing, spring one end and connecting plate bottom fixed connection, the other end and the positioning groove fixed connection of spring.
Furthermore, the bottom of the bracket base is provided with a caster.
When specifically using, in order to prevent the unexpected slope of civil engineering construction support and convenient the removal, placed the iron plate on the diagonal position of support base, installed the truckle in the bottom of support base.
Compared with the prior art, the utility model, following beneficial effect has: the guide mechanism is arranged on the construction support, so that the operation platform is lifted more stably; the buffering assembly is designed on the guide steel pipe, so that the operation platform can be prevented from falling rapidly due to accidents, the safety of constructors is guaranteed, and the safety of the civil engineering construction support is improved.
Drawings
Fig. 1 is a schematic perspective view of an embodiment of a civil engineering construction support of the present invention;
FIG. 2 is an exploded view of a construction support in an embodiment of the civil engineering construction support of the present invention;
FIG. 3 is a schematic perspective view of a buffer assembly in an embodiment of a civil engineering construction support of the present invention;
FIG. 4 is a schematic perspective view of a locking mechanism in an embodiment of the civil engineering construction scaffold of the present invention;
reference numerals in the drawings of the specification include:
the device comprises a guide mechanism 1, a guide steel pipe 101, a ball hole 1011, a square hole 1012, a buffer component 102, a steel ball 1021, a connecting rod 10211, an elastic sheet 1022, a connecting plate 1023, a clamping mechanism 1024, a movable rod 10241, a spring 10242, a bump 10243, a positioning groove 102431, a limiting block 10244, a construction support 2, a support base 201, a hydraulic cylinder 202, a telescopic column 2021, an operation platform 203, a guardrail 2031, a bearing plate 2032, a notch 2033, a connecting fixing plate 204, an iron block 205 and a caster 206.
Detailed Description
In order to make the present invention better understood by those skilled in the art, the technical solutions of the present invention are further described below with reference to the accompanying drawings and examples.
Wherein the showings are for the purpose of illustration only and are shown by way of illustration only and not in actual form, and are not to be construed as limiting the present patent; for a better understanding of the embodiments of the present invention, some parts of the drawings may be omitted, enlarged or reduced, and do not represent the size of an actual product; it will be understood by those skilled in the art that certain well-known structures in the drawings and descriptions thereof may be omitted.
The same or similar reference numerals in the drawings of the embodiments of the present invention correspond to the same or similar parts; in the description of the present invention, it should be understood that if the terms "upper", "lower", "left", "right", "inner", "outer", etc. are used to indicate the orientation or positional relationship based on the orientation or positional relationship shown in the drawings, it is only for convenience of description and simplification of description, but it is not indicated or implied that the device or element referred to must have a specific orientation, be constructed in a specific orientation, and be operated, and therefore, the terms describing the positional relationship in the drawings are used only for illustrative purposes and are not to be construed as limiting the present patent, and the specific meaning of the terms will be understood by those skilled in the art according to the specific circumstances.
In the description of the present invention, unless otherwise explicitly specified or limited, the term "connected" or the like, if appearing to indicate a connection relationship between the components, is to be understood broadly, for example, as being either a fixed connection, a detachable connection, or an integral part; can be mechanically or electrically connected; they may be directly connected or indirectly connected through intervening media, or may be connected through one or more other components or may be in an interactive relationship with one another. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
The first embodiment is as follows:
as shown in fig. 1 to 4, a civil engineering building construction support includes a construction support 2, the construction support 2 includes a support base 201, a hydraulic cylinder 202, a telescopic column 2021, an operation platform 203 and a connection fixing plate 204, the hydraulic cylinder 202 is installed at the center of the support base 201, the hydraulic cylinder 202 is connected with the telescopic column 2021, the telescopic column 2021 is fixedly connected with the operation platform 203 through the connection fixing plate 204, the operation platform 203 includes a bearing plate 2032 and a guardrail 2031, the guardrail 2031 is installed on the bearing plate 2032, and a notch 2033 is arranged on the bearing plate 2032; still include guiding mechanism 1, guiding mechanism 1 and construction support 2 fixed connection, guiding mechanism 1 includes direction steel pipe 101 and buffer assembly 102, and direction steel pipe 101 passes breach 2033 and support base 201 fixed connection, and direction steel pipe 101 is equipped with ball hole 1011 and square hole 1012, and buffer assembly 102 installs in ball hole 1011 and square hole 1012.
When the civil engineering construction support is used specifically, due to the lack of a guide mechanism in the lifting process, the operation platform is shaken and is not stable enough in the lifting process, and the use safety of the construction support is not guaranteed, so that the civil engineering construction support is designed and comprises the guide mechanism 1 and the construction support 2, wherein the construction support 2 utilizes the hydraulic cylinder 202 as power to stretch the telescopic column 2021, the operation platform 203 is fixedly connected with the telescopic column 2021, and the telescopic column 2021 is utilized to stretch and descend the operation platform 203; the concrete principle of the construction method is that when the operation platform 203 ascends, the operation platform 203 firstly contacts with a bump 10243 and extrudes the bump 3536 zxft 36 to move towards the steel pipe 101, after the operation platform 203 is separated from the bump 3926, the operation platform 203 rebounds and resets under the action of a spring 3528 and under the action of a civil engineering zxft 3528 to play a role in buffering and extruding the steel ball, 351021 drives the whole buffering assembly 102 to move towards the steel pipe 101, when the operation platform 203 descends to be in contact with the top of a bump 3835 zxft 3935, the bump 3524 is in buffering and extruding contact with the steel ball, the steel ball 1021 drives the whole buffering assembly 102 to move towards the steel pipe 101, and when the operation platform 203 is unexpected, the operation platform 203 descends to be in contact with the top of the bump 3835 zxft 3935, the bump 24 zxft 24 is a horizontal notch 20334, the steel ball support cannot be horizontally extruded, and the construction worker can be prevented from dropping into the steel ball support 3534.
The above are merely examples of the present invention, and common general knowledge of known specific structures and characteristics of the embodiments is not described herein, and those skilled in the art will know all the common technical knowledge in the technical field of the present invention before the application date or priority date, can know all the prior art in this field, and have the ability to apply the conventional experimental means before this date. It should be noted that, for those skilled in the art, without departing from the structure of the present invention, several modifications and improvements can be made, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicability of the patent.
Claims (5)
1. The utility model provides a civil engineering construction support which characterized in that: the construction support comprises a construction support (2), wherein the construction support (2) comprises a support base (201), a hydraulic cylinder (202), a telescopic column (2021), an operation platform (203) and a connecting and fixing plate (204), the hydraulic cylinder (202) is installed at the center of the support base (201), the hydraulic cylinder (202) is connected with the telescopic column (2021), the telescopic column (2021) is fixedly connected with the operation platform (203) through the connecting and fixing plate (204), the operation platform (203) comprises a bearing plate (2032) and a guardrail (2031), the guardrail (2031) is installed on the bearing plate (2032), and a notch (2033) is formed in the bearing plate (2032);
still include guiding mechanism (1), guiding mechanism (1) and construction support (2) fixed connection, guiding mechanism (1) is including direction steel pipe (101) and buffering subassembly (102), direction steel pipe (101) pass breach (2033) and support base (201) fixed connection, direction steel pipe (101) are equipped with ball hole (1011) and square hole (1012), install in ball hole (1011) and square hole (1012) buffering subassembly (102).
2. A civil engineering construction support as claimed in claim 1, wherein: buffer unit (102) include steel ball (1021), connecting rod (10211), elastic sheet (1022), connecting plate (1023) and screens mechanism (1024), steel ball (1021) are installed in ball hole (1011), the inside at direction steel pipe (101) is installed in connecting rod (10211), steel ball (1021) are connected through connecting rod (10211) and connecting plate (1023) middle part, the upper end and the direction steel pipe (101) inner wall of connecting plate (1023) are articulated, elastic sheet (1022) one end and direction steel pipe (101) inner wall fixed connection, the other end and the connecting plate (1023) middle part fixed connection of elastic sheet (1022), screens mechanism (1024) and connecting plate (1023) swing joint, screens mechanism (1024) is installed in square hole (1012).
3. A civil engineering construction support as claimed in claim 2, wherein: the clamping mechanism (1024) comprises a movable rod (10241), a spring (10242), a bump (10243) and a limiting block (10244), one end of the movable rod (10241) penetrates through a round hole in the bottom of a connecting plate (1023) and is connected with the bump (10243), the other end of the movable rod (10241) is connected with the limiting block (10244), a positioning groove (102431) is arranged on the bump (10243), the spring (10242) is sleeved on the periphery of the movable rod (10241), one end of the spring (10242) is fixedly connected with the bottom of the connecting plate (1023), and the other end of the spring (10242) is fixedly connected with the positioning groove (102431).
4. A civil engineering construction support as claimed in claim 3, wherein: and an iron block (205) is placed on the diagonal position of the support base (201).
5. A civil engineering construction support as claimed in claim 4, wherein: and the bottom of the bracket base (201) is provided with a caster (206).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222031518.4U CN218758612U (en) | 2022-08-03 | 2022-08-03 | Civil engineering construction support |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222031518.4U CN218758612U (en) | 2022-08-03 | 2022-08-03 | Civil engineering construction support |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218758612U true CN218758612U (en) | 2023-03-28 |
Family
ID=85689566
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202222031518.4U Active CN218758612U (en) | 2022-08-03 | 2022-08-03 | Civil engineering construction support |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218758612U (en) |
-
2022
- 2022-08-03 CN CN202222031518.4U patent/CN218758612U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101553966B1 (en) | Wall-mounted Tower Crane Climbing Device | |
KR101873394B1 (en) | Climbing shoe of climbing system | |
CN218758612U (en) | Civil engineering construction support | |
CN211891475U (en) | Improved simple top plate drilling device | |
CN210195457U (en) | Safety protective guard is used in civil engineering | |
CN112982933B (en) | Simple scaffold device for spherical tank construction | |
JPH09268778A (en) | Disassembling method of water-contained gas holder and member used for the same method | |
CN111874794A (en) | Building engineering building materials overhead hoist | |
CN219100658U (en) | Side tilting protection device for building construction | |
CN111009849A (en) | A operation support for insulator is changed | |
CN219276262U (en) | Make things convenient for simple and easy device that beam slab bottom was perforated | |
CN220555787U (en) | Box girder bridge deck safety device | |
CN219671345U (en) | Steel protects a guiding device | |
CN209929468U (en) | Base station ground heightening frame | |
CN221700947U (en) | Lifting platform anti-falling device | |
CN220868767U (en) | Articulated steel structure welding operation platform | |
CN220167441U (en) | Building climbing frame | |
CN210396064U (en) | Scaffold for building | |
CN212129856U (en) | Strutting arrangement is used in building engineering construction | |
CN220822421U (en) | Bridge cable hoisting system | |
CN213710283U (en) | Outdoor removal support frame for building engineering | |
KR102599079B1 (en) | Construction climbing system with returnable lifting and lowering device | |
CN217734758U (en) | Anti-overturning scaffold with strong stability | |
CN215924161U (en) | Lifting lug for dismounting working of overlong overhanging steel structure cornice of high-rise building | |
CN219592036U (en) | Construction site cable protection frame |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |