CN218752271U - Vertical steel shear key installation frock of tube coupling joint - Google Patents

Vertical steel shear key installation frock of tube coupling joint Download PDF

Info

Publication number
CN218752271U
CN218752271U CN202223067530.7U CN202223067530U CN218752271U CN 218752271 U CN218752271 U CN 218752271U CN 202223067530 U CN202223067530 U CN 202223067530U CN 218752271 U CN218752271 U CN 218752271U
Authority
CN
China
Prior art keywords
shear key
bearing platform
key
vertical steel
shear
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223067530.7U
Other languages
Chinese (zh)
Inventor
蒋贤德
肖佳发
钱雪圃
钟情
刘春标
高建雄
林涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Salvage Bureau
Original Assignee
Guangzhou Salvage Bureau
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Salvage Bureau filed Critical Guangzhou Salvage Bureau
Priority to CN202223067530.7U priority Critical patent/CN218752271U/en
Application granted granted Critical
Publication of CN218752271U publication Critical patent/CN218752271U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forklifts And Lifting Vehicles (AREA)

Abstract

The utility model belongs to the technical field of immersed tube tunnel construction, a vertical steel shear force key installation frock of coupling joint is disclosed. The tool can bear the shear key so as to install the shear key on the pipe joint connector, and comprises a bearing platform, a fixing part, a height increasing part and a forklift limiting part; the bearing platform is abutted against the lower end face of the shear key so as to drive the shear key to move; the fixing part is convexly arranged on the bearing platform, is positioned at one end of the bearing platform and can be abutted against the side surface of the shear key; the height increasing part is connected to one side of the bearing platform far away from the fixing part and is arranged at a preset height; the spacing portion of fork truck is located the one end that bearing platform was kept away from to the portion of increasing height, and fork truck's fork can cooperate with the spacing portion of fork truck to when realizing lifting through fork truck, increase the height that lifts of shear force key. The utility model provides a vertical steel shear force key installation frock of coupling can be on the basis that does not harm the shear force key, and the supplementary installation that realizes the coupling and go up the shear force key reduces intensity of labour, improves security and installation effectiveness.

Description

Vertical steel shear key installation frock of tube coupling joint
Technical Field
The utility model relates to a immersed tube tunnel construction technical field especially relates to vertical steel shear key installation frock of tube coupling joint.
Background
The immersed tube tunnel is characterized in that tunnel tube sections are prefabricated in sections, and temporary water stopping heads are arranged at two ends of each section of the tunnel tube sections. And floating the pipe sections to the axis of the tunnel, then sinking the pipe sections into the pre-dug foundation trench, and completing the underwater connection among the pipe sections through various measures of pipe joint joints.
In order to ensure the stability of the pipe section after sinking and butt joint, the vertical displacement of the pipe joint needs to be limited. The existing measures for limiting the vertical displacement of a immersed tube joint in an immersed tube tunnel are to install a vertical steel shear key or a vertical concrete shear key, and limit the relative displacement of two adjacent sections of tube sections by erecting the shear key, which is described in the text as a vertical steel shear key. A commonly used vertical steel shear key is shown in fig. 1 and 2, taking an xiangyang fish girl tunnel as an example: the height H1 of the middle wall shear key is 2.1m, the width L1 is 0.55m, the thickness is 0.95m, and the weight is about 3.1 tons; the height H2 of the side wall shear key is 1.65m, the width L2 is 0.45m, the thickness is 0.95m, and the weight is about 2.3 tons.
The existing shear key is installed in place by adopting a chain block hoisting mode, but the installation mode has the following three disadvantages: firstly, hoisting eye plates need to be welded on the top of an end steel shell of a pipe joint connector and a shear key, a GINA water stop, an OMEGA water stop and a shear key body in a pipe section can be damaged to a certain extent, the hoisting eye plates need to be detached and subjected to secondary corrosion prevention after construction is completed, construction procedures are complex, and the construction period can be prolonged. Secondly, the space of the pipe joint is narrow and small, which is not beneficial to the installation of hoisting facilities. Take Xiangyang Yulianzhou tunnel as an example: the inner side surface of the side wall shear key is almost close to the vertex of the OMEGA water stop belt; the distance between the top of the shear key on the middle wall and the top of the end steel shell and the top of the OMEGA water stop belt is only 0.6m; the distance between the top of the shear key on the side wall and the top of the end steel shell and the top point of the OMEGA water stop belt is only 0.2m, and the installation difficulty of hoisting facilities is high. Thirdly, the maximum weight of the shear key is 3.1 tons, the minimum weight is 2.3 tons, the shear key is lifted in place completely by manpower, the width of a pipe joint is only 1.15m, and the construction personnel can not conveniently stand and the shear key can not be installed in place; the installation of end steel shell top hoisting facilities relates to high altitude construction and operation of starting a fire, and the danger coefficient is great, has very big potential safety hazard, and the construction degree of difficulty is high, efficient.
Another mode adopts an automatic forklift, as shown in fig. 3, the forklift lanes can be opened and closed synchronously, the performances of forward tilting, backward tilting and synchronous lifting can be realized, and the shear keys are assisted to be installed in place. Take Xiangyang Yulianzhou tunnel as an example: the lifting height of the shear key on the middle wall is 3.9m, the lifting height of the shear key on the side wall is 3.1m, and the lifting height of the forklift is only 2.7m, so that the in-place installation requirements of the shear keys on the middle wall and the side wall cannot be met.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a vertical steel shear force key installation frock of tube coupling joint can be on the basis of not damaging the shear force key, and the supplementary installation that realizes the shear force key on the tube coupling joint reduces intensity of labour, improves security and installation effectiveness.
To achieve the purpose, the utility model adopts the following technical proposal:
the vertical steel shear key installation frock of tube coupling joint can bear the shear key, in order will the shear key install in the tube coupling joint includes:
the bearing platform can be abutted against the lower end face of the shear key so as to drive the shear key to move;
the fixing part is convexly arranged on the bearing platform, is positioned at one end of the bearing platform and can be abutted against the side surface of the shear key;
the height increasing part is connected to one side, far away from the fixing part, of the bearing platform and is arranged at a preset height;
the spacing portion of fork truck locates increase the portion and keep away from load-bearing platform's one end, fork truck's fork can with the cooperation of the spacing portion of fork truck, in order to pass through when fork truck realizes lifting, increase the height that lifts of shear force key.
Optionally, the carrying platform includes a plurality of carrying rods, and the plurality of carrying rods are connected to form a frame structure.
Optionally, the fixing portion includes at least two fixing members, and the two fixing members are disposed on the supporting platform at intervals.
Optionally, increase the portion and include that a plurality of increases the piece, a plurality of the one end that increases the piece all connect in load-bearing platform keeps away from one side of fixed part.
Optionally, a base is arranged at one end, away from the bearing platform, of the height increasing piece, and the plane where the base is located is parallel to the bearing platform.
Optionally, the spacing portion of fork truck with the base interval sets up, so that the fork can stretch into the base with between the spacing portion of fork truck.
Optionally, the fork truck spacing portion includes two at least locating parts, the locating part is connected in adjacent increase between the piece, two the locating part with the interval of base is the same, with can simultaneously with the fork butt.
Optionally, the pipe joint vertical steel shear key installation tool is made of square steel.
Has the beneficial effects that:
the utility model provides a vertical steel shear force key installation frock of coupling, after adjusting the shear force key to the installation gesture, through the lower terminal surface of bearing platform butt shear force key, through the side butt of fixed part and shear force key, make the shear force key spacing by bearing platform and fixed part to can realize bearing and drive the purpose that the shear force key removed, can not cause the damage to the shear force key; bearing platform below is equipped with increases the high portion, fork truck's fork can with increase the spacing cooperation of fork truck that the load-bearing platform was kept away from to the portion, thereby can lift this frock through the fork, in order to realize the lifting to the shear force key, because the shear force key is fixed in on this frock, thereby make the lift height upper limit of shear force key for the lift upper limit of fork and the high sum of this frock, thereby can realize the installation to the articulated shear force key of pipe section steadily, this frock enables the installation of shear force key and passes through fork truck and realizes, satisfy the high requirement of lifting, when reducing intensity of labour, also can improve the security and the installation effectiveness of shear force key installation.
Drawings
FIG. 1 is a schematic view of a prior art mid-wall shear key;
FIG. 2 is a schematic illustration of a sidewall shear key of the prior art;
FIG. 3 is a schematic view of a prior art forklift mounted shear key;
fig. 4 is a schematic view of the pipe joint vertical steel shear key installation tool provided by the embodiment of the present invention when being matched with a forklift;
fig. 5 is an isometric view of a vertical steel shear key installation tool for a pipe joint provided by an embodiment of the invention;
FIG. 6 is a front view of a vertical steel shear key installation tool for a pipe joint provided by an embodiment of the present invention;
fig. 7 is a side view of a vertical steel shear key installation tool for a pipe joint provided by an embodiment of the present invention;
fig. 8 is a top view of the tool for installing the vertical steel shear key of the pipe joint according to the embodiment of the present invention.
In the figure:
100. a shear key; 200. a forklift; 210. a pallet fork; 300. a pipe joint;
1. a load-bearing platform; 11. a carrier bar;
2. a fixed part; 21. a fixing member;
3. a heightening part; 31. a heightening part; 32. a base;
4. a forklift limiting part; 41. and a limiting member.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings and examples. It is to be understood that the specific embodiments described herein are merely illustrative of the invention and are not limiting of the invention. It should be further noted that, for the convenience of description, only some of the structures related to the present invention are shown in the drawings, not all of the structures.
In the description of the present invention, unless expressly stated or limited otherwise, the terms "connected," "connected," and "fixed" are to be construed broadly, e.g., as meaning permanently connected, detachably connected, or integral to one another; can be mechanically or electrically connected; they may be directly connected or indirectly connected through intervening media, or may be connected through the use of two elements or the interaction of two elements. The specific meaning of the above terms in the present invention can be understood as a specific case by those skilled in the art.
In the present disclosure, unless expressly stated or limited otherwise, the first feature "on" or "under" the second feature may comprise direct contact between the first and second features, or may comprise contact between the first and second features not directly. Also, the first feature being "on," "above" and "over" the second feature includes the first feature being directly on and obliquely above the second feature, or merely indicating that the first feature is at a higher level than the second feature. A first feature being "under," "below," and "beneath" a second feature includes the first feature being directly under and obliquely below the second feature, or simply meaning that the first feature is at a lesser elevation than the second feature.
In the description of the present embodiment, the terms "upper", "lower", "right", and the like are used based on the orientations and positional relationships shown in the drawings, and are only for convenience of description and simplification of operation, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used only for descriptive purposes and are not intended to be limiting.
As shown in fig. 3 to fig. 8, the tool for installing a vertical steel shear key of a pipe joint connector (hereinafter referred to as "tool") provided in this embodiment can bear the shear key 100, so as to install the shear key 100 on the pipe joint connector 300, and includes a bearing platform 1, a fixing portion 2, a height increasing portion 3 and a forklift limiting portion 4; the bearing platform 1 can be abutted against the lower end face of the shear key 100 so as to drive the shear key 100 to move; the fixing part 2 is convexly arranged on the bearing platform 1, is positioned at one end of the bearing platform 1 and can be abutted against the side surface of the shear key 100; the heightening part 3 is connected to one side of the bearing platform 1 far away from the fixing part 2, and the heightening part 3 is arranged at a preset height; the spacing portion 4 of fork truck locates the one end that increases the portion 3 and keep away from load-bearing platform 1, and fork 210 of fork truck 200 can cooperate with the spacing portion 4 of fork truck to when realizing lifting through fork truck 200, increase the lift height of shear force key 100.
This frock can be adjusted to the installation gesture at shear force key 100 after, through the lower terminal surface of 1 butt shear force key 100 of load-bearing platform, through the side butt of fixed part 2 with shear force key 100, makes shear force key 100 spacing jointly by load-bearing platform 1 and fixed part 2 to can bear and drive shear force key 100 and remove, thereby make the installation can not cause the damage to shear force key 100 and coupling 300. The below of load-bearing platform 1 is equipped with the portion of increasing 3, and fork 200's fork 210 can with increase the spacing portion 4 cooperation of fork truck that the portion 3 kept away from load-bearing platform 1 one end setting of portion 4 to can lift this frock through fork 210, and then realize the lifting to shear force key 100, make the upper limit of the lift height of shear force key 100 be fork 210 lift the upper limit and increase the high sum of portion 3, thereby can realize steadily that shear force key 100's installation on the tube-section joint 300. Preferably, the preset height of the heightening part 3 is set as required, and the use requirement can be met. It is understood that the shear key 100 in the present embodiment is specifically referred to as a vertical steel shear key. The tool can enable the installation of the shear key 100 to be realized through the lifting of the forklift 200, and can improve the safety and the installation efficiency of the installation process of the shear key 100 while meeting the installation height requirement and reducing the labor intensity.
Optionally, the load-bearing platform 1 comprises a plurality of load-bearing bars 11, and the plurality of load-bearing bars 11 are connected to each other to form a frame structure.
The carrier bar 11 has a carrier plane to enable the shear key 100 to be stably placed on the carrier platform 1. The bearing platform 1 with a frame structure is formed by connecting a plurality of bearing rods 11 end to end, so that the weight of the bearing platform 1 can be reduced, and the load of the pallet fork 210 can be reduced.
Optionally, the fixing portion 2 includes at least two fixing members 21, and the two fixing members 21 are disposed on the supporting platform 1 at intervals.
Preferably, the fixing member 21 is a rod-shaped structure having an abutment surface, and abuts against the side surface of the shear key 100 through the abutment surface. The distance between the two fixing pieces 21 can be set as required, and the shear key 100 can be fixed and limited. Further, the two fixing members 21 may be disposed on the same side of the shear key 100, or disposed on both sides of the shear key 100.
With continued reference to fig. 3-8, optionally, the height increasing portion 3 includes a plurality of height increasing pieces 31, and one end of each of the plurality of height increasing pieces 31 is connected to a side of the supporting platform 1 away from the fixing portion 2.
The height increasing member 31 may be a rod or a plate, and may increase the lifting height of the shear key 100 placed on the load-bearing platform 1 and have a certain strength. The height is increased by the plurality of heightening pieces 31, and the overall weight of the tool can be reduced.
Optionally, a base 32 is provided at an end of the height increasing member 31 away from the carrying platform 1, and a plane of the base 32 is parallel to the carrying platform 1.
The base 32 may be formed by connecting a plurality of rod-like members, so as to reduce the overall weight while improving the stability of the tool.
Optionally, the forklift limiting part 4 is spaced apart from the base 32 so that the pallet fork 210 can extend between the base 32 and the forklift limiting part 4.
The forklift stopper 4 may have a groove-like structure or a plate-like structure parallel to the plane of the base 32, and may be configured to allow the fork 210 to perform a function of lifting the tool.
Optionally, the forklift limiting part 4 includes at least two limiting members 41, the limiting members 41 are connected between adjacent height increasing members 31, and the two limiting members 41 have the same distance from the base 32 so as to be capable of abutting against the pallet fork 210 at the same time.
In this embodiment, the tooling is provided with four height increasing members 31, the limiting members 41 are connected between two adjacent height increasing members 31, and the two limiting members 41 are arranged at intervals along the extending direction of the fork 210, so that the fork 210 can stably lift the tooling by abutting against the two limiting members 41 at the same time.
Optionally, the pipe joint vertical steel shear key installation tool is made of square steel, and each part of the tool can be formed through welding machining. Preferably, the tool is made of square steel with the specification of 100mm multiplied by 200mm multiplied by 6 mm.
It can be understood that parameters such as the size of each part of the tool can be set according to actual conditions, and the size can be set according to the specification of the middle wall shear key 100, so that the applicability of the tool is improved, the lifting height of the shear key 100 can be increased, and the overall weight can be reduced.
When the tool is used, the shear key 100 is adjusted to be suitable for installation, the shear key 100 is moved to the tool through the forklift 200, the lower end face of the shear key 100 is made to contact with the bearing platform 1, the side face of the shear key 100 abuts against the fixing portion 2, the shear key 100 is fixed on the tool through fasteners such as tighteners or binding bands, at the moment, the shear key 100 and the tool are integrated, and the shear key 100 can move under the driving of the tool. Make fork truck 200 be located the frock and be equipped with one side of fixed part 2, through fork 210 and the spacing portion 4 cooperation of fork truck, with lifting to the preset position of frock, make shear force key 100 reach the pre-buried panel department of tube coupling joint 300 and counterpoint to be fixed in shear force key 100 on tube coupling joint 300 through fixed knot structures such as bolts. It will be appreciated that during installation, the shear key 100 is typically installed adjacent the end steel shell of the pipe joint 300. Specifically, as shown in fig. 3, taking the shear key 100 of the wall in the pipe joint connector 300 as an example, three shear keys 100 are arranged on the same vertical surface, the shear keys 100 near the pipe joint connector 300 and located at two ends are installed first, and then the shear key 100 located between the two shear keys 100 is installed, so that a space can be reserved for a tool, and interference with the installed shear keys 100 is avoided. After the shear key 100 is fixed to the pipe joint 300, the fastening member is released, and the fixing portion 2 is positioned on the side close to the forklift 200, so that the tool can be removed.
It is obvious that the above embodiments of the present invention are only examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. Numerous obvious variations, rearrangements and substitutions will now occur to those skilled in the art without departing from the scope of the invention. This need not be, nor should it be exhaustive of all embodiments. Any modification, equivalent replacement or improvement made within the spirit and principle of the present invention should be included in the protection scope of the claims of the present invention.

Claims (8)

1. Vertical steel shear key installation frock of tube coupling joint, its characterized in that can bear shear key (100) to with shear key (100) install in tube coupling joint (300), include:
the bearing platform (1) can be abutted against the lower end face of the shear key (100) to drive the shear key (100) to move;
the fixing part (2) is convexly arranged on the bearing platform (1), is positioned at one end of the bearing platform (1), and can be abutted against the side surface of the shear key (100);
the height increasing part (3) is connected to one side, far away from the fixing part (2), of the bearing platform (1), and the height increasing part (3) is arranged at a preset height;
spacing portion of fork truck (4), locate increase portion (3) and keep away from the one end of load-bearing platform (1), fork (210) of fork truck (200) can with spacing portion of fork truck (4) cooperation, in order to pass through when fork truck (200) realize lifting, increase the lifting height of shear force key (100).
2. The tool for installing the vertical steel shear key of the pipe joint connector according to claim 1, wherein the bearing platform (1) comprises a plurality of bearing rods (11), and the bearing rods (11) are connected with one another to form a frame structure.
3. The tool for installing the vertical steel shear key of the pipe joint connector according to claim 1, wherein the fixing portion (2) comprises at least two fixing pieces (21), and the two fixing pieces (21) are arranged on the bearing platform (1) at intervals.
4. The pipe joint vertical steel shear key installation tool according to claim 1, wherein the heightening part (3) comprises a plurality of heightening pieces (31), and one ends of the heightening pieces (31) are connected to one side, away from the fixing part (2), of the bearing platform (1).
5. The pipe joint vertical steel shear key installation tool according to claim 4, wherein a base (32) is arranged at one end, away from the bearing platform (1), of the heightening part (31), and the plane where the base (32) is located is parallel to the bearing platform (1).
6. The pipe joint vertical steel shear key installation tool according to claim 5, wherein the forklift limiting part (4) and the base (32) are arranged at intervals, so that the pallet fork (210) can extend into a position between the base (32) and the forklift limiting part (4).
7. The tool for installing the vertical steel shear key of the pipe joint connector according to claim 6, wherein the forklift limiting part (4) comprises at least two limiting parts (41), the limiting parts (41) are connected between the adjacent heightening parts (31), and the distance between the two limiting parts (41) and the base (32) is the same so as to be abutted against the pallet fork (210) at the same time.
8. The pipe joint vertical steel shear key installation tooling of any one of claims 1-7, wherein the pipe joint vertical steel shear key installation tooling is made of square steel.
CN202223067530.7U 2022-11-18 2022-11-18 Vertical steel shear key installation frock of tube coupling joint Active CN218752271U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223067530.7U CN218752271U (en) 2022-11-18 2022-11-18 Vertical steel shear key installation frock of tube coupling joint

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223067530.7U CN218752271U (en) 2022-11-18 2022-11-18 Vertical steel shear key installation frock of tube coupling joint

Publications (1)

Publication Number Publication Date
CN218752271U true CN218752271U (en) 2023-03-28

Family

ID=85651754

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223067530.7U Active CN218752271U (en) 2022-11-18 2022-11-18 Vertical steel shear key installation frock of tube coupling joint

Country Status (1)

Country Link
CN (1) CN218752271U (en)

Similar Documents

Publication Publication Date Title
CN210914947U (en) Hoisting and turning-over system suitable for large prefabricated stand board
CN218752271U (en) Vertical steel shear key installation frock of tube coupling joint
CN110877704A (en) Shipboard installation method of large ship equipment
CN210066499U (en) Suspension bridge girder steel aerial accurate butt joint system
CN109537466B (en) Positioning method for suspending steel structure beam in air
CN115709845A (en) Pipe joint connector vertical steel shear key installation tool and installation method
WO2023173676A1 (en) Space truss support platform, system and method for super-deep slurry wall
CN116101892A (en) Vertical prefabricated box culvert lifting and overturning system and construction method thereof
CN216429085U (en) Engineering construction is with platform of unloading
CN209924462U (en) Rail type horizontal load moving and transporting device for steel structure sliding construction
CN112573344B (en) Use method of hoisting and turning-over device for super-large concrete prefabricated stand plate
CN211920627U (en) Light lifting appliance for dismantling cantilever box girder segment
CN210763974U (en) Be suitable for reverse construction method to get soil mouthful and pass suspension type electric hoist for material
CN212893471U (en) Lifting appliance for T-shaped beam template
CN221053297U (en) I-steel anchoring device for suspension type ladder cage shelving platform for vertical shaft
CN210621485U (en) Station hoisting system for hoisting corrugated steel web
CN216662192U (en) Special fixture for horizontal transportation of ALC (autoclaved lightweight concrete) plate
CN213804952U (en) Deviation correcting device for beam structure
CN217229950U (en) Special lifting appliance suitable for cylindrical part
CN214733915U (en) H-shaped crane beam turnover device
CN217458425U (en) Lifting appliance for lifting bridge deck concrete baffle
CN215326417U (en) Adjustable lifting appliance for lifting laminated plate bracket
CN210795584U (en) Internal climbing tower crane
CN220449533U (en) Adjustable I-shaped section steel beam lifting appliance
JP7150889B2 (en) Steel sheet pile connection method, pull-in jig, and continuous wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20230802

Address after: 510290 No.1 courtyard, 2356 Nanzhou Road, Haizhu District, Guangzhou City, Guangdong Province

Patentee after: GUANGZHOU SALVAGE BUREAU

Address before: No. 536, Binjiang East Road, Haizhu District, Guangzhou, Guangdong 510230

Patentee before: GUANGZHOU SALVAGE BUREAU OF THE MINISTRY OF TRANSPORT

TR01 Transfer of patent right