Novel protection network for building engineering Download PDF

Info

Publication number
CN218715346U
CN218715346U CN202222881181.6U CN202222881181U CN218715346U CN 218715346 U CN218715346 U CN 218715346U CN 202222881181 U CN202222881181 U CN 202222881181U CN 218715346 U CN218715346 U CN 218715346U
Authority
CN
China
Prior art keywords
fixed
outside
protection network
groove
fixed frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222881181.6U
Other languages
Chinese (zh)
Inventor
李恩铭
陈伟
管威
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202222881181.6U priority Critical patent/CN218715346U/en
Application granted granted Critical
Publication of CN218715346U publication Critical patent/CN218715346U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

The utility model relates to a novel protection network for building engineering, including fixed frame, the spread groove has been seted up to the inside of fixed frame, the outside fixedly connected with spliced pole of fixed frame, the outside of fixed frame is provided with mounting structure. This novel protection network for building engineering, through setting up the spread groove, the spliced pole, the transverse mounting board, first stopper, vertical mounting panel and second stopper, conveniently install this novel protection network of a plurality of each other and form integral protection network together, and the installation is dismantled simple and conveniently, through setting up the resettlement groove, solid fixed ring, couple and buffer spring, conveniently improve the shock resistance and the buffer property of this protection network, make buffer spring convenient to install and dismantle simultaneously and change, through setting up the mounting groove, the screw hole, the screw thread post, the fixed plate, perforate and the protection network body, the change can be dismantled to certain solitary protection network to the convenience, can't dismantle it after avoiding certain solitary protection network to appear damaging and change.

Description

Novel protective net for constructional engineering
Technical Field
The utility model relates to a protection network technical field for the building engineering specifically is a novel protection network for building engineering.
Background
The building engineering is a part of construction engineering, and refers to an engineering entity formed by the construction of various house buildings and their auxiliary facilities and the installation activities of lines, pipelines and equipment matched with the various house buildings, when the building engineering is carried out, a protective net needs to be built on the periphery of the building for preventing non-constructors from entering a construction area, so that a construction site of the building engineering can be protected and protected, meanwhile, the injury of sundries falling from the building to pedestrians can be prevented, and the construction safety is enhanced.
Present protection network for building engineering is mostly to form integral protection network through the welded mode with a plurality of protection network welding even together, this kind of mode installation is complicated, and dismantle more difficult when needing to be changed or maintaining, installer's work efficiency has been reduced, and can't dismantle it after certain solitary protection network appears damaging and change, influence the safety protection effect of job site, on the other hand, current protection network for building engineering only bears the buffering through the tension of protection network itself to the heavy object that falls, make the impact resistance and the buffer of protection network lower, can not satisfy the user demand, so propose a novel protection network for building engineering and solve above-mentioned problem.
SUMMERY OF THE UTILITY MODEL
The utility model is not enough to prior art, the utility model provides a novel protection network for building engineering, it is simple and convenient to possess the installation and dismantle, can dismantle the change to certain solitary protection network, can't dismantle it after avoiding certain solitary protection network to damage to appear and change, thereby influence the safety protection effect of job site, improve the shock resistance and the buffer of this protection network, advantages such as user demand have been satisfied, it is most to form integral protection network with a plurality of protection network welding through the welded mode with current protection network for building engineering, this kind of mode installation is complicated, and dismantle more difficultly when needing to be changed or maintaining, installer's work efficiency has been reduced, and can't dismantle it after certain solitary protection network damages to appear and change, influence the safety protection effect of job site, on the other hand, current protection network for building engineering only bears the buffering through the tension of protection network itself to the heavy object that falls, make the shock resistance and the buffer of protection network lower, can not satisfy user demand's problem.
In order to achieve the above object, the utility model provides a following technical scheme: a novel protective net for constructional engineering comprises a fixed outer frame, wherein a connecting groove is formed in the fixed outer frame, a connecting column is fixedly connected to the outer part of the fixed outer frame, and an installation structure is arranged on the outer part of the fixed outer frame;
the mounting structure includes horizontal mounting panel, first stopper, vertical mounting panel, second stopper, resettlement groove, solid fixed ring, couple, buffer spring, mounting groove, screw hole, screw thread post, fixed plate, perforation and protection network body, horizontal mounting panel fixed connection is in the outside of fixed frame, the outside swing joint of horizontal mounting panel has first stopper, the outside fixedly connected with vertical mounting panel of fixed frame, the outside swing joint of vertical mounting panel has the second stopper, the resettlement groove has been seted up to the inside of fixed frame, the solid fixed ring of inside fixedly connected with of fixed frame, gu fixed ring's inside swing joint has the couple, the outside fixedly connected with buffer spring of couple, the mounting groove has been seted up to the inside of fixed frame, the inside threaded hole has been seted up to the inside of fixed frame, the inside swing joint of fixed frame has the screw thread post, the outside swing joint of screw thread post has the fixed plate, the inside of fixed plate has seted up the perforation, the outside fixedly connected with body of protection network body of fixed plate.
Further, the quantity of spread groove is two, two the spread groove is the top inboard of seting up in the fixed frame left and right sides symmetrically, the quantity of spliced pole is two, two the top of spliced pole is the bottom of symmetry fixed connection in the fixed frame left and right sides, and two spliced poles are corresponding with two spread grooves respectively.
Furthermore, the quantity of horizontal mounting panel is four, four every adjacent two in the horizontal mounting panel is a set of, and is two sets of the outside of horizontal mounting panel respectively with the outside of fixed frame top and the outside fixed connection of bottom, and the inside of the horizontal mounting panel of top has seted up the first spacing hole of several, the quantity of first stopper is the same with first spacing hole, the top of first stopper rotates with the bottom of bottom horizontal mounting panel respectively and is connected.
Further, the quantity of vertical mounting panel is four, four every adjacent two is a set of in the vertical mounting panel, and is two sets of the outside of vertical mounting panel respectively with the outside fixed connection of fixed frame left and right sides, and the inside of right side vertical mounting panel has seted up the spacing hole of several second, the quantity of second stopper is the same with the spacing hole of second, the right side of second stopper rotates with the left side of left side vertical mounting panel respectively and is connected.
Further, the quantity of resettlement groove is two, two the resettlement groove is the symmetry and sets up at the top inboard and the bottom inboard of fixed frame, gu fixed ring's quantity is twelve, twelve every horizontal adjacent six in the fixed ring is a set of, and is two sets of gu fixed ring's outside respectively with the top inboard and the bottom inboard fixed connection of fixed frame, and two sets of solid fixed ring is located the inside of two resettlement grooves respectively, the quantity of couple is twelve, twelve the inside of couple respectively with the inside swing joint of twelve solid fixed ring, twelve every horizontal adjacent six in the couple is a set of, buffer spring's quantity is six, six buffer spring's top and bottom respectively with the adjacent one side fixed connection of two sets of couples.
Further, the quantity of mounting groove is two, two the mounting groove is the inside that the symmetry was seted up in the fixed frame left and right sides, the quantity of fixed plate is two, two the outside of fixed plate is pegged graft in the inside of the fixed frame left and right sides through two mounting grooves respectively, and the adjacent one side of two fixed plates respectively with the left and right sides fixed connection of protection network body, the quantity of screw hole is six, six every vertical adjacent three is a set of in the screw hole, two sets of the inside of the fixed frame left and right sides is seted up respectively to the screw hole, fenestrate quantity is six, six every vertical adjacent three is a set of in the perforation, and is two sets of the perforation is seted up respectively in the inside of two fixed plates, and every perforation is corresponding with every screw hole respectively, the quantity of screw thread post is six, six the outside of screw thread post is run through six perforation respectively and is in the inside of the fixed frame left and right sides through six screw hole threaded connection.
Compared with the prior art, the technical scheme of the application has the following beneficial effects:
this novel protection network for building engineering, through setting up the spread groove, the spliced pole, the transverse mounting board, first stopper, vertical mounting panel and second stopper, conveniently install this novel protection network of a plurality of each other and form integral protection network together, and the installation is dismantled simple and conveniently, through setting up the resettlement groove, solid fixed ring, couple and buffer spring, conveniently improve the shock resistance and the buffer of this protection network, satisfy the user demand, make buffer spring convenient to install and dismantle simultaneously and change, through setting up the mounting groove, the screw hole, the screw thread post, the fixed plate, perforate and protection network body, the change can be dismantled to certain solitary protection network to the convenience, and it is simple and convenient to change, can't dismantle it after avoiding certain solitary protection network to appear damaging and change, thereby influence the safety protection effect of job site.
Drawings
FIG. 1 is a schematic view of the front three-dimensional structure of the present invention;
FIG. 2 is a schematic view of the three-dimensional explosion structure of the present invention;
fig. 3 is a schematic view of the partial side sectional structure of the present invention.
In the figure: 1. fixing the outer frame; 2. connecting grooves; 3. connecting columns; 4. a mounting structure; 401. a transverse mounting plate; 402. a first stopper; 403. a vertical mounting plate; 404. a second limiting block; 405. a placing groove; 406. a fixing ring; 407. hooking; 408. a buffer spring; 409. mounting grooves; 410. a threaded hole; 411. a threaded post; 412. a fixing plate; 413. perforating; 414. a protective net body.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, a novel protective net for construction engineering includes a fixed outer frame 1, a connecting groove 2 is formed inside the fixed outer frame 1, a connecting column 3 is fixedly connected to the outside of the fixed outer frame 1, and a mounting structure 4 is arranged outside the fixed outer frame 1.
The mounting structure 4 comprises a transverse mounting plate 401, a first limiting block 402, a vertical mounting plate 403, a second limiting block 404, a mounting groove 405, a fixing ring 406, a hook 407, a buffer spring 408, a mounting groove 409, a threaded hole 410, a threaded post 411, a fixing plate 412, a perforation 413 and a protective net body 414, wherein the transverse mounting plate 401 is fixedly connected to the outside of the fixed outer frame 1, the outside of the transverse mounting plate 401 is movably connected with the first limiting block 402, the outside of the fixed outer frame 1 is fixedly connected with the vertical mounting plate 403, the outside of the vertical mounting plate 403 is movably connected with the second limiting block 404, by arranging a connecting groove 2, a connecting post 3, the transverse mounting plate 401, the first limiting block 402, the vertical mounting plate 403 and the second limiting block 404, a plurality of the novel protective nets are conveniently and mutually mounted to form an integral protective net, the mounting and dismounting are simple and convenient, the mounting and dismounting are provided, the mounting groove 405 is arranged inside of the fixed outer frame 1, the fixing ring 406 is fixedly connected with the fixing ring 406, the hook 407 is arranged inside of the fixed outer frame 1, the outer frame is fixedly connected with the buffer spring 408, the mounting groove 412 is conveniently arranged, the mounting groove 412 is arranged, the mounting groove 411 and the threaded post is arranged, the mounting groove 412 is arranged on the outer frame is arranged, the fixing plate is arranged on the outer frame 410, the convenience can be dismantled certain solitary protection network and change, and change simple and conveniently, avoids certain solitary protection network to appear damaging the back unable change of dismantling it to influence the safety protection effect of job site.
When the method is implemented, the method comprises the following steps:
1) Firstly, a connecting column 3 installed at the bottom of a novel B protective net is inserted into a connecting groove 2 formed in the top of the novel A protective net, meanwhile, a first limiting block 402 installed at the bottom of the novel B protective net penetrates through the inside of a transverse mounting plate 401 installed at the top of the novel A protective net, and then the first limiting block 402 is rotated to carry out limiting and fixing, so that the novel A protective net and the novel B protective net are installed together;
2) Then, a second limiting block 404 arranged on the left side of the novel protection net C penetrates through the inside of a vertical mounting plate 403 arranged on the right side of the novel protection net A, and then the second limiting block 404 is rotated, so that the novel protection net A and the novel protection net C are mounted together, and the whole protection net is formed by analogy;
3) Then, when an individual protective net is damaged and needs to be disassembled, the threaded column 411 is manually rotated outwards, so that the threaded column 411 is withdrawn from the inside of the through hole 413, and then the fixing plate 412 is pulled out from the inside of the mounting groove 409, and the disassembly can be completed;
4) Finally, during replacement and installation, the fixing plate 412 installed on the intact protective net body 414 is inserted into the fixing outer frame 1 through the installation groove 409, the through hole 413 corresponds to the threaded hole 410, then the threaded column 411 is manually rotated, and the threaded column 411 penetrates through the through hole 413 and is installed in the threaded hole 410 in a threaded mode, so that installation and fixation are completed.
To sum up, this novel protection network for building engineering, through setting up spread groove 2, spliced pole 3, horizontal mounting plate 401, first stopper 402, vertical mounting plate 403 and second stopper 404, conveniently install this novel protection network of a plurality of each other and constitute integral protection network, and the installation is dismantled simple and conveniently, through setting up resettlement groove 405, gu fixed ring 406, couple 407 and buffer spring 408, conveniently improve the shock resistance and the buffer of this protection network, satisfy the user demand, make buffer spring 408 convenient to install and dismantle simultaneously and change, through setting up mounting groove 409, screw hole 410, threaded post 411, fixed plate 412, perforation 413 and protection network body 414, the convenience can be dismantled certain solitary protection network and change, and change simple and convenient, can't dismantle it after avoiding certain solitary protection network to appear damaging and change, thereby influence the safety protection effect of job site.
Moreover, firstly, a connecting column 3 arranged at the bottom of the novel B protective net is inserted into a connecting groove 2 arranged at the top of the novel A protective net, meanwhile, a first limiting block 402 arranged at the bottom of the novel B protective net is enabled to penetrate through the inside of a transverse mounting plate 401 arranged at the top of the novel A protective net, then, the first limiting block 402 is rotated to carry out limiting and fixing, so that the novel A protective net and the novel B protective net are arranged together, then, a second limiting block 404 arranged at the left side of the novel C protective net is enabled to penetrate through the inside of a vertical mounting plate 403 arranged at the right side of the novel A protective net, then, a second limiting block 404 is rotated, so that the novel A protective net and the novel C protective net are arranged together, and the whole protective net is formed by analogy, then, when a certain single protective net is damaged and needs to be disassembled, a threaded column 411 is manually rotated outwards, so that the threaded column 411 exits from the inside of a perforation 413, then, a fixing plate 412 is pulled out from the inside of a mounting groove 409, so that the disassembly can be completed, when the installation is changed at last, insert the inside of fixed frame 1 through mounting groove 409 with the fixed plate 412 of installation on intact protection network body 414, and make perforation 413 corresponding with screw hole 410, then manual rotation screw post 411, screw post 411 runs through perforation 413 screw thread and installs in screw hole 410, thereby accomplish the installation fixed, it forms integral protection network to have solved current protection network for building engineering mostly to link a plurality of protection network welding together through the welded mode, this kind of mode installation is complicated, and dismantle more difficultly when needing to be changed or maintaining, installer's work efficiency has been reduced, and can't dismantle it after damage appears in certain solitary protection network and change, influence the safety protection effect of job site, on the other hand, current protection network for building engineering only bears the heavy object that falls through the tension of protection network itself and delays the weight of bearing And the impact resistance and the buffering performance of the protective net are lower, so that the use requirement cannot be met.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising a … …" does not exclude the presence of another identical element in a process, method, article, or apparatus that comprises the element.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a building engineering uses novel protection network, includes fixed frame (1), its characterized in that: the connecting groove (2) is formed in the fixed outer frame (1), the connecting column (3) is fixedly connected to the outside of the fixed outer frame (1), and the mounting structure (4) is arranged on the outside of the fixed outer frame (1);
the mounting structure (4) comprises a transverse mounting plate (401), a first limiting block (402), a vertical mounting plate (403), a second limiting block (404), a placing groove (405), a fixing ring (406), a hook (407), a buffer spring (408), a mounting groove (409), a threaded hole (410), a threaded column (411), a fixing plate (412), a perforation (413) and a protective net body (414), wherein the transverse mounting plate (401) is fixedly connected to the outside of the fixing outer frame (1), the outside of the transverse mounting plate (401) is movably connected with the first limiting block (402), the outside of the fixing outer frame (1) is fixedly connected with the vertical mounting plate (403), the outside of the vertical mounting plate (1) is movably connected with the second limiting block (404), the inside of the fixing outer frame (1) is provided with the placing groove (405), the inside of the fixing outer frame (1) is fixedly connected with the fixing ring (406), the inside of the fixing ring (406) is movably connected with the hook (407), the outside of the hook (407) is fixedly connected with the buffer spring (408), the inside of the fixing outer frame (1) is provided with the mounting groove (409), the inside of the fixing outer frame (1) is provided with the threaded column (410), and the threaded column (1) is fixedly connected with the threaded column (411), the outer portion of the threaded column (411) is movably connected with a fixing plate (412), a through hole (413) is formed in the fixing plate (412), and a protective net body (414) is fixedly connected to the outer portion of the fixing plate (412).
2. The novel protective net for constructional engineering as claimed in claim 1, wherein: the quantity of spread groove (2) is two, two spread groove (2) are the top inboard that the symmetry was seted up in fixed frame (1) left and right sides, the quantity of spliced pole (3) is two, two the top of spliced pole (3) is the bottom of symmetry fixed connection in fixed frame (1) left and right sides, and two spliced poles (3) are corresponding with two spread grooves (2) respectively.
3. The novel protective net for constructional engineering as claimed in claim 1, wherein: the quantity of transverse installation board (401) is four, four every adjacent two are a set of in transverse installation board (401), and are two sets of the outside of transverse installation board (401) respectively with the outside at fixed frame (1) top and the outside fixed connection of bottom, and the inside of top transverse installation board (401) has seted up the first spacing hole of several, the quantity of first stopper (402) is the same with first spacing hole, the top of first stopper (402) is rotated with the bottom of bottom transverse installation board (401) respectively and is connected.
4. The novel protective net for constructional engineering as claimed in claim 1, wherein: the quantity of vertical mounting panel (403) is four, four every adjacent two is a set of in vertical mounting panel (403), and is two sets of the outside of vertical mounting panel (403) respectively with the outside fixed connection of fixed frame (1) left and right sides, and the inside of right side vertical mounting panel (403) has seted up the spacing hole of several second, the quantity of second stopper (404) is the same with the spacing hole of second, the right side of second stopper (404) is connected with the left side rotation of left side vertical mounting panel (403) respectively.
5. The novel protection net for constructional engineering according to claim 1, characterized in that: the quantity of resettlement groove (405) is two, two resettlement groove (405) are the symmetry and offer at the top inboard and the bottom inboard of fixed frame (1), the quantity of solid fixed ring (406) is twelve, twelve every horizontal adjacent six in solid fixed ring (406) is a set of, and is two sets of gu fixed ring (406) outside respectively with the top inboard and the bottom inboard fixed connection of fixed frame (1), and two sets of solid fixed ring (406) are located the inside of two resettlement grooves (405) respectively, the quantity of couple (407) is twelve, twelve the inside of couple (407) respectively with the inside swing joint of twelve solid fixed ring (406), twelve every horizontal adjacent six in couple (407) are a set of, the quantity of buffer spring (408) is six, six the top and the bottom of buffer spring (408) respectively with the adjacent one side fixed connection of two sets of couple (407).
6. The novel protective net for constructional engineering as claimed in claim 1, wherein: the quantity of mounting groove (409) is two, two mounting groove (409) is the symmetry and sets up in the inside of fixed frame (1) the left and right sides, the quantity of fixed plate (412) is two, two the outside of fixed plate (412) is pegged graft in the inside of fixed frame (1) the left and right sides through two mounting groove (409) respectively, and the adjacent one side of two fixed plates (412) respectively with the left and right sides fixed connection of protection network body (414), the quantity of screw hole (410) is six, six every vertical adjacent three is a set of, two sets of in screw hole (410) is set up respectively in the inside of fixed frame (1) the left and right sides, the quantity of perforation (413) is six, six every vertical adjacent three is a set of, two sets of in perforation (413) is set up respectively in the inside of two fixed plates (412), and every perforation (413) is corresponding with every screw hole (410) respectively, the quantity of screw thread post (411) is six, six the outside of screw thread post (411) runs through six perforation (413) respectively and is connected in the fixed frame (410) the inside of the left and right sides through six screw hole (413).
CN202222881181.6U 2022-10-31 2022-10-31 Novel protection network for building engineering Active CN218715346U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222881181.6U CN218715346U (en) 2022-10-31 2022-10-31 Novel protection network for building engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222881181.6U CN218715346U (en) 2022-10-31 2022-10-31 Novel protection network for building engineering

Publications (1)

Publication Number Publication Date
CN218715346U true CN218715346U (en) 2023-03-24

Family

ID=85595429

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222881181.6U Active CN218715346U (en) 2022-10-31 2022-10-31 Novel protection network for building engineering

Country Status (1)

Country Link
CN (1) CN218715346U (en)

Similar Documents

Publication Publication Date Title
CN216340813U (en) Steel punching protection vertical net for turnover type environment-friendly external scaffold
CN218715346U (en) Novel protection network for building engineering
CN211818647U (en) A security fence for hydraulic and hydroelectric engineering
CN212269153U (en) Construction floor escape way
CN211256664U (en) Guardrail for bridge floor
CN210013348U (en) Partition structure of communication machine room
CN209040673U (en) A kind of anti-climbing spliced wall guardrail being easily installed
CN112177230A (en) Assembled furred ceiling is used to interior decoration convenient to installation
CN213039059U (en) Personnel warning device for building safety protection
CN216239690U (en) Scaffold pedal unit with guardrail and scaffold working platform
CN216197188U (en) Deformation-preventing protective net for construction
CN218029294U (en) Steel construction communication computer lab that can build fast
CN211974640U (en) Net structure for repairing blade barbed wire protective net
CN216076209U (en) Adjust nimble outer hanging handling frame of building
CN215717074U (en) Assembled super high-rise I-steel protection canopy of encorbelmenting
CN214886145U (en) Construction protection device for safety engineering
CN216986897U (en) Fixed type climbing frame spraying device for house construction
CN212406346U (en) Fence for electric power
CN216866222U (en) Water conservancy rail guard convenient to maintenance is changed
CN221143825U (en) But fast assembly and safety warning rail guard for building engineering of dismantlement
CN106836679B (en) Fence stairwell protection network
CN217760184U (en) Interim protective structure
CN217518377U (en) Sound insulation screen arranged in school fence
CN217079498U (en) Broken line grating assembly and broken line grating
CN220058779U (en) Hard protector on I-steel layer encorbelments

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant