CN218699910U - Cover half device for construction - Google Patents

Cover half device for construction Download PDF

Info

Publication number
CN218699910U
CN218699910U CN202222781795.7U CN202222781795U CN218699910U CN 218699910 U CN218699910 U CN 218699910U CN 202222781795 U CN202222781795 U CN 202222781795U CN 218699910 U CN218699910 U CN 218699910U
Authority
CN
China
Prior art keywords
side baffle
wall
sliding
building construction
construction according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202222781795.7U
Other languages
Chinese (zh)
Inventor
常浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202222781795.7U priority Critical patent/CN218699910U/en
Application granted granted Critical
Publication of CN218699910U publication Critical patent/CN218699910U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a cover half device for construction belongs to cover half device technical field, include: the side baffle comprises a bottom plate, two side baffles and two side baffles positioned between the two side baffles; the top end of the side baffle is connected with two connecting blocks, the upper surface of each connecting block is provided with a moving frame in an L-shaped structure in a fitting manner, the inner wall of the vertical section of the moving frame is connected with a second sliding block, the second sliding block is in sliding connection with a second sliding groove formed in the outer wall of the side baffle, the top end of the side baffle is provided with a plurality of threaded holes which are arranged at equal intervals, and the threaded holes, the connecting blocks and the moving frame are locked and fixed through locking bolts; the integrative injection moulding in top of bottom plate has the joint piece of two symmetry settings, the joint groove of being connected with joint piece block is seted up to the bottom surface of side shield. This cover half device for construction, simple structure has practiced thrift a large amount of manpowers.

Description

Cover half device for construction
Technical Field
The utility model belongs to the technical field of the cover half device, especially, relate to a cover half device for construction.
Background
With the progress of science and technology and the development of society, road and bridge buildings gradually tend to be modularized, and the modularized buildings have the advantages of being simple to process, low in cost, capable of greatly shortening the construction period and the like;
in the correlation technique, the module need use the mould in the manufacture process, and conventional bridge module mould includes die block and side form, and the side form encloses by four steel form boards and establishes to form, because the template size is fixed, so correspond the module of each kind of specification, all need prepare one set of mould, and mould cost is higher during the construction.
Therefore, the fixed die device for building construction is provided to solve the problems.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving prior art, the mould need be used to the module in the manufacturing process, and conventional bridge module mould includes die block and side form, and the side form encloses by four steel form and establishes to constitute, because the size of template is fixed, so correspond the module of each kind of specification, all need prepare one set of mould, the higher problem of mould cost during the construction, and the cover half device for the construction that proposes.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
a cover half device for construction includes:
the side baffle comprises a bottom plate, two side baffles and two side baffles positioned between the two side baffles;
the top of limit baffle is connected with two connecting blocks, and the upper surface laminating of connecting block is provided with the removal frame of L type structure, be connected with second slider on the inner wall of the vertical section of removal frame, and two sliding connection of spout that second slider and side shield outer wall were seted up, the screw hole that a plurality of equidistance were arranged is seted up on the top of side shield, and through locking bolt locking between screw hole, connecting block and the removal frame and fix.
Through above-mentioned technical scheme, remove frame and connecting block and pass through locking bolt and the different built-up connection of a plurality of screw holes to adjust the distance between two limit baffles, can produce the module of the different specifications of multiunit, improve the device's practicality.
Preferably, the integrative injection moulding in top of bottom plate has the joint piece of two symmetry settings, the joint groove of being connected with joint piece block is seted up to the bottom surface of side shield.
Through above-mentioned technical scheme, be convenient for install or dismantle bottom plate, two side shields and two limit baffles.
Preferably, the inner wall of the side baffle is provided with a first sliding groove, a first sliding block is connected to the first sliding groove in a sliding mode, a scraping rod is arranged between the first sliding blocks, and the top end of the scraping rod is connected with a handle.
Through above-mentioned technical scheme, use through the cooperation of handle, spout one and slider one, drive and scrape the pole and carry out transverse motion, shakeout the cement of pouring into, unnecessary cement falls down from the discharge gate on the side shield, has saved the manual work to the operation of polishing on uneven surface, has practiced thrift a large amount of manpowers.
Preferably, the outer wall of the first sliding block is connected with a fixing frame of a U-shaped structure, the outer walls of two sides of the fixing frame are provided with positioning holes, the outer walls of two sides of the scraping rod are provided with two moving holes, the moving holes are connected with positioning pins matched and connected with the positioning holes in a sliding mode, and the positioning pins are connected with the inner walls of the moving holes through compression springs.
Through above-mentioned technical scheme, scrape the pole and insert between two fixed frames for the locating pin receives the extrusion, and through compression spring's elasticity effect, make locating pin and the locating hole on the fixed frame be connected, thereby be convenient for install or dismantle the pole of scraping.
Preferably, the vertical section of the clamping block is of a trapezoidal structure.
Through above-mentioned technical scheme, the joint piece of trapezium structure improves joint strength between bottom plate and the side board.
Preferably, a sealing gasket is connected in a groove formed in the outer walls of the two sides of the side baffle, and the other end of the sealing gasket abuts against the inner wall of the side baffle.
Through above-mentioned technical scheme, through the setting of sealed the pad, guarantee the leakproofness between side shield and the limit baffle.
Preferably, a discharge port is formed in the outer side wall of the side baffle, and a lower port of the discharge port is parallel to the bottom surface of the scraping rod.
Through above-mentioned technical scheme, when scraping the material of pole, discharge unnecessary cement through the discharge gate.
To sum up, the utility model discloses a technological effect and advantage: according to the fixed die device for building construction, the movable frame and the connecting block are connected with the plurality of threaded holes in different combinations through the locking bolts, so that the distance between the two side baffles is adjusted, a plurality of groups of modules with different specifications can be manufactured, and the practicability of the device is improved;
the scraping rod is driven to transversely move through the matching use of the handle, the sliding groove I and the sliding block I, poured cement is flattened, and redundant cement falls from a discharge hole in the side baffle, so that the manual polishing operation on the uneven surface is omitted, and a large amount of manpower is saved; this cover half device for construction, simple structure has practiced thrift a large amount of manpowers.
Drawings
Fig. 1 is a schematic structural view of the present invention;
fig. 2 is an enlarged view of the structure a in fig. 1 according to the present invention;
FIG. 3 is a schematic view of the combination structure of the scraping rod and the fixing frame of the present invention;
fig. 4 is a schematic structural diagram of the side baffle of the present invention.
In the figure: 1. a base plate; 2. a side dam; 3. an edge baffle; 4. a scraping rod; 5. a handle; 6. a clamping block; 7. a first sliding chute; 8. connecting blocks; 9. a movable frame; 10. locking the bolt; 11. a second sliding block; 12. a second chute; 13. a threaded hole; 14. a first sliding block; 15. a fixing frame; 16. positioning pins; 17. a compression spring; 18. positioning holes; 19. a discharge port; 20. and a gasket.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1, 2 and 3, a stationary mold device for construction includes: the sealing structure comprises a bottom plate 1, two side baffles 2 and two side baffles 3 positioned between the two side baffles 2, wherein sealing gaskets 20 are connected in grooves formed in the outer walls of the two sides of each side baffle 3, and the other ends of the sealing gaskets 20 are abutted against the inner walls of the side baffles 2, so that the sealing property of an inner cavity of a mold is ensured, and cement is prevented from flowing out from gaps between the side baffles 2;
the top of limit baffle 3 is connected with two connecting blocks 8, and the upper surface laminating of connecting block 8 is provided with the removal frame 9 of L type structure, be connected with two 11 of slider on the inner wall of the vertical section of removal frame 9, and two 12 sliding connection of spout that two 11 of slider and 2 outer walls of side shield were seted up, the screw hole 13 that a plurality of equidistance were arranged is seted up on the top of side shield 2, and screw hole 13, it is fixed through locking bolt 10 locking between connecting block 8 and the removal frame 9, remove frame 9 and connecting block 8 through locking bolt 10 and the different built-up connection of a plurality of screw holes 13, thereby adjust the distance between two limit baffles 3, can produce the module of the different specifications of multiunit.
Referring to fig. 1, the integrative injection moulding in top of bottom plate 1 has the joint piece 6 that two symmetries set up, and the joint groove of being connected with 6 blocks of joint piece is seted up to the bottom surface of side shield 2, and the vertical section of joint piece 6 is the trapezium structure, and the joint piece 6 of trapezium structure improves joint strength between bottom plate 1 and the side shield, and is convenient for install or dismantle bottom plate 1, two side shields 2 and two side shields 3.
Referring to fig. 3 and 4, first sliding grooves 7 are formed in the inner walls of the two side guards 2, first sliding grooves 14 are slidably connected to the first sliding grooves 7, a scraping rod 4 is arranged between the first sliding blocks 14, the top end of the scraping rod 4 is connected with a handle 5, a fixing frame 15 of a U-shaped structure is connected to the outer wall of the first sliding block 14, positioning holes 18 are formed in the outer walls of the two sides of the fixing frame 15, two moving holes are formed in the outer walls of the two sides of the scraping rod 4, a positioning pin 16 matched and connected with the positioning holes 18 is slidably connected in each moving hole, the positioning pin 16 is connected with the inner wall of each moving hole through a compression spring 17, the scraping rod 4 is inserted between the two fixing frames 15, the positioning pin 16 is extruded, the positioning pin 16 is connected with the positioning holes 18 in the fixing frame 15 through the elastic effect of the compression spring 17, the scraping rod 4 is convenient to install or disassemble, a discharging hole 19 is formed in the outer side guard 3, a lower end of the discharging hole 19 is parallel to the bottom surface of the scraping rod 4, and when the scraping rod 4 is scraped, and excessive water is discharged through the discharging hole 19.
The working principle is as follows: when using, at first through two joint pieces 6 with two 2 joints of side shield in the both sides on bottom plate 1, insert two side shield 3 between two side shield 2 after that, utilize locking bolt 10 with connecting block 8 afterwards, it is fixed to remove frame 9 and screw hole 13 and connect, fix the reinforcing bar and place in the mould after that, and to leading-in right amount cement in the mould, through handle 5, spout 7 and 14 cooperation of slider are used, it carries out transverse motion to drive scraping rod 4, shakeouts the cement of pouring, unnecessary cement falls down from discharge gate 19 on side shield 3, stop work waits for it to solidify, after solidifying, with bottom plate 1, side shield 2 and side shield 3 demolish can.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (7)

1. A cover half device for construction includes:
the side baffle plate comprises a bottom plate (1), two side baffle plates (2) and two side baffle plates (3) positioned between the two side baffle plates (2);
its characterized in that, the top of side shield (3) is connected with two connecting blocks (8), and the upper surface laminating of connecting block (8) is provided with removal frame (9) of L type structure, be connected with two (11) of slider on the inner wall of the vertical section of removal frame (9), and two (12) sliding connection of spout that two (11) of slider and side shield (2) outer wall were seted up, screw hole (13) that a plurality of equidistance were arranged are seted up on the top of side shield (2), and are fixed through locking bolt (10) locking between screw hole (13), connecting block (8) and the removal frame (9).
2. The fixed die device for building construction according to claim 1, wherein two symmetrically arranged clamping blocks (6) are integrally injection molded at the top end of the bottom plate (1), and clamping grooves clamped and connected with the clamping blocks (6) are formed in the bottom surface of the side baffle (2).
3. A fixed die device for building construction according to claim 1, wherein the inner walls of the two side baffles (2) are provided with first sliding grooves (7), first sliding blocks (14) are connected in the first sliding grooves (7) in a sliding manner, a scraping rod (4) is arranged between the two first sliding blocks (14), and the top end of the scraping rod (4) is connected with a handle (5).
4. A fixed die device for building construction according to claim 3, wherein the outer wall of the first sliding block (14) is connected with a fixed frame (15) with a U-shaped structure, the outer walls of the two sides of the fixed frame (15) are respectively provided with a positioning hole (18), the outer walls of the two sides of the scraping rod (4) are respectively provided with two moving holes, the moving holes are internally and slidably connected with positioning pins (16) which are matched and connected with the positioning holes (18), and the positioning pins (16) are connected with the inner walls of the moving holes through compression springs (17).
5. A fixed die device for building construction according to claim 2, wherein the vertical section of the clamping block (6) is a trapezoidal structure.
6. A fixed die device for building construction according to claim 1, characterized in that the groove formed on the outer wall of the two sides of the side baffle (3) is connected with a sealing gasket (20), and the other end of the sealing gasket (20) is abutted against the inner wall of the side baffle (2).
7. A fixed die device for building construction according to claim 1, wherein the outer side wall of the side baffle (3) is provided with a discharge hole (19), and the lower port of the discharge hole (19) is arranged in parallel with the bottom surface of the scraping rod (4).
CN202222781795.7U 2022-10-21 2022-10-21 Cover half device for construction Expired - Fee Related CN218699910U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222781795.7U CN218699910U (en) 2022-10-21 2022-10-21 Cover half device for construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222781795.7U CN218699910U (en) 2022-10-21 2022-10-21 Cover half device for construction

Publications (1)

Publication Number Publication Date
CN218699910U true CN218699910U (en) 2023-03-24

Family

ID=85588563

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222781795.7U Expired - Fee Related CN218699910U (en) 2022-10-21 2022-10-21 Cover half device for construction

Country Status (1)

Country Link
CN (1) CN218699910U (en)

Similar Documents

Publication Publication Date Title
CN109944461B (en) High-rise building connecting beam horizontal hole plugging structure and construction method thereof
CN111360982A (en) PC component manufacturing and forming machine and manufacturing and forming method
CN218699910U (en) Cover half device for construction
CN216372666U (en) Autoclaved aerated concrete production mold
CN210791416U (en) Quick forming die for concrete pouring
CN106217611B (en) A kind of adjustable curb stone mould
CN214871425U (en) Concrete prefabricated part mould with three-dimensional positioning slurry leakage prevention plate
CN216152643U (en) Hollow concrete pier mould
CN216609432U (en) A general side forms for PC trade preparation superimposed sheet component
CN216372671U (en) Solid brick embryo mould of concrete
CN213533158U (en) Fixing device is used in production of cement superimposed sheet
CN212385649U (en) Flashing PC steel mould is decorated to roofing parapet
CN210375928U (en) Self-vibration concrete test mould
CN219445458U (en) Green shaping template of prefabricated shear force wall keyway and mould
CN108145831B (en) Building module shaping mould case
CN207630231U (en) A kind of brick-making mould of included material scraping plate
CN206011400U (en) A kind of adjustable curb stone mould
CN210233412U (en) Recycled aggregate concrete root stone preparation mould
CN213288579U (en) Combined casting die
CN218314202U (en) Pouring mold for building prefabricated wall
CN220972752U (en) Concrete pier-wrapping die suitable for different sizes
CN220699956U (en) Polymer mortar shaping auxiliary device
CN219081002U (en) Self-supporting detachable steel bar truss template connecting piece
CN215212182U (en) Indoor ground concrete pouring device
CN113478624B (en) Side mold capable of being recycled for producing laminated plate and using method thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20230324