CN218712980U - Protect broken stake bobbing machine of muscle - Google Patents
Protect broken stake bobbing machine of muscle Download PDFInfo
- Publication number
- CN218712980U CN218712980U CN202222733631.7U CN202222733631U CN218712980U CN 218712980 U CN218712980 U CN 218712980U CN 202222733631 U CN202222733631 U CN 202222733631U CN 218712980 U CN218712980 U CN 218712980U
- Authority
- CN
- China
- Prior art keywords
- pile
- pile foundation
- support frame
- breaking
- hammer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The utility model discloses a protect broken stake bobbing machine of muscle, include with pile foundation complex ring support frame, the ring support frame cover is established on the pile foundation, and the circumference distributes on the ring support frame has a plurality of broken stake points, and every broken stake point department all installs the vibration hammer, and directional pile foundation of vibration hammer and hammer point and pile foundation side contact cooperation. The utility model discloses a concrete on the hammering stake is carried out with high pressure, low frequency to the vibratory hammer, makes the concrete broken. And the annular support frame is confined while the pile is crushed, so that the hammer tip is pressed against the side surface of the pile foundation all the time. Thus, the concrete is crushed, the reinforcing steel bars are protected, and the disturbance and the loss of the pile foundation are minimum. The utility model can improve the efficiency of pile head breaking; the operation risk is reduced; reduce the damage to the pile body and protect the reinforcing steel bars.
Description
Technical Field
The utility model relates to an electric power industry transformer substation pile foundation construction technical field, concretely relates to protect broken stake bobbing machine of muscle.
Background
The pile foundation construction of the transformer substation is very important, the pile breaking work of the pile foundation is particularly important, and whether the quality of the pile foundation and the quality of the steel bars meet the requirements or not is controlled in the pile breaking process.
Pile breaking (also called pile head breaking): when pouring the cast-in-place pile, the top elevation of the cast-in-place pile should be 0.5 to 1.0m higher than the designed top elevation of the pile so as to ensure the strength of the pile head concrete, but the part of the pile head higher than the designed top elevation of the pile must be chiseled off in the subsequent process construction, and the chiseling off of the part of the pile head concrete is called as 'broken pile head'. In order to guarantee pile head quality in the time of pile foundation construction, pile bolck elevation all will generally be higher than the design elevation, for example bored concrete pile: when the concrete is poured, sediment at the bottom of the pile and impurities precipitated in slurry in the pouring process can form a certain thickness on the surface of the concrete, generally called as floating slurry, so that after the concrete is solidified, the excess pouring part is chiseled off, main ribs (steel bars) above the elevation of the pile top are exposed, and after the pile foundation is detected to be qualified, the construction of the bearing platform is carried out.
The existing pile head breaking tool mainly comprises manpower and machinery, the mechanical name of the pile head breaking tool is a pile breaking machine, a pile cutting machine and the like, the speed is many times faster than that of the manpower, and if the construction period is shorter, the pile head breaking tool is generally broken by the machinery. However, the technical defects existing at present are as follows: the manual breaking efficiency is low, and the operation risk is high; the mechanical breaking is easy to damage the pile body in the construction process, and particularly causes loss to the steel bars of the pile foundation.
Due to the fact that pile breaking workload is large, potential safety hazards are large, required repetitive workload is large, and the existing breaking mode is difficult to meet the requirements.
SUMMERY OF THE UTILITY MODEL
The utility model discloses a solve the problem among the prior art, provide a protect broken stake bobbing machine of muscle.
In order to solve the technical problem, the utility model adopts the following technical scheme:
the utility model provides a protect broken stake bobbing machine of muscle, includes the annular bracing frame with pile foundation complex, and the annular bracing frame cover is established on the pile foundation, and the circumference distributes on the annular bracing frame has a plurality of broken stake points, and every broken stake point department all installs the bobbing hammer, and the directional pile foundation of bobbing hammer and the contact cooperation of hammer point and pile foundation side.
Preferably, the annular support frame is of a diameter-adjustable structure.
Preferably, the annular support frame consists of a fastening frame and a fixed frame which are sequentially distributed at intervals, and the fastening frame and the fixed frame are both arc-shaped and are sequentially connected to form a circular structure;
the fixing frame is in a cylindrical form, the end part of the fastening frame extends into the fixing frame and is in sliding fit with the fixing frame, and the joint of the fixing frame and the fixing frame is locked through screws.
Preferably, the fastening frame and the fixing frame are respectively provided with a vibration hammer.
Preferably, the vibration hammer is a high-pressure low-frequency vibration hammer.
Preferably, the vibration hammer is connected with a high-pressure air pump.
The utility model has the advantages that:
the utility model discloses a concrete on the hammering stake is carried out with high pressure, low frequency to the vibratory hammer, makes the concrete broken. And the annular support frame is confined while the pile is crushed, so that the hammer tip is pressed against the side surface of the pile foundation all the time. Thus, the concrete state is broken, the reinforcing steel bars are protected, and the disturbance and the loss of the pile foundation are minimum.
The utility model can improve the efficiency of pile head breaking; the operation risk is reduced; reduce the damage to the pile body and protect the reinforcing steel bars.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is a top view of fig. 1.
The drawings are for illustrative purposes only and are not to be construed as limiting the patent; for the purpose of better illustrating the embodiments, certain features of the drawings may be omitted, enlarged or reduced, and do not represent the size of an actual product; it will be understood by those skilled in the art that certain well-known structures in the drawings and descriptions thereof may be omitted.
Detailed Description
The following detailed description of the embodiments of the present invention will be made with reference to the accompanying drawings. It is to be understood that the description of the embodiments herein is for purposes of illustration and explanation only and is not intended to limit the invention.
As shown in fig. 1 to fig. 2, the utility model discloses a protect broken stake bobbing machine of muscle, include with pile foundation 1 complex ring carrier, the ring carrier cover is established on the pile foundation, and the circumference distributes on the ring carrier has a plurality of broken stake points, and every broken stake point department all installs vibratory hammer 2, and vibratory hammer 2 is directional pile foundation 1 and the cooperation of hammer point and pile foundation side contact.
In order to realize the size of the annular support frame which can be matched with the size of the pile foundation and to realize that the annular support frame is embraced on the pile foundation, the annular support frame is of a diameter-adjustable structure.
Specifically, the annular support frame comprises fastening frame 3 and mount 4 of interval distribution in proper order, and fastening frame 3 and mount 4 are the arc to connect gradually and form circular structure.
Meanwhile, the fixing frame 4 is in a cylindrical form, the end part of the fastening frame 3 extends into the fixing frame 4 and is in sliding fit with the fixing frame, and the joint of the fixing frame and the fixing frame is locked through the screw 5.
In this embodiment, the fastening frame 3 and the fixing frame 4 are respectively provided with two, and the vibration hammers 2 are respectively arranged on the fastening frame 3 and the fixing frame 4.
In this embodiment, the vibration hammer 2 is a high-pressure low-frequency vibration hammer, and the vibration hammer 2 is connected to a high-pressure air pump 6.
The embodiment also discloses a method for protecting the reinforcement and breaking the pile, and the vibration machine for protecting the reinforcement and breaking the pile comprises the following steps of:
(1) Firstly, combining an annular support frame, combining and sleeving a fastening frame 3 and a fixing frame 4 on a pile foundation, and adjusting the diameter of the annular support frame according to the diameter of the pile foundation to enable a vibration hammer to be in contact with the pile foundation, so that the reinforcement bar breaking vibration machine is integrally embraced on the pile foundation;
(2) Starting a high-pressure air pump, enabling a high-pressure low-frequency vibration hammer to work, hammering concrete on the pile at high pressure and low frequency, and crushing the concrete; and the annular support frame is confined while the pile is crushed, so that the hammer tip is pressed against the side surface of the pile foundation all the time. Thus, the concrete state is broken, the reinforcing steel bars are protected, and the disturbance and the loss of the pile foundation are minimum.
The utility model can improve the efficiency of pile head breaking; the operation risk is reduced; reduce the damage to the pile body and protect the reinforcing steel bars.
The above embodiments are only used for illustrating but not limiting the technical solutions of the present invention, and although the present invention is described in detail with reference to the above embodiments, those of ordinary skill in the art should understand that: the present invention may be modified or substituted with equivalents without departing from the spirit and scope of the invention, which should be construed as being limited only by the claims.
If the terms "first," "second," etc. are used herein to define parts, those skilled in the art will recognize that: the use of "first" and "second" is merely for convenience in describing the invention and to simplify the description, the words do not have a special meaning unless otherwise stated.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", "axial", "radial", "circumferential", and the like, indicate the orientation or positional relationship indicated based on the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Claims (6)
1. The utility model provides a protect broken stake bobbing machine of muscle which characterized in that: the pile foundation vibration device comprises an annular support frame matched with a pile foundation, wherein the annular support frame is sleeved on the pile foundation, a plurality of pile breaking points are circumferentially distributed on the annular support frame, a vibration hammer is mounted at each pile breaking point, and the vibration hammer points point to the pile foundation and contact with the side face of the pile foundation to be matched.
2. The bar-protecting pile-breaking vibrator according to claim 1, wherein: the annular support frame is of a diameter-adjustable structure.
3. The bar-protecting pile-breaking vibrator according to claim 2, wherein: the annular support frame consists of fastening frames and fixing frames which are sequentially distributed at intervals, and the fastening frames and the fixing frames are arc-shaped and are sequentially connected to form a circular structure;
the fixing frame is in a cylindrical form, the end part of the fastening frame extends into the fixing frame and is in sliding fit with the fixing frame, and the joint of the fixing frame and the fixing frame is locked through screws.
4. The bar-protecting pile-breaking vibrator according to claim 3, wherein: and the fastening frame and the fixing frame are respectively provided with a vibration hammer.
5. A bar-protecting pile-breaking vibrator according to any one of claims 1-4, characterized by: the vibration hammer is a high-pressure low-frequency vibration hammer.
6. The bar-protecting pile-breaking vibrator according to claim 5, wherein: the vibration hammer is connected with a high-pressure air pump.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222733631.7U CN218712980U (en) | 2022-10-18 | 2022-10-18 | Protect broken stake bobbing machine of muscle |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222733631.7U CN218712980U (en) | 2022-10-18 | 2022-10-18 | Protect broken stake bobbing machine of muscle |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218712980U true CN218712980U (en) | 2023-03-24 |
Family
ID=85586021
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202222733631.7U Active CN218712980U (en) | 2022-10-18 | 2022-10-18 | Protect broken stake bobbing machine of muscle |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218712980U (en) |
-
2022
- 2022-10-18 CN CN202222733631.7U patent/CN218712980U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN218712980U (en) | Protect broken stake bobbing machine of muscle | |
CN209855737U (en) | Light drill bit fisher for pile foundation punching engineering | |
CN104060814A (en) | Cantilever beam anchoring piece and mounting method and dismounting method thereof | |
CN108487238A (en) | A kind of filling pile head processing unit and its construction method | |
CN115492108A (en) | Rib-protecting pile-breaking vibrator and rib-protecting pile-breaking method | |
CN211848785U (en) | Cast-in-place concrete road terrace template quick supporting and dismounting device | |
CN211340764U (en) | Mechanical connection precast pile | |
CN212027084U (en) | Adjustable combined steel formwork with supporting rod | |
CN109853539B (en) | Lengthening pile casing and construction method thereof | |
CN208201865U (en) | Column hammer and rammed bulb pile equipment | |
CN102704691B (en) | Whole-bundle disanchoring device and disanchoring method adopting same | |
CN106049503A (en) | Pretreatment method for blasting demolition of reinforced concrete supporting beam in foundation pit | |
CN213978954U (en) | Construction tool for quickly separating pile head of cast-in-place pile | |
CN212329878U (en) | Broken dismouting of corrosion bolt is put | |
CN215640538U (en) | Convenient muscle material anchor auxiliary device of repeatedly usable | |
CN212336692U (en) | Wall connecting piece structure with detachable embedded part | |
CN211472476U (en) | High-strength environment-friendly prestressed concrete pipe pile | |
CN220746577U (en) | Bridge anticollision wall structure | |
CN210965340U (en) | Metal composite hammer head of hammer crusher | |
CN219034811U (en) | Isolated drop shaft grid screen assembly | |
CN218346166U (en) | Temporary casing for pile foundation engineering | |
CN218952766U (en) | Can have enough to meet need novel wall spare buries even | |
CN212897614U (en) | Quick-release split bolt | |
CN111396094B (en) | Temporary transverse support for tunnel step construction and mounting method thereof | |
CN217949030U (en) | Reinforced concrete pile structure for foundation engineering construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |