CN218714420U CN202222849130.5U CN202222849130U CN218714420U CN 218714420 U CN218714420 U CN 218714420U CN 202222849130 U CN202222849130 U CN 202222849130U CN 218714420 U CN218714420 U CN 218714420U
Authority
CN
China
Prior art keywords
grg
plate body
fixed mounting
fossil fragments
daylighting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222849130.5U
Other languages
Chinese (zh)
Inventor
甘宜振
张玉良
耿超
高俊峰
冯晓明
张欢
刘泽明
陆卫华
郭玉杰
吴利敏
刘广西
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gold Mantis Fine Decoration Technology Suzhou Co Ltd
Original Assignee
Gold Mantis Fine Decoration Technology Suzhou Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gold Mantis Fine Decoration Technology Suzhou Co Ltd filed Critical Gold Mantis Fine Decoration Technology Suzhou Co Ltd
Priority to CN202222849130.5U priority Critical patent/CN218714420U/en
Application granted granted Critical
Publication of CN218714420U publication Critical patent/CN218714420U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Door And Window Frames Mounted To Openings (AREA)

Abstract

The utility model discloses a prevent to warp ready-package GRG daylighting window project organization that subsides, include: building floor, first installation skeleton, second installation skeleton and GRG decorative board, be provided with the daylighting passageway of rectangle on the building floor, first installation skeleton fixed mounting is on building floor top surface, second installation skeleton includes perpendicular fossil fragments and articulates fossil fragments, perpendicular fossil fragments fixed mounting is on the lateral wall of daylighting passageway, articulate fossil fragments fixed mounting on perpendicular fossil fragments, the cross-section of GRG decorative board is "L" type, the GRG decorative board includes first plate body and second plate body, the first plate body back is provided with pre-buried installed part, first plate body is through pre-buried installed part fixed mounting on first installation skeleton, the second plate body back is provided with the pendant, the second plate body articulates on articulating fossil fragments through the pendant. The utility model discloses compare in prior art, improve the steadiness of GRG material installation, prevent that GRG lighting window from warping and subsiding, effectively improve the installation effectiveness simultaneously.

Description

Prevent to warp ready-package GRG lighting window project organization who subsides
Technical Field
The utility model belongs to the lighting window field especially relates to a prevent to warp ready-package GRG lighting window project organization who subsides.
Background
Inconvenient window of seting up on to the building side wall, perhaps rely on window on the building side wall alone to make indoor daylighting effect can not satisfy the demand, can set up the daylighting window at the building top usually for external light source can enter into indoorly through the roof, produces good daylighting effect.
The daylighting window on the top of the existing public space usually utilizes GRG materials to decorate a daylighting channel, but the volume of a single GRG material unit is large, the installation is not stable enough, and the installation is easy to deform and settle. Meanwhile, GRG material units are required to be fixed with a base steel frame through a plurality of embedded mounting pieces, and therefore mounting efficiency is low.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a: the utility model provides a prevent to warp ready-package GRG lighting window project organization who subsides improves the steadiness of GRG material installation on the one hand, prevents that GRG lighting window warp to subside, and on the other hand effectively improves the installation effectiveness.
In order to achieve the above purpose, the utility model adopts the following technical scheme: a prevent to warp ready-package GRG daylighting window project organization that subsides, includes: building floor, first installation skeleton, second installation skeleton and GRG decorative board, be provided with the daylighting passageway of rectangle on the building floor, first installation skeleton fixed mounting is on building floor top surface, second installation skeleton includes perpendicular fossil fragments and articulates fossil fragments, perpendicular fossil fragments fixed mounting is on the lateral wall of daylighting passageway, articulate fossil fragments fixed mounting on perpendicular fossil fragments, the cross-section of GRG decorative board is "L" type, the GRG decorative board includes first plate body and second plate body, the first plate body back is provided with pre-buried installed part, first plate body is through pre-buried installed part fixed mounting on first installation skeleton, the second plate body back is provided with the pendant, the second plate body articulates on articulating fossil fragments through the pendant.
As a further description of the above technical solution:
the steel frame conversion layer is arranged below the building floor slab, an angle steel 6 is arranged on one side of the steel frame conversion layer, one side of the angle steel is fixedly installed on the steel frame conversion layer through a connecting rod, and the angle steel contacts the bottom of the vertical keel.
As a further description of the above technical solution:
steelframe conversion layer below is provided with the furred ceiling decorative layer, and the furred ceiling decorative layer includes jib, keel frame and furred ceiling decorative panel, and jib fixed mounting is on steelframe conversion layer, and keel frame fixed mounting is in the jib bottom, and furred ceiling decorative panel fixed mounting is in the keel frame below.
As a further description of the above technical solution:
the top of the suspender is fixed through the nut after penetrating through the steel frame conversion layer.
As a further description of the above technical solution:
the keel frame comprises a main keel and a secondary keel, the main keel is fixedly arranged at the bottom of the hanging rod, and the secondary keel is fixedly arranged below the main keel.
As a further description of the above technical solution:
the ceiling decorative panel is provided with a through hole corresponding to the lighting channel.
As a further description of the above technical solution:
the ceiling decorative panel contacts the bottom of the GRG decorative panel.
As a further description of the above technical solution:
the furred ceiling decorative board back is provided with the kicking block, and kicking block contact GRG decorative board side.
As a further description of the above technical solution:
the ceiling decorative panel is a gypsum board.
To sum up, owing to adopted above-mentioned technical scheme, the beneficial effects of the utility model are that:
1. the utility model discloses in, because the cross-section of GRG decorative board is "L" type, the weight of GRG decorative board is shared by building floor on the one hand, and on the other hand GRG decorative board bottom receives the support of furred ceiling decorative panel, prevents effectively that GRG daylighting window warp and subsides.
2. The utility model discloses in, the GRG decorative board is through articulating the installation in vertical direction, and it is fixed only that the top is passed through pre-buried installed part, compares in only fixed through pre-buried installed part, reduces the installation degree of difficulty, improves the installation effectiveness.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings for immersing the embodiments are briefly described below, it should be understood that the following drawings only illustrate some embodiments of the present invention, and therefore should not be considered as limiting the scope, and for those skilled in the art, other related drawings can be obtained according to these drawings without inventive efforts.
Fig. 1 is a side view angle structural diagram of a rapid-installation GRG lighting window design structure for preventing deformation and settlement.
Fig. 2 is a partially enlarged view of a portion a in fig. 1.
Fig. 3 is a partially enlarged view of B in fig. 1.
Fig. 4 is a partially enlarged view of C in fig. 1.
Fig. 5 is a schematic structural diagram of a GRG decorative plate in a rapid-installation GRG lighting window design structure for preventing deformation and settlement.
Fig. 6 is a schematic structural diagram of a ceiling veneer in a rapid-installation GRG daylight window design structure for preventing deformation and settlement.
Illustration of the drawings:
1. building a floor slab; 11. a light collecting channel; 2. a first mounting frame; 3. a second mounting framework; 31. a vertical keel; 32. hanging a keel; 4. a GRG decorative plate; 41. a first plate body; 411. pre-burying a mounting piece; 42. a second plate body; 421. hanging parts; 5. a steel frame conversion layer; 6. angle steel; 61. a connecting rod; 7. a ceiling decorative layer; 71. a boom; 711. a nut; 72. a keel frame; 721. a main keel; 722. a false keel; 73. a ceiling veneer; 731. a through hole; 732. and (7) a top block.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all, embodiments of the present invention. The components of embodiments of the present invention, as generally described and illustrated in the figures herein, may be arranged and designed in a wide variety of different configurations.
Thus, the following detailed description of the embodiments of the invention, as presented in the figures, is not intended to limit the scope of the invention, as claimed, but is merely representative of selected embodiments of the invention. Based on the embodiments of the present invention, all other embodiments obtained by a person skilled in the art without making creative efforts belong to the protection scope of the present invention.
It should be noted that: like reference numbers and letters refer to like items in the following figures, and thus, once an item is defined in one figure, it need not be further defined and explained in subsequent figures.
In the description of the embodiments of the present invention, it should be noted that the terms "upper", "inner" and the like indicate the position or positional relationship based on the position or positional relationship shown in the drawings, or the position or positional relationship which is usually placed when the utility model is used, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element to which the term refers must have a specific position, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.
In the description of the present invention, it should also be noted that, unless otherwise explicitly specified or limited, the terms "disposed," "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Referring to fig. 1-6, the present invention provides a technical solution: a prevent to warp ready-package GRG daylighting window project organization that subsides, includes: building floor 1, first installation skeleton 2, second installation skeleton 3 and GRG decorative board 4, be provided with the daylighting passageway 11 of rectangle on the building floor 1, 2 fixed mounting of first installation skeleton are on 1 top surface of building floor, second installation skeleton 3 includes vertical keel 31 and articulates fossil fragments 32, vertical keel 31 fixed mounting is on daylighting passageway 11's lateral wall, articulate fossil fragments 32 fixed mounting on vertical keel 31, GRG decorative board 4's cross-section is "L" type, GRG decorative board 4 includes first plate body 41 and second plate body 42, first plate body 41 back is provided with pre-buried installed part 411, first plate body 41 is through pre-buried installed part 411 fixed mounting on first installation skeleton 2, second plate body 42 back is provided with the pendant 421, second plate body 42 articulates on articulating fossil fragments 32 through pendant 421.
Building floor 1 below sets up steel frame conversion layer 5, 5 one sides of steel frame conversion layer are provided with angle steel 6, 6 one sides of angle steel are through connecting rod 61 fixed mounting on steel frame conversion layer 5, 6 contact vertical joist 31 bottoms of angle steel, connecting rod 61 passes through welded fastening and installs on steel frame conversion layer 5, angle steel 6 and connecting rod 61 welded fastening, angle steel 6 can form the support to vertical joist 31, thereby effectively improve the steadiness of GRG material installation, prevent that GRG daylighting window from warping and subsiding.
Steel frame conversion layer 5 below is provided with furred ceiling decorative layer 7, furred ceiling decorative layer 7 includes jib 71, keel frame 72 and furred ceiling decorative board 73, jib 71 fixed mounting is on steel frame conversion layer 5, keel frame 72 fixed mounting is in jib 71 bottom, furred ceiling decorative board 73 fixed mounting is in keel frame 72 below, keel frame 72 includes main joist 721 and false keel 722, main joist 721 fixed mounting is in jib 71 bottom, false keel 722 fixed mounting is in main joist 721 below, furred ceiling decorative board 73 is the gypsum board.
The top of the suspender 71 is fixed through a nut 711 after penetrating through the steel frame conversion layer 5, and the ceiling decorative panel 73 contacts the bottom of the GRG decorative panel 4. Make the mounting height of furred ceiling decorative layer 7 can adjust in a flexible way like this to effectively guarantee furred ceiling decorative board 73 to the support of GRG decorative board 4, prevent that GRG daylighting window from warping and subsiding.
Be provided with the through-hole 731 that the position corresponds daylighting passageway 11 on the furred ceiling decorative panel 73, the furred ceiling decorative panel 73 hides the piece between the GRG decorative board 4, improves decorative effect.
The furred ceiling decorative board 73 back is provided with kicking block 732, and kicking block 732 contact GRG decorative board 4 side, and assistance-localization real-time GRG decorative board 4, restriction GRG decorative board 4 position change prevents that GRG daylighting window from warping and subsiding.
The working principle is as follows: when the GRG decorative board 4 is installed, the GRG decorative board 4 is firstly hung on the hanging keel 32 through the hanging piece 421, and then is fixedly installed on the first installation framework 2 through the pre-embedded installation piece 411, a gap filler is arranged in the abutted seams of the two adjacent GRG decorative boards 4, and the ceiling decorative layer 7 is installed at last. Because the cross-section of GRG decorative board 4 is "L" type, the weight of GRG decorative board 4 is shared by building floor 1 on the one hand, and on the other hand 4 bottoms of GRG decorative board receive the support of furred ceiling decorative board 73, prevent effectively that GRG daylighting window from warping and subsiding. GRG decorative board 4 is through articulating the installation in vertical direction, and it is fixed only that the top passes through pre-buried installed part 411, compares in only fixing through pre-buried installed part 411, reduces the installation degree of difficulty, improves the installation effectiveness.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (9)

1. The utility model provides a prevent to warp ready-package GRG daylighting window project organization that subsides which characterized in that includes: building floor (1), first installation skeleton (2), second installation skeleton (3) and GRG decorative board (4), be provided with daylighting passageway (11) of rectangle on building floor (1), first installation skeleton (2) fixed mounting be in on building floor (1) top surface, second installation skeleton (3) are including erectting fossil fragments (31) and articulate fossil fragments (32), erectting fossil fragments (31) fixed mounting be in on the lateral wall of daylighting passageway (11), articulate fossil fragments (32) fixed mounting on erectting fossil fragments (31), the cross-section of GRG decorative board (4) is "L" type, GRG decorative board (4) are including first plate body (41) and second plate body (42), first plate body (41) back is provided with pre-buried installed part (411), first plate body (41) pass through pre-buried installed part (411) fixed mounting be in on first installation skeleton (2), second plate body (42) back is provided with pendant (421), second plate body (42) pass through pendant (32) articulate.
2. The quick-mounting GRG daylighting window design structure capable of preventing deformation and settlement of claim 1, characterized in that, a steel frame conversion layer (5) is arranged below the building floor (1), an angle steel (6) is arranged on one side of the steel frame conversion layer (5), one side of the angle steel (6) is fixedly mounted on the steel frame conversion layer (5) through a connecting rod (61), and the angle steel (6) contacts with the bottom of the vertical keel (31).
3. The quick-mounting GRG lighting window design structure capable of preventing deformation and settlement as claimed in claim 2, wherein a ceiling decoration layer (7) is arranged below the steel frame conversion layer (5), the ceiling decoration layer (7) comprises a suspension rod (71), a keel frame (72) and a ceiling decoration panel (73), the suspension rod (71) is fixedly mounted on the steel frame conversion layer (5), the keel frame (72) is fixedly mounted at the bottom of the suspension rod (71), and the ceiling decoration panel (73) is fixedly mounted below the keel frame (72).
4. The quick-mounting GRG lighting window design structure capable of preventing deformation and settlement as claimed in claim 3, wherein the top of the hanger rod (71) is fixed by a nut (711) after passing through the steel frame conversion layer (5).
5. The quick-assembly GRG daylighting window design structure of preventing deformation settlement of claim 3, characterized in that, keel frame (72) includes main joist (721) and false keel (722), main joist (721) fixed mounting is in jib (71) bottom, false keel (722) fixed mounting is in main joist (721) below.
6. The quick-mounting GRG lighting window design structure capable of preventing deformation and settlement as claimed in claim 3, wherein the ceiling facing panel (73) is provided with a through hole (731) corresponding to the lighting channel (11).
7. The quick-install GRG lighting window design structure capable of preventing deformation and settlement of claim 6, wherein the ceiling facing panel (73) contacts the bottom of the GRG decorative panel (4).
8. The quick-install GRG lighting window design structure capable of preventing deformation and settlement as claimed in claim 7, wherein the ceiling facing panel (73) is provided with a top block (732) on the back, and the top block (732) contacts the side of the GRG facing panel (4).
9. The quick-install GRG lighting window design structure capable of preventing deformation and settlement as claimed in claim 3, wherein the ceiling facing panel (73) is gypsum board.
CN202222849130.5U 2022-10-27 2022-10-27 Prevent to warp ready-package GRG lighting window project organization who subsides Active CN218714420U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222849130.5U CN218714420U (en) 2022-10-27 2022-10-27 Prevent to warp ready-package GRG lighting window project organization who subsides

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222849130.5U CN218714420U (en) 2022-10-27 2022-10-27 Prevent to warp ready-package GRG lighting window project organization who subsides

Publications (1)

Publication Number Publication Date
CN218714420U true CN218714420U (en) 2023-03-24

Family

ID=85593535

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222849130.5U Active CN218714420U (en) 2022-10-27 2022-10-27 Prevent to warp ready-package GRG lighting window project organization who subsides

Country Status (1)

Country Link
CN (1) CN218714420U (en)

Similar Documents

Publication Publication Date Title
CN210947364U (en) High strength furred ceiling decorative structure
CN210976276U (en) Suspended ceiling decoration structure
CN218714420U (en) Prevent to warp ready-package GRG lighting window project organization who subsides
CN203284930U (en) Suspended ceiling structure with decorative light bar
CN218437715U (en) Top surface hidden type lamp groove structure convenient for mounting lamp strip
CN209907705U (en) Prevent furred ceiling structure of gypsum board deformation
US3786602A (en) Modular ceiling assembly
CN215888818U (en) Clamping and inserting type grade-falling keel
CN114412046A (en) Anti-deformation anti-falling assembled buckle suspended ceiling
CN215820539U (en) Curtain box structure
CN213806274U (en) Wall arc metal plate installation bolt aluminum alloy connecting piece
CN211923178U (en) Indoor integrated ceiling of building
CN208202294U (en) Furred ceiling conversion layer structure
CN207827663U (en) A kind of single-row staircase decorative board mounting structure and staircase
EP2083128A1 (en) Cantilevered ceiling system
CN207648734U (en) Assembled furred ceiling light trough
CN217537694U (en) Simple wall brick mounting structure
CN217679934U (en) Folding shape smallpox and suspended ceiling
CN215330839U (en) Suspended ceiling structure
CN216766458U (en) Square tube furred ceiling suspended ceiling connection structure
CN217053982U (en) Inclination adjustable shape inclined ceiling structure of preapring for an unfavorable turn of events
JPH0630982Y2 (en) Partition wall for urinals in the toilet room
CN218721185U (en) Assembled smallpox light trough
CN218758248U (en) Aluminum net ceiling plate
CN215290935U (en) Architectural decoration furred ceiling based on BIM technique