CN218667034U - Construction device for laying anti-corrosion terrace - Google Patents

Construction device for laying anti-corrosion terrace Download PDF

Info

Publication number
CN218667034U
CN218667034U CN202222970229.0U CN202222970229U CN218667034U CN 218667034 U CN218667034 U CN 218667034U CN 202222970229 U CN202222970229 U CN 202222970229U CN 218667034 U CN218667034 U CN 218667034U
Authority
CN
China
Prior art keywords
coiled material
hole
telescopic link
handle
link cover
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222970229.0U
Other languages
Chinese (zh)
Inventor
王均春
王丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Shenneng Construction Engineering Co ltd
Original Assignee
Anhui Shenneng Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Shenneng Construction Engineering Co ltd filed Critical Anhui Shenneng Construction Engineering Co ltd
Priority to CN202222970229.0U priority Critical patent/CN218667034U/en
Application granted granted Critical
Publication of CN218667034U publication Critical patent/CN218667034U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Building Awnings And Sunshades (AREA)

Abstract

The utility model discloses a construction equipment for anticorrosive terrace is laid, including the handle, handle downside fixedly connected with connecting rod, the other end fixed connection telescopic link cover of connecting rod, telescopic link cover both ends are through flexible spacing subassembly and coiled material clamp expansion joint, the output of coiled material clamp and the central hole roll connection of the fine cloth coiled material of glass, and the connecting rod rotates through spacing subassembly and connects the ground depression bar. The utility model discloses simple structure, through the use of structure coiled material clamp and handle, make the personnel not carry out the roll shop of the fine cloth of glass under the condition that needs stoop, through increasing the depression bar, realize just accomplishing behind the roll shop and smooth the process, improve the operating efficiency, also avoided having to exist and caused follow-up terrace to apply paint bubbly risk with a brush because of artifical smoothing the area of leaking, reduce the operation to staff's waist strain, use through the combination of flexible spacing subassembly and extension bar, the suitability of device to different width coiled materials has further been improved, the practicality of device is improved.

Description

A construction equipment for anticorrosive terrace is laid
Technical Field
The utility model relates to a anticorrosive technical field of terrace especially relates to a construction equipment for anticorrosive terrace is laid.
Background
Anticorrosive terrace is the ground that uses specific material and technology to carry out construction treatment and demonstrate certain decoration and functionality to original ground, make the terrace can stand fork truck, the truck rolls for a long time, make the ground serious corrosion-resistant, strong acid and alkali resistance, chemical solvent resistance, shock-resistant, prevent that ground chap from satisfying each item operation production demand, in the work progress, mainly adopt one cloth three to scribble and draw, the construction process of two cloth five coats, after basic processing and undercoat process end, can artifical tiling glass fiber cloth and middle coat construction, although the artifical in-process of laying glass fiber cloth need bend over or crouch down and roll the glass fiber cloth book backward, and need constantly manually smooth partial fold glass fiber cloth in the laying process, not only work efficiency is not high, there is the risk that the follow-up terrace caused because of artifical smoothing the leakage area and applies paint the bubble, and serious strain to staff's waist.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the shortcoming that exists among the prior art, and the construction equipment who is used for anticorrosive terrace to lay that proposes.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
the utility model provides a construction equipment for anticorrosive terrace is laid, includes the handle, handle downside fixedly connected with connecting rod, the other end fixed connection telescopic link cover of connecting rod, telescopic link cover both ends are through flexible spacing subassembly and coiled material clamp expansion joint, the output of coiled material clamp and the central hole roll connection of the fine cloth coiled material of glass, the connecting rod passes through spacing subassembly and rotates the connection ground depression bar.
Preferably, flexible spacing subassembly includes the telescopic link cover that cavity set up, telescopic link cover both sides upper end sets up the stopper, the stopper middle part is left the hole and is set up the screw thread, the stopper passes through hole and bolt threaded connection, the coiled material clamp is U type structure, the telescopic link cover inner wall of laminating of coiled material clamp one end outer wall, and the hole radius that the terminal corresponds the stopper middle part sets up a plurality of equidistance locating holes, and the locating hole corresponds the bolt and sets up the screw thread, the coiled material clamp other end roll connection coiled material roller bearing, coiled material roller bearing radius is unanimous with fine cloth coiled material middle part refill inner wall radius.
Preferably, the ground pressure lever includes the adjustable shelf, and the one end cavity of adjustable shelf sets up, and the other end fixed connection depression bar of adjustable shelf, depression bar and telescopic link cover length are unanimous and the both ends of depression bar are overlapped the section with the telescopic link and are aimed at parallelly, and the both ends middle part of depression bar sets up the sunken screw hole, and the depression bar passes through screw hole and extension bar threaded connection, and both sides all set up sunken recess near one side of glass fiber cloth coiled material about the adjustable shelf.
Preferably, the limiting assembly comprises a fixing rod arranged between two connecting rods, the outer wall of the fixing rod is rotatably connected with the inner wall of the hollow end of the movable frame, a limiting groove and two limiting fixture blocks are respectively arranged at positions corresponding to the pressing rods on the connecting rods, protruding ends of the limiting fixture blocks are provided with hole grooves, and the limiting fixture blocks are connected with the bolts through the hole grooves in a sliding mode.
Preferably, the handle, the telescopic rod sleeve and the connecting rod corners are all arranged by adopting round corners, and two connecting rods are symmetrically connected with the central shafts of the handle and the telescopic rod sleeve.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses simple structure, through the use of structure coiled material clamp and handle, make the personnel not carry out the roll shop of the fine cloth of glass under the condition that needs stoop, through increasing the depression bar, realize just accomplishing behind the roll shop and smooth the process, improve the operating efficiency, also avoided having to exist and caused follow-up terrace to apply paint bubbly risk with a brush because of artifical smoothing the area of leaking, reduce the operation to staff's waist strain, use through the combination of flexible spacing subassembly and extension bar, the suitability of device to different width coiled materials has further been improved, the practicality of device is improved.
Drawings
In order to more particularly and intuitively illustrate an embodiment of the present invention or a prior art solution, a brief description of the drawings needed for use in the description of the embodiment or the prior art will be provided below.
Fig. 1 is a schematic structural diagram of the present invention;
fig. 2 is a schematic structural diagram ii provided by the present invention;
fig. 3 is a third schematic structural diagram of the present invention;
fig. 4 is a fourth schematic structural diagram proposed by the present invention;
fig. 5 is an enlarged schematic view of a part a of the present invention;
fig. 6 is an enlarged schematic view of a part B of the present invention;
fig. 7 is an enlarged schematic view of a part C according to the present invention.
In the figure: the device comprises a handle 1, a connecting rod 2, a coil clamp 3, a positioning hole 301, a coil rolling shaft 302, a telescopic rod sleeve 4, a limiting block 401, a bolt 402, a glass fiber cloth coil 5, a fixing rod 6, a ground pressure rod 7, a movable frame 701, a pressure rod 702, a threaded hole 703, an extension rod 704, a limiting groove 8, a limiting clamping block 9 and a bolt 10.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-7, a construction equipment for laying anticorrosion terrace, including handle 1, handle 1 downside fixedly connected with connecting rod 2, the other end fixed connection telescopic link cover 4 of connecting rod 2, telescopic link cover 4 both ends are through flexible spacing subassembly and coiled material clamp 3 telescopic connection, the output of coiled material clamp 3 and the central hole roll connection of glass fiber cloth coiled material 5, connecting rod 2 rotates through spacing subassembly and connects ground depression bar 7, install glass fiber cloth coiled material 5 that needs to lay between two coiled material clamps 3 through adjusting flexible spacing subassembly earlier before the construction, put down ground depression bar 7 and make its contact on the glass fiber cloth that has already laid, artifical alright with according to construction requirement pulling device, accomplish laying of glass fiber cloth under the roll of glass fiber cloth coiled material 5, and accomplish even flattening through ground depression bar 7, avoid glass fiber cloth to lay the problem that there is the fold unevenly.
In the present case, flexible spacing subassembly includes telescopic link cover 4 that cavity set up, telescopic link cover 4 both sides upper end sets up stopper 401, stopper 401 middle part is left the hole and is set up the screw thread, stopper 401 passes through hole and bolt 402 threaded connection, coiled material clamp 3 is U type structure, 3 one end outer wall laminating telescopic link cover 4 inner walls of coiled material clamp, and the hole radius that this end corresponds stopper 401 middle part sets up a plurality of equidistance locating holes 301, and locating hole 301 corresponds bolt 402 and sets up the screw thread, realize the different locating hole 301 of adjusting bolt 402 threaded connection and realize the adjustment of distance, the increase device is to the practicality of different width coiled materials, 3 other end roll connection coiled material roller bearings of coiled material clamp 302, coiled material roller bearings 302 radius is unanimous with the 5 middle part refill inner wall radius of fine cloth coiled material of glass, the roll laying of the fine cloth coiled material of the glass of being convenient for.
In the present case, ground depression bar 7 includes adjustable shelf 701, the one end cavity of adjustable shelf 701 sets up, other end fixed connection depression bar 702 of adjustable shelf 701, depression bar 702 is unanimous with 4 length of telescopic link cover and the both ends of depression bar 702 are even the section is aligned parallelly with telescopic link cover 4, basic condition through setting for basic length assurance device use, the both ends middle part of depression bar 702 sets up sunken screw hole 703, depression bar 702 passes through screw hole 703 and 704 threaded connection of extension bar, ensure the uniformity on compaction surface on the one hand, on the other hand detachable equipment has improved the in service behavior of device, improve the practicality, one side that both sides are close to glass fiber cloth coiled material 5 about adjustable shelf 701 all sets up sunken recess, reduce the whole weight of adjustable shelf 701, also provide bigger roll space for the installation of glass fiber cloth coiled material 5, the actual operation of being convenient for.
In the present case, spacing subassembly includes the dead lever 6 that sets up between two connecting rods 2, and 6 outer walls of dead lever rotate the inner wall of connecting the cavity one end of adjustable shelf 701, and the position that corresponds depression bar 702 on connecting rod 2 respectively sets up a spacing recess 8 and two spacing fixture blocks 9, and the protrusion end of spacing fixture block 9 sets up the hole groove, and spacing fixture block 9 passes through hole groove sliding connection bolt 10, and simple structure and unity make things convenient for whole use.
In the present case, handle 1, telescopic link cover 4 all adopt the fillet setting with 2 corners of connecting rod, and the personnel's operation of being convenient for reduces the hand friction, adopts two connecting rods 2 and handle 1, telescopic link cover 4 axis symmetric connection, improves the holistic structural stability of device.
The above, only be the embodiment of the preferred of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, which are designed to be replaced or changed equally, all should be covered within the protection scope of the present invention.

Claims (5)

1. The utility model provides a construction equipment for anticorrosive terrace is laid, includes handle (1), its characterized in that, handle (1) downside fixedly connected with connecting rod (2), other end fixed connection telescopic link cover (4) of connecting rod (2), telescopic link cover (4) both ends are through flexible spacing subassembly and coiled material clamp (3) telescopic connection, the output of coiled material clamp (3) and the central hole roll connection of fine cloth coiled material of glass (5), and connecting rod (2) rotate through spacing subassembly and connect ground depression bar (7).
2. The construction device for laying anticorrosive terrace according to claim 1, characterized in that, flexible spacing subassembly includes telescopic link cover (4) that cavity set up, telescopic link cover (4) both sides upper end sets up stopper (401), stopper (401) middle part is left the hole and is set up the screw thread, stopper (401) pass through hole and bolt (402) threaded connection, coiled material clamp (3) are U type structure, coiled material clamp (3) one end outer wall laminating telescopic link cover (4) inner wall, and the hole radius that this end corresponds stopper (401) middle part sets up a plurality of equidistance locating holes (301), and locating hole (301) correspond bolt (402) and set up the screw thread, coiled material clamp (3) other end roll connection coiled material roller bearing (302), coiled material roller bearing (302) radius is unanimous with glass fine cloth coiled material (5) middle part refill inner wall radius.
3. The construction device for laying the anti-corrosion terrace according to claim 2, wherein the ground pressure lever (7) comprises a movable frame (701), one end of the movable frame (701) is arranged in a hollow mode, the other end of the movable frame (701) is fixedly connected with a pressure lever (702), the length of the pressure lever (702) is consistent with that of the telescopic rod sleeve (4), two ends of the pressure lever (702) are aligned and parallel with a connecting section of the telescopic rod sleeve (4), an inward concave threaded hole (703) is formed in the middle of each of two ends of the pressure lever (702), the pressure lever (702) is in threaded connection with the extension rod (704) through the threaded hole (703), and inward concave grooves are formed in one side, close to the glass fiber cloth coiled material (5), of the left side and the right side of the movable frame (701).
4. The construction device for laying the anti-corrosion terrace according to claim 3, wherein the limiting component comprises a fixing rod (6) arranged between two connecting rods (2), the outer wall of the fixing rod (6) is rotatably connected with the inner wall of the hollow end of the movable frame (701), a limiting groove (8) and two limiting clamping blocks (9) are respectively arranged on the connecting rods (2) corresponding to the positions of the pressing rods (702), a hole groove is formed in the protruding end of each limiting clamping block (9), and the limiting clamping blocks (9) are slidably connected with the bolts (10) through the hole grooves.
5. The construction device for laying the anti-corrosion terrace according to claim 4, wherein the corners of the handle (1), the telescopic rod sleeve (4) and the connecting rods (2) are all arranged by round angles, and the two connecting rods (2) are symmetrically connected with the central axes of the handle (1) and the telescopic rod sleeve (4).
CN202222970229.0U 2022-11-08 2022-11-08 Construction device for laying anti-corrosion terrace Active CN218667034U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222970229.0U CN218667034U (en) 2022-11-08 2022-11-08 Construction device for laying anti-corrosion terrace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222970229.0U CN218667034U (en) 2022-11-08 2022-11-08 Construction device for laying anti-corrosion terrace

Publications (1)

Publication Number Publication Date
CN218667034U true CN218667034U (en) 2023-03-21

Family

ID=85568691

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222970229.0U Active CN218667034U (en) 2022-11-08 2022-11-08 Construction device for laying anti-corrosion terrace

Country Status (1)

Country Link
CN (1) CN218667034U (en)

Similar Documents

Publication Publication Date Title
CN218667034U (en) Construction device for laying anti-corrosion terrace
CN209957098U (en) Portable wiring device
CN213256428U (en) Pipe bending machine with multi-roller pipe fitting lifting structure
CN210907532U (en) Bending device for heat pipe machining
CN209531765U (en) Long shaft straightener
CN211085085U (en) Flatness detection device for building insulation material
CN203806871U (en) Portable waterwheel frame
CN207812872U (en) Material-paving auxiliary tool
CN111760941A (en) Roll bending forming machine for forming directional guide
CN216909004U (en) Automatic production equipment for fire hose
CN205577371U (en) Novel convenient wipeing wall device
CN206256670U (en) A kind of emulsion paint paints device
CN216193373U (en) Tubular coated fabric traction device for textile industry
CN211134968U (en) Centering device for upper sleeve of high-precision aluminum plate hot continuous rolling unit
CN213742131U (en) Cylinder brush for building engineering
CN207041497U (en) It is flat to drag framework and exempt to hand-wash flat drag
CN217379674U (en) Adjustable rolling brush limiting device
CN212507226U (en) Whitewash device for building decoration
CN220848911U (en) Wall surface repairing device for building engineering
CN208950251U (en) A kind of fitting-up engineering wall plaster device
CN220014332U (en) Waterproof coating rolling brush device
CN218234229U (en) Roller brush with hydraulic display device
CN215631803U (en) Novel masonry structure mortar joint closing device
CN214349246U (en) Device is buckled to lightning-arrest muscle switching steel of portable beam column
CN220262037U (en) Heat supply pipeline heat preservation joint coating closing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant