CN218754513U CN202222917932.5U CN202222917932U CN218754513U CN 218754513 U CN218754513 U CN 218754513U CN 202222917932 U CN202222917932 U CN 202222917932U CN 218754513 U CN218754513 U CN 218754513U
Authority
CN
China
Prior art keywords
wire rope
rings
transformer substation
prefabricated cabin
steel wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222917932.5U
Other languages
Chinese (zh)
Inventor
郝敬涛
潘志武
张宗义
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Electric Group Intelligent Power Equipment Co ltd
Original Assignee
Nanjing Electric Group Intelligent Power Equipment Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Electric Group Intelligent Power Equipment Co ltd filed Critical Nanjing Electric Group Intelligent Power Equipment Co ltd
Priority to CN202222917932.5U priority Critical patent/CN218754513U/en
Application granted granted Critical
Publication of CN218754513U publication Critical patent/CN218754513U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a prefabricated cabin of transformer substation is with hoist structure, including prefabricated cabin body of transformer substation, first wire rope and second wire rope, the both sides of prefabricated cabin body bottom of transformer substation have first rings soon, it has the couple to hang in the first rings, first suspension clasp has been hung at the top of couple, it has second fixing bolt to revolve in the first suspension clasp, the cover that goes up of second fixing bolt has first wire rope, first wire rope's top cover has the second rings, the top of second rings has the supporting steel soon, the cross-section of supporting steel presents "worker" style of calligraphy, the second rings are provided with four in the bottom of supporting steel, the utility model discloses then hang on the second suspension clasp through second wire rope, then through the mutual coincidence of the becket on the second wire rope, make four becket hang simultaneously on the lifting hook of loop to only need a loop just can hoist, thereby still solved simultaneously the lifting rope extrusion cabin top, reduce prefabricated cabin damage.

Description

Hoisting structure for prefabricated cabin of transformer substation
Technical Field
The utility model relates to a hoisting structure specifically is a hoisting structure is used in prefabricated cabin of transformer substation.
Background
The prefabricated cabin transformer substation is a high-voltage switch device, a distribution transformer and a low-voltage distribution device, is factory prefabricated indoor and outdoor compact distribution equipment which is integrated according to a certain wiring scheme, namely functions of high-voltage power receiving, transformer voltage reduction, low-voltage distribution and the like are organically combined together, and the prefabricated cabin transformer substation is installed in a moistureproof, antirust, dustproof, ratproof, fireproof, antitheft, heat-insulating, totally closed and movable steel structure box body, is mechanically and electrically integrated and operates in a totally closed mode, is particularly suitable for urban network construction and transformation, and is a brand-new transformer substation which rises after civil construction of the transformer substation. The prefabricated cabin transformer substation is suitable for mines, factory enterprises, oil-gas fields and wind power stations, replaces the original civil power distribution room and power distribution station, and becomes a novel complete set of power transformation and distribution device. Prefabricated cabin transformer substation is applicable to residential quarter, the urban public becomes, flourishing city, construction power etc, hoisting structure need be used in the installation of the prefabricated cabin of transformer substation, the four corners in prefabricated cabin is installed to the prefabricated cabin of current transformer substation generally adoption rings when hoist and mount, then directly use four wire rope to hang on rings, then hang on the loop wheel through wire rope, need use two loop wheel machines, the troublesome poeration, the crowded ballast roof portion still easily of lifting rope simultaneously, lead to prefabricated cabin to damage, for solving above-mentioned problem, a hoisting structure is used to prefabricated cabin of transformer substation, urgent need to be developed.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a prefabricated for cabin hoisting structure of transformer substation generally adopts rings to install the four corners in prefabricated cabin when hoist and mount, then directly uses four wire rope to hang on rings, then hangs on the loop wheel through wire rope, need use two loop wheel machines, troublesome poeration, the lifting rope is still crowded ballast roof portion easily simultaneously, leads to prefabricated cabin to damage.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a prefabricated for cabin hoist structure of transformer substation, includes prefabricated cabin body of transformer substation, first wire rope and second wire rope, the both sides of prefabricated cabin body bottom of transformer substation have first rings soon, it has the couple to hang in the first ring, first suspension clasp has been hung at the top of couple, it has second fixing bolt to revolve in the first suspension clasp, the last cover of second fixing bolt has first wire rope, first wire rope's top cover has second rings, the top of second rings has the support steel soon, the cross-section of support steel presents "worker" style of calligraphy, second rings are provided with four in the bottom of support steel.
Preferably, the number of the first lifting rings is four, and the first lifting rings are symmetrical with respect to the center of the prefabricated substation body.
Preferably, both ends of the first steel wire rope are wound into circular rings, the first suspension buckle and the second fixing bolt are clamped on the circular rings on the first steel wire rope, and the second hanging ring is clamped on the circular rings on the first steel wire rope. Preferably, a hanging piece is arranged at the top of the support steel, and a second hanging buckle and a first fixing bolt are clamped in the hanging piece.
Preferably, a second steel wire rope is sleeved in the second suspension buckle, the bottom of the second steel wire rope is wound into a ring, and the second suspension buckle is sleeved in the second steel wire rope.
Preferably, a rope ring is arranged at the top of the second steel wire rope, the second steel wire rope is provided with two strands, and the rope rings on the two second steel wire ropes are overlapped with each other.
Compared with the prior art, the beneficial effects of the utility model are that: this prefabricated for cabin hoist and mount structure of transformer substation is rational in infrastructure, has following advantage:
the device is convenient to hoist by being provided with the first hanging ring, the hook, the first steel wire rope, the second hanging ring, the supporting steel and the second steel wire rope, and the top of the prefabricated cabin is prevented from being extruded, therefore, in use, the first hanging ring is arranged at the bottom of the prefabricated cabin body of the transformer substation according to the gravity center of the prefabricated cabin body of the transformer substation, the second hanging ring is screwed into the bottom of the supporting steel, the hook is hung on the first hanging ring, the hook is hung on the hanging piece through the second hanging buckle and the first fixing bolt, the second hanging buckle is hung on the second hanging buckle through the second steel wire rope, and the rope rings on the second steel wire rope are overlapped with each other, so that the four rope rings are hung on the lifting hook of the crane at the same time, the hoisting can be realized by only one crane, the extrusion of the top of the cabin is also solved at the same time, and the damage to the prefabricated cabin is reduced.
Drawings
Fig. 1 is a schematic front view of the present invention;
FIG. 2 is a schematic view of the side view of the present invention;
fig. 3 is an enlarged schematic structural view of a point a in fig. 1 according to the present invention;
fig. 4 is an enlarged schematic structural view of the utility model at the position B in fig. 2;
fig. 5 is a side view schematic structural diagram of the hook and the first suspension buckle assembly of the present invention.
In the figure: 1. a transformer substation prefabricated cabin body; 2. a first hoisting ring; 3. hooking; 4. a first suspension clasp; 5. a first wire rope; 6. a second hoisting ring; 7. supporting steel; 8. a second wire rope; 9. a rope loop; 10. a second suspension clasp; 11. a first fixing bolt; 12. a hanger; 13. and a second fixing bolt.
Detailed Description
The technical solution in the embodiment of the present invention will be clearly and completely described below with reference to the drawings in the embodiment of the present invention, and all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention based on the embodiment of the present invention.
Referring to fig. 1-5, the present invention provides an embodiment: a hoisting structure for a prefabricated cabin of a transformer substation comprises a prefabricated cabin body 1 of the transformer substation, a first steel wire rope 5 and second steel wire ropes 8, wherein first hoisting rings 2 are screwed on two sides of the bottom of the prefabricated cabin body 1 of the transformer substation, a hook 3 is hung in the first hoisting ring 2, a first hanging buckle 4 is hung at the top of the hook 3, a second fixing bolt 13 is screwed in the first hanging buckle 4, the first steel wire rope 5 is sleeved on the second fixing bolt 13, a second hoisting ring 6 is sleeved at the top of the first steel wire rope 5, a support steel 7 is screwed at the top of the second hoisting ring 6, the cross section of the support steel 7 is I-shaped, and four second hoisting rings 6 are arranged at the bottom of the support steel 7; the first hanging ring 2 is arranged at the bottom of the prefabricated cabin body 1 of the transformer substation according to the gravity center of the prefabricated cabin body 1 of the transformer substation, the second hanging ring 6 is screwed into the bottom of the support steel 7, the hook 3 is hung on the first hanging ring 2, then the four rope rings 9 are hung on a hanging piece 12 through a second hanging buckle 10 and a first fixing bolt 11, then the four rope rings are hung on the second hanging buckle 10 through a second steel wire rope 8, and then the four rope rings 9 are overlapped with each other through the rope rings 9 on the second steel wire rope 8, so that the four rope rings 9 are hung on a hanging hook of a crane at the same time, and the hoisting can be realized by only one crane, the problem that the lifting rope extrudes the cabin top is solved at the same time, and the damage to the prefabricated cabin is reduced;
the four first lifting rings 2 are arranged at the bottom of the prefabricated cabin body 1 of the transformer substation, the first lifting rings 2 are symmetrical about the center of the prefabricated cabin body 1 of the transformer substation, two ends of a first steel wire rope 5 are wound into a circular ring, a first lifting buckle 4 and a second fixing bolt 13 are clamped on the circular ring of the first steel wire rope 5, a second lifting ring 6 is clamped on the circular ring of the first steel wire rope 5, a lifting piece 12 is arranged at the top of the supporting steel 7, and a second lifting buckle 10 and a first fixing bolt 11 are clamped in the lifting piece 12.
A second steel wire rope 8 is sleeved in the second suspension clasp 10, the bottom of the second steel wire rope 8 is wound into a circular ring, the second suspension clasp 10 is sleeved in the second steel wire rope 8, a rope ring 9 is arranged at the top of the second steel wire rope 8, two strands of second steel wire ropes 8 are arranged, and the rope rings 9 on the two second steel wire ropes 8 are overlapped;
when the lifting device is used, the first lifting ring 2 is arranged at the bottom of the prefabricated cabin body 1 of the transformer substation according to the gravity center of the prefabricated cabin body 1 of the transformer substation, the second lifting ring 6 is screwed into the bottom of the supporting steel 7, the hook 3 is hung on the first lifting ring 2, the hook is connected with the lifting piece 12 through the second lifting buckle 10 and the first fixing bolt 11, the second lifting buckle 10 is hung on the second steel wire rope 8, the rope rings 9 on the second steel wire rope 8 are overlapped with each other, the four rope rings 9 are hung on a lifting hook of a crane simultaneously, the lifting can be carried out by only one crane, the problem that the lifting rope extrudes the cabin roof is solved simultaneously, and the damage to the prefabricated cabin is reduced.

Claims (6)

1. The utility model provides a prefabricated for cabin hoisting structure of transformer substation which characterized in that: including prefabricated cabin body of transformer substation (1), first wire rope (5) and second wire rope (8), the both sides of prefabricated cabin body of transformer substation (1) bottom have first rings (2) soon, hang in first rings (2) and have couple (3), first suspension clasp (4) have been hung at the top of couple (3), revolve in first suspension clasp (4) and have second fixing bolt (13), the last cover of second fixing bolt (13) has first wire rope (5), the top cover of first wire rope (5) has second rings (6), the top of second rings (6) has support steel (7) soon, the cross-section of support steel (7) presents "worker" style of calligraphy, second rings (6) are provided with four in the bottom of support steel (7).
2. The hoisting structure for the prefabricated cabin of transformer substation of claim 1, characterized in that: the four first lifting rings (2) are arranged at the bottom of the prefabricated cabin body (1) of the transformer substation, and the first lifting rings (2) are symmetrical about the center of the prefabricated cabin body (1) of the transformer substation.
3. The hoisting structure for the prefabricated cabin of the transformer substation of claim 1, characterized in that: the two ends of the first steel wire rope (5) are wound into circular rings, the first suspension buckle (4) and the second fixing bolt (13) are clamped on the circular rings of the first steel wire rope (5), and the second hanging ring (6) is clamped on the circular rings of the first steel wire rope (5).
4. The hoisting structure for the prefabricated cabin of transformer substation of claim 1, characterized in that: the top of the supporting steel (7) is provided with a hanging piece (12), and a second hanging buckle (10) and a first fixing bolt (11) are clamped in the hanging piece (12).
5. The hoisting structure for the prefabricated cabin of the transformer substation of claim 4, characterized in that: and a second steel wire rope (8) is sleeved in the second suspension buckle (10), the bottom of the second steel wire rope (8) is wound into a circular ring, and the second suspension buckle (10) is sleeved in the second steel wire rope (8).
6. The hoisting structure for the prefabricated cabin of the transformer substation of claim 1, characterized in that: the top of the second steel wire rope (8) is provided with a rope ring (9), the second steel wire rope (8) is provided with two strands, and the rope rings (9) on the two second steel wire ropes (8) are overlapped with each other.
CN202222917932.5U 2022-11-03 2022-11-03 Hoisting structure for prefabricated cabin of transformer substation Active CN218754513U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222917932.5U CN218754513U (en) 2022-11-03 2022-11-03 Hoisting structure for prefabricated cabin of transformer substation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222917932.5U CN218754513U (en) 2022-11-03 2022-11-03 Hoisting structure for prefabricated cabin of transformer substation

Publications (1)

Publication Number Publication Date
CN218754513U true CN218754513U (en) 2023-03-28

Family

ID=85645609

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222917932.5U Active CN218754513U (en) 2022-11-03 2022-11-03 Hoisting structure for prefabricated cabin of transformer substation

Country Status (1)

Country Link
CN (1) CN218754513U (en)

Similar Documents

Publication Publication Date Title
CN218754513U (en) Hoisting structure for prefabricated cabin of transformer substation
CN202848860U (en) Special sling for flexible busbar installation
CN109249833B (en) Automatic lifting wire collecting device for charging pile
CN103738861A (en) Integral hoisting method for A type column of steel pipe of ultra-high voltage transformer station
CN212475769U (en) Equipment hoisting structure for electric power transmission and distribution
CN206487129U (en) Safety hanging cradle for industrial premises Construction of Steel Structure
CN213546968U (en) Box-type substation convenient to hoist and mount
CN215798234U (en) Bearing mechanism for installation engineering based on digital monitoring terminal of transformer substation
CN201857235U (en) Power off-free disconnect switch lifting appliance
CN205135073U (en) Compound light pole
CN204138146U (en) A kind of for European-type transformer substation hanging apparatus
CN212174337U (en) A safe hanging flower basket for construction of industrial factory building steel construction
CN209778245U (en) Hoisting accessory suitable for cable well lid
CN114165061A (en) Construction method of vertical transportation system
CN209748088U (en) Wheel type bracket for bypass flexible cable of power distribution network
CN209306856U (en) Small-sized separation type electrical hoisting apparatus
CN105502146A (en) Lifting device for European style transformer station
CN215772080U (en) Box-type substation convenient to hoist and mount
CN217535236U (en) Many balanced lifts by crane of unit formula looped netowrk cabinet are with hoist
CN212358816U (en) Assembled light steel keel frame for suspended ceiling
CN202483211U (en) Energy saving integration base station with balance weight
CN214152639U (en) Fixing device of distribution network equipment
CN210739024U (en) Triangle force-reducing hoop communication device
CN210118691U (en) Double-layer lifting lamp panel of high-pole lamp
CN215711084U (en) Hoisting structure of horizontal water turbine generator set

Legal Events